Upload
muhammad-andri
View
251
Download
5
Embed Size (px)
DESCRIPTION
Project Management Task
Citation preview
Muhammad Andri Alkautsar R.1106070073Metalurgi dan Material
TUGAS MANAJEMEN PROYEK
1. Gantt Chart dari tabel pekerjaan Task Start Time
(Weeks)Duration (Weeks) End Date
A 0 5 5B 6 3 9C 7 4 11D 7 9 16E 8 2 10F 9 8 17G 12 7 19
Tabel Gantt Chart
A
B
C
D
E
F
G
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Tugas terakhir (task g) akan selesai pada minggu ke 19.
2. Rencana pengeluaranWeek Task Weekly Direct Expense Cumulative Expense1 A 10 102 A 10 203 A 10 304 A 10 405 A 10 506 0 507 B 15 658 B,C,D 75 1409 B,C,D,E,F 105 24510 C,D,E,F 90 33511 C,D,F 80 41512 D,F 55 47013 D,F,G 65 535
Muhammad Andri Alkautsar R.1106070073Metalurgi dan Material
14 D,F,G 65 60015 D,F,G 65 66516 D,F,G 65 73017 F,G 55 78518 G 10 79519 G 10 805
Grafik cumulative expense
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 190
100
200
300
400
500
600
700
800
900Cumulative
Expense; 805
Cumulative Expense
Cum
ulat
ive
Expe
nse
$100
0
Grafik weekly expense
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 190
20
40
60
80
100
120
Chart Title
Series1
Week
Wee
kly
exp
ense