Upload
banamali-naskar
View
215
Download
0
Embed Size (px)
Citation preview
8/12/2019 Ev m Presentation 200509
1/41
21 September 2005 Earned Value Management 1
Earned Value ManagementManaging Scope, Cost, and Schedule to
Improve Project Performance
Scott S. Lynde, PMP
21 September 2005
8/12/2019 Ev m Presentation 200509
2/41
8/12/2019 Ev m Presentation 200509
3/41
21 September 2005 Earned Value Management 3
Agenda
Earned value management (EVM) backgroundBackground The Basics A Process MS Project Conclusion
Basic EVM terms and formulas A practical approach and process
Using Microsoft Project for EVM Conclusion
8/12/2019 Ev m Presentation 200509
4/4121 September 2005 Earned Value Management 4
A Quick Quiz
The project budget is $200k
The project duration is 4 months The work is evenly distributed
After 2 months, $90k is spent
Is the Project Over, On, or Under Budget?
Plan
Actual$ 50100
150
200
Time1 2 3 4
8/12/2019 Ev m Presentation 200509
5/4121 September 2005 Earned Value Management 5
The Answer: It Depends!
The project budget is $200k The project duration is 4 months The work is evenly distributed After 2 months, $90k is spent After 2 months, the planned work is $100k What if the project is:
50% complete?
45% complete?
40% complete?
70 80 90 100
Plan (Cost/Work) = $100k
Actual Costs = $90k
Work = $80kWork Accomplished = $90kWork Accomplished = $100k
EVM Integrates Scope, Cost, and Schedule to Improve Performance Management
8/12/2019 Ev m Presentation 200509
6/41
8/12/2019 Ev m Presentation 200509
7/41
21 September 2005 Earned Value Management 7
EVM Background
Background The Basics ConclusionA Process MS Project
Late 1800s - 1962American Factories
1962 - 1967PERT/Cost
1967 - 1996C/SCSC
1996 - PresentEVM: ANSI/EIA 748
1962Introduction ofPERT/Cost 1965
USAF formsC/SPCS group
1967DoD issuesC/SCSC 1996
32 EVMS criteriadefined; terms
simplified
1998ANSI/EIA 748guide published
Simplificat
ion
Adop
tion
1958US Navy
introduces PERT
8/12/2019 Ev m Presentation 200509
8/41
21 September 2005 Earned Value Management 8
EVM Background
Background The Basics ConclusionA Process MS Project
EVM Has Been Gaining Momentum
Published Papers on Earned Value
0
5
10
15
20
25
30
1995 1996 1997 1998 1999 2000 2001 2002
8/12/2019 Ev m Presentation 200509
9/41
8/12/2019 Ev m Presentation 200509
10/41
8/12/2019 Ev m Presentation 200509
11/41
21 September 2005 Earned Value Management 11
The Project Lifecycle
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
12/41
21 September 2005 Earned Value Management 12
A Framework for EVM
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
13/41
21 September 2005 Earned Value Management 13
3+1 Core Data Elements
Background The Basics ConclusionA Process MS Project
Planned Value (PV)
How much work is supposed to be done at a given point in time
Prepared during planning as a (cumulative) time-phased budget Referred to as the performance measurement baseline AKA the budgeted cost of work scheduled (BCWS)Actual Costs (AC)
The level of resources (typically $) expended to date Typically obtained from an organizations accounting system AKA the actual cost of work performed (ACWP)Earned Value (EV)
How much work has actually been accomplished Obtained by tracking and measuring progress on project work AKA the budgeted cost of work performed (BCWP)Budget at Completion (BAC)
The total planned value for the project
8/12/2019 Ev m Presentation 200509
14/41
21 September 2005 Earned Value Management 14
A Framework for EVM
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
15/41
21 September 2005 Earned Value Management 15
A Framework for EVM
Background The Basics ConclusionA Process MS Project
Planned Value
Actual Costs
Earned Value
8/12/2019 Ev m Presentation 200509
16/41
21 September 2005 Earned Value Management 16
Variances
Background The Basics ConclusionA Process MS Project
Cost Variance
CV = EV AC Determines how much the project is over or under budgetSchedule Variance
Cost: SV = EV PV Determines how much work is ahead or behind schedule
Ignores the critical path Converges to zero
Negative Variances are Unfavorable; Positive Variances are Favorable
8/12/2019 Ev m Presentation 200509
17/41
21 September 2005 Earned Value Management 17
A Framework for EVM
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
18/41
21 September 2005 Earned Value Management 18
A Framework for EVM
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
19/41
21 September 2005 Earned Value Management 19
Forecasts
Background The Basics ConclusionA Process MS Project
(Independent) Estimate at Completion
(I)EAC = BAC / CPI (cost performance index) EAC = AC + ETC (estimate to complete) EAC = project manager outlook Assumes the team will continue to operate
at the same efficiency level Projects the final cost of the project Forecasts the final project costVariance at Completion
VAC = BAC EAC Determines how much the project will beover or under budget when done
Studies of Hundreds or Large Defense Projects Have Shown that
EAC Is Accurate Within a Statistical Range by the 15-20% Mark
8/12/2019 Ev m Presentation 200509
20/41
21 September 2005 Earned Value Management 20
A Framework for EVM
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
21/41
21 September 2005 Earned Value Management 21
A Framework for EVM
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
22/41
21 September 2005 Earned Value Management 22
Performance Indices
Background The Basics ConclusionA Process MS Project
Cost Performance Index (CPI)
CPI = EV / AC Indicates the cumulative cost efficiency of a project howefficiently the team uses its resources ($)
Schedule Performance Index (SPI)
SPI = EV / PV Indicates how efficiently the team is using its timeTo-Complete Performance Index (SPI)
TCPI = (BAC EV) / (BAC AC) Indicates the efficiency required on remaining work in order toachieve a target (BAC or EAC)
For SPI and CPI, Values Greater than 1.0 Are Favorable; Less than 1.0 Are Unfavorable
8/12/2019 Ev m Presentation 200509
23/41
21 September 2005 Earned Value Management 23
A Framework for EVM
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
24/41
21 September 2005 Earned Value Management 24
A Framework for EVM
Background The Basics ConclusionA Process MS Project
Official ANSI standard for EVMS has 32 criteria; only 10 are necessary
Define authorized work elements Identify project organizational
structure and assign responsibility
Integrate planning, scheduling,budgeting, work authorization,and cost accumulation processes
Schedule the authorized work in asequential manner that identifies
the significant task dependencies Select EV measurement
techniques
Establish and maintain a time-phased baseline
Record direct costs consistently ina formal manner
Periodically generate projectmetrics to assess performance
Periodically develop revisedestimate at completion forecasts
Incorporate authorized changes ina timely manner
I.e., Practice Good Project Management
8/12/2019 Ev m Presentation 200509
25/41
21 September 2005 Earned Value Management 25
A Practical Process: Planning
Background The Basics ConclusionA Process MS Project
CostAccountant
ProjectManager
ProjectTeam
Decompose work
scope to amanageable
level
Assignunambiguousresponsibility
Develop a
performancemeasurement
baseline
Determine EV
measurementtechnique for all
tasks
Determinereportingfrequency
Provide time-phased budget tocost accountant
Basic
PMEV
PV BAC
1
2
3
5
4
6
#MS Project Demo
8/12/2019 Ev m Presentation 200509
26/41
8/12/2019 Ev m Presentation 200509
27/41
21 September 2005 Earned Value Management 27
Earned Value Recognition
Background The Basics ConclusionA Process MS Project
Fixed formulas
Used on short-duration tasks
Used when product is well-understood
E.g., 50/50 or 25/75, or 0/100Weighted milestone
Used on long-duration tasks Used when there are observable
intermediate milestones Value is assigned to milestonesPercent complete Simple and easy Subjective Used when no objective
indicators exist
Apportioned effort
Used when a task has a direct,supportive relationship to anothertask (e.g., quality assurance (QA))
Typically calculated as apercentage of main task EV
Level of effort
Used for activities that do notproduce tangible outcomes e.g.,
project management PV is automatically credited asEV at end of each period
8/12/2019 Ev m Presentation 200509
28/41
21 September 2005 Earned Value Management 28
Earned Value Recognition
Background The Basics ConclusionA Process MS Project
Duration of Work Effort
Product of Work 1-2 Measurement Periods >2 Measurement Periods
TangibleFixed Formula
Weighted Milestone
Percent Complete
Intangible Apportioned Effort
Level of Effort
Recognition Methods for Project Activities Should Be Determined During Planning
8/12/2019 Ev m Presentation 200509
29/41
8/12/2019 Ev m Presentation 200509
30/41
21 September 2005 Earned Value Management 30
Our Project: Painting
Background The Basics ConclusionA Process MS Project
8/12/2019 Ev m Presentation 200509
31/41
21 September 2005 Earned Value Management 31
Our Schedule
Background The Basics ConclusionA Process MS Project
WBS Task Nam e
0 Painting the Room1 Design
1.1 Browse catalogs for ideas1.2 Obtain swatches
1.3 Evaluate swatches and choose paints
John Doe,Jane DoeJohn Doe,Jane Doe
8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PMTue Oct 25 Wed Oct 26
WBS Task Name
2 Procurement
2.1 Procure paint and supplies
3 Preparation
3.1 Take down pictures
3.2 Remove electrical outlets
3.3 Tape walls
3.4 Room ready for painting
4 Painting
4.1 Paint wall 1
4.2 Paint wall 2
4.3 Paint wall 3
4.4 Paint wall 4
4.5 Room painted
4.6 Paint dried
5 Cleanup
5.1 Remove tape
5.2 Touch up mistakes
5.3 Install electrical outlets
5.4 Hang pictures
6 Painting complete
John Doe,Paint and s upplies[1]
Jane Doe
Jane Doe
John Doe
10/27
John Doe
Jane Doe
John Doe
Jane Doe
10/28
10/28
John Doe,Jane Doe
John Doe
Jane Doe
Jane Doe,John D
10/29
8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PMFri Oct 28 Sat Oct 29
8/12/2019 Ev m Presentation 200509
32/41
Producing a Time Phased Budget5
8/12/2019 Ev m Presentation 200509
33/41
21 September 2005 Earned Value Management 33
Producing a Time Phased Budget(cont.)5
Background The Basics ConclusionA Process MS Project
Option 2: Analysis Toolbar
9 k d
8/12/2019 Ev m Presentation 200509
34/41
21 September 2005 Earned Value Management 34
9 Track and Report ProgressBackground The Basics ConclusionA Process MS Project
First, save a baseline
Set the status date Track progress
View the % complete
or earned value
Retrieve Actual Costs;10
8/12/2019 Ev m Presentation 200509
35/41
21 September 2005 Earned Value Management 35
Retrieve Actual Costs;Analyze Data10
Plug AC and EV into spreadsheet model If necessary, calculate EV from % complete:
EV = BAC * % complete
Background The Basics ConclusionA Process MS Project
P t ti F t
8/12/2019 Ev m Presentation 200509
36/41
21 September 2005 Earned Value Management 36
Presentation Formats
Background The Basics ConclusionA Process MS Project
Project
S-curves Dashboard speedometers
Bulls-eye chartPortfolio
Bulls-eye chart
SPI/CPI trending
P t ti F t P j t
8/12/2019 Ev m Presentation 200509
37/41
21 September 2005 Earned Value Management 37
Presentation Formats: Project
Background The Basics ConclusionA Process MS Project
30.1 99.0
P t ti F t P tf li
8/12/2019 Ev m Presentation 200509
38/41
21 September 2005 Earned Value Management 38
Presentation Formats: Portfolio
Background The Basics ConclusionA Process MS Project
C l i
8/12/2019 Ev m Presentation 200509
39/41
21 September 2005 Earned Value Management 39
Conclusion
EVM is NOT HARD! (But the acronyms are!)
EVM can be applied to any project with a definedscope, schedule, and budget
EVM provides a closed-loopfeedback system
EVM is predictive
EVM will impress your friends EVM is gaining momentum
Background The Basics ConclusionA Process MS Project
EVM Is Coming to a Project Near You
8/12/2019 Ev m Presentation 200509
40/41
21 September 2005 Earned Value Management 40
Earned Value ManagementManaging Scope, Cost, and Schedule to
Improve Project Performance
Scott S. Lynde, PMP
21 September 2005
Reference
8/12/2019 Ev m Presentation 200509
41/41
21 September 2005 Earned Value Management 41
Reference
Fleming, Quentin W. and Koppelman, Joel M.Earned Value Project Management, 2nd Ed.
Project Management Institute, June 2000.
Practice Standard For Earned Value ManagementProject Management Institute, October 2004.
Christensen, David S. and Heise, Scott."Cost Performance Index StabilityNational Contract Management Journal 25, Spring1993, pp. 7-15.