CRONOGRAMA VALORIZADO DE AVANCE DE OBRA OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL EN LA CALLE EDUCADOR ES TRAMO AV. COLLPA - AV. LOS POETAS - CONTRATISTA: CONSORCIO VIAL EDUCADORES FECHA DE ENTREGA DE TERRENO: 02/07/2013 FECHA DE ELABORACION: 22/11/2013 ENTIDAD: EN EL DISTRITO CRNL. GREGORIO ALBARRACIN L ANCHIPA -TACNA - TACNA RESIDENTE DE OBRA: ING. VICTOR RAUL REYES ANAYA FECHA DE INICIO DE PLAZO CONTRACTUAL: 03/07/2013 ELABORADO POR: VRA UBICACIÓN: GREGORIO ALBARRACIN LANCHIPA -TACNA-TACNA INSPECTOR DE OBRA: ING. FELIX FRISANCHO CAMERO FECHA PREVISTA DE TERMINO DE PLAZO CONTRACTUAL: 30/10/2013 FECHA REPROGRAMADA DE TERMINO DE PLAZO CONTRACTUAL: 29/12/2013 PLAZO EJECUCION: 180 d.c. JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE ITEM DESCRIPCION UND PRESUPUESTO L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L METRADO PRECIO PARCIAL 1 2 3 4 ! " 8 # 10 11 12 13 14 1 1!1" 18 1# 20 21 22 23 24 2 2" 2" 28 2# 30 31 1 2 3 4 ! " 8 # 10 11 12 13 14 1 1! 1" 18 1#20 21 22 23 24 2 2! 2"28 2# 30 31 1 2 3 4 ! " 8 # 10 11 12 13 14 1 1! 1" 18 1# 20 21 22 23 24 2 2! 2" 28 2# 30 1 2 3 4 ! " 8 # 10 11 12 13 141 1! 1" 18 1# 20 21 2223 24 2 2! 2" 28 2# 30 31 1 2 3 4 ! " 8 # 10 11 12 13 14 1 1! 1" 18 01.01.00 OBRAS PROVISIONALES GLB - - !$""3.1! $!48.1! 3".00 3".00 53.13 01.02.00 SEGURIDAD % SALUD GLB - - 1!$8!2."" "$8!!.8" $38!.82 1$804.4 !51.1! 01.03.00 T RABAJOS PRELIMINARES GLB - - #$1#0.!8 84$42".#2 3$833.20 1$21".01 30!.25 01.04.00 VEREDAS DE CONCRETO DE PIEDRA LAVADA COLOREADO GLB - - 242$3"0.40 01.04.01 MOVIMIENTO DE TIERRAS 94,957.7 !$#"4.3! 32$#31.1" 01.04.02 CONCRETO SIMPLE !47,4!".!" $224.80 13$#2.8" 01.0.00 JARDINERAS GLB 13$!88.!4 !$844.32 01.0!.00 OTROS GLB 8$3!3.44 4$"84.#0 2!70.90 01.0".00 BERMAS DE ADO&UIN GLB - - 333$"4#.!" 01.0".01 MOVIMIENTO DE TIERRAS "5,""4.#5 1"$!!".42 4$41!.8 3312."!25 01.0".02 ADO$UINADO EN BERMAS 9#,4!4.# 1$01!.23 10$844.#4 23$10.18 29510.7 01.08.00 PAVIMENTACION GLB - - 4"$3#!.10 23$!#8.0 $#24.2 01.0#.00 PAVIMENTO EN VIA GLB - - 20$#8".1 1$8"0.38 01.10.00 SE'ALI(ACION GLB 21$831.2 01.11.00 PORTICO DE INGRESO DE BIENVENIDA GLB 24$42.81 01.11.01 MOVIMIENTO DETIERRAS 9%%.7& "38."0 228.00 01.11.02 OBRASDECONCRETO SIMPLE #.79 282."# 01.11.03 OBRAS DECONCRETO ARMADO ",&"." 14$#.!3 01.12.00 CARPINTERIA METALICA GLB $#!4.#" 01.13.00 VARIOS GLB 1!$!4#.3 01.14.00 INSTALACIONES E LECTRICAS GLB #$133.# 01.1.00 MITIGACION DE IMPACTO AMBIENTAL GLB 4$00.00 112.00 112.00 112.00 08.0! "1".9! 01.1!.00 EDUCACION VIAL GLB 4$000.00 1000.00 1000.00 1000.00 41.!1 5!.39 COSTO DIRECTO 1$101$#1.1 1!2$2!".11 2#2$##1.80 130$!0." 24$4!#.8 656,568.80 GASTOS GENERALES '!&.&() !!,"95."5 !%,55!.5 9,##5.!% !","%."% ,495.9 UTILIDAD '#.5&() 9",%%.79 !",79.7& 4,9&4."& !!,!&5."& ,&79.94 SUB TOTAL 1$30"$#"3.2# 1#2$!11.0! 34"$"81.2! 1$082.23 2#$04."1 I.G.V'!#() "5,4"5.!9 "4,%%9.99 %,%&&.%" 7,9!4.#& 5,#." PRESUPUESTO DE OBRA 1$43$408.48 22"$281.0 410$381.8# 182$##".03 34$2"3.#4 ( AVANCE MENSUAL 14."3) 2!.#) 11.8!) 2.22) ) AVANCE ACUMULADO 14."3) 41.32) 3.1") .3#)

Cronograma de Ejecucion Valorizado Fechado Hasta Navidad

Embed Size (px)

DESCRIPTION

cronogramaaaa

Citation preview

CRON VAL OPCCRONOGRAMA VALORIZADO DE AVANCE DE OBRA

OBRA:MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL EN LA CALLE EDUCADORES TRAMO AV. COLLPA - AV. LOS POETAS -CONTRATISTA:CONSORCIO VIAL EDUCADORESFECHA DE ENTREGA DE TERRENO: 02/07/2013FECHA DE ELABORACION: 22/11/2013ENTIDAD:EN EL DISTRITO CRNL. GREGORIO ALBARRACIN LANCHIPA -TACNA - TACNARESIDENTE DE OBRA:ING. VICTOR RAUL REYES ANAYAFECHA DE INICIO DE PLAZO CONTRACTUAL: 03/07/2013ELABORADO POR: VRAUBICACIN:GREGORIO ALBARRACIN LANCHIPA -TACNA-TACNA INSPECTOR DE OBRA:ING. FELIX FRISANCHO CAMEROFECHA PREVISTA DE TERMINO DE PLAZO CONTRACTUAL: 30/10/2013FECHA REPROGRAMADA DE TERMINO DE PLAZO CONTRACTUAL: 29/12/2013PLAZO EJECUCION:180 d.c.JULIOAGOSTOSEPTIEMBREOCTUBRENOVIEMBREDICIEMBREITEMDESCRIPCIONUNDPRESUPUESTOLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMETRADOPRECIOPARCIAL12345678910111213141516171819202122232425272728293031123456789101112131415161718192021222324252627282930311234567891011121314151617181920212223242526272829301234567891011121314151617181920212223242526272829303112345678910111213141516171819202122232425262728293012345678910111213141516171819202122232425262728293031

01.01.00OBRAS PROVISIONALESGLB--6,773.165,648.16375.00375.0053.13159.386613.785

01.02.00SEGURIDAD Y SALUDGLB--16,862.777,866.875,386.821,804.54451.141353.4115509.3575

01.03.00TRABAJOS PRELIMINARESGLB--95,190.6884,427.923,833.201,217.01304.25912.7694277.9225

01.04.00VEREDAS DE CONCRETO DE PIEDRA LAVADA COLOREADOGLB--242,370.4001.04.01MOVIMIENTO DE TIERRAS94,957.2756,974.3632,931.17

01.04.02CONCRETO SIMPLE147,413.135,224.80135,592.87

01.05.00JARDINERASGLB13,688.646,844.321,711.085133.248,555.40

01.06.00OTROSGLB8,363.444,784.902470.90

01.07.00BERMAS DE ADOQUINGLB--333,749.6701.07.01MOVIMIENTO DE TIERRAS35,334.8517,667.424,416.853312.64259937.92750

01.07.02ADOQUINADO EN BERMAS298,414.8251,016.23105,844.9423,510.1829510.8788532.61249117.13

01.08.00PAVIMENTACIONGLB--47,396.1023,698.055,924.524443.38513330.155

01.09.00PAVIMENTO EN VIAGLB--250,987.511,870.38249117.13001.10.00SEALIZACIONGLB21,831.5221831.5221831.5201.11.00PORTICO DE INGRESO DE BIENVENIDAGLB24,452.8101.11.01MOVIMIENTO DE TIERRAS966.70738.70228.0001.11.02OBRAS DE CONCRETO SIMPLE282.79282.7901.11.03OBRAS DE CONCRETO ARMADO23,203.3214,559.63926.752780.24

01.12.00CARPINTERIA METALICAGLB5,964.971840.005508.33

01.13.00VARIOSGLB16,649.5316,649.53

01.14.00INSTALACIONES ELECTRICASGLB9,133.959,133.95

01.15.00MITIGACION DE IMPACTO AMBIENTALGLB4,500.001125.001125.001125.00508.06616.941125.00

01.16.00EDUCACION VIALGLB4,000.001000.001000.001000.00451.61548.391000.00

COSTO DIRECTO1,101,915.15162,267.11292,991.80130,650.5724,469.85656,568.8046,189.47426,505.18GASTOS GENERALES (10.20%)112,395.3516,551.2529,885.1613,326.362,495.924,711.3343,503.53UTILIDAD (8.50%)93,662.7913,792.7024,904.3011,105.302,079.943,926.1036,252.94SUB TOTAL1,307,973.29192,611.06347,781.26155,082.2329,045.7154,826.90506,261.65I.G.V(18%)235,435.1934,669.9962,600.6327,914.805,228.239,868.8491,127.10PRESUPUESTO DE OBRA1,543,408.48227,281.05410,381.89182,997.0334,273.9464,695.74597,388.75

% AVANCE MENSUAL14.73%26.59%11.86%2.22%4.19%38.71%% AVANCE ACUMULADO14.73%41.32%53.17%55.39%59.58%98.29%