2
(2018 exc. GST for three dwellings inc. transport) February 2019 HOW to Prefab Transition Housing PROJECT INTENT 1m 1.5m 2m 2.5m 0m 4m 6m 2m 8m Completed Transition Housing Portal frames, panels and roof assembled on-site (construction only) Contractor: Architect: Te Puni Kokiri – Ha o te Ora Wharekauri Trust Easybuild Ltd (PrefabNZ Member) Easybuild Ltd (PrefabNZ Member) Tony Synge Easybuild Ltd Bay of Plenty branch Completed December 2018 Structural Engineer: Builder: Status: Floor Area: Prefab Type: Prefab Materials Used: 73.3m² per dwelling Panel + Component Timber portal frames, pre-finished panels on screw pile foundations 2018 Islands Chatham This case study follows the prefabrication, transportation and assembly of three dwellings from New Plymouth to the Chatham Islands - the first of 15 houses provided by Easybuild into this remote New Zealand community. COST (NZD) TIME (months) Client: Ha o te Ora Wharekauri Trust wanted to implement transitional housing on the Chatham Islands for those who need short- term accommodation before moving into permanent homes. This required a quality housing solution with maximum speed of construction. Easybuild’s Bay of Plenty (BOP) branch was the contractor appointed for the three dwellings. In a 12-week programme, Easybuild completed three new homes alongside the infrastructure for the following twelve dwellings. The use of prefabrication, pre- planning and MultiProof¹ consents enabled this project to meet its challenging time- frame. Building in the remote, boat-access-only, Chatham Island’s was the overarching challenge for the project. The Islands have limited sub-trades as well as scarce and expensive food and accommodation. The lack of building supplies available meant all supplies for the project needed to be shipped from mainland New Zealand (NZ). The exposed weather conditions and limited cellphone reception also posed challenges to the project. Many construction activities were being completed concurrently to meet the short timeframe, which consequently meant the project was being built faster than Local Authority could inspect and fundamentally challenged the construction completion time- frames. PROJECT CHALLENGES ¹ A MultiProof consent is a national multiple-use approval statement by the Ministry of Business, Innovation and Employment (MBIE) which states that a set of plans and specification for a building complies with Building Code.

February 2019 HOW to Prefab Transition Housing€¦ · Prefab Type: Prefab Materials Used: 73.3m² per dwelling Panel + Component Timber portal frames, pre-finished panels on screw

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • (2018 exc. GST for threedwellings inc. transport)

    February 2019 HOW to Prefab

    Transition Housing

    PROJECT INTENT

    1M 1.5M 2M 2.5M 0m 4m 6m2m 8m

    Completed Transition Housing

    Portal frames, panels and roof assembled on-site

    (construction only)

    Contractor:

    Architect:

    Te Puni Kokiri – Ha o te Ora Wharekauri Trust

    Easybuild Ltd (PrefabNZ Member)

    Easybuild Ltd (PrefabNZ Member)

    Tony Synge

    Easybuild Ltd Bay of Plenty branch

    Completed December 2018

    Structural Engineer:

    Builder:

    Status:

    Floor Area:

    Prefab Type:

    Prefab Materials Used:

    73.3m² per dwelling

    Panel + Component

    Timber portal frames, pre-finished panels on screw pile foundations

    2018

    IslandsChatham

    This case study follows the prefabrication, transportation and assembly of three dwellings from New Plymouth to the Chatham Islands - the first of 15 houses provided by Easybuild into this remote New Zealand community.

    COST (NZD) TIME (months)

    Client: Ha o te Ora Wharekauri Trust wanted to implement transitional housing on the Chatham Islands for those who need short-term accommodation before moving into permanent homes. This required a quality housing solution with maximum speed of construction. Easybuild’s Bay of Plenty (BOP) branch was the contractor appointed for the three dwellings.

    In a 12-week programme, Easybuild completed three new homes alongside the infrastructure for the following twelve dwellings. The use of prefabrication, pre-planning, and MultiProof¹ consents enabled this project to meet its challenging time-frame.

    Building in the remote, boat-access-only, Chatham Island’s was the overarching challenge for the project. The Islands have limited sub-trades as well as scarce and expensive food and accommodation. The lack of building supplies available meant all supplies for the project needed to be shipped from mainland New Zealand (NZ). The exposed weather conditions and limited cellphone reception also posed challenges to the project.

    Many construction activities were being completed concurrently to meet the short time-frame. Consequently, this meant the project was being built faster than Local Authority could inspect and fundamentally challenged the construction completion time-frames.

    PROJECT CHALLENGES

    ¹ A MultiProof consent is a national multiple-use approval statement by the Ministry of Business, Innovation and Employment (MBIE) which states that a set of plans and specification for a building complies with the Building Code.

    (2018 exc. GST for threedwellings inc. transport)

    February 2019 HOW to Prefab

    Transition Housing

    PROJECT INTENT

    1m 1.5m 2m 2.5m 0m 4m 6m2m 8m

    Completed Transition Housing

    Portal frames, panels and roof assembled on-site

    (construction only)

    Contractor:

    Architect:

    Te Puni Kokiri – Ha o te Ora Wharekauri Trust

    Easybuild Ltd (PrefabNZ Member)

    Easybuild Ltd (PrefabNZ Member)

    Tony Synge

    Easybuild Ltd Bay of Plenty branch

    Completed December 2018

    Structural Engineer:

    Builder:

    Status:

    Floor Area:

    Prefab Type:

    Prefab Materials Used:

    73.3m² per dwelling

    Panel + Component

    Timber portal frames, pre-finished panels on screw pile foundations

    2018

    IslandsChatham

    This case study follows the prefabrication, transportation and assembly of three dwellings from New Plymouth to the Chatham Islands - the first of 15 houses provided by Easybuild into this remote New Zealand community.

    COST (NZD) TIME (months)

    Client: Ha o te Ora Wharekauri Trust wanted to implement transitional housing on the Chatham Islands for those who need short-term accommodation before moving into permanent homes. This required a quality housing solution with maximum speed of construction. Easybuild’s Bay of Plenty (BOP) branch was the contractor appointed for the three dwellings.

    In a 12-week programme, Easybuild completed three new homes alongside the infrastructure for the following twelve dwellings. The use of prefabrication, pre-planning and MultiProof¹ consents enabled this project to meet its challenging time-frame.

    Building in the remote, boat-access-only, Chatham Island’s was the overarching challenge for the project. The Islands have limited sub-trades as well as scarce and expensive food and accommodation. The lack of building supplies available meant all supplies for the project needed to be shipped from mainland New Zealand (NZ). The exposed weather conditions and limited cellphone reception also posed challenges to the project.

    Many construction activities were being completed concurrently to meet the short timeframe, which consequently meant the project was being built faster than Local Authority could inspect and fundamentally challenged the construction completion time-frames.

    PROJECT CHALLENGES

    ¹ A MultiProof consent is a national multiple-use approval statement by the Ministry of Business, Innovation and Employment (MBIE) which states that a set of plans and specification for a building complies with Building Code.

  • Transition Housing

    Portal frames assembled on-site

    Easybuild creates its affordable housing units with custom pre-finished panels that are fitted between timber portal frames. These building elements are constructed in-factory, flat-packed and then shipped to site where they are assembled twice as fast as conventional homes. These houses can be built with semi-skilled labour and are approximately 30% cheaper to build than bespoke homes.

    The clients and funders are thrilled with the project’s outcome. The use of prefabrication over conventional construction saved the client approximately $400,000 and allowed the project to be completed eight months faster. This project is a great example of how good planning teams can be mobilised to deliver efficient and affordable housing in almost any location.

    MATERIAL

    CONSTRUCTION

    FEEDBACK

    HOW to Prefab Transition Housing

    REFERENCES

    Mike Fox (Easybuild Ltd). Personal Communication with Eleni Timoteo. December, 2018. Images: Courtesy of Easybuild Ltd

    For more information on Easybuild visit:https://www.easybuild.co.nz/

    The use of Surefoot² driven pole piles enabled the construction of foundations for all three homes when more conventional solutions were not available on the Island. This meant the houses were ready for their floors sooner than conventional piling. The limited access to machinery on the Island meant Easybuild needed to drive the piles in with kango hammers. The factory-made building elements slotted together at site to reduce the need for trimming. One form of fixing was predominantly used to assemble each dwelling structure. Repetition in fixing heavily reduced on-site construction time, and as a result, reduced the project’s cost.

    Given the challenges of building remotely, it typically takes 12 months to complete a single traditional dwelling in the Chatham Islands. The locals were therefore sceptical about the predicted 12-week timeframe. When the project’s construction came to completion the locals were very impressed by the successful outcome and 75% time savings.

    The success of the project relied on timely delivery and product suitability. Prefabricated construction supported this success and eased the construction of the offshore project.

    prefabnz.com

    Southern Tiare - Ship used for project transportation

    Dwelling site plan (not to scale)

    ² Surefoot footings are an “all in one system” that does not need concrete. The shape and high strength steel combine to create a very efficient pile cap.

    https://www.easybuild.co.nz/