Upload
manjunath-ds
View
316
Download
3
Embed Size (px)
Citation preview
DISTRBUTION SYSTEM FAULT MANAGEMENT.
VISHVESHWARAYA TECHNOLOGICAL UNIVERSITY,BELGAUM.
DEPT OF ELECTRICAL AND ELCTRONICS
BMS COLLAGE OF ENGINEERING (EVENINIG)
BENGALURU .
TEAM
MEMBERSD.S.MANJUNATHVINAY KUMAR.MVISHNUVARDHANA .H.V.KIRAN KUMAR.G.
GUIDED BY: ASSOCIATE PROF, SRI S. PRAKASH.ELECTRICAL AND E,ECTRONICS DPT.
BMSCOLLAG OF ENGINEERING (EVEN).
AGENDAINTRODUCTION.CURRENTLY EXISTING SYSTEM. NEW FAULT MANAGEMENT
SYSTEM.ADVANTAGES, APPLICATIONS,
IMPROVEMENTS.
INTRODUCTION
DISTRIBUTION SYSTEM. Distribution system is that part of
the power system which distributes power from distribution substation to local use .
Generally the higher voltage for distribution is 11000v and the lower voltages are 400 v and 220v.
General layout of distribution system
7
33KV
Sub station
11KV
Distribution Transformer
11KV
Distribution Substation
0.4KV
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH (CLOSED)
STATION CIRCUIT BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM
8
TYPES OF FAULTS IN DISTRIBUTION SYSTEM.LINE TO LINE FAULT .LINE TO GROUND FAULT .3 PHASE FAULTS.OVER CURRENT FAULTS .
LINE TO LINE FAULT.IT’S THE FAULT WHICH OCCURS
BETWEEN ANY OF THE 2 LINES .AT THIS FAULT THE VOLTAGE
ACROSS TWO LINES WILL BE ZERO, AND CURRENT IS MAXIMUM.
V=0,I=∞
LINE TO GROUND FAULTIT IS THE FAULT OCCURS
BETWEEN ANY LINE TO GROUND.AT THIS FAULT THE VOLTAGE
ACROSS LINE TO GROUND IS ZERO, AND CURRENT IS MAXIMUM.
V=0,I=∞
THREE PHASE FAULTSOVER CURRENT FAULTSIN OVERCURRENT FAULTS THE
CURRENT IS MAXIMUM ,THAT IS MORE THAN RATED VALUE.
EFFECT OF FAULTS.
CURRENTLY EXISTING SYSTEM
Over view of currently existing system.
Service station
Service vehicle
Consumer under dark
fault clearing system of current existing system.
Sub A
Feeder B010 from Sub BFeeder A007
from Sub A
OpenTie-Switch
Closed Switches
Distribution Transformers
Inferred Fault Location
Customer trouble calls
Sub A
Feeder B010 from Sub BFeeder A007
from Sub A
OpenTie-Switch
Closed Switches
Distribution Transformers
fault clearing system of current existing system.
Inferred Fault Location
Customer trouble calls
Customer trouble calls
Difficulties in currently existing system.Fault Identification takes too much time.At the time of raining it is too difficult find
and correct faults.With the human error fatal accidents are
common .L.V. distribution faults(after the secondary
of distribution transformer) are cannot be identified from existing relays, faults like conductor down, overloading, short circuiting of conductors etc. which unexpected and very difficult identify.
New fault management
system.
Objective of fault management system.To improve reliability and quality
of service of distribution system by
Reducing frequency and duration of power interruptions to targets consistent with best international practice
To operate efficiently and safely by
Minimizing power losses Applying manpower resources effectively
Method involved It will be consisting of control room with a
signal indicating system it may be a computer monitor or big screen
Which will be indicating the status of all section voltage and current with alarm for any abnormal conditions .
After I identifying the fault feeder all loads are removed from the network and network will be charged idly with full voltage and limiting current through a current limiter which may be a saturable reactor so it limits the fault currents.
Continued…….After charging the line idly , all sections
current and voltage status will be absorbed and faulty section is identified.
after identifying faulty section, it will be isolated from the healthy one from remotely .
After clearing the fault the section will be closed.
Fault cleared successfully.
on on
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH (CLOSED)
STATION CIRCUIT BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM
24
on off
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH (CLOSED)
STATION CIRCUIT BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM
25
Saturable reactor
on on
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH (CLOSED)
STATION CIRCUIT BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM
26
Saturable reactor
lV. Remote-controlled switch network
Normally-open point
Telecontrolled SwitchesSubstation CBs
33/11kV Substation
10km
10km
12.5km
10km
10km10km
10km
10km
10km10km
10km
10km
10km
10km
17.5km
10km
10km
20km
Feeder 1
Feeder 2Optical Fiber
Fault
Control room
Communications
Advantages Applications
Advantages The new fault management system has a
wide and verity range of applications and advantages .
The down time is got reduced.Less interruption system can be ensured to
the customer.Revenue loss is got reduced. With moves toward deregulation and open
competition, access to accurate and timely outage information is critical in order to maximize operational efficiency, minimize customer complaints, and maintain electric system reliability
Continued…..Implementing same system to
the L.V. distribution the transformer secondary side faults can be identified and cleared immediately which ensures the safety for men and machines.
Present Operations ( Average time to restore Power Supply 40 Minutes )
Circuit Breaker
R/S feederR/S feeder
Normally open point
RMU / DT
R/S feeder
Circuit Breaker
R/S feeder
Normally open point
Supply restored manually for part network typical time 15 – 20 mins
Circuit Breaker
R/S feederR/S feeder
Normally open point
RMU / DT
CB Trips on fault
Circuit Breaker
R/S feederR/S feeder
Normally open point now closed manually
Additional network restored manually, total time 40 mins
Faulty Section
Circuit Breaker
R/S feederR/S feeder
Remote operation to close switch
Additional network restored, total time 11-18 mins
Circuit Breaker
R/S feederR/S feeder
Normally open point
Automated RMU / DT with FPI
Circuit Breaker
R/S feederR/S feeder
Normally open point
FPI indicates passage of fault current
CB Trips
Circuit Breaker
R/S feederR/S feeder
Normally open point
Remote Operation of RMU Switch & Partial Restoration of supply – typically 1-2 mins
After Automation ( Average time to restore Power Supply to healthy section 1-2 Minutes)
Impact of new fault management System. Power Restored
to Customers on Healthy Sections
of FeederFault
Occurs
CustomerReportsOutage
Travel Time
FaultLocated
Investigation& Patrol Time
Time to PerformManual Switching Repair Time
FeederBack toNormal
5 – 10 minutes
15 – 20 minutes
10 - 15 minutes
45 – 75 minutes
15 – 30 minutes
1 - 4 Hours
Power Restoredto Customers on Healthy Sections
of FeederFault
Occurs
CustomerReportsOutage
Travel Time
FaultLocated
Investigation& Patrol Time
Time to PerformManual Switching Repair Time
FeederBack toNormal
5 – 10 minutes
15 – 20 minutes
10 - 15 minutes
45 – 75 minutes
15 – 30 minutes
1 - 4 Hours
FaultOccurs
CustomerReportsOutage
Travel Time
FaultLocated
Investigation& Patrol Time
Time to PerformManual Switching Repair Time
FeederBack toNormal
5 – 10 minutes
15 – 20 minutes
10 - 15 minutes
45 – 75 minutes
15 – 30 minutes
1 - 4 Hours
Without Automation
With Automation
minutes Hoursminutesminutes Hoursminutesminutes Hoursminutes1 – 2
minutes1 – 2
minutes1 – 2
minutes
FieldCrews
On- Scene
15 – 30
FeederBack toNormal
Power Restoredto Customers on Healthy Sections
of Feeder
Travel Time Repair Time
1 - 4 5 - 10
PatrolTime
CustomerReportsOutage
FaultOccurs
FieldCrews
On- Scene
15 – 30
FeederBack toNormal
Power Restoredto Customers on Healthy Sections
of Feeder
Travel Time Repair Time
1 - 4 5 - 10
PatrolTime
CustomerReportsOutage
FaultOccurs
FieldCrews
On- Scene
15 – 30
FeederBack toNormal
Power Restoredto Customers on Healthy Sections
of Feeder
Travel Time Repair Time
1 - 4 5 - 10
PatrolTime
CustomerReportsOutage
FaultOccurs
Applications.Fault Location, Isolation, and Service Restoration
◦ Can detect and locate fault, isolate the faulty section, restore power to “healthy” feeder segments
Load Shedding◦ Can shed one feeder section if necessary
Cold Load Pickup◦ Can pick up feeder load one section at a time
Feeder Reconfiguration◦ Can balance load between feeders and reduce losses
“Intelligent” Substation Bus Transfer◦ Can transfer load to another substation following
transformer failure
RTU
RTU
Primary Plant Interface
KEY ELEMENTS of DASData & Control
Pathway
Communications
MasterStation
Substation1
2
3
4Optical Fibre, Cable
Radio
Microwave
RTU
1
2 RTU
3
4Communications
Master Station
Line
Reporting
Analysis
5
5 Control Room, Corporate Usage
Control Room Operators
Outage Analysis
Operational analysis, decisions, issue controls
5
Thanks to all our teachers and
friends for being a part of our learning
life.