A low - cost high performance MV RMU with circuit breakers for use in remote controlled MV / LV substations. Luca GIANSANTE. Fabio GIAMMANCO. Italian AEEG regulation scenario Main strategies Limits of current switchgear Overcome apparatus limits New approach State of the Art: DY900 - PowerPoint PPT Presentation
Citation preview
Frankfurt (Germany), 6-9 June 2011
A low - cost high performance MV RMU with circuit breakers for use in remote
controlled MV / LV substations
Fabio GIAMMANCO Luca GIANSANTE
Frankfurt (Germany), 6-9 June 2011
• Italian AEEG regulation scenario• Main strategies• Limits of current switchgear• Overcome apparatus limits• New approach• State of the Art: DY900• Results• Developments
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Main content
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Italian AEEG regulation scenario
Italian Authority for Electrical Energy and Gas (AEEG)
CUMULATIVE DURATION OF LONG LASTING
SUPPLY INTERRUPTION PER LV CUSTOMER
> 3 minutes• Planned
• Accidental with fault localization
• Accidental without fault localization
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Italian AEEG regulation scenarioFRAME REGULATION
• DURATION OF LV CUSTOMER SUPPLY INTERRUPTIONS WITHOUT NOTICE
• NUMBER OF SUPPLY INTERRUPTIONS WITHOUT NOTICE PER LV CUSTOMER
INDIVIDUAL REGULATION
• NUMBER OF CUSTOMER SUPPLY INTERRUPTIONS (FOR MV CUSTOMERS ONLY)
• LONG LASTING INTERRUPTIONS (LV AND MV CUSTOMERS)
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Italian AEEG regulation scenario
FOCUS
• DURATION OF LV CUSTOMER SUPPLY
INTERRUPTIONS
• NUMBER OF SUPPLY INTERRUPTIONS WITHOUT
NOTICE PER LV CUSTOMER
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Main strategies
1. REDUCE THE TIME NECESSARY TO FIND AND ISOLATE THE FAULT KEEPING IT AS SHORT AS THE 3 MIN DEADLINE
2. MINIMIZE THE NUMBER OF CUSTOMERS AFFECTED BY THE FAULT
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Limits of current switchgear
SWITCH DISCONNECTORS MAIN LIMITS
• OPERATION TIME
• MAKING AND BREAKING CAPABILITY
• ELECTRICAL AND MECHANICAL ENDURANCE
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
THE GOAL
TO OVERCOME THE SWITCH DISCONNECTOR LIMITS WHILST FINDING
A GOOD TRADE-OFF BETWEEN THE NEED FOR THE EXPECTED PERFORMANCE AND LIFETIME COSTS
Overcome apparatus limits
Frankfurt (Germany), 6-9 June 2011
CIRED WIEN 2007 CIRED PRAGUE 2009
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Overcome apparatus limits
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
With ICS DY800
Overcome apparatus limits
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
New approach
Compact RMU with circuit-breaker per each line with disconnector and grounding switch
Configuration: 2LineCB + 1PT
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
State of the art: DY900
Underwater immersion resistant
Compatible with remote control smart units
High perfomance
Highly reliable in polluted networks
Frankfurt (Germany), 6-9 June 2011
• DY900 is fast, accurate, reliable and easy to adapt into existing systems.
• 10% - 15% reduction of the cumulative duration of long lasting supply interruption per LV customer.
• 40% reduction of the number of interruptions per customer.
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Results
Frankfurt (Germany), 6-9 June 2011
High level of
performance and economy
Adoption of SF6
insulated solutions
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Results
Reliability andoperational safety
Environmental issue
Frankfurt (Germany), 6-9 June 2011
• Two additional configurations: 3LineCB + 1PT and 3LineCB.
• Device for MV customer connection SF6 insulated with current and voltage transformer inside.
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Next developments
Frankfurt (Germany), 6-9 June 2011
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468
Next developments
Frankfurt (Germany), 6-9 June 2011
THANKS FOR YOUR ATTENTION
Luca GIANSANTE – ITALY – Session 3 – Paper ID0468