Ev m Presentation 200509

Embed Size (px)

Citation preview

  • 8/12/2019 Ev m Presentation 200509

    1/41

    21 September 2005 Earned Value Management 1

    Earned Value ManagementManaging Scope, Cost, and Schedule to

    Improve Project Performance

    Scott S. Lynde, PMP

    21 September 2005

  • 8/12/2019 Ev m Presentation 200509

    2/41

  • 8/12/2019 Ev m Presentation 200509

    3/41

    21 September 2005 Earned Value Management 3

    Agenda

    Earned value management (EVM) backgroundBackground The Basics A Process MS Project Conclusion

    Basic EVM terms and formulas A practical approach and process

    Using Microsoft Project for EVM Conclusion

  • 8/12/2019 Ev m Presentation 200509

    4/4121 September 2005 Earned Value Management 4

    A Quick Quiz

    The project budget is $200k

    The project duration is 4 months The work is evenly distributed

    After 2 months, $90k is spent

    Is the Project Over, On, or Under Budget?

    Plan

    Actual$ 50100

    150

    200

    Time1 2 3 4

  • 8/12/2019 Ev m Presentation 200509

    5/4121 September 2005 Earned Value Management 5

    The Answer: It Depends!

    The project budget is $200k The project duration is 4 months The work is evenly distributed After 2 months, $90k is spent After 2 months, the planned work is $100k What if the project is:

    50% complete?

    45% complete?

    40% complete?

    70 80 90 100

    Plan (Cost/Work) = $100k

    Actual Costs = $90k

    Work = $80kWork Accomplished = $90kWork Accomplished = $100k

    EVM Integrates Scope, Cost, and Schedule to Improve Performance Management

  • 8/12/2019 Ev m Presentation 200509

    6/41

  • 8/12/2019 Ev m Presentation 200509

    7/41

    21 September 2005 Earned Value Management 7

    EVM Background

    Background The Basics ConclusionA Process MS Project

    Late 1800s - 1962American Factories

    1962 - 1967PERT/Cost

    1967 - 1996C/SCSC

    1996 - PresentEVM: ANSI/EIA 748

    1962Introduction ofPERT/Cost 1965

    USAF formsC/SPCS group

    1967DoD issuesC/SCSC 1996

    32 EVMS criteriadefined; terms

    simplified

    1998ANSI/EIA 748guide published

    Simplificat

    ion

    Adop

    tion

    1958US Navy

    introduces PERT

  • 8/12/2019 Ev m Presentation 200509

    8/41

    21 September 2005 Earned Value Management 8

    EVM Background

    Background The Basics ConclusionA Process MS Project

    EVM Has Been Gaining Momentum

    Published Papers on Earned Value

    0

    5

    10

    15

    20

    25

    30

    1995 1996 1997 1998 1999 2000 2001 2002

  • 8/12/2019 Ev m Presentation 200509

    9/41

  • 8/12/2019 Ev m Presentation 200509

    10/41

  • 8/12/2019 Ev m Presentation 200509

    11/41

    21 September 2005 Earned Value Management 11

    The Project Lifecycle

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    12/41

    21 September 2005 Earned Value Management 12

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    13/41

    21 September 2005 Earned Value Management 13

    3+1 Core Data Elements

    Background The Basics ConclusionA Process MS Project

    Planned Value (PV)

    How much work is supposed to be done at a given point in time

    Prepared during planning as a (cumulative) time-phased budget Referred to as the performance measurement baseline AKA the budgeted cost of work scheduled (BCWS)Actual Costs (AC)

    The level of resources (typically $) expended to date Typically obtained from an organizations accounting system AKA the actual cost of work performed (ACWP)Earned Value (EV)

    How much work has actually been accomplished Obtained by tracking and measuring progress on project work AKA the budgeted cost of work performed (BCWP)Budget at Completion (BAC)

    The total planned value for the project

  • 8/12/2019 Ev m Presentation 200509

    14/41

    21 September 2005 Earned Value Management 14

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    15/41

    21 September 2005 Earned Value Management 15

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

    Planned Value

    Actual Costs

    Earned Value

  • 8/12/2019 Ev m Presentation 200509

    16/41

    21 September 2005 Earned Value Management 16

    Variances

    Background The Basics ConclusionA Process MS Project

    Cost Variance

    CV = EV AC Determines how much the project is over or under budgetSchedule Variance

    Cost: SV = EV PV Determines how much work is ahead or behind schedule

    Ignores the critical path Converges to zero

    Negative Variances are Unfavorable; Positive Variances are Favorable

  • 8/12/2019 Ev m Presentation 200509

    17/41

    21 September 2005 Earned Value Management 17

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    18/41

    21 September 2005 Earned Value Management 18

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    19/41

    21 September 2005 Earned Value Management 19

    Forecasts

    Background The Basics ConclusionA Process MS Project

    (Independent) Estimate at Completion

    (I)EAC = BAC / CPI (cost performance index) EAC = AC + ETC (estimate to complete) EAC = project manager outlook Assumes the team will continue to operate

    at the same efficiency level Projects the final cost of the project Forecasts the final project costVariance at Completion

    VAC = BAC EAC Determines how much the project will beover or under budget when done

    Studies of Hundreds or Large Defense Projects Have Shown that

    EAC Is Accurate Within a Statistical Range by the 15-20% Mark

  • 8/12/2019 Ev m Presentation 200509

    20/41

    21 September 2005 Earned Value Management 20

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    21/41

    21 September 2005 Earned Value Management 21

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    22/41

    21 September 2005 Earned Value Management 22

    Performance Indices

    Background The Basics ConclusionA Process MS Project

    Cost Performance Index (CPI)

    CPI = EV / AC Indicates the cumulative cost efficiency of a project howefficiently the team uses its resources ($)

    Schedule Performance Index (SPI)

    SPI = EV / PV Indicates how efficiently the team is using its timeTo-Complete Performance Index (SPI)

    TCPI = (BAC EV) / (BAC AC) Indicates the efficiency required on remaining work in order toachieve a target (BAC or EAC)

    For SPI and CPI, Values Greater than 1.0 Are Favorable; Less than 1.0 Are Unfavorable

  • 8/12/2019 Ev m Presentation 200509

    23/41

    21 September 2005 Earned Value Management 23

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    24/41

    21 September 2005 Earned Value Management 24

    A Framework for EVM

    Background The Basics ConclusionA Process MS Project

    Official ANSI standard for EVMS has 32 criteria; only 10 are necessary

    Define authorized work elements Identify project organizational

    structure and assign responsibility

    Integrate planning, scheduling,budgeting, work authorization,and cost accumulation processes

    Schedule the authorized work in asequential manner that identifies

    the significant task dependencies Select EV measurement

    techniques

    Establish and maintain a time-phased baseline

    Record direct costs consistently ina formal manner

    Periodically generate projectmetrics to assess performance

    Periodically develop revisedestimate at completion forecasts

    Incorporate authorized changes ina timely manner

    I.e., Practice Good Project Management

  • 8/12/2019 Ev m Presentation 200509

    25/41

    21 September 2005 Earned Value Management 25

    A Practical Process: Planning

    Background The Basics ConclusionA Process MS Project

    CostAccountant

    ProjectManager

    ProjectTeam

    Decompose work

    scope to amanageable

    level

    Assignunambiguousresponsibility

    Develop a

    performancemeasurement

    baseline

    Determine EV

    measurementtechnique for all

    tasks

    Determinereportingfrequency

    Provide time-phased budget tocost accountant

    Basic

    PMEV

    PV BAC

    1

    2

    3

    5

    4

    6

    #MS Project Demo

  • 8/12/2019 Ev m Presentation 200509

    26/41

  • 8/12/2019 Ev m Presentation 200509

    27/41

    21 September 2005 Earned Value Management 27

    Earned Value Recognition

    Background The Basics ConclusionA Process MS Project

    Fixed formulas

    Used on short-duration tasks

    Used when product is well-understood

    E.g., 50/50 or 25/75, or 0/100Weighted milestone

    Used on long-duration tasks Used when there are observable

    intermediate milestones Value is assigned to milestonesPercent complete Simple and easy Subjective Used when no objective

    indicators exist

    Apportioned effort

    Used when a task has a direct,supportive relationship to anothertask (e.g., quality assurance (QA))

    Typically calculated as apercentage of main task EV

    Level of effort

    Used for activities that do notproduce tangible outcomes e.g.,

    project management PV is automatically credited asEV at end of each period

  • 8/12/2019 Ev m Presentation 200509

    28/41

    21 September 2005 Earned Value Management 28

    Earned Value Recognition

    Background The Basics ConclusionA Process MS Project

    Duration of Work Effort

    Product of Work 1-2 Measurement Periods >2 Measurement Periods

    TangibleFixed Formula

    Weighted Milestone

    Percent Complete

    Intangible Apportioned Effort

    Level of Effort

    Recognition Methods for Project Activities Should Be Determined During Planning

  • 8/12/2019 Ev m Presentation 200509

    29/41

  • 8/12/2019 Ev m Presentation 200509

    30/41

    21 September 2005 Earned Value Management 30

    Our Project: Painting

    Background The Basics ConclusionA Process MS Project

  • 8/12/2019 Ev m Presentation 200509

    31/41

    21 September 2005 Earned Value Management 31

    Our Schedule

    Background The Basics ConclusionA Process MS Project

    WBS Task Nam e

    0 Painting the Room1 Design

    1.1 Browse catalogs for ideas1.2 Obtain swatches

    1.3 Evaluate swatches and choose paints

    John Doe,Jane DoeJohn Doe,Jane Doe

    8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PMTue Oct 25 Wed Oct 26

    WBS Task Name

    2 Procurement

    2.1 Procure paint and supplies

    3 Preparation

    3.1 Take down pictures

    3.2 Remove electrical outlets

    3.3 Tape walls

    3.4 Room ready for painting

    4 Painting

    4.1 Paint wall 1

    4.2 Paint wall 2

    4.3 Paint wall 3

    4.4 Paint wall 4

    4.5 Room painted

    4.6 Paint dried

    5 Cleanup

    5.1 Remove tape

    5.2 Touch up mistakes

    5.3 Install electrical outlets

    5.4 Hang pictures

    6 Painting complete

    John Doe,Paint and s upplies[1]

    Jane Doe

    Jane Doe

    John Doe

    10/27

    John Doe

    Jane Doe

    John Doe

    Jane Doe

    10/28

    10/28

    John Doe,Jane Doe

    John Doe

    Jane Doe

    Jane Doe,John D

    10/29

    8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PMFri Oct 28 Sat Oct 29

  • 8/12/2019 Ev m Presentation 200509

    32/41

    Producing a Time Phased Budget5

  • 8/12/2019 Ev m Presentation 200509

    33/41

    21 September 2005 Earned Value Management 33

    Producing a Time Phased Budget(cont.)5

    Background The Basics ConclusionA Process MS Project

    Option 2: Analysis Toolbar

    9 k d

  • 8/12/2019 Ev m Presentation 200509

    34/41

    21 September 2005 Earned Value Management 34

    9 Track and Report ProgressBackground The Basics ConclusionA Process MS Project

    First, save a baseline

    Set the status date Track progress

    View the % complete

    or earned value

    Retrieve Actual Costs;10

  • 8/12/2019 Ev m Presentation 200509

    35/41

    21 September 2005 Earned Value Management 35

    Retrieve Actual Costs;Analyze Data10

    Plug AC and EV into spreadsheet model If necessary, calculate EV from % complete:

    EV = BAC * % complete

    Background The Basics ConclusionA Process MS Project

    P t ti F t

  • 8/12/2019 Ev m Presentation 200509

    36/41

    21 September 2005 Earned Value Management 36

    Presentation Formats

    Background The Basics ConclusionA Process MS Project

    Project

    S-curves Dashboard speedometers

    Bulls-eye chartPortfolio

    Bulls-eye chart

    SPI/CPI trending

    P t ti F t P j t

  • 8/12/2019 Ev m Presentation 200509

    37/41

    21 September 2005 Earned Value Management 37

    Presentation Formats: Project

    Background The Basics ConclusionA Process MS Project

    30.1 99.0

    P t ti F t P tf li

  • 8/12/2019 Ev m Presentation 200509

    38/41

    21 September 2005 Earned Value Management 38

    Presentation Formats: Portfolio

    Background The Basics ConclusionA Process MS Project

    C l i

  • 8/12/2019 Ev m Presentation 200509

    39/41

    21 September 2005 Earned Value Management 39

    Conclusion

    EVM is NOT HARD! (But the acronyms are!)

    EVM can be applied to any project with a definedscope, schedule, and budget

    EVM provides a closed-loopfeedback system

    EVM is predictive

    EVM will impress your friends EVM is gaining momentum

    Background The Basics ConclusionA Process MS Project

    EVM Is Coming to a Project Near You

  • 8/12/2019 Ev m Presentation 200509

    40/41

    21 September 2005 Earned Value Management 40

    Earned Value ManagementManaging Scope, Cost, and Schedule to

    Improve Project Performance

    Scott S. Lynde, PMP

    21 September 2005

    Reference

  • 8/12/2019 Ev m Presentation 200509

    41/41

    21 September 2005 Earned Value Management 41

    Reference

    Fleming, Quentin W. and Koppelman, Joel M.Earned Value Project Management, 2nd Ed.

    Project Management Institute, June 2000.

    Practice Standard For Earned Value ManagementProject Management Institute, October 2004.

    Christensen, David S. and Heise, Scott."Cost Performance Index StabilityNational Contract Management Journal 25, Spring1993, pp. 7-15.