ID Task Name Duration Start Finish Predecessors
1 Semnalizarea locului de munca 0.5 hrs Mon 1/12/15 Mon 1/12/152 Curatarea portiunii uzate 0.5 hrs Mon 1/12/15 Mon 1/12/15 13 Incarcarea efectiva a uzurii 1 hr Mon 1/12/15 Mon 1/12/15 24 Curatarea finala a sudurii 0.5 hrs Mon 1/12/15 Mon 1/12/15 35 Polizare 0.5 hrs Mon 1/12/15 Mon 1/12/15 46 Control final 0.5 hrs Mon 1/12/15 Mon 1/12/15 57 Curatenie finala la punctul de lucru 0.5 hrs Mon 1/12/15 Mon 1/12/15 6
0 15 30 45 0 15 30 45 0 15 30 45Sat Jan 3, 8 AM Sat Jan 3, 9 AM Sat Jan 3, 10 AM S
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: Proiect Ciontea MihaiDate: Tue 1/13/15