Dibbin HE 100MW

Embed Size (px)

Citation preview

  • 8/14/2019 Dibbin HE 100MW

    1/115

    100 MW DIBBIN H.E. PROJECTARUNACHAL PRADESH

    Preliminary Feasibility Report

    July 2004

    Government of India

    Ministry of PowerCentral Electricity Authority

    Consultant :

  • 8/14/2019 Dibbin HE 100MW

    2/115

    ISO 9001-2000

    50,000 MW HYDROELECTRIC INITIATIVES

    100 MW DIBBIN H.E. PROJECTARUNACHAL PRADESH

    Preliminary Feasibility Report

    July 2004

    North Eastern Electric Power Corporation Ltd.

    (A Government of India Enterprise)

    Government of India

    Ministry of PowerCentral Electricity Authority

    Consultant :

  • 8/14/2019 Dibbin HE 100MW

    3/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative i

    FOREWORD ......................................................................................................... ..................................................... 1

    SALIENT FEATURES .......................................................................................... .................................................... 2CHAPTER I ......................................................................................... ...........................EXECUTIVE SUMMARY

    1.1 INTRODUCTION........... ............................................................................................................ ................. 5

    1.2 SCOPE OF WORK................ ..................................................................................................... ................. 6

    1.3 HYDROLOGY ......................................................................................................... .................................... 6

    1.4 POWER POTENTIAL STUDIES...................................................................................... ........................ 6

    1.5 POWER EVACUATION ASPECTS..... ................................................................................................. ... 7

    1.6 ENVIRONMENTAL ASPECTS................................................................................................. ............... 7

    1.8 FINANCIAL ASPECTS............................................................................................... ............................... 8

    1.9 CONCLUSIONS ........................................................................................ .................................................. 8

    CHAPTER II................................................................................................................PROJECT BACKGROUND

    2.1 ARUNACHAL PRADESH .......................................................................................................... ............. 10

    2.2 THE RIVER SYSTEM................................................................................................. ............................. 11

    2.3 THE PROJECT...................... .................................................................................................... ................ 12

    2.4 POWER SCENARIO ................................................................................................... ............................. 12

    2.5 NECESSITY OF THE PROJECT ............................................................................................ ............... 14

    2.6 INFRASTRUCTURE ................................................................................................... ............................. 15

    2.7 PROSPECTS AND PROBLEMS................... .......................................................................................... 16

    CHAPTER III ........................................................................................ ........................................PROJECT AREA

    3.1 DESCRIPTION OF PROJECT INCLUDING RIVER SYSTEM.............. ......................................... 19

    3.2 SOCIO ECONOMIC AND OTHER ASPECTS ................................................................................. 22

    CHAPTER IV.....................................................................................TOPOGRAPHICAL & GEOTECHNICAL

    4.1 INTRODUCTION........... .............................................................................................. ............................. 29

    4.2 LOCATION .................................................................................................. .............................................. 29

    4.3 GEOMORPHOLOGY/PHYSIOGRAPHY ........................................................................................... . 29

    4.4 REGIONAL GEOLOGY OF EAST KAMENG DISTRICT ............................................................... 30

    4.5 TECTONICS ................................................................................................... ........................................... 32

    4.6 NEOTECTONICS, SEISMICITY & EARTHQUAKES ...................................................................... 34

    4.7 SEISMICITY......... ........................................................................................................ ............................. 34

    4.8 GEOTECHNICAL APPRAISAL ............................................................................................. ............... 34

    4.9 CONSTRUCTION MATERIALS ........................................................................................................... 35

    4.10 CONCLUSIONS AND RECOMMENDATIONS .................................................................................. 36

    Table of Contents

  • 8/14/2019 Dibbin HE 100MW

    4/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative ii

    CHAPTER V ............................................................................................... ....................................... HYDROLOGY

    5.1 GENERAL .................................................................................................... .............................................. 39

    5.2 BASIN CHARACTERISTICS ...................................................................................................... ........... 395.3 METEOROLOGICAL PROPERTIES OF KAMENG BASIN........................................................... 40

    5.4 PROJECT PROPOSAL .......................................................................................... .................................. 40

    5.5 WATER AVAILABILITY STUDIES .............................................................................................. ....... 40

    5.6 METHODOLOGY................................................................ ..................................................................... 43

    5.7 DESIGN FLOOD STUDIES .......................................................................................... ............................. 44

    CHAPTER VI...................................................................................... CONCEPTUAL LAYOUT & PLANNING

    6.1 INTRODUCTION........... .............................................................................................. ............................. 52

    6.2 RIVER DIVERSION WORK........................................................................................................ ........... 52

    6.3 DIVERSION DAM................................................................................... .................................................. 54

    6.4 DESILTING TANK...................................................................................................... ............................. 57

    6.5 INTAKE CHANNEL AND POWER INTAKE.................................... .................................................. 58

    6.6 HEAD RACE TUNNEL .......................................................................................... .................................. 58

    6.7 SURGE SHAFT.................................... .................................................................................................. .... 59

    6.8 PENSTOCKS........................................................... ................................................................................... 60

    6.9 POWER HOUSE..................................................... ................................................................................... 60

    6.10 ELECTRO-MECHANICAL EQUIPMENT ......................................................................................... . 61

    6.11 TAIL RACE CHANNEL ............................................................................................. ............................. 61

    6.12 FURTHER STUDIES ................................................................................................... ............................. 61

    CHAPTER VII......................................................................................................................POWER POTENTIAL

    7.1 INTRODUCTION........... ............................................................................................................ ............... 64

    7.2 FIXATION OF FULL RESERVOIR LEVEL ............................................................................ ........... 64

    7.3 FIXATION OF MINIMUM DRAW DOWN LEVEL........................................................................... 64

    7.4 FIXATION OF TAIL WATER LEVEL .................................................................................. ............... 65

    7.5 DISCHARGE DATA .................................................................................................... ............................. 65

    7.6 OPERATING HEAD................................................................................... .............................................. 66

    7.7 EFFICIENCY .................................................................................................... ......................................... 66

    7.8 INSTALLED CAPACITY ........................................................................................... ............................. 66

    7.9 ENERGY GENERATION ........................................................................................... ............................. 67

    7.10 UNIT SIZE.................................................................................................. ................................................ 67

    7.11 SUMMARY OF RESULTS ......................................................................................... ............................. 67

    7.12 FURTHER STUDIES ................................................................................................... ............................. 68

  • 8/14/2019 Dibbin HE 100MW

    5/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative iii

    CHAPTER VIII ................................................................................... ............................. POWER EVACUATION

    8.1 APPRAISAL OF EXISTING POWER EVACUATION FACILITIES.............................................. 70

    8.2 PROPOSED EVACUATION SYSTEM TO NEAREST FACILITY................................................. . 70

    CHAPTER IX................................................................................................................ENVIRONMENT ASPECT9.1 GENERAL INFORMATION............................................................................................. ...................... 74

    9.2 SUBMERGENCE AREA...................................................................................... .................................... 74

    9.3 RIVER SYSTEM .......................................................................................................... ............................. 75

    9.4 SEISMICITY......... ........................................................................................................ ............................. 75

    9.5 EXISTING LANDUSE/LANDCOVER AROUND THE PROPOSED DAM SITE .......................... 76

    9.6 FOREST TYPES IN THE VICINITY OF PROJECT AREA ............................................................. 77

    9.7 FAUNAL ELEMENTS AROUND THE PROJECT AREA................................................................. 79

    9.8 EXISTENCE OF ANY PROTECTED AREA/ARCHAEOLOGICAL SITES..... ............................. 79

    9.9 HUMAN SETTLEMENT ............................................................................................ ............................. 80

    9.10 RELIEF AND REHABILITATION.................................................................................. ...................... 80

    9.11 RECOMMENDATIONS AND MITIGATIVE MEAUSRES............................................................... 80

    CHAPTER X ............................................................................................... ............................ INFRASTRUCTURE

    10.1 THE PROJECT........ ..................................................................................................... ............................. 81

    10.2 ACCESS ROADS .......................................................................................................... ............................. 82

    10.3 IMPROVEMENT OF EXISTING STATE HIGHWAY ROAD.......................................................... 82

    10.4 CONSTRUCTION OF NEW ROADS ................................................................................................... . 83

    10.5 CONSTRUCTION FACILITIES................................................................................ ............................. 83

    10.6 PROJECT ROADS ......................................................................................... ........................................... 83

    10.7 PROJECT HEADQUARTERS, OFFICES AND COLONIES ............................................................ 84

    10.8 EXPLOSIVE MAGAZINE ........................................................................................................ ............... 85

    10.9 SCHOOL, PRIMARY HEALTH CARE, BANK, PETROL PUMP................................................... 85

    10.10 CONSTRUCTION POWER........................ ............................................................................................. 86

    10.11 TELE-COMMUNICATION.............................................................. ....................................................... 87

    CHAPTER XI.............................................................................CONSTRUCTION PLANNING & SCHEDULE

    11.1 INTRODUCTION................. ...................................................................................................... ............... 90

    11.2 BASIS OF STUDY ........................................................................................................ ............................. 9011.3 MAJOR COMPONENT .............................................................................................. ............................. 90

    11.4 MATERIAL SOURCES......................................... ................................................................................... 91

    11.5 BASIC CONSIDERATIONS........................................................................................................... ......... 91

    11.6 CONSTRUCTION CONTRACTS........................................................................................... ................ 91

    11.7 SCHEDULE OF WORKING HOURS................. ................................................................................... 92

    11.8 CONSTRUCTION PERIOD ..................................................................................................... ............... 93

    11.9 STAGE I ACTIVITIES................................................................................... .......................................... 93

  • 8/14/2019 Dibbin HE 100MW

    6/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative iv

    11.10 STAGE II ACTIVITIES .............................................................................................. ............................. 93

    11.11 STAGE III ACTIVITIES........ ................................................................................................... ............... 94

    11.12 RIVER DIVERSION WORK........................................................................................................ ........... 94

    11.13 DIVERSION DAM................................................................................................. .................................... 9411.14 HEAD RACE TUNNEL .............................................................................................. .............................. 95

    11.15 SURGE SHAFT............................... .......................................................................................................... . 95

    11.17 PENSTOCKS............................................................... ............................................................................... 96

    11.18 POWER HOUSE.................................................. ...................................................................................... 96

    11.19 ELECTRO-MECHANICAL WORKS.................................................................................................... 96

    11.20 SWITCHYARD...................................................................................................... .................................... 96

    CHAPTER XII.............................................................................................................................COST ESTIMATE

    12.1 INTRODUCTION................. ...................................................................................................... ............... 98

    12.2 COST ESTIMATE................ ................................................................................................. .................... 98

    CHAPTER XIII .......................................................................................... ...............ECONOMIC EVALUATION

    13.1 GENERAL .................................................................................................. .............................................. 100

    13.2 PROJECT BENEFITS ................................................................................................. ........................... 100

    13.3 INPUTS DATA AND ASSUMPTIONS..................................................... ............................................ 100

    13.4 ESTIMATED COST AND PHASING .................................................................................................. 101

    13.5 DEPRECIATION........................................ ............................................................................................. 101

    13.6 LOAN AMORTIZATION ........................................................................................... ........................... 102

    13.7 WORKING CAPITAL REQUIREMENTS.................................................................................... ...... 102

    13.8 ENERGY SALE PRICE.............................................................. ............................................................ 102

    13.9 ESTIMATES OF WORKING RESULTS ............................................................................................ 103

    13.10 INTERNAL RATE OF RETURN (IRR).................................................................................... ........... 103

    13.11 DEBT SERVICE COVERAGE RATIO (DSCR)................................................................................. 103

    13.12 PAYBACK PERIOD ............................................................................................... ................................ 104

    13.13 CONCLUSION................................... ...................................................................................................... 104

  • 8/14/2019 Dibbin HE 100MW

    7/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative v

    CHAPTER I ......................................................................................... ...........................EXECUTIVE SUMMARY

    1.1 A vicinity map

    1.2 A conceptual layout map

    CHAPTER IV.....................................................................................TOPOGRAPHICAL & GEOTECHNICAL

    4.1 Geological Map of East Kameng District

    CHAPTER V ............................................................................................... ....................................... HYDROLOGY

    ANNEXURES

    5.1 Ten Daily Flow Series-Bichom

    5.2 Ten Daily Flow Series - Dibbin

    5.3 Calculation of Equivalent Slope5.4 Details of SUG Parameters

    5.5 Calculation of Effective Rainfall Values

    5.6 Details of Rainfall Excess5.7 Convolution of Design Flood Hydrograph

    5.8 Copy of Comments on Hydrology Chapter and their replies

    FIGURES

    5.1 Synthetic Unit Hydrograph

    5.2 100 year return period flood

    PLATES

    I Index Map

    II Isohyetal MapIII Project Component Layout

    IV Raingauge and Discharge Sites

    CHAPTER VI...................................................................................... CONCEPTUAL LAYOUT & PLANNING

    Drawing No. : NP-PFR-DB-601 Conceptual Layout

    Drawing No. : NP-PFR-DB-602 Upstream view of Dam

    Drawing No. : NP-PFR-DB-603 Details of Desilting Chamber

    Drawing No. : NP-PFR-DB-604 Details of Intake ChannelDrawing No. : NP-PFR-DB-605 Details of Water Conductor system

    Drawing No. : NP-PFR-DB-606 Cross Section of Tunnel

    Drawing No. : NP-PFR-DB-607 Details of Surge ShaftDrawing No. : NP-PFR-DB-608 Cross Section of Turbine Hall

    Drawing No. : NP-PFR-DB-609 Cross Section of Power House

    Drawing No. : NP-PFR-DB-610 Cross Section of Coffer Dams

    Annexure 6.1 Copy of the comments received from CWC and replies

    CHAPTER VII......................................................................................................................POWER POTENTIAL

    Annexure 7.1 Copy of Comments and their repliesTables 7.1-7.19 Power Potential Studies

    List of Annexures

  • 8/14/2019 Dibbin HE 100MW

    8/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative vi

    CHAPTER VIII ................................................................................... ............................. POWER EVACUATION

    Annexure 8.1 Power Map of North Eastern Region

    Annexure 8.2 Single Line Diagram

    Annexure 8.3 Power Evacuation systemAnnexure 8.4 Proposed Switchyard Layout

    Annexure 8.5 Copy of the comments received on Power Evacuation

    CHAPTER IX................................................................................................................ENVIRONMENT ASPECT

    Annexure 9.1 Drainage Map of Tizu River of the Bishum Chu river of Dibbin Project

    Annexure 9.2 Map showing Submergence Area due to reservoir of proposed projectAnnexure 9.3 Seismic zoning map of North East and Eastern Part of India showing

    location of the proposed Dibbin HE scheme

    Annexure 9.4 IRS-ID LISS III Scene of 7 km Radius area of the proposed project

    Annexure 9.5 IRS-ID PAN Scene of 7 km Radius area of the proposed projectAnnexure 9.6 Landuse/Landcover Map of Submergence Area

    CHAPTER XI.............................................................................CONSTRUCTION PLANNING & SCHEDULE

    11.1 Construction Schedule

    CHAPTER XII.............................................................................................................................COST ESTIMATE

    12.1 Cost Abstract

    CHAPTER XIII .......................................................................................... ...............ECONOMIC EVALUATION

    Annexure 13.1 Inputs and Assumptions

    Annexure 13.1A Year Wise Allocation of Project Cost

    Annexure 13.2 General Breakdown of Scheme Cost

    Annexure 13.3 Calculation of Interest During Construction (IDC)

    Annexure 13.4 Calculation Depreciation including Advance Against Deprecation

    Annexure 13.5 Loan AmortizationAnnexure 13.6 Calculation of Working Capital Requirements

    Annexure 13.7 Calculation of Sale Price of Energy

    Annexure 13.8 Estimates of Working ResultsAnnexure 13.9 Internal Rate of Return (Project)

    Annexure 13.10 Debt Services Coverage Ratio

    Annexure 13.11 Payback Period

    List of Annexures & Drawings

  • 8/14/2019 Dibbin HE 100MW

    9/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 1

    FOREWORDWith the objective of accelerating capacity addition and developing untapped hydro power potential

    in India in a phased and systematic manner, the Central Electricity Authority (CEA) had conductedRanking Studies, based on inter-se-priority for their development, so as to have a shelf of prioritized

    schemes. A noble initiative towards development of such potential has been initiated by the Honble

    Prime Minister of India, on May 24, 2003 at Vigyan Bhawan, by launching the 50,000 MW hydro

    electric initiative, to be taken up under the aegis of the Ministry of Power.

    North Eastern Electric Power Corporation Ltd. (NEEPCO) has been entrusted by CEA to prepare

    the Pre-Feasibility Reports for 18 hydro electric projects with an installed capacity of 4915 MW in

    the States of Arunachal Pradesh and Nagaland.

    In the first two stages of this ambitious programme, the Design & Engineering group ofNEEPCOhas prepared the Pre-Feasibility Reports of 12 projects with an installed capacity of 4100 MW. ThePre-Feasibility Reports of these twelve Hydro Electric Projects were submitted to CEA. Pre-

    Feasibility studies of additional three projects in the Kameng river valley have now been taken up

    by NEEPCO. The enclosed Pre-Feasibility report of Dibbin Hydro Electric Project (100 MW) has

    been estimated at a cost of 371.52Crores (including IDC) at September 2003 price level, with a first

    year tariff of Rs.2.53/kWh.

    I am highly indebted and thankful to Honble Union Minister of Power; Honble Union Minister of

    State for Power; Shri R.V. Shahi, Secretary (Power), Government of India; and Shri H.L. Bajaj,

    Chairman, CEA for the opportunity given to NEEPCO for undertaking the task and being a part of

    the Mission 2012: Power for all. I also thank Messrs Premier Mott MacDonald for rendering

    necessary support service to NEEPCO in preparation of the reports.

    New Delhi S.C. SharmaJuly 2004 Chairman & Managing Director

  • 8/14/2019 Dibbin HE 100MW

    10/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 2

    SALIENT FEATURES

    LOCATION

    State Arunachal Pradesh

    River Bichom, tributary of Kameng riverLocation of dam

    Longitude 92 31' 16" E

    Latitude 27 27' 00" N

    Access to the project By road from Tezpur (Assam) via Balipara Bhalukpongand Rupa

    Nearest Rail head Bhalukpong

    Airport Tezpur

    HYDROLOGY

    Catchment area at Dam Site 607 sq.kmMaximum average discharge at dam site 143.54 cumecs

    Minimum average discharge at dam site 7.58 cumecs

    DIVERSION DAM

    Type Gated Dam

    Full reservoir level (FRL) 1185 m

    Minimum draw down level (MDDL) 1179 m

    Deepest River Bed Level 1160 m

    Total length at top of dam 143 m

    SPILLWAY

    Type Gated spillway

    Width of spillway block 78 m

    No. of bays 5 bays

    Crest level of spillway 1171 m

    Spillway gates 5 nos. 11.1m x 14 m

    Energy dissipation system Stilling basin

    Design flood 3740

    SUBMERGENCE

    Villages submerged Nil

    Area submerged 6.4 Ha

    RESERVOIR

    Gross storage 0.26 Mcum

    Live storage 0.21 Mcum

  • 8/14/2019 Dibbin HE 100MW

    11/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 3

    INTAKE

    Invert level of intake 1171 m

    Intake gate size 5 m x 5 m

    Trash rack Semi circularHEAD RACE TUNNEL

    Size 5.0 m

    Shape Modified horse shoe type section

    Velocity 4.03 m/sec

    Length 4430 m

    SURGE SHAFT

    Type Simple

    Diameter 13.7 m

    Height 60.33 m

    Bottom Elevation 1135.67 m

    POWER HOUSE

    Installed Capacity 100 MW

    Units 2 x 50 MW

    Type of Turbine Francis

    Design head 150 m

    Annual Design Energy (90% dependable

    year)335.72 GWh

    Annual energy in 90% year on 95%

    machine availability

    332.00 GWh

    Minimum TWL 1020 m

    FINANCIAL ASPECT

    Total Project Cost Rs. 371.52 crores

    Tariff for 1st year

    After considering 12% free power

    Without considering 12% free power

    Rs. 2.53 per kWh

    Rs. 2.23 per kWh

    Levelised tariff for 35 years

    After considering 12% free power

    Without considering 12% free power

    Rs. 2.04 per kWh

    Rs. 1.79 per kWhCost per MW installed Rs. 3.71 Crores

    CONSTRUCTION PERIOD 4 years (excluding 30 months of Pre-constructionactivities)

  • 8/14/2019 Dibbin HE 100MW

    12/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 4

    CHAPTER-I

    Executive Summary

  • 8/14/2019 Dibbin HE 100MW

    13/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 5

    1.1 INTRODUCTION

    1.1.1 Dibbin HE Project is proposed on river Bichom, in its upper reaches, which is a

    tributary of Kameng river in west District. The installed capacity of the project would

    be 100 MW (2x50 MW) and the annual energy generation from the project in a 90%

    dependable year is assessed as 335.72 MU.The levelised tariff at May 2004 price level

    would be Rs. 2.53 per kWh with 12% free power and Rs 2.23 per kWh without 12%

    free power. The scheme envisages construction of a gated dam 27 m high located just

    downstream of the confluence of Ditya Bung river with Bichom river with its co-

    ordinates at 9231'16"E and 2727'00"N to divert the river water Bichom into the water

    conductor system.

    1.1.2 The water conductor system shall comprise an intake channel, a surface desilting

    chamber, a head race tunnel, a surge shaft, pressure shaft and penstocks.

    1.1.3 The dam site of Dibbin H.E. Project is located in the upper reach of river Bichom

    where the river bed level is EL 1160 m just downstream of confluence of Bichom Chu

    with Difya Ru with its co-ordinates at 9231' 16" E and 2727'00" N. The dam site is

    approachable through PWD road from Rupa upto Nafra and then a foot path of about

    15 km upto Dibbin village. Power house site is located near Nachibin villagewith its

    co-ordinates at 27024'36"N and 92

    031'12"E. Nafra is connected to Rupa town by a

    PWD road. UptoRupa town the road from Balipara is maintained by Border Roads

    Task Force (BRTF) of the Government of India. Balipara, in turn is connected to

    Tezpur on the National Highway No. 52. Tezpur which is the nearest airport for Dibbin

    H.E. Project, is about 25 km from Balipara.

    1.2 SCOPE OF THE PROJECT

    1.2.1 DibbinHE Project envisages construction of:

    A gated dam 27 m high located just downstream of the confluence of Ditya Bung

    river with Bichom river.The length of the dam will be 143 mconsisting of 78 m of

    overflow section and 32 m of non-overflow section on the left bank and 33 m on the

    right bank. The reservoir upstream of dam will have a live storage of 0.21 Mcum to

    enable operation of one unit for peaking for 2.0 hours during morning as well as

    evening hours of non-monsoon period.

  • 8/14/2019 Dibbin HE 100MW

    14/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 6

    A spillway with 5 bays of 11.1 m clear opening each and 4.5 m wide piers

    controlled by 5 nos. radial gates each of size 11.1 m x 14 m.

    An energy dissipation arrangement of stilling basin type of length 97 m.

    A desilting tank 100 m long and 135 m wide divided into two compartments. A head race tunnel 5.0 m diameter and 4.43 km long.

    A surge shaft at the outlet of the head race tunnel 13.7 m diameter and 60.33 m

    height.

    Two pressure shafts 3 m diameter and 50 m long and thereafter 2 surface penstocks

    of 3.0 m diameter and 103 m length.

    A surface power house located on the left bank of Bichom having installation of 2

    units of 50 MW each with Francis type turbine designed for a net head of 150 m .

    A short length of tail race channel to discharge the tail waters of Dibbin HE project

    into Ditch Bru.

    A vicinity map showing 13 projects in Kameng basin is placed at Annexure 1.1 and a

    conceptual layout map at Annexure 1.2.

    1.3 HYDROLOGY

    The catchment area at Dibbin HE project dam site is a 607 sq. km. Dibbin project falls

    in Bichom sub-basin. Within Dibbin project area, there is no hydro meteorological

    network. However a G&D site is available at Bichom dam site and at this G&D site

    Bichom flow series is available for 13 years. Catchment area of Bichom river at

    Bichom G&D site is 2277 sq km. Therefore flow series for Dibbin HE project has been

    arrived at on proportionate catchment area basis and is used for the PFR purpose of this

    hydro electric project. The Bichom series has been transformed into 10 daily discharge

    series for Dibbin dam site on catchment area proportionate basis and taking into

    account rainfall variability 100 year design flood has been considered for design of

    diversion structure. The probable 100 year flood works out to 3740 cumecs. The design

    flood values have been estimated by Hydro-meteorological approach. The study needs

    to be reviewed at the DPR stage when site specific short term rainfall-runoff data as

    well as discharge data would become available.

    1.4 POWER POTENTIAL STUDIES

    1.4.1 The annual energy generation in 90% and 50% dependable years has been computed

    using 10-daily discharge series generated for Dibbin HE project diversion dam site.

  • 8/14/2019 Dibbin HE 100MW

    15/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 7

    Annual energies were calculated for different installed capacities and the optimum

    capacity was determined as 100 MW for this scheme. The annual energy generation in

    a 90% dependable year would be 335.72 MU as detailed below:

    Particulars 90% Dependable Year

    Annual Generation

    Annual Energy Generation (GWh) 335.72

    Annual Load Factor (%) 38.32

    Generation during Lean Flow Season (Nov-Apr)

    Power output (MW) 19.95

    Lean Load Factor (%) 19.95

    1.4.2 A live storage of 0.21 Mcum has been provided in the pondage to enable operation of

    two unit of the power house for peaking for 2.0 hours during morning hours and 2.0

    hours during evening hours during non-monsoon period. The power station will operate

    as a base load station during the monsoon period.

    1.5 POWER EVACUATION

    The power generated at Dibbin HE project will be evacuated through LILO

    arrangement of already approved 220 kV double circuit lines from Utung to the

    switchyard of Kameng HE project (under construction). This power will be transmitted

    to the Bhalukpong pooling point on 400 kV double circuit lines, which in turn, will be

    transmitted to the National Grid.

    1.6 ENVIRONMENTAL ASPECTS

    1.6.1 The predominant landuse in the vicinity of project area is forest. The dense forests

    constitute more than 48% of the total area and area under open forest and scrubs cover

    about 16% and 13% area, respectively. Agricultural and settlements landuse/landcover

    accounts for than 16% of the study area. Shifting cultivation also covers more than 7%

    of the project area.

    1.6.2 The proposed diversion structure is 27 m high, the proposed reservoir would lead to

    submergence of only 6.4 ha of land, which is comprised mainly of barren waste land

    and degraded forests on the left bank slopes and open forest on the right bank hence it

    would not lead to the submergence of any human habitation.

  • 8/14/2019 Dibbin HE 100MW

    16/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 8

    1.7 ESTIMATES OF THE COST

    The project is estimated to cost Rs. 371.52 crores including IDC at May 2004 price

    level. The preliminary cost estimate of the project has been prepared as per guidelines

    of CEA/CWC. The break down of the cost estimates is given below:

    Civil works 216.22 crores

    E&M works 104.62 crores

    Sub-Total (Generation) 320.84 crores

    Transmission works Not included

    Total (Hard Cost) 320.84 crores

    Interest During Construction 50.68 crores

    Grand Total 371.52 crores

    1.8 FINANCIAL ASPECT

    Dibbin HE project, with an estimated cost of Rs. 371.52 crores (including IDC of 50.68

    crores) and design energy of 355.72 GWh in a 90% dependable year is proposed to be

    completed in a period of 4 years (excluding 30 months of pre-construction activities).

    The tariff has been worked out considering a debt-equity ratio of 70:30, 16% return on

    equity, and annual interest rate on loan at 10%. The tariff at the power house busbars

    for the first year has been worked out to Rs. 2.53/kWh (with 12% free power) and Rs.

    2.23/kWh (without free power) and levelised tariff for 35 years have been worked outto Rs. 2.04 / kWh (with 12% free power) and Rs 1.79/kWh (without 12% free power).

    1.9 CONCLUSION

    Dibbin Hydro Electric Project involves simple civil works and could be completed in

    4 years (excluding 30 months of pre-construction activities). The project would afford

    design energy of 335.72 GWh at the power house busbars in a 90% dependable year.

    The cost per MW installed work out Rs. 3.71 crores. The Preliminary Feasibility Report

    indicates that the scheme merit consideration for taking up detailed Survey,

    Investigation and preparation of DPR.

  • 8/14/2019 Dibbin HE 100MW

    17/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 9

    CHAPTER - II

    Project Background

  • 8/14/2019 Dibbin HE 100MW

    18/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 10

    2.1 ARUNACHAL PRADESH

    2.1.1 Arunachal Pradesh the Land of the Rising Sun with an area of 83,743 sq. km. is the

    largest state in the North eastern region sharing international boundaries with Bhutan inthe west, China in the north and Myanmar in the east. The states of Assam and

    Nagaland flank its Southern and South eastern borders. Forest covers about 82% area of

    the State and numerous turbulent streams, roaring rivers, deep gorges, lofty mountains,

    snow clad peaks and rich diversity of flora and fauna characterize the landscape. The

    climate varies from sub-tropical in the south to temperate and alpine in the north with

    large areas experiencing snowfalls during winter. The heights of the mountain peaks

    vary, the highest peak being Kangte (7090 above MSL) in West Kameng District. The

    major rivers that drain the area with their numerous tributaries are Siang, Kameng,

    Subansiri, Kamla, Lohit, Dibang, Noa - Dehing and Tirap. The State is administratively

    divided into 15 districts. The state capital is at Itanagar at an altitude of 530 m above

    MSL. It is named after the brick fort built by Ahom King of Assam in the 14th

    century.

    2.1.2 A wide variety of altitudinal gradients and climatic conditions have given rise to varied

    eco-systems which form the habitat of diverse plant wealth and wild life in the State.

    Due to its high species diversity, the region has been identified as a global hot spot for

    bio-diversity conservation. The pre-dominant forest types occurring in the state are

    Tropical Semi Evergreen, Tropical Wet Evergreen, Sub-tropical, Pine, Temperate and

    Sub-Alpine / Alpine Forests. There are also degraded forests and grass lands.

  • 8/14/2019 Dibbin HE 100MW

    19/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 11

    2.1.3 The State harbors a rich variety of wildlife which includes four major cats namely tiger,

    leopard clouded leopard and snow leopard. The region is home to seven species of

    primates, large mammals like elephants, gaur and wild buffalo. High altitude animals

    include musk deer, bharal, Himalayan black bear, red panda etc. The State animal is

    Mithun (Bos Frontails) existing both in wild and semi-domesticated form. This animal

    has religious significance and intimate relation with socio-cultural life of the people.

    The bird fauna of the State include more than 500 species. This is the richest state for

    pheasants with some species found at different altitudes. The rivers contain a wealth of

    fishes. The State also abounds in a variety of reptiles and amphibians.

    2.1.4 The forests of the State cover about 82% of the States geographical area of which 960

    sq.km. have been set aside as protected area comprising two national parks (Namdapa

    and Mouling) and nine wildlife sanctuaries.

    2.1.5 The population of Arunachal Pradesh is 1091117 (2001 census). The people are of

    Mongoloid stock with heritage of arts and crafts, enchanting folk songs with their own

    distinct and diverse culture, dialects and lifestyles. There are 20 major tribes in the

    State namely Adi, Nyishi, Apatani, Bugun, Galo, Hrusso, Koro, Meyor, Monpa, Tagin,

    Mishmi, Sajolang, Sartang, Tai Khamti, Yobin, Singpho, Sherduken, Khamba,

    Tangshang and Memba. The State has a literacy rate of 54.74%.

    2.2 THE RIVER SYSTEM

    2.2.1 The Kameng river which is also known as Jia - Bhareli in its lower reaches originates in

    the upper Himalayan ranges at an elevation of about 4800 m. The river has a total

    length of about 198 km. and drains about 12,500 sq. km. of catchment area into the

    Brahmaputra river about 10 km upstream of Tezpur town in Assam. During the course

    of its long journey it is joined by several major tributaries namely Bichom, Digien,

    Tenga, Pachuk and Pakke which originate at high altitudes. Map of Kameng River

    Basin is attached as Annexure 8.2.

    2.2.2 The rainfall in the basin is quite high and varies from about 1000 mm in higher reaches

    to about 5750 mm in the foot hills spread over 8-9 months excepting the dry days in

    winter. The upper regions also receive precipitation from snow clad mountains which

    contribute to the river flow during lean period. On this account fairly high perennial

    discharge continues to be available in the river all the year around. Such a favorable

    river discharge pattern and the fact that a total fall of more than 3000 m is available in

  • 8/14/2019 Dibbin HE 100MW

    20/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 12

    the river system make it very attractive for developing a series of hydro-electric power

    stations on the main river and its tributaries. A 600 MW hydro electric project is

    currently being constructed by NEEPCO which will bring waters from Bichom and

    Tenga rivers through a tunnel to a power station at Kimi with tail race discharging into

    Kameng river.

    2.3 THE PROJECT

    2.3.1 Dibbin H.E. Project is located in the upper reach of river Bichom which is a major

    tributary of Kameng river. It envisages construction of a gated dam 21m high near

    village Dibbin where the river bed level is at EL 1160 m and is situated in West

    Kameng District. The waters of river Bichom will be diverted through a tunnel to a

    surface power house on the right bank of Bichom river near Nachibin village. Installed

    capacity planned for the power house is 100 MW.

    2.3.2 The proposed reservoir would lead to submergence of 6.4 ha of land which is mainly

    under barren waste land and degraded forests / scrub. Very little submergence area is

    under dense forest.

    2.3.3 The human settlements in the project area are scattered.

    2.3.4 There are no monuments of archeological or national importance which would be

    affected by project activities directly or indirectly.

    2.4 POWER SCENARIO

    2.4.1 The per capita power consumption of Arunachal Pradesh is below 100 kWh as

    compared to the national average of 373 kWh. The State plans to harness its enormous

    natural resources like forests and hydro power and exploit its mineral wealth to usher in

    an era of economic development and raise the per capita electricity consumption to 500

    kWh by the end of Eleventh Five year Plan period i.e. 2012. The States generating

    capacity was only 32.03 MW hydro and 28.63 MW diesel till now which has increased

    substantially with the completion of 405 MW Ranganadi hydro power project. 600 MW

    Kameng hydro project and 1600 MW Subansiri Project are under construction and

    these projects will provide electricity not only to Arunachal Pradesh and other states in

    the north-eastern region but also to other power starved regions of the country.

  • 8/14/2019 Dibbin HE 100MW

    21/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 13

    Energy and Peak Load Shortages

    7.5

    10.78.6

    19.1

    14.4

    3.1

    7.87.9

    -0.7 -1.6

    13

    -1.6

    -5

    0

    5

    10

    15

    20

    25

    NR WR SR ER NERs Overall

    Supply Shortages Peak Deficit

    2.4.2 The power scenario has therefore to be viewed in the national perspective. According to

    50000 MW Hydropower Initiative of the Ministry of Power, the energy requirement of

    the country in 2002-03 was 5,45,674 MkWh of which only 4,97,589 MkWh were

    available, leaving a shortfall of 8.8%. While the peaking requirement was 81,492 MW,

    a peak of only 71,547 MW could be met leaving a shortage of 12.2%. The regionwise

    shortage of energy and peaking capacity is depicted in the following graph:

    Source: Blue print for Power Sector Development MoP 2001

    2.4.3 Against the present installed generating capacity of 1,07,973 MW, the share of hydro,

    with 26,910 MW capacity, is only 25%. Thermal (coal, gas and diesel) accounts for the

    maximum share of 71% with 76,607 MW. Nuclear capacity is about 2.5% with 2720

    MW and wind 1,736 MW i.e. 1.6%. This is graphically depicted below:

    Source : 50000 MW Hydro-electric

    Initiative May 2003

    Shares in Installed Capacity - March, 2003

    58%

    3% 2%

    1%

    11%

    25%

    Hydro, 26910 MW

    Gas, 11633 MW

    Diesel, 1173 MW

    Wind, 1736 MW

    Nuclear, 2720 MW

    Coal, 63801 MW

  • 8/14/2019 Dibbin HE 100MW

    22/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 14

    2.4.4 Most of the regions of the country are suffering from power shortages leading to

    irregular and unreliable supply. The problem becomes acute during peak hours. Based

    on the projections made in the 16th

    Electric Power Survey, an additional generating

    capacity of over 100,000 MW needs to be added to ensure Power on Demand by

    2012. This, in effect, means doubling the existing capacity which has been created in

    the last half a century in the next ten years. Not only has the capacity to be added but

    also the present hydro-thermal imbalance of 25:75 has to be corrected and brought to

    40:60 to meet the peak load requirements, achieve frequency and voltage stability and

    provide system operating flexibility under changing seasonal and diurnal load pattern.

    For achieving a 40:60 hydro thermal ratio in an installed capacity of around 200,000

    MW the total requirement of hydro capacity will be 80,000 MW which means that

    53,000 MW additional hydro capacity has to be created in the next 10 years.

    2.5 NECESSITY OF THE PROJECT

    2.5.1 According to categorization of schemes by CEA the Category A schemes in different

    river basins all over India total to 7800 MW as shown in the table below:

    River Basin-wise Summary of Categorisation of the Schemes Ranked by CEA

    Category A Category B Category C TotalS.No. River System

    Nos MW Nos MW Nos MW Nos MW

    1. Indus 11 4088 51 8811 17 6080 79 189792. Ganga 20 2023 54 9616 1 600 75 12239

    3. Central Indian 3 283 9 1425 1 186 13 1894

    4. East Flowing 11 1412 26 6469 2 88 39 7969

    5. West Flowing 1 35 10 958 14 1508 25 2501

    6. Brahmaputra 52 7800 97 42574 19 12954 168 63328

    Source: 50000 MW Hydro-electric Initiative May 2003

    2.5.2 The entire Category A schemes needs to be taken up for completion by 2012. Out of

    the above, Arunachal Pradesh has 31 schemes with a total installed capacity of 5047

    MW against which NEEPCO has been allotted 15 schemes with a total installed

    capacity of 3220 MW. There is therefore scope for development of all these projects

    subject to their technical and economic feasibility. NEEPCO has already carried out

    pre-feasibility studies for six projects totaling to 2460 MW and has now taken up

    similar studies for six more projects as per directive of the Government of India.

  • 8/14/2019 Dibbin HE 100MW

    23/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 15

    Construction of 100 MW Dibbin H.E. Project on high priority is justified on the basis

    of pre-feasibility studies carried out by NEEPCO.

    2.6 INFRASTRUCTURE

    2.6.1 Power Evacuation

    A 400 kV sub-station for evacuation of power from Rangnadi project has been

    constructed. Power will be transported to 400 kV Balipara substation already

    constructed by PGCIL from where it will be taken to other regions. A 400 kV

    substation is also planned at Khuppi for transmission of 600 MW power from Kameng

    hydro electric project power to Balipara and onwards to other regions. A power map

    of North-eastern region and Sikkim prepared by PGCI is attached as Annexure 8.1 in

    Chapter VIII. The State government has also taken steps to construct a state grid at 132

    kV covering all the districts and to electrify all villages up to the inter-state and

    international borders. The power evacuation facilities will need to be upgraded and

    augmented substantially as new projects are taken up.

    A number of major hydro electric power stations are planned in the Kameng Valley. As

    only a small portion of the power generated at these stations will be utilized in

    Arunachal Pradesh itself, it will be appropriate to interconnect these stations and take

    the pooled power to Bhalukpong sub-station for being exported to other regions of thecountry. Scheme for evacuation of power from Dibbin HE Project is given in Chapter

    VIII Power Evacuation.

    Communications

    2.6.2 The State has a network of about 15,000 km of roads including border roads for access

    to all areas of the State.

    2.6.3 The dam site of Dibbin H.E. Project is located in the upper reach of river Bichom

    where the river bed level is EL 1160 m just downstream of confluence of Bichom Chu

    with Difya Ru with its co-ordinates at 9231' 16" E and 2727'00" N. The dam site is

    approachable through PWD road from Rupa upto Nafra and then a foot path of about

    15Km upto Dibbin village. Power house site is located near Nachibin village. Nafra is

    connected to Rupa town by a PWD road. UptoRupa town the road from Balipara is

    maintained by Border Roads Task Force (BRTF) of the Government of India. Balipara,

    in turn is connected to Tezpur on the National Highway No. 52. Tezpur which is the

    nearest airport for Dibbin H.E. Project, is about 25 km from Balipara.

  • 8/14/2019 Dibbin HE 100MW

    24/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 16

    2.6.4 The state highway from Rupa to Nafra is metalled and black topped, but considerable

    portion of the road needs improvement. Beyond Nafra, a new road of about 15 Km is

    required to be constructed for movement of mechanized equipment and transport of

    heavy electro-mechanical equipment for Dibbin H.E. Project right upto power house

    site as well as to dam site.

    2.6.5 Telecommunication facilities in the State comprise 94 telephone exchanges, 70 of

    which have STD facilities. In addition 695 PCOs have STD facilities. Internet

    connections are also available.

    2.6.6 Central assistance is being provided for infrastructural development in the State and is

    being utilized for accelerated development.

    2.7 PROSPECTS AND PROBLEMS

    2.7.1 Arunachal Pradesh is very rich in natural resources. The state has a strong base for

    mainstream and downstream industries based on:

    (a) Abundant resources of hydro power potential, biodiversity of rich forests,

    tourism, horticulture and floriculture.

    (b) Access to the large markets in south-east Asian countries if traditional trade

    routes are re-established and developed.

    2.7.2 Rich Natural Resources

    Rich natural resources of the state can be converted into real goods if limitations, which

    the State is confronted with, are overcome. A study commissioned by the State

    Government has listed various limitations to the development. The important ones are:

    (i) Gestation period of the projects is much higher as compared to other States of

    the country.

    (ii) Prolonged rainy season leading to less effective working time per year for

    building infrastructure.

    (iii) Higher cost due to long distance of transportation.

    (iv) Inadequate industrial infrastructure, lack of industrial experience and non-

    availability of technical expertise.

    (v) Reluctance of investors.

    (vi) Prohibitive cost of laying power line for longer distances.

    (vii) Inadequate investment in exploration of untapped natural resources.

  • 8/14/2019 Dibbin HE 100MW

    25/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 17

    2.7.3 The State is fully seized of these problems and has taken various steps to encourage

    investment. The industrial policy encourages establishment of industries in the private

    and cooperative sectors for the accelerated development of the State. The incentives

    include:

    Central capital investment subsidy scheme;

    Transport subsidy scheme;

    Central interest subsidy scheme;

    Comprehensive insurance scheme, etc.

    2.7.4 Incentives have also been announced by the State government to encourage private

    sector participation (both Indian and foreign) in the development of hydro-electric / gas

    based power projects. The state is thus poised for accelerated development and is an

    attractive destination for investment.

  • 8/14/2019 Dibbin HE 100MW

    26/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 18

    CHAPTER - III

    Project Area

  • 8/14/2019 Dibbin HE 100MW

    27/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 19

    3.1 DESCRIPTION OF PROJECT INCLUDING RIVER SYSTEM

    River System

    3.1.1 Arunachal Pradesh is divided into five river valleys; the Kameng, the Subansiri, the

    Siang, the Lohit and the Tirap. All these are fed by snow from the Himalayas and

    countless rivers and rivulets. Kameng river basin covers almost the entire West

    Kameng and East Kameng districts as also a part of Lower Subansiri district. A number

    of tributaries like Bichom, Tenga, Pachi, Papu and Pachuk contribute to River Kameng

    before it joins River Brahmaputra about 10 kms upstream of Tezpur. The river acquires

    the name Jia-Bhareli in the last 50 km before it joins River Brahmaputra.

    3.1.2 The Bishum Chu originates in the glaciated areas in the Greater Himalayan range at an

    altitude of about 5,650m. It drains a number of glacial lakes in the upper reaches.

    Bishum Chu flows generally in the southward direction and is joined by a number of

    streams both on left and right banks up to the proposed project site. Kachho Bung is the

    first major left bank tributary of Bishum Chu. Further downstream it is joined by

    another stream named Sama Bung. Chang Dimung Chu and Mijung Chu are main right

    bank tributaries of Bishum Chu. Immediately upstream of the proposed dam site

    Bishum Chu is joined by Deyang Bung on its left bank. The catchment area of Bishum

    Chu up to the proposed dam site is 607 sq km. Total length of the river from its origin

    up to dam site is about 44 km.

    BED SLOPE OF BICHOM RIVER

    0

    1000

    2000

    3000

    4000

    5000

    6000

    1 2 3 4 5 6 7 8 9 10 11 12

    Distance (KM)

    Elevation(M)

  • 8/14/2019 Dibbin HE 100MW

    28/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 20

    3.1.3 Bhareli/Kameng River in its total route of about 200 km carries the discharge of all its

    major and minor tributaries and drains a total catchment of about 8,540 sq.km. upto

    Bhareli II proposed dam site. The catchment area extends across international border

    and some of the tributaries have origin in Bhutan/ Tibet. About 20% of the total

    catchment area in the upper reaches remains snow bound throughout the year and keeps

    contributing to the river flow during the lean months in the form of glacial melt. The

    remaining catchment area of about 80% is rain fed. The basin receives varying amounts

    of rainfall, ranging from a minimum of 1000 mm in the upper reaches to about 5700

    mm in the foot hills annually and the average rainfall is fairly high. The river flow in

    the Kameng river system is, therefore, quite large and the variation in river flows in

    different months is not as large as in the case of purely rain fed rivers. Comparatively

    less variation in flow and high discharge and bed slope make the river suitable for

    setting up a number of hydro electric schemes.

    3.1.4 The catchment is covered by thick forest which gives the advantage of maximum

    runoff of the rain water into the river and also ensures minimum inflow of silt. The

    Kameng river system passes through a thick forest cover having rich bio-diversity. The

    area has a number of species of flora and fauna and abundant aquatic life in the river.

    3.1.5 The Kameng in its upper reaches generally flows in north-south direction. Taking large

    turns in its course, Kameng River flows in narrow valleys upto Seppa town, the head

    quarters of East Kameng District after which it widens out. In the reach upto Seppa

    town, the river is joined by a number of tributaries viz Para, Pachi, Pache, Pachuk etc.

    About 18 km downstream of Seppa town, the river is joined by one of its major

    tributaries, the Bichom. The combined river then takes a turn and flows in the westerly

    direction. About 35 km downstream of the confluence of Bichom, the Kameng river

    takes a U bend and starts flowing in the easterly direction. Downstream of confluence

    of Dikhu Nala, the Kameng River takes a north south course and finally meets River

    Brahmaputra about 10 kms. upstream of Tezpur.

    3.1.6 The Kameng basin spreads over an area of 12500 sq.km. The tributaries/ sub-tributaries

    drain catchment areas ranging from 4600 sq.km. to 280 sq.km. The drop in elevation

    from the origin to the confluence with the main river is from about 4800 m to about 120

    m. The major tributaries of Kameng River, namely Bichom, Digien, Tenga, Pakke,

  • 8/14/2019 Dibbin HE 100MW

    29/115

  • 8/14/2019 Dibbin HE 100MW

    30/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 22

    3.1.12 Dibbin Hydro Electric project is envisaged as a run of the river scheme with 27 m high

    dam. The dam is expected to have the deepest foundation at EL 1160 m. The crest level

    of the dam is kept at EL 1171 m. The length of the dam at top would be around 143 m.

    In order to provide a little storage to meet the diurnal variation in the demand of water

    of turbines in the power station during lean months, the dam would be provided with

    five numbers of radial gates of size 11.1 m x 14 m.

    3.1.13 The water conductor system would comprise a desilting basin to eliminate silt particles

    above 200 microns size, a tunnel intake, 4.43km long head race tunnel of 5 m diameter,

    a surge shaft and two penstock of 3 m diameter 143 m long. A surface power house

    with an installed capacity of 2 x 50 MW is proposed on the right bank of Bichom river

    near Nachibin village.

    3.2 SOCIO ECONOMIC AND OTHER ASPECTS

    3.2.1 On 15th August 1947 when India became an independent nation, North East Frontier

    Agency (NEFA) became a Union Territory and acquired the name of Arunachal

    Pradesh. In 1975 it acquired a legislature and finally on 20th

    February 1987 it became

    the 25th

    State of the Union of India. The State has an area of 83,743 sq. km and a

    population of 1, 09,117 (according to 2001 census) giving an average density of just 13

    people per sq. km.

    The State has been developing steadily through Five Year Plans with emphasis on

    development of infrastructure such as roads and bridges, buildings, educational

    institutions, hospitals and health care units etc. The economy of the State is largely

    agrarian. Other areas important to the economy of the state are horticulture, forest and

    small and medium scale industries.

    3.2.2 The state of Arunachal Pradesh is bestowed with rich natural resources which include

    rich forest area, mineral resources like dolomite, limestone, graphite, marble etc.Development of hydro projects will give ample scope for development of agro- based

    industries and industries with basic mineral resources. Other socio-economic benefits to

    the people, from these projects will include employment to workers, development of

    communications, markets and other benefits consequent to large scale construction

    activity.

  • 8/14/2019 Dibbin HE 100MW

    31/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 23

    3.2.3 The Gross State Domestic Product of the State during 2000-01 as per quick estimates was

    estimated as follows:

    (Rs. in lakhs)

    Particulars At current prices At constant prices

    Primary Sector 65,186 39,062

    Secondary Sector 36,796 24,919

    Tertiary Sector 76,318 46,598

    GSDP 178,300 1,10,579

    The per capita income during 2000-01 at current prices was Rs. 16,343 and at constant

    prices Rs. 10,136. The share of primary sector has come down from 46.19% in 1990-91

    to 35.33% in 2000-01 while that of tertiary (services) sector has increased from 32.25%

    to 42.14% during the same period. The share of the secondary sector (manufacturing,

    construction etc.) has remained almost the same. Transport, tourism and public

    administration has contributed to the increase in the tertiary sector.

    3.2.4 Arunachal Pradesh is largely rural with 94 percent of its population living in villages

    scattered all over the state. The indigenous people are tribes with rich and glorious

    heritage of arts and crafts. The State has 20 major tribes and a number of sub-tribes

    having their own ethos, dialects and cultural identities which present a unique scenario

    of unity in diversity. Most of the tribal communities are ethnically similar having

    derived from an original common stock but their geographical isolation from each other

    has brought amongst them certain distinctive characteristics in language, dress and

    customs.

    3.2.5 The total literacy in the State has risen from 41.57% in 1991 to 54.74% in 2001. The

    State has 12 towns and 3649 villages. As against the decadal (1991-2001) growth rate

    of 21.34% at the national level, population of the State has grown by 26.21%. The sex

    ratio of Arunachal Pradesh at 901 female to 1000 males is lower than the national

    average of 933.

    Tribes

    3.2.6 There are about 20 major tribes with a number of sub-tribes in Arunachal Pradesh.

    Larger tribes are Adi, Akas, Apatanis, Buguns, Singhpos, Membas, Mishmis, Mijis,

    Thongsas, Hrusso, Monpas, Nyishi, Sherdukpens, Tagins, Khamti, Yobin, Wanchos,

    Noctes.

  • 8/14/2019 Dibbin HE 100MW

    32/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 24

    Cultural Group

    3.2.7 The people of Arunachal Pradesh may be divided into three cultural groups on the basis

    of their socio-religious activities.

    (i) The Monpas and Sherkukpens of Tawang and West Kameng districts follow the

    lamaistic tradition of Mahayana Buddhism. These communities have richly

    decorated Buddhist temples called Gompas. They practice terrace cultivation

    and also breed herds of Yak and mountain sheep. Membas and Khambas living

    in northern borders are culturally similar. Khamtis and Singphos inhabiting the

    eastern part of the State are Buddhists of Hinayana sect.

    (ii) The Adis, Akas, Apatinis, Bangnis, Nishis, Mishmis, Mijis, Thongsas, etc.

    worship Sun and Moon Gods (Donyi-Polo and Abo-Tani), and are the original

    ancestors for most tribes. They traditionally practice Jhumming or shifting

    cultivation and paddy-cum-pisiculture.

    (iii) Noctes and Wanchos adjoining Nagaland practice elementary form of

    Vaishnavism

    Social Structure

    3.2.8 The tribals of Arunachal Pradesh have highly ordered and organized system of

    functioning in their village. All matters relating to the community as a whole are

    decided at the village level. The traditional village Panchayat of an Adi Village islocally known as Kebang. It is a judicio-administrative body consisting of mature

    and influential elders and looks after the administration of justice in the society by

    settling all matters of dispute. Similar self-governing institutions exist among other

    tribes. They are variously called as Jong among the Sherdukpens, Mel among the

    Akas, Buliang among the Apatanis etc.

    Economic Development

    3.2.9 Arunachal Pradesh could be justifiably called the power house of India with a total

    untapped hydro power potential of 49,126 MW from 89 identified schemes. The State

    and Central Governments encourage private sector participation (both Indian and

    Foreign) in the development of hydro-electric power projects. National Hydro-electric

    Power Corporation (NHPC) a Government of India enterprise and North East Electric

    Power Corporation (NEEPCO) also a Government of India enterprise for power

    development in the north-eastern region have been entrusted with the task of

    developing hydro as well as gas based power projects. NEEPCO has recently

  • 8/14/2019 Dibbin HE 100MW

    33/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 25

    completed 405 MW Ranganadi hydro-electric power project and NHPC has taken up

    the construction of 1600 MW Subansiri project. NEEPCO is developing 600 MW

    Kameng Hydro-electric power project from the waters of Bichom / Tenga rivers which

    are tributaries of Kameng river. In addition 31 schemes with power potential of 5047

    MW which have been identified as Category A schemes are being investigated in

    Arunachal Pradesh. Out of these, 15 schemes with a power potential of 3945 MW are

    being investigated by NEEPCO. All these schemes are on Kameng river system. All

    these projects are planned to be completed by the year 2012. The state is therefore

    poised to become a major exporter of power to other regions of the country.

    3.2.10 The state has also prepared its own State development plan and proposes to increase the

    present per capita consumption of about 100 kWh of electricity to 500 kWh by the time

    the above mentioned hydro projects are completed. The State is already in the process

    of creating 132 kV State power grid with distribution centres in every district. 400 kV

    lines and switchyards will also be constructed for evacuation of power from hydro

    electric projects to various distribution centres and also outside the Sate for which the

    Power Grid Corporation of India is preparing a plan of action. The State Government

    has decided to electrify all its villages by conventional or non-conventional energy by

    the year 2012 and provide electricity to all.

    3.2.11 Dibbin Hydro Electric Project will have an installation of 2 x 50 MW to generate

    335.72 MU of electricity in a 90% dependable year. The project would provide benefits

    of free power to Arunachal Pradesh amounting to 12% power generated. The

    development of project will enhance the quality of life of the people living in and

    around the project by way of development of roads and communication, availability of

    reliable, dependable, un-interrupted power for development of small/medium

    industries, development of tourism etc.

    3.2.12 The State has rich tourism potential with high snow clad mountains, numerous

    turbulent streams, roaring rivers, deep gorges, endless variety of flora and fauna and

    places of scenic beauty. Being conscious of the importance of tourism as a vehicle of

    economic development the State has recognized tourism as a thrust area and has opened

    up a number of tourist circuits including the Tawang monastery on the Indo-China

    border.

  • 8/14/2019 Dibbin HE 100MW

    34/115

  • 8/14/2019 Dibbin HE 100MW

    35/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 27

    v) Ornaments are mostly made of beads. Notches and Wanchos weave them into

    attractive designs. Silver ornaments are a specialty of the Mishmis.

    vi) Wood carving unique and artistic articles are produced in Tirap, Upper and

    West Siang, Lohit and Tawang.

    3.3 Dibbin Hydro Electric Project will thus provide the much needed infrastructure to the

    State for its all round development and improvement in the quality of life of its people.

    The project will also be a valuable source of hydro power to the rest of the country.

  • 8/14/2019 Dibbin HE 100MW

    36/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 28

    Chapter IV

    Topographical and Geotechnical Aspects

  • 8/14/2019 Dibbin HE 100MW

    37/115

  • 8/14/2019 Dibbin HE 100MW

    38/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 30

    subdivided into Inner Lesser Himalaya and Outer Lesser Himalaya, the former lying to

    the south of the Higher Himalaya comprises mainly of Paleoproterozoic - The Bomdila

    Group and Ziro Gneises and Mesoproterozoic - The Dirang Formation. The Outer

    Lesser Himalaya is the zone that lies immediately to the north of the Sub-Himalaya. It

    is made-up of Early Permian rocks Lower Gondwana Group. It is characterised by

    dendritic drainage with broad V-shaped valleys at places filled by Quaternary deposits

    forming terraces.

    4.3.3 The Higher Himalaya is a narrow zone that lies between the Lesser Himalaya in the

    south and the Tethys Himalaya in the north. It is chiefly made up the Archaean-

    Paleoproterozoic sequence constituting the Central Crystalline and Mesoproterozoic -

    the Dar formation, which forms the basement for the Phaenerozoic succession of theTethys Himalaya, this physiographic region is also referred to as the Himadari or

    Greater Himalaya (Singh, 1971). The southern limit is defined by the MCT while in the

    north imperceptibly passes into the Tethys Himalaya. This zone is characterised by

    highly rugged topography with some snow-bound high peaks.

    4.3.4 Drainage : The Kameng River (also known as Bhareli) is one of the principal

    tributaries of the mighty Brahmaputra River of the district draining about 9,860 km2

    of

    western Arunchal Himalaya through its network of smaller streams such as Tenga,

    Bichom, Papu, Pacha, Pachi, Para, Wacha rivers. It originates from the southeastern

    slopes of Higher Himalaya and drains the Dafla Hill in the Lesser Himalaya, and cuts

    deep gorge through the Siwalik rocks of the Sub-Himalaya. It enters the Brahmaputra

    Plain near Bhalukpong. The Kameng (Bhareli) River and its tributaries are transverse

    rivers excepting small stretches where it is subsequent to the structural weak planes

    such as MBF.

    4.4 REGIONAL GEOLOGY OF EAST KAMENG DISTRICT

    4.4.1 The generalised stratigraphy as worked out by Kumar (1997) in the East Kameng

    district, Arunachal Pradesh, is given in Table 1. There is no record of Archaean rocks

    from this part. The Sela Group is oldest poly-phase deformed sequence of

    metasediments, which is tenatively considered to be of Early Paleoproterozoic age. Its

    southern limit is defined by a major tectonic plane-the Main Central Thrust (MCT),

    which separates it from the Dirang Formation (Mesoproterozoic). The Bomdila Group

    comprises low to medium-grade metasediments, which includes quartzite with

  • 8/14/2019 Dibbin HE 100MW

    39/115

  • 8/14/2019 Dibbin HE 100MW

    40/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 32

    Age Group Formation Member Lithology

    A Oligomictic conglomerate

    containing grit to cobble sizerounded to subrounded clasts of

    quartzite, pinkish to greyish white

    coloured.

    Cambrian Deed Biotite granite (500+19Ma)

    Granite gneiss

    Mesoproterozoic Dirang Low-grade metasediments

    comprising garnet-muscovite-biotite schist, phyllite, sericite

    quartzite, calc-silicate, tremolite-

    actinolite marble.

    Mafic sills & dykes

    Ziro Geneisses (Biotite grantie

    gneiss 1914+25Ma & Tourmaline

    bearing leuco-granite 1676+122Ma) Ultramafic dykes and sills.

    Niumi Crystalline limestone, dolostone/

    dolomite, quartzite & green

    phyllite, carbonaceous phyllite,

    chlorite/ actinoalite-hornblendephyllite with thin beds of marble.

    Chilliepam

    Kabak Dolomite, with black phyllite.

    Oligomictic conglomerate with

    clasts of quartzite.

    Jameri Quartzite with thin bands of

    phyllite.

    Tenga

    Along Mafic metavolcanics, drab greenchlorite phyllite.

    Bomdila

    Khetabari Quartzite schistose to massive,

    garnet mica sachist, para-

    amphibolite

    Schistose quartzite, acid tuff,phyllite, carbonaceous &

    graphitic phyllite, marble & calc-silicate.

    Galensiniak Kyantite-sillimanite+stanurolite

    gneiss and schist, quartzite,

    migmatite.

    Paleoproterozoic

    Se La

    Taliha Calc-silicate marble, graphitic

    schist, amphibolite, sillimanite

    gneiss.

    4.5 TECTONICS

    4.5.1 Taking into consideration the stratigraphy and structure, the Arunachal Himalaya has

    been divided into two broad tectonic divisions, viz. the Frontal Fold Belt (FFB) made

    up of Siwalik Group and forming the Sub-Himalaya, and the Main Himalayan Belt

    (MHB) comprising Paleoproterozoic to Middle Eocene sediments and associated acid

    magmatic rocks forming the Lesser Himalaya and Higher Himalaya. The two belts are

    separated by the MBF (Kumar, 1997). The MHB is further subdivided into two zones-

    zone I and Zone II, the former forming the Higher Himalaya and the latter Lesser

    Himalaya.

  • 8/14/2019 Dibbin HE 100MW

    41/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 33

    4.5.2 Within MHB, the data on structures within Zone I is scanty, while the rock sequences

    of Zone II shows structures related to 4 or 5 (D1,2,3,4,5) deformational episodes. Of these,

    the first three deformations (D1,2,3) are restricted to the Bomdila group and associated

    acidic intrusions, and Dirang Formation. The first two deformations (D1,2) have been

    related to the Luliangian and Zhongyuean orogenic movements during Late

    Paleoproterozoic, and the latter (D3) to Mesoproterozoic deformation. The oldest

    deformation (D1) is restricted to the Khetabari Formation only. The folds (F1) related to

    deformation (D1) are isoclinal to reclined often rootless with angular to subangular

    thick hinges, straight attenuated limbs. It is accompanied with metamorphism (M1) of

    almandine-amphibolite facies and development of schistosity parallel to bedding. the

    folds (F2) developed during deformation (D2) are superimposed over F1 and are of

    regional dimensions. These are moderately tight to open asymmetrical, trend in ENE -

    WSW direction where not re-oriented and are accompanied with development of strong

    schistosity, matamorphism (M2) of green schist facies, and acidic intrusions of

    Proterozoic age. The deformation (D3) is post Dirang Formation but pre sedimentation

    of the Lower Gondwana Group, and the folds (F3), where not re-oriented, are isoclinal,

    reclined or asymmetrical with axial plane striking NNE-SSW to NE-SW and plunging

    towards north. Fourth deformation (D4) gave rise to large scale asymmetrical upright to

    overturned folds (F4) having ENE-WSW trending axial plain dipping towards north.

    Since this deformation has folded not only the Lower Gondwana sequence into an

    overturned isoclinal syncline but also the Yinkiong Formation (Paleocene-Early

    Eocene) it marks the initiation of the Himalayan Orogeny (HOM-1) related to strong

    compressional orogenic movements due to collision of the Gondwana Plate with Asian

    Plate along the Indus-Tsangpo Suture. The deformation (D5) refolded all the earlier

    doformational structures. The associated folds (F5) are generally open broad,

    asymmetrical with axial plane trending NNW-SSE. This deformation is related to

    collision of the Central Burmese Plate with the Gondwana and Asian Plate along the

    Tidding Suture in the eastern part of Arunachal Pradesh but before the development of

    Foredeep.

    4.5.3 The folds (F6) are restricted to FFB and are post Kimin Formation (Upper Siwalik) but

    pre-Older Alluvium and are thus related to deformation (D6) during last phase of the

    Himalayan Orogeny (HOM 4) in early Middle Pleistocene which resulted in the

  • 8/14/2019 Dibbin HE 100MW

    42/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 34

    development of the Sub-Himilaya. The folds are doubly plunging trending in ENE-

    WSW to NE-SW.

    4.6 NEOTECTONICS, SEISMICITY & EARTHQUAKES

    4.6.1 It is under continuous stress field and still undergoing crustal adjustments since the last

    phase of Himalayan Orogeny about 45 millions years ago. these Crustal

    adjustments/movements - the Neotectonic activity, is identifiable in the form of block

    movements resulting in reactivation of some existing major tectonic movements and

    development of cross-faults, and release of stress waves causing earthquakes.

    4.6.2 In the area of the two cross - the Bomdila Fault (Nandi, 2001) and the Roing Fault

    (Kumar, 1997) have been recorded which post date Himalayan Orogeny and have

    affected the sedimentation of the Quarternay sediments in the Brahmaputra Plain and

    continue in the area of three proposed hydroelectric schemes, East Kameng District viz.

    Dibbin, Phanchung and Tarang Warang in the East Kameng District Arunachal

    Himalaya.

    4.7 SEISMICITY

    4.7.1 The Arunachal Pradesh in the northeastern region of India, situated at the tri-junction of

    three plates, viz. Indian Indo-Burmese and Eurasian, falls in seismic zone-V. Seismicity

    in the Eastern Himalaya is relatively sparse, and earthquake events are more

    concentrated in areas traversed by cross-faults/lineaments (Nandi, 2001). They occur in

    diffused pattern having post-collisional intracratonic characteristics. The earthquakes

    events (total 974), occurring between 1964-1993, having magnitude > 4 have shallow

    focal depth i.e. < 70 km. except for few events. The earthquake of 1947 (epicentre at

    280

    30' : 940

    00') having magnitude M=7.5 was recorded from this domain. Nandi

    (2001) has also related microseismicity of Zero area to a deep seated N.W. trending

    fault running parallel to the Bomdila and Roing Fault.

    4.8 GEOTECHNICAL APPRAISAL

    4.8.1 In the project area the rocks exposed belong to the Zero Gneisses (Bomdila Gneiss,

    Kaura and Basu Roy, 1981) and the Dirang Formation (MAP-

    DIB4-1). The Zero Gneisses include undifferentiated augen gneiss, quartz-biotite

    gneiss intrusive in the Tenga Formation of the Bomdila Group. It encloses enclaves of

    quartzite of the Tenga Formation. The Dirang Formation comprises a basal unit of

    garnetiferous mica schist, quartzite and phyllite at the base and an upper unit of ochre

  • 8/14/2019 Dibbin HE 100MW

    43/115

  • 8/14/2019 Dibbin HE 100MW

    44/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 36

    from identified potential sources for complete range of physical parameters like

    abrasion, impact, crushing values, alkali aggregate reaction, flakeness index, elongation

    index, specific gravity, water absorption, fineness modulus, silt and clay contents and

    organic impurities. Further a portion of excavated rock from the tunnel is also proposed

    to be used for construction. River sand deposits would be tested for its suitability for

    use as fine aggregate in concrete and crushed sand may also be used to obtain well-

    graded sand.

    4.10 CONCLUSIONS AND RECOMMENDATIONS

    4.10.1 The Dibbin H.E. Project involves, construction of a 27m high diversion dam on Bishum

    River, an approximately 4.43 km. long Head Race Tunnel (H.R.T.) and a power house

    for the generation of 100MW of power utilizing a gross head of 165m Prefeasibility

    stage studies have been carried out on the basis of field traverses and available

    geological data.

    4.10.2 The project is located in Lesser Himalayas with complex, geological and geotectonic

    setting and in Zone V as per the seismic Zoning Map of India prepared by Indian

    Standard Institution (IS : 1893 - 1984). The rocks exposed in the Project Area belong to

    Zero Gneisses and the Dirang Formation. The Zero

    4.10.3 Gneisses include undifferentrated augen gneiss, quartz-biotite gneiss intrusive in the

    Tenga Formation of the Bomdila Group. the Dirang Formation includes, at the base

    ganetiferous mica schist, quartzite, and phyllite and an overlying unit of ochre schist

    carb schist, laminated flaggy quartzite, calc schist, marble and phyllite.

    4.10.4 At the proposed 27m high dam site, the inferred bed rock is quartz-biotite schist with

    occasional bands of quartzite. The site appears prima-facie suitable. To fix the dam axis

    detailed geological mapping would be required and drilling of two or three shallow

    holes to determine the depth to fresh and sound rock.

    4.10.5 The approximately 4.43 km. long H.R.T. shall encounter predominantly schist and

    quartzite of Dirang Formation. These rocks, generally shall not pose tunnelling problem

    except when shear zones charged with water would be encountered. The rock cover

    over the tunnel shall vary from 100m to 500m. The drainage patterin the the H.R.T.

    alignment area is 'Radial' which would require detail field studies to evaluate its

    implication on tunnelling.

  • 8/14/2019 Dibbin HE 100MW

    45/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 37

    4.10.6 The power house site is located on the left bank of Ditchi Bru close to the confluence

    with Bishum Chu, on river terrace material. Drilling of one hole has been suggested at

    this site.

  • 8/14/2019 Dibbin HE 100MW

    46/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 38

    CHAPTER-V

    Hydrology

  • 8/14/2019 Dibbin HE 100MW

    47/115

    DIBBIN HE PROJECT (100 MW)

    ISO 9001-2000

    PMs 50,000 MW initiative 39

    5.1 GENERAL

    5.1.1 The hydrological inputs play a very vital role in planning, execution and operation of

    any water resources development project. The hydrological studies are carried out at all

    the stages of project development starting from the pre-feasibility stage and are

    continued even during the operation of the project. Hydrological studies usually cover

    the assessment of quantities of available water and its time variation, estimation of

    design flood usually required for the hydraulic design as well as safety of the structure

    and sedimentation studies, important from life point view of the project as well as its

    effect on the live storage.

    5.1.2 The river Brahmaputra is one of the biggest river in the world. The total length of

    Brahmaputra river in India is 885 km and its drainage basin in India is 1,95,000 sq. km.

    There are 25 principal north bank tributaries of this river. The major one are Subansiri,

    the Manas, the Dibang, the Dhansiri, the Torsa, and the Teesta etc. The kameng is one

    of these 25 principal north tributaries of this river. The State of Arunachal Pradesh is

    enriched with tributaries like Tawang Chu, Kameng, Subansiri, Dihang etc. which

    originates from the mighty Himalayas. These are perennial in nature and carry them

    floods almost every year during monsoon and as such have huge-hydro potential. The

    Kameng river is one of the river system and its drainage area lies in India

    approximately between longitudes 92-00-00" to 93-20-55" E and latitudes 26-38-

    00 to 28-59-50" N. The drainage area of the Kameng is about 10,777 sq. km. The

    river Pachu, Bichom, Papu and Pakhe are the main tributaries of the Kameng. The

    Kameng originates at an elevation of 6000 m. The Central Electricity Authority (CEA)

    has identified about 31 probable potential sites in the Kameng basin. An index map of

    the some of the identified hydro electric potential is shown in Plate-I.

    5.2 BASIN CHARACTERISTICS

    The topography of the Kameng Basin in upper reaches divides itself in to two distinct

    zones i.e. Greater Himalayas and Lower Himalayas. The Greater Himalayas abounds

    with Glaciers and mostly are covered with permanent snow above elevation 5000 m

    while lower regions in Himalayas are generally rain fed. The topography of the basin is

    hilly with steep slopes in u