13
06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24 - Hanger 26 - Etc 27 IV. Technical Data - Impedence 28 - Voltage Drop 28 - Temperature Rise 29 V. Install Information 30

(LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

06 / 07

CR-LVLS 전선 Busduct System Catalogue

06 of 08

ContentsII. General Data 20

III. Component

- Feeder 22

- Flanged End 23

- Fittings 24

- Hanger 26

- Etc 27

IV. Technical Data

- Impedence 28

- Voltage Drop 28

- Temperature Rise 29

V. Install Information 30

Page 2: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

Ⅱ. General Data

Congration

Indoor Type

[3 conductor] [4 conductor] [5 conductor]

Outdoor Type (sun exposure)[

Basic StructureThe CR-LV consists of conductors and epoxy resin. Since the resin performs as insulation and housing which provides protec-

tion to the interior structure, additional bus ducts or housing are not necessary.

For outdoor installation (sun exposure), a sun shade is used to prevent the epoxy resin from being exposed to direct sunlight.

• Sunshade(steel)

While other bus ducts with metal housing require grounding, the CR-LV does not require additional grounding because the epoxy resin insulation

itself performs as housing. (Additional grounding is available on request. Please contact our design team for further information.)

R R RS S ST T TN/E N/E N/E

]

20 CR-LV/MV LS C&S-Busway System

TOSHIBA
Highlight
20001066
텍스트 상자
CR-LV Housing is consist of epoxy insulation material, not metal housing therefore, it does not need outer earthing bar (Additional grounding is available on request. Please contact our design team for further information)
Page 3: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

06 / 07

Double-headed bolts are used to ensure a proper torque level when installing

the joint kit. If a torque wrench applies a pressure of 800 to 1000kgf·cm to the

outer bolt head, the head of the outer bolt and the tag attached to it will break

off on its own. Thus, it allows easy inspection for the proper application of the

bolts at the connection.

Double Head Bolts

Both joint plates of the joint kit and the conductors are tin plated. (A silver

plated option is available.) It prevents discoloration and corrosion of the joint

plates. In order to ensure easy maintenance and reliability, double -headed

bolts and visible labels are used to check the application, and a disc spring

allows an even connection of the contact surface.

Feature

The CR-Way uses a joint kit method.

!

sure a proper torque level when installing

ies a pressure of 800 to 1000kgf·cm to the

er bolt and the tag attached to it will break

spection for the proper application of the

pp pr g

ontact surface.

Joint Kit

Precaution

Be sure to clean the interior of the connections prior to installation. Use caution not to twist the joint kit while inserting it, and after it is inserted.

An excessive pressure during installation may break the kit. Make sure that the double-headed bolts and the red tags are intact.

If a proper torque is not applied at the connection, it may cause heat during operation.

The number of double-headed

Number of DH bolts 1 2 3 4 6

630, 800, 1000,

1250, 1600, 2000CU

Ampere

(A)AL

2500, 3200,

3600, 40005000 6300 7500

630, 800,

1000, 1250

1600,

2000, 2500-

3200,

3600, 40005000, 6300

Ge

me

ral D

ata

CR-LV/MV LS C&S-Busway System 21

Page 4: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

Ⅲ Component

FeederAlthough the standard length of the LS C&S CR-LV Bus Duct feeder is 3 meters, it can be adjusted to the installation

environment, or on request.

[Fig. CL1-3]

B

t

W A

B B

W A

140

2B+140

[Fig. CL1-2] [Fig. CL1-2]

B

3B+280

B

W A

140B 140

Ampere(A)Dimension(mm) Weight(kg/m)

Fig.t W A 3W 4W 4W+50%E 4W+100%E

AL

630

6.35

41 78 21.3 23.7 23.2 23.3

CL1-1

800 65 102 26.7 30.4 29.5 29.6

1000 86 123 32.4 37.8 36.3 36.4

1250 108 145 38.5 42.7 42.7 42.6

1600 164 201 53.5 59.4 59.3 59.4

2000 210 247 65.7 72.9 72.8 71.9

2500 126 163 85.2 99.4 95.1 97.4

3200 164 201 106.3 118 118 118.4

CL1-23600 184 221 116.4 129.7 129.6 130.1

4000 210 247 124.7 138.6 139 139.3

5000 184 221 182.8 193.2 193.4 189.1

6300 210 247 192.6 214.8 215.3 214.4CL1-3

CU

630

6.35

41 78 26.5 30.1 30.9 31.8

800 41 78 26.5 30.1 30.9 31.8

CL1-1

1000 57 94 32.2 37.3 38.9 39.6

1250 73 110 38.3 44.6 46.4 47.7

1600 108 145 51.7 60.4 62.5 64.8

2000 145 182 66.3 77.5 80.2 83.4

2500 195 232 85.7 100.3 104.2 108.4

3200 108 145 104.6 122.9 127.8 131.8

CL1-23600 126 163 118.6 139.5 145 151.4

4000 145 182 134.8 158.3 164.6 170.4

5000 195 232 173.5 203.9 214 220.5

6300 164 201 204.3 241.5 252.3 260CL1-3

7500 195 232 261.2 309 324.1 334.5

* B : 3WGE=90mm, 4WGE/4WHE/4WFE=100mm

22 CR-LV/MV LS C&S-Busway System

Page 5: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

06 / 07

Flanged EndThe !anged end is connected to either a transformer or a

panel. Dimension details are shown below.

Ampere(A)Dimension (mm)

Fig.t W A B

AL

630

6.35

41 ~

100

CL2-2800 62 ~

1,000 86 40CL2-3

1,250 108 50

1,600 164 60CL2-5

2,000 210 70

2,500 (2)126 40

130

CL2-4

3,200 (2)164 60

CL2-5

3,600 (2)184 60

4,000 (2)210 70

5,000 (3)184 60

6,300 (3)210 70

CU

630

6.35

41 ~

100

CL2-2800 41 ~

1,000 57 ~

1,250 73 40CL2-3

1,600 108 50

2,000 145 50 CL2-4

2,500 195 70 CL2-5

3,200 (2)108 50

130

CL2-3

3,600 (2)126 40CL2-4

4,000 (2)145 50

5,000 (2)195 70 CL2-5

6,300 (3)164 60 CL2-5

7,500 (3)195 70 CL2-5

[Fig. CL2-1]

[Fig. CL2-2] [Fig. CL2-3] [Fig. CL2-4] [Fig. CL2-5]

Co

mp

on

en

t

CR-LV/MV LS C&S-Busway System 23

Page 6: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

Elbow[Vertical] [Horizontal]

O"set[Vertical] [Horizontal]

Ⅲ Component

XY

X

Y

Y

XZ

X

Z

Y

Ampere(A)Dimension(mm)

X Y

1 단 500 500

2 단 500 500

3 단 500 500

Ampere(A)Dimension(mm)

X Y Y

1 단 500 150 500

2 단 500 150 500

3 단 500 150 500

Ampere(A)Dimension(mm)

X Y Z

1 단 500 300 500

2 단 500 300 500

3 단 500 300 500

Ampere(A)Dimension(mm)

X Y

1 단 500 500

2 단 600 600

3 단 700 700

FittingsFittings including the elbow and tee are designed to adapt to any change made to the direction of the bus duct installation.

The same features have been applied to the fittings of the CR-Way, and the size specifications are shown below.

(The standard dimension of each fitting is the same as the dimension shown in the table below. Please contact our design

team for information about the minimum dimension.)

24 CR-LV/MV LS C&S-Busway System

Page 7: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

06 / 07

Expansion(optional)

Tee

Combination

[Vertical] [Horizontal]

X

Y

Z

X

Y

Z

Y

Z

X

Ampere(A)Dimension(mm)

X Y Z

1 단 500 300 500

2 단 600 400 600

3 단 700 500 700

Ampere(A)Dimension(mm)

X Y Z

1 단 500 500 500

2 단 500 500 500

3 단 500 500 500

Ampere(A)Dimension(mm)

X Y Z

1 단 500 500 500

Co

mp

on

en

t

CR-LV/MV LS C&S-Busway System 25

Page 8: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

Ⅲ Component

Horizontal

Vertical Hangers

Hangers Both horizontal and vertical hangers are available for the CR-LV depending on the installation environment.

The standard horizontal installation method of the CR-LV requires two supports for each product. The standard 3 meter bus ducts are designed to be

installed at 1.5 meters intervals, and the space between the hangers should not surpass 2 meters at the most. (Please contact the design team for further

information.)

For vertical installation of The CR-LV, install the vertical hangers first, and fix the bus ducts on the hangers for better support.

Rigid hanger

Hanger rod

Hanger clamp

Hanger bar

Base

26 CR-LV/MV LS C&S-Busway System

Page 9: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

06 / 07

Etc.Wall Flange Floor Opening

• W : The width of the product

• H : The height of the product

• W : The width of the product

• H : The height of the product

The required minimum distances from a wall for heat dissipation and maintenance

W+160

W+60

W+10

W

H+160

H+60

H+10

H

Wall opening sizeCut out

W+60

H+60

W

H

Floor opening sizeCut out

250mm

50mm

50mm

50mm

500mm

BEAM

벽, 천정 벽, 천정 벽

벽벽

접속부

A wall flange is used to seal the gaps produced during

bus duct installation on the walls, ceilings and floors.

The company does not provide glass wool or fire forms.

Co

mp

on

en

t

CR-LV/MV LS C&S-Busway System 27

Page 10: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

Ⅳ. Technical Data

The short circuit strength of the CL-LV has been tested as specified in IEC 61439-2, 6 [(previous standard) IEC 60439-1, 2], and certified by KEMA.

Short Circuit Strength

Ampere(A) 630 800 1000 1250 1600 2000 2500 3200 3600 4000 5000 6300 7500

AL1sec 40 40 50 50 50 80 80 80 100 100 100 130 130

3sec 23 23 29 29 29 46 46 46 58 58 58 75 75

CU1sec 40 40 50 50 50 80 80 80 100 100 100 130 -3sec 23 23 29 29 29 46 46 46 58 58 58 75 -

Ampere(A) Impedancex10-3Ω(uΩ/100m,60Hz) Voltage Drop (V/100m)

R X Z 0.7 0.8 0.9 1

AL

630 14.72 7.11 16.34 16.78 17.50 17.83 16.06800 9.78 5.44 11.19 14.87 15.37 15.49 13.55

1000 7.14 4.30 8.34 13.98 14.37 14.38 12.371250 5.76 3.61 6.80 14.32 14.67 14.64 12.471600 3.92 2.57 4.69 12.70 12.98 12.89 10.872000 3.14 2.09 3.77 12.78 13.04 12.95 10.892500 2.68 1.78 3.21 13.60 13.88 13.78 11.583200 2.13 1.40 2.55 13.81 14.10 14.00 11.793600 1.58 1.26 2.03 12.54 12.63 12.32 9.884000 1.39 1.12 1.78 12.26 12.34 12.03 9.625000 1.06 0.87 1.36 11.75 11.81 11.49 9.146300 0.92 0.76 1.20 13.00 13.06 12.70 10.08

CU

630 8.57 7.11 11.14 12.09 12.14 11.80 9.35800 8.57 7.11 11.14 15.35 15.41 14.98 11.87

1000 6.42 5.77 8.63 14.91 14.88 14.36 11.111250 5.09 4.85 7.03 15.21 15.12 14.50 11.021600 3.56 3.61 5.07 14.06 13.90 13.25 9.872000 2.74 2.85 3.96 13.71 13.53 12.86 9.502500 2.12 2.22 3.07 13.30 13.12 12.46 9.183200 1.94 2.03 2.81 15.59 15.38 14.60 10.763600 1.70 1.78 2.46 15.34 15.14 14.38 10.614000 1.51 1.57 2.18 15.08 14.89 14.15 10.465000 0.88 1.20 1.48 12.72 12.30 11.35 7.606300 0.79 1.08 1.34 14.44 13.95 12.87 8.587500 0.58 0.82 1.01 12.91 12.45 11.47 7.59

F F F P P P P Pα(부하 상수)

VdVV = I x 3(R cosθ + X sinθ)

실제 전압 강하 = α x VdVV x x Rated load current

Actual load current

100m

Actual length of the line (m)

α = 1== , concentrated load

(a place such as an electrical room)

α = 0.5== , Distributed load

(a place such as a vertical section)

F : Flanged End (panel connections) P : Plug-in Unit

VdVV = voltage drop[V] I = rated road amperes[A] R = R resistance[Ω] X = X reactance[Ω] / cos = power factor / sim = reactive factor

Technical DataImpedance and Voltage DropThe formula to measure the voltage drop of a busduct is shown below. The impedance and voltage drop values for aluminum and

copper conductors are shown in the table below.

The values listed are measured between the upper and middle lines at 60Hz. For a 50Hz installation, multiply the reactance (X) by 0.83.

28 CR-LV/MV LS C&S-Busway System

Page 11: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

06 / 07

Classication 1 2 3 4 5 6 7 8 9

Censer Location Joint Conductor Exterior of EpoxyAmbient

Temperature

Temperature Rise

Value 69K 62K 65K 63K 52K 51K 44K 50K 21.4

80

70

60

50

40

30

20

10

0 1 2 3 4 5 6 7 8

5

6

7 8

1 2 3 4

Tem

pe

ratu

re(

)

Time(hr)

- Joint -

1

2 3

4

5

6

9

7 8

The temperature rise limit is an important property which determines the performance of bus ducts. The temperature rise limit of the

bus duct is designed so that when a bus duct is operated with a rated current , the temperature limit values of the housing are within

55K as specified in IEC61439-2 and 6 [(previous standard) IEC 60439-1 and 2].

Temperature Rise

Tech

nica

l Da

ta

CR-LV/MV LS C&S-Busway System 29

Page 12: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

Ⅴ. Install Information

Before connecting the bus ducts, be sure to align them at the top and the bottom and the

left and the right as well as horizontally and vertically. (This applies for joint connection of

the horizontal and vertical ducts.) Make sure that the joint kit is not tilted. Be sure that the

surface is clear of particles before connecting them.

Check List

• The alignment of the bus ducts.

• The surface of the joint must be clear of dust or particles.

Using a torque wrench, slowly tighten the exposed bolt head of a double head bolt. Connect

the bus ducts temporally first, and check the function of the insulation (100MΩ or higher)

by checking the insulation resistance. Make sure the insulation is working normally before

breaking off the double-head bolt head. The double-head bolt head is designed to break off

at 800~1000Kgf•cm, therefore tighten the exposed head until it breaks off. Once the exposed

head and the red tag attached to it have been cut off, the state of the joint connection should

be visible, which means they are properly connected.

Check List

• Check the connection of the joint: The head of the double-head bolt and the red

tag should be cut off.

Assemble the ducts using a molding flask and rubber packing. Spray plenty of release

agent inside of the molding flask when the assembly is finished.

Check List

• Assembling the molding flask

• Spraying the release agent

• Assorting the vertical type and horizontal type

While assembling the molding flask, be sure to position the rubber packing of the mold-

ing flask at 40 mm from the block end. Make sure there are no gaps between the rubber

packing and the bus ducts.

Check List

• The location of the rubber packing: 40mm from the block end

1

2

3

4

CR – LV (Joint Kit)

30 CR-LV/MV LS C&S-Busway System

Page 13: (LSC BUS en .pdf) · 2016-11-11 · 06 / 07 CR-LV LS 전선 Busduct System Catalogue 06 of 08 Contents II. General Data 20 III. Component - Feeder 22 - Flanged End 23 - Fittings 24

06 / 07

Be sure to keep the ambient temperature at 25°C or higher before mixing the epoxy resin and

filler. When mixing the epoxy resin in a cool environment, be sure to cover the mixing container

to keep warm. It is to maintain the temperature of the container at 25°C or higher. In order of

filler, epoxy resin and hardener, add them into the mixing container, and mix it for 15 minutes

using a hand drill. (Please contact our design team for information about how to maintain the

temperature of the container when mixing the epoxy resin in a cool environment.)

Check List

• The ambient temperature: 25° C or higher

• Mix filler, epoxy resin and hardener for 15 minutes

Pour the mixture into the molding flask. Maintain the ambient temperature at 25° C. When

molding in a cool environment, cover the molding flask to keep warm to maintain the

temperature at the molding flask. Remove foams on the surface of the mixture for about

1 hour. Mold only three joints out of a total of four, and continue molding the entire line

following the same procedure. Wait for 8 hours, and check the function of the insulation

by checking the insulation resistance. When it is normal, finish molding the remaining

joint. (Please contact our design team for information about covering the container when

molding the epoxy resin in a cool environment.)

Check List

• Ambient temperature: 25°C or higher

• Removing foams on the surface of the mixture for 1 hour

Remove the mixture form the molding flask, and polish the rough surface with

sandpaper.

Check List

• When to remove the molding flask: 8 hours after the molding

• Polishing the surface with sandpaper

Perform the final inspection to check the performance of the joint.

Check List

• Final inspection of the joint

5

6

7

8

Inta

ll In

form

atio

n

CR-LV/MV LS C&S-Busway System 31