Upload
whitney-green
View
214
Download
0
Embed Size (px)
Citation preview
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
COMMISSIONING &
OPERATION OF SOLEIL.
J.C. Besson, J.F. Lamarre, A. Bence, X. Deletoille, Y. Denis, S. Petit, R. Cuoq, P. Da Silva, D. Pereira, G. Roux,
Synchrotron Soleil, St Aubin, France.
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
SOLEIL Synchrotron
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Summary
1) Installation and Commissionning2) The Control Room
3) Software and Hardware Architecture
4) Some Software Applications
5) Balance-Sheet
6) Conclusion
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Installation Accelerators
SOLEIL is a third generation Synchrotron radiation Source, located at the Plateau de Saclay near Paris.
Storage Ring
Booster
LinacSextupoles (220/280 Kg)
Quadrupoles (900/1200 Kg)
Dipoles (3,5T)
Long Girder (4,8m–7,8T)
Cell with 3 girders
The 354 m circumference storage ring is mainly composed of 32 (+1) dipoles, 160 quadrupoles, 120 sextupoles, 2 RF cryomodules, ~ 200 vacuum chambers, 6 injection equipments; 12 beamline front-ends and 4 insertion devices (initially).
The 157 m circumference Booster comprises 36 dipoles, 44 quadrupoles, 28 sextupoles, 1 RF cavity and 8 injection/extraction equipment
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Installation Accelerators
TOTAL MANPOWER INSTALLATION (tunnels)
0
5
10
15
20
25
30
men
/ d
ays
0
1000
2000
3000
4000
5000
6000
men
x d
ays
Out Ressources (m/d)Plumber & Electrician (m/d)Ressources Soleil (m/d)Out Ressources (mxd)Plumber & Electrician (mxd)Ressources Soleil (mxd)
LT1 BOOSTER STORAGE RING
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Installation Accelerators General Planning
1st beam in the Linac on July 2nd,2005
1st beam in the Booster at 110 MeV on July 23rd 2005
Booster : 1st beam accelerated to 2.75 GeV on October 13th 2005
Booster : 1st extraction of 2.75 GeV beam on May 6th, 20061st turn in the storage ring on May 14th, 2006
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Commissioning organization
• A commissioning team of about 20 persons composed of the machine physics group and people coming from different areas was constituted in the early stage.
• They shared their experience and their knowledge in the preparation of the different phases of the commissioning and in the analysis of the results.
• This organization allowed a fast progress of the commissioning (round clock operation) and different ways to see and solve the encountered problems.
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Commissioning organization
General planning
Detailed protocol for each session
Electronic logbook
One report of each session
A commissioning team
People working 3 x 8h; 7d/7; (example : 7h am-3h pm-11h pm-7h am)
Overlap of 1/2 an hour between 2 successive team
On-call and shift people.
weekly meeting for commissioning team and for each encountered problem
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
J. M. FilholM. P. LevelP. Brunelle M. A. TordeuxA. LoulergueA. MadurA. NadjiL. NadolskiR. NagaokaB. PottinJ. C. BessonJ. F. Lamarre J. C. DenardL. CassinariM. E. CouprieP. MarchandP. Lebasque
Magnets & insertions Group
Security Group
Vacuum Group
Power supply group
RF Group
Elect. Control & Acquisition Group
Diagnostics Group
The team: at less one representative from each sudivision
operation Group
Inf. Control & Acquisition Group
Facilities Group
Linac Group
Commissioning team
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Commissioning Milestones in 2006
10 e
ffec
tive
wee
ks
14/5 First turn 04/6 First stored beam04/6 First beam accumulation : 8.35mA
04/7 100mA achieved10/7 5 A.h beam dose
Shutdown 11/7 – 4/09
13/9 First photons to a beamline (DIFFABS)16/9 200mA21/9 First photons to a beamline (TEMPO)25/9 300mA achieved ; 30A.h29/9 U20 at 5.5mm gap21/9 First photons to a beamline (ODE)15/10 Beam lifetime =8h @100mA in 312 bunches
12/12 First photons to a beamline (SAMBA)13/12 First photons to a beamline (DESIRS)21/12 70 A.h beam dose21/12 Beam lifetime =10h @100mA in 312 bunches
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Quadrupoles and Correctors ON, Sextupoles and RF OFF.
After correction of first turn trajectory and closing the first turn.
Sextupoles ON and RF OFF.
successive turns detected by the FCT
successive turns detected by the FCT
First turns (May 14, 2006)
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
10 mm vertical aperture chambers
When the beam could be circulated for the first time in the Storage Ring it goes several times through the 10 mm small vertical aperture of the 10 insertion device chambers distributed along the ring without any correction.
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Closed Orbit with All correctors OFF
(BPM offsets included after BBA)
Hrms=3.1mmmax=6.40mm
Vrms=0.41mmmax=1.44mm
=> Excellent magnet alignment
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
0
50
100
150
200
250
300
mA
0
20
40
60
80
100
120
A.h
Current (average over 1 hour)Integrated Dose
Current and Integrated Dose, year 2006
maximum current of 300mA possible with only one cryomodule RF was reached after only 30A.h of integrated current dose
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Beam position stability (with SOFB)
mA
Beam current
X (PX1)
X (CASSIOPEE)
Z (PX1)
Z (CASSIOPEE)
m
injection(Source point Positions)
on 2 straight sections during a 8 hours beamline shift. DX ~ 3 µm , DZ ~ 1 µm
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Parameters Design Achieved as of June 2007
Energy ( GeV ) 2.75 2.74
RF frequency ( MHz ) 352.2 352.197
Betatron Tunes 18.20 / 10.30 18.2009 / 10.2990
Natural Chromaticities -53 / -23 -53 / -19
Momentum Compaction 1 / 2 4.5 x 10-4 / 4.6 x 10-3
4.55 x 10-4 / 4.30 x 10-3
Emittance H ( nm.rad ) 3.73 3.70 ± 0.2
Energy spread 1.016 x 10-3 1.0 x 10-3
Coupling, V/H<1% 0.3% (without correction)
Current Multibunch mode ( mA ) 500 300
Average Pressure ( mbar ) 1 x 10-9 3 x 10-9
Beam Lifetime ( h ) 16 h 9h @ 300 mA / 22h @ 100 mA
Single bunch current ( mA ) 12 20
Beam position stability, m ( H ) 20 (rms) 3 ptp
Beam position stability, m ( V ) 0.8(rms) 2 ptp
STORAGE RING COMMISSIONING
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Results and innovations
• We had no problems with innovations
• This good result clearly demonstrates the beneficial effect of the NEG coating on the aluminium chamber. This technology was never seen before on accelerators at such extensive use.
• 2 other innovations concern the RF system: the dedicated Superconducting cavities (1st cryomodule enable alone operation up to 300 mA, a 2nd cryomodule which is being build by ACCEL will enable to reach 500 mA) and the solid state RF amplifiers that are used for the first time in the world for such high power. Except few transistor failures, the system is very stable.
• Specific and innovative electromagnetic insertion devices were developed for VUV beamlines: – 3 HU256 (10eV to 1000eV) 3.6 meter long – 1 HU640 (5eV to 40eV) 10 meter longExtended spectral range :from UV (5 eV) up to hard X-Rays (15
KeV)
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
RF System Innovations
Each of the four cavities is powered by a 190 kW solid state
amplifier consisting in a combination of four “towers”
producing about 50 kW each.
Solid State RF Amplifiers 4 x 190 kW power amplifiers
1st cryomodule inside SR tunnel
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
• During the shifts, within the operation group, 8 operators take their turns every 8 hours in order to ensure the presence of one of them 24h/24h and 7 days a week in the control room.
• This operator is assisted by 1 or 2 part-time operators (like ESRF) who come for majority from SOLEIL source division. Before being ready to work in control room, they get training by the "machine physicists" on the general operation of the machine.
• During shutdown, permanence in control room is ensured by an operator during the normal schedule.
• Apart from the operation of the machine, the operators are implied in the result analysis and in the developments (software and equipment) enabling a better understanding and operation of the installation.
Operation organization
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Formation of the operation group
0
1
2
3
4
5
6
7
8
9
10
Jan-04 Jan-05 Jan-06 Jan-07
Booster Commissioning 07/06 et 09/06
SR Commissioning Anneau
Machines Installation from 21/09/04 to 05/05/06
0
1
2
3
4
5
6
7
8
9
10
Jan-04 Jan-05 Jan-06 Jan-07
Booster Commissioning 07/06 et 09/06
SR Commissioning Anneau
Staff Numbe
r
According to their arrival
Operators were involved in the machines installation and the supervision applications development
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
TL1BOOSTER/TL2SR light monitor
SR beam size measurement
Pinhole camera
TUNE Measurement
Control room Organization
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
TL1 to BOOSTER
BOOSTER to TL2
TL2 to Storage Ring
Storage Ring FCT
Machine Status
FCT Linac & TL1
Control Room Organization
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Beam Orbit
Control Room Organization
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Alarm Survey Application
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Booster injection & extraction Application
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Hardware architecture
Supervision/Control
CONTROL BOX
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
binding
generic applications Machine Physics
Device
TANGO software bus
Monitoring
Equipments
Device
Configuration Archiving
Devices TANGO
binding
MATLAB, IGOR,python, Labview
JIVE DEV TREE
SD
SD
ESC
DLT
PROLIANT 8000
Magnet power suppliesMotors
Globalscreen
Graphic User Interface
3 major tools used
Software architecture
TDB - HDB
Flow meter FaultNO Fault
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
ELOG (ELectronic LogBooks)
Making an entry for single event
Attachement File
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Acquisition data
Compilation
(MTBF, breakdowns,…)
Extraction results in
Excel
Extracted data from ELOG in Operator JAVA Program
Post processing
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Automatic Excel file creation
Sharing out of the effective beam time = 558h24About the whole run 4-2007
From 2007, May the 25th to 2007, Jun the 20th
Breakdowns total time = 171h01About the whole run 4-2007
From 2007, May the 25th to 2007, Jun the 20th Accelerator physics time
Mixed time
Beam lines time
Health physics time
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
0
1
2
3
4
5
6
7
8
28 May 2007 4 June 2007 11 June 2007 18 June 2007
Number of lines that take beam per day, during 4th Run of 2007
5 to 8 lines used the beam of photons regularly Eventually: 25 Beamlines
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Balance - sheet
In year 2006, over the 2084 operating hours
The availability of the beam represented 83.5 % of total time, with 11.2 % of time of
breakdowns and 5.3 % of time of injection, preparation of manipulations, or interventions
In year 2007, From January to July, 93.8% of the 1426 total hours of beam were delivered to beam lines
91,7%
4,5%
3,8%
95,1%
2,5%
2,4%
95,6%
1,1%
3,3%
91,6%
1,3%
7,1%
94,3%
2,2%
3,5%
80%
90%
100%
Dead time dueto failures
Injection
Beam
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
planned of operation of the year 2007
Mon-01 . . . Thu-01 l l l Thu-01 . . . Sun-01 . . . Tue-01 l l l Fri-01 l l l Sun-01 m m m Wed-01 . . . Sat-01 m m m Mon-01 . . . Thu-01 l l l Sat-01 l l l Tue-01 . . .Tue-02 . . . Fri-02 l l l Fri-02 m m m Mon-02 . . . Wed-02 l l l Sat-02 l l l Mon-02 m m m Thu-02 . . . Sun-02 m m m Tue-02 . . . Fri-02 l l l Sun-02 l l l Wed-02 . . .
Wed-03 . . . Sat-03 l l l Sat-03 m m m Tue-03 . . . Thu-03 l l l Sun-03 m m m Tue-03 l l l Fri-03 . . . Mon-03 m m m Wed-03 . . . Sat-03 l l l Mon-03 m m m Thu-03 . . .Thu-04 . . . Sun-04 m m m Sun-04 m m m Wed-04 . . . Fri-04 l l l Mon-04 m m m Wed-04 l l l Sat-04 . . . Tue-04 l l l Thu-04 . . . Sun-04 l l l Tue-04 m m m Fri-04 . . .Fri-05 . . . Mon-05 m m m Mon-05 m m m Thu-05 . . . Sat-05 l l l Tue-05 l l l Thu-05 l l l Sun-05 . . . Wed-05 l l l Fri-05 . . . Mon-05 m m m Wed-05 l l l Sat-05 . . .Sat-06 . . . Tue-06 m m m Tue-06 l l l Fri-06 . . . Sun-06 l l l Wed-06 l l l Fri-06 l l l Mon-06 . . . Thu-06 l l l Sat-06 . . . Tue-06 m m m Thu-06 l l l Sun-06 . . .
Sun-07 . . . Wed-07 l l l Wed-07 l l l Sat-07 . . . Mon-07 m m m Thu-07 l l l Sat-07 l l l Tue-07 . . . Fri-07 l l l Sun-07 . . . Wed-07 l l l Fri-07 l l l Mon-07 . . .Mon-08 . . . Thu-08 l l l Thu-08 l l l Sun-08 . . . Tue-08 m m m Fri-08 l l l Sun-08 m m m Wed-08 . . . Sat-08 l l l Mon-08 . . . Thu-08 l l l Sat-08 l l l Tue-08 . . .Tue-09 . . . Fri-09 l l l Fri-09 l l l Mon-09 . . . Wed-09 l l l Sat-09 l l l Mon-09 m m m Thu-09 . . . Sun-09 m m m Tue-09 . . . Fri-09 l l l Sun-09 m m m Wed-09 . . .
Wed-10 . . . Sat-10 l l l Sat-10 l l l Tue-10 . . . Thu-10 l l l Sun-10 m m m Tue-10 l l l Fri-10 . . . Mon-10 m m m Wed-10 . . . Sat-10 l l l Mon-10 m m m Thu-10 . . .Thu-11 . . . Sun-11 l l l Sun-11 m m m Wed-11 . . . Fri-11 l l l Mon-11 m m m Wed-11 l l l Sat-11 . . . Tue-11 l l l Thu-11 . . . Sun-11 l l l Tue-11 l l l Fri-11 . . .Fri-12 . . . Mon-12 m m m Mon-12 m m m Thu-12 . . . Sat-12 l l l Tue-12 l l l Thu-12 l l l Sun-12 . . . Wed-12 l l l Fri-12 m m m Mon-12 . . . Wed-12 l l l Sat-12 . . .Sat-13 . . . Tue-13 m m m Tue-13 l l l Fri-13 . . . Sun-13 l l l Wed-13 l l l Fri-13 l l l Mon-13 . . . Thu-13 l l l Sat-13 m m m Tue-13 . . . Thu-13 l l l Sun-13 . . .
Sun-14 . . . Wed-14 . . . Wed-14 l l l Sat-14 . . . Mon-14 . . . Thu-14 l l l Sat-14 l l l Tue-14 . . . Fri-14 l l l Sun-14 m m m Wed-14 . . . Fri-14 l l l Mon-14 . . .Mon-15 . . . Thu-15 . . . Thu-15 l l l Sun-15 . . . Tue-15 . . . Fri-15 l l l Sun-15 m m m Wed-15 . . . Sat-15 l l l Mon-15 m m m Thu-15 . . . Sat-15 l l l Tue-15 . . .Tue-16 . . . Fri-16 . . . Fri-16 l l l Mon-16 . . . Wed-16 . . . Sat-16 l l l Mon-16 m m m Thu-16 . . . Sun-16 m m m Tue-16 l l l Fri-16 . . . Sun-16 l l l Wed-16 . . .
Wed-17 . . . Sat-17 . . . Sat-17 l l l Tue-17 . . . Thu-17 . . . Sun-17 l l l Tue-17 l l l Fri-17 . . . Mon-17 m m m Wed-17 l l l Sat-17 . . . Mon-17 l l l Thu-17 . . .Thu-18 . . . Sun-18 . . . Sun-18 m m m Wed-18 . . . Fri-18 . . . Mon-18 m m m Wed-18 l l l Sat-18 . . . Tue-18 l l l Thu-18 l l l Sun-18 . . . Tue-18 . . . Fri-18 . . .Fri-19 m m m Mon-19 . . . Mon-19 m m m Thu-19 . . . Sat-19 . . . Tue-19 m m m Thu-19 l l l Sun-19 . . . Wed-19 l l l Fri-19 l l l Mon-19 . . . Wed-19 . . . Sat-19 . . .Sat-20 m m m Tue-20 . . . Tue-20 m m m Fri-20 m m m Sun-20 . . . Wed-20 . . . Fri-20 l l l Mon-20 . . . Thu-20 l l l Sat-20 l l l Tue-20 . . . Thu-20 . . . Sun-20 . . .
Sun-21 m m m Wed-21 . . . Wed-21 l l l Sat-21 m m m Mon-21 . . . Thu-21 . . . Sat-21 . . . Tue-21 . . . Fri-21 l l l Sun-21 m m m Wed-21 . . . Fri-21 . . . Mon-21 . . .Mon-22 m m m Thu-22 . . . Thu-22 l l l Sun-22 m m m Tue-22 . . . Fri-22 . . . Sun-22 . . . Wed-22 . . . Sat-22 l l l Mon-22 m m m Thu-22 . . . Sat-22 . . . Tue-22 . . .Tue-23 m m m Fri-23 . . . Fri-23 l l l Mon-23 m m m Wed-23 . . . Sat-23 . . . Mon-23 . . . Thu-23 . . . Sun-23 l l l Tue-23 l l l Fri-23 m m m Sun-23 . . . Wed-23 . . .
Wed-24 l l l Sat-24 . . . Sat-24 l l l Tue-24 l l l Thu-24 . . . Sun-24 . . . Tue-24 . . . Fri-24 . . . Mon-24 . . . Wed-24 l l l Sat-24 m m m Mon-24 . . . Thu-24 . . .Thu-25 l l l Sun-25 . . . Sun-25 l l l Wed-25 l l l Fri-25 m m m Mon-25 . . . Wed-25 . . . Sat-25 . . . Tue-25 . . . Thu-25 l l l Sun-25 m m m Tue-25 . . . Fri-25 . . .Fri-26 l l l Mon-26 . . . Mon-26 m m m Thu-26 l l l Sat-26 m m m Tue-26 . . . Thu-26 . . . Sun-26 . . . Wed-26 . . . Fri-26 l l l Mon-26 m m m Wed-26 . . . Sat-26 . . .Sat-27 l l l Tue-27 . . . Tue-27 m m m Fri-27 l l l Sun-27 m m m Wed-27 . . . Fri-27 . . . Mon-27 . . . Thu-27 . . . Sat-27 l l l Tue-27 l l l Thu-27 . . . Sun-27 . . .
Sun-28 m m m Wed-28 . . . Wed-28 . . . Sat-28 l l l Mon-28 m m m Thu-28 . . . Sat-28 . . . Tue-28 . . . Fri-28 . . . Sun-28 m m m Wed-28 l l l Fri-28 . . . Mon-28 . . .
Mon-29 m m m Thu-29 . . . Sun-29 m m m Tue-29 l l l Fri-29 m m m Sun-29 . . . Wed-29 . . . Sat-29 . . . Mon-29 m m m Thu-29 l l l Sat-29 . . . Tue-29 . . .Tue-30 l l l Fri-30 . . . Mon-30 m m m Wed-30 l l l Sat-30 m m m Mon-30 . . . Thu-30 . . . Sun-30 . . . Tue-30 l l l Fri-30 l l l Sun-30 . . . Wed-30 . . .
Wed-31 l l l Sat-31 . . . Thu-31 l l l Tue-31 . . . Fri-31 m m m Wed-31 l l l Mon-31 . . . Thu-31 . . .
Jan-2008Sep-2007 Oct-2007 Nov-2007 Dec-2007May-2007 Jun-2007 Jul-2007 Aug-2007Jan-2007 Feb-2007 Mar-2007 Apr-2007
Planned ObjectivesL 3096 hours Beam Lines 3 000 hours Beam LinesM 1800 hours Machine 1 000 hours Machine . 3864 hours Shutdown
L
M
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
CONCLUSION ANDMAIN OBJECTIVES FOR EARLY 2008
• The SOLEIL accelerator complex is now fully operational. The transition from the commissioning phase to the operation phase went smoothly, thanks to:– The strong implication and participation of the operation group during
the commissioning of the machine.– Significant efforts from the machine physics groups and from the
different groups in charge of equipment to transfer their knowledge to the operation crew.
– The machine availability already reached 93.8 % over the 1521 hours of beam time delivered to the beamlines during the first 7 months of 2007. We are now aiming at increasing further this availability.
• The next objectives set-up for 2008 are:– 500mA operation (with second cryomodule)– Preparation for top-up operation– Single bunch and 8 bunches operation– Secure beam stability with many insertion devices– Increase beam availability.
Commissioning & Operation of SOLEIL Jean-Claude Besson – Trieste – WAO 2007
Operator’s Team
Operation manager
Engineer