Fm Project Epdib 2010-11

Embed Size (px)

Citation preview

  • 8/8/2019 Fm Project Epdib 2010-11

    1/43

    FM Project EPGDIB 2010-11

    Submitted By : SatishKumar Deshpande

    Roll No. 85

  • 8/8/2019 Fm Project Epdib 2010-11

    2/43

  • 8/8/2019 Fm Project Epdib 2010-11

    3/43

    Problem 1 Share Purchase decision Pg 66

    Problem 5

    a) Value of Bond at

    market rate of 9%

    Interest 60

    Required Rate of Return 0.09

    Terminal value of Bond 1000

    Current Bond Value 924.1

    Texo

    Interest 90

    Required Rate of Return 0.09

    Terminal value of Bond 1000

    Current Bond Value 1000

    Maxco

    Current value of Taco will be Rs. 924 and that of Maco will be Rs.

    1000 per bond.

  • 8/8/2019 Fm Project Epdib 2010-11

    4/43

    Problem 1 Share Purchase decision Pg 66

    Problem 5

    b) Value of Bond at

    market rate of

    12%

    Texo

    Maxco

    Current value of Taco will be Rs.855.89 and that of Maco will be

    Rs. 927.94 per bond.

    Interest 60

    Required Rate of Return 0.12

    Terminal value of Bond 1000

    Current Bond Value 856

    Interest 90

    Required Rate of Return 0.12

    Terminal value of Bond 1000

    Current Bond Value 927.95

  • 8/8/2019 Fm Project Epdib 2010-11

    5/43

    Problem 1 Share Purchase decision Pg 66

    Problem 5c) Which Bond declins more with Inc in Intrest rate ?

    The reduction is high in Maxo as the coupon interest rate is higher

    in Taxo than compared to Taxo.

    Value of Bond V/s Int rate

    0

    200

    400

    600

    800

    1000

    1200

    4% 5% 6% 7% 8% 9% 10% 11% 1 2% 13% 14% 15%

    Int Rate

    Va

    lueo

    fBon

    d Texo

    Maxco

    Sl. NoInte re st

    ra te T e x o M a x c o

    Diffo ve r

    pre vio usT e x o

    Diffo ve r

    pre vio usM a x c o

    1 4 % 1055.5 1138.8 NA NA

    2 5 % 1027.2 1108.9 28.3 29.8

    3 6% 1000.0 1080.2 27.2 28.7

    4 7% 973.8 1052.5 26.2 27.7

    5 8% 948.5 1025.8 25.3 26.7

    6 9% 924.1 1000.0 24.4 25.8

    7 10% 900.5 975.1 23.5 24.9

    8 11% 877.8 951.1 22.7 24.0

    9 12% 855.9 927.9 21.9 23.2

    10 13% 834.7 905.6 21.2 22.4

    11 14% 814.3 883.9 20.4 21.6

    12 15% 794.5 863.0 19.8 20.9

  • 8/8/2019 Fm Project Epdib 2010-11

    6/43

    Problem 1 Share Purchase decision Pg 66

    Problem 5

    d) Value of Bond at

    market rate of 6%

    Texo

    Maxco

    Current value of Taco will be Rs.1000 and that of Maco will be Rs.

    1080 per bond.

    Interest 60

    Required Rate of Return 0.06

    Terminal value of Bond 1000

    Current Bond Value 1000.0

    Interest 90

    Required Rate of Return 0.06

    Terminal value of Bond 1000

    Current Bond Value 1080.2

  • 8/8/2019 Fm Project Epdib 2010-11

    7/43

    Problem 1 Share Purchase decision Pg 66

    Problem 5

    E-a) Value of Bond at

    market rate of 6%

    and maturity 8years

    Texo

    Maxco

    Current value of Taco will be Rs.834 and that of Maco will be Rs.

    1080 per bond.

    Interest 60

    Required Rate of Return 9%

    Terminal value of Bond 1000

    Current Bond Value 834

    Interest 90

    Required Rate of Return 9%

    Terminal value of Bond 1000

    Current Bond Value 1000.0

  • 8/8/2019 Fm Project Epdib 2010-11

    8/43

    Problem 1 Share Purchase decision Pg 66

    Problem 5

    E-b) Value of Bond at

    market rate of 6%

    and maturity 8years

    Texo

    Maxco

    Current value of Taco will be Rs.1000 and that of Maco will be Rs.

    1186 per bond.

    Interest 60

    Required Rate of Return 6%

    Terminal value of Bond 1000

    Current Bond Value 1000

    Interest 90

    Required Rate of Return 6%

    Terminal value of Bond 1000

    Current Bond Value 1186.3

  • 8/8/2019 Fm Project Epdib 2010-11

    9/43

    Problem 1 Share Purchase decision Pg 66

    Problem 5

    E-b) Value of Bond at

    market rate of

    12% and maturity8 years

    Texo

    Maxco

    Current value of Taco will be Rs.702 and that of Maco will be Rs.

    851 per bond.

    Interest 60

    Required Rate of Return 12%

    Terminal value of Bond 1000

    Current Bond Value 702

    Interest 90

    Required Rate of Return 12%

    Terminal value of Bond 1000

    Current Bond Value 851.0

  • 8/8/2019 Fm Project Epdib 2010-11

    10/43

    Problem No 2 Page 67 -19

    Value of Share

  • 8/8/2019 Fm Project Epdib 2010-11

    11/43

    Problem 2 Share Value Pg 67 Problem 19

    Please Ref the excel sheet for detail calculation.

    Sl. No Assumption NPV Decision

    1 Dividend Payout constant 30 Since NPV is < 80 Do Not Purchase

    2 Dividend Growth at 6% per year perpetuity 81 Buy The share as NPV>80

    3 Different Growth Rate Varied 68.81 Since NPV is < 80 Do Not Purchase

  • 8/8/2019 Fm Project Epdib 2010-11

    12/43

    Problem No 3 Page 81 -11

    Which security to select for Investment

  • 8/8/2019 Fm Project Epdib 2010-11

    13/43

    Problem 3Which Share to select (

    Expected rate of return & Variance)

    Return

    Probabili

    ty Expected Rate of Return Variance

    30% 0.1 3% 0.06%

    20% 0.2 4% 0.10%

    10% 0.4 4% 0.20%

    5% 0.2 1% 0.20%

    -10% 0.1 -1% 0.14%

    Total 1 11% 0.70%

    Since the standard Deviation is low in company Y and Expected

    rate of return is high in Y choose company Y

    Security X

    Std Dev 8%

    Return

    Probabilit

    y Expected Rate of Return

    Varianc

    e

    -20% 0.05 -1% 0.07%

    10% 0.25 3% 0.18%

    20% 0.3 6% 0.08%

    30% 0.3 9% 0.01%

    40% 0.1 4% 0.05%

    Total 1 21% 0.39%

    Std Dev 6%

    Security Y

  • 8/8/2019 Fm Project Epdib 2010-11

    14/43

  • 8/8/2019 Fm Project Epdib 2010-11

    15/43

  • 8/8/2019 Fm Project Epdib 2010-11

    16/43

    Problem No 5 Page 115 -02

    Beta and risk of the project

  • 8/8/2019 Fm Project Epdib 2010-11

    17/43

    Problem 5Beta & risk of Project

    Since the expected rate of return of the company and the new

    project is same we can accept the project.

    More over the risk of project is similar to firms current risk

    Beta 1.21

    Risk free rate of return 8.50%

    Market premium 9.50%

    Expected rate of return on New project 20%

  • 8/8/2019 Fm Project Epdib 2010-11

    18/43

    Problem No 6 Page 164 -11

    IRR from NPV Graph

  • 8/8/2019 Fm Project Epdib 2010-11

    19/43

    Problem 6 IRR from NPV Graph

    Discount rate Project A Project B

    0% INR 7,784.00 INR 5,830.00

    5% INR 5,712.34 INR 4,689.56

    10% INR 3,977.46 INR 3,696.47

    20% INR 1,263.89 INR 2,054.40

    30% (INR 731.00) INR 755.58

    40% (INR 2,236.15) (INR 295.19)

    Based on the Higher IRR and also based on the fact that NPV will

    turn negative only after37% risk of capital

    I would recommend project B

    IRR through NPV Graph

    (INR4,000.00)

    (INR2,000.00)

    INR0.00

    INR2,000.00

    INR4,000.00

    INR6,000.00

    INR8,000.00

    INR10,000.00

    0% 5% 10% 20% 30% 40%

    Discount Rate

    NPV

    Project A

    Project B

    37%

    26%

  • 8/8/2019 Fm Project Epdib 2010-11

    20/43

    Problem No 7 Page 190 -08

    WACC

  • 8/8/2019 Fm Project Epdib 2010-11

    21/43

    Problem No 7 Page 190 -08

    WACC

    Source of capital BV BV Weight MV MV Weights

    Cost of

    Capit

    al W eighted avg BV Weighted Avg MV

    Ordinary Shares 30 0.3 60 0.5 15.57% 5% 8%

    Reservs 10 0.1 0 15.57% 2% 0%

    Preference Shares 20 0.2 24 0.2 10% 2% 2%

    Debt 40 0.4 36 0.3 11% 4% 3%

    Total 100 1 120 1 12% 13%

    Weighted Avg cost of Capital on book value is 12% and on

    Market value it is 13%

  • 8/8/2019 Fm Project Epdib 2010-11

    22/43

    Problem No 8 Page 224 -07

    New Machine Proposal

  • 8/8/2019 Fm Project Epdib 2010-11

    23/43

    Problem No 8 Page 224 -07

    New Machine ProposalCost of new machine 40000

    Installation cost 8000

    Cash salvage of old

    machine -20000

    Total Investment 28000

    Dep per year on St

    line method 7000

    1. Initial Investment

    Cash flow due to investment 28000

    Increase in working Capital 10000

    Total 38000

    2. Cash Flow Initial Year

  • 8/8/2019 Fm Project Epdib 2010-11

    24/43

    Problem No 8 Page 224 -07

    New Machine Proposal

    Annual Saving before tax 16000

    Tax -6400

    Saving in cash due to Dep effect 2800

    Net cash inflow 12400

    3. Cash Flow in Subsequent Years Initial

    Investment

    Salvage Value of new machine 14000

    Opportunity lot due to diaposal of old machine inyear Zero

    -4000

    Working capital returned back 10000

    Diff tax paid on sale of Machine -4000

    Toatl cash flow 16000

    4. Cash flow Final Year

  • 8/8/2019 Fm Project Epdib 2010-11

    25/43

    Problem No 8 Page 224 -07

    New Machine Proposal

    Time Period Cash flow

    0 -38000

    1 12400

    2 12400

    3 12400

    4 28400

    NPV 12235

    Calculations of NPV

    Since NPV is positive accept the project

    Since IRR > 10% accept the project

    Profitability > 1 accept the project.

  • 8/8/2019 Fm Project Epdib 2010-11

    26/43

    Problem No 9 Page 224 -07

    Indopax Should the machine be bought

  • 8/8/2019 Fm Project Epdib 2010-11

    27/43

    Problem No 9 Page 224 -07

    Indopax Should the machine be bought

    Profitablity statemnt of the company

    Year 1 Year 2 Year 3 Year 4 Year 5

    Quantity 10000 12000 14400 17280 20736

    Sleeling price 20 22 24.2 26.62 29.282

    Total Sales 200000 264000 348480 459993.6 607191.6

    Cost / Unit 10 11.5 13.225 15.20875 17.49006

    COGS 100000 138000 190440 262807.2 362673.9

    EBDIT 100000 126000 158040 197186.4 244517.6

    Depriciation 100000 100000 100000 100000 100000

    EBIT 0 26000 58040 97186.4 144517.6

    Tax @ 35% 0 9100 20314 34015.24 50581.17

    PAT 0 16900 37726 63171.16 93936.45

    Cash flow 100000 116900 137726 163171.2 193936.5

  • 8/8/2019 Fm Project Epdib 2010-11

    28/43

    Problem No 9 Page 224 -07

    Indopax Should the machine be bought

    Year I cash flow 500000

    Cash Flow pattern

    Year Cash Flow

    0 -500000

    1 100000

    2 116900

    3 137726

    4 163171.16

    5 193936.45

    Nominal Disciunt rate 0.2

    inflation 0.1

    Real discount rate 0.09091

    NPV Using Real discount rate $36,710.03

    Since NPV is positive the machine should be bought

  • 8/8/2019 Fm Project Epdib 2010-11

    29/43

    Problem No 10 Page 241 -01

    Damodar Company

  • 8/8/2019 Fm Project Epdib 2010-11

    30/43

    Problem No 10 Page 241 -01

    Damodar Company

    Project C0 C1 C2 C3 C4 NPV 10% PVAFA AEV

    X 150 30 30 30 30 222.81 3.17 70.29

    Y 75 40 40 131.29 1.736 75.63

    Since the annual equivalent cost of Y is grater than X accept project Y

  • 8/8/2019 Fm Project Epdib 2010-11

    31/43

    Problem No 11 Page 309 -10

    DOL, DFL and combined leverage

  • 8/8/2019 Fm Project Epdib 2010-11

    32/43

  • 8/8/2019 Fm Project Epdib 2010-11

    33/43

    Problem No 11 Page 309 -10

    DOL, DFL and combined leverage

    This ratio can be very useful, as it summarizes theeffects of combining both financial and operatingleverage, and what effect this combination, or

    variations of this combination, has on thecorporation's earnings. Not all corporations useboth operating and financial leverage, but if they do,then this formula can be used.

    It is worth noting that a firm with a relatively highlevel of combined leverage is seen as riskier than afirm with less combined leverage, as the highleverage means more fixed costs to the firm.

    What is the effect of combined leverage ?

  • 8/8/2019 Fm Project Epdib 2010-11

    34/43

    Problem No.12

    Assuming the existence of the corporate

    income taxes describe M-M position

    on the issue of an optimum capitalstructure

  • 8/8/2019 Fm Project Epdib 2010-11

    35/43

    Problem No.12

    Please open the Below link in EDIT

    mode. ( In case you are not able to

    view it please ref the attached files inthe zip folder.

    Microsoft Word

    Document

  • 8/8/2019 Fm Project Epdib 2010-11

    36/43

    Problem No.13

    Define capital Structure. What are the

    elements of capital structure?

    What do you mean by appropriate capital

    Structure?

    Whar are the features of Appropriate

    Capital Structure

  • 8/8/2019 Fm Project Epdib 2010-11

    37/43

    Problem No.13

    Please open the Below link in EDIT

    mode. ( In case you are not able to

    view it please ref the attached files inthe zip folder.

    Microsoft Word

    Document

  • 8/8/2019 Fm Project Epdib 2010-11

    38/43

    Problem No.14

    The primary purpose for which a firm

    exists is the payment of dividend.

    Therefore, irrespective of the firmsneeds and the desires of shareholders,

    a firm should follow a policy of very

    high dividend payout. Do you agree?Why and Why not?

  • 8/8/2019 Fm Project Epdib 2010-11

    39/43

    Problem No.14

    Please open the Below link in EDIT

    mode. ( In case you are not able to

    view it please ref the attached files inthe zip folder.

    Microsoft Word

    Document

  • 8/8/2019 Fm Project Epdib 2010-11

    40/43

    Problem No 15 Page 412 -03

    Brown & Crown

  • 8/8/2019 Fm Project Epdib 2010-11

    41/43

  • 8/8/2019 Fm Project Epdib 2010-11

    42/43

    Problem No 15 Page 412 -03

    Brown & Crown

    Conclusion It seems that Brown is paying a uniform Dividend irrespective of the performance of

    the company.

    We cannot tell from the figures which company is more profitable unless we knowthe capital structure of the company.

    Since brown is giving consistent Dividend it is perceived as a more stable company

    compared to Crown.

    Due to the above reason Brown has

    higher market price.

  • 8/8/2019 Fm Project Epdib 2010-11

    43/43