94
DEPARTMENT OF ENERGY ENERGY UTILIZATION MANAGEMENT BUREAU Training Manual for Micro-hydropower Technology June 2009 MHP – 6

MHP-6

Embed Size (px)

DESCRIPTION

Hydropower

Citation preview

  • DEPARTMENT OF ENERGY ENERGY UTILIZATION MANAGEMENT BUREAU

    Training Manual

    for

    Micro-hydropower Technology

    June 2009

    MHP 6

  • This manual was developed by the Department of Energy (DOE) through the technical assistance under the Project on Sustainability Improvement of Renewable Energy Development for Village Electrification in the Philippines which was provided by the Japan International Cooperation Agency (JICA).

  • Table of Contents

    1 General......................................................................................................1 2 Scope .........................................................................................................1 3 Objectives..................................................................................................1 4 Implementation structure ........................................................................1

    4.1 Implementation structure ...........................................................................1 4.2 Roles and responsibilities ............................................................................2

    5 Outline of the Training.............................................................................2 5.1 Purpose.........................................................................................................2 5.2 Trainer .........................................................................................................2 5.3 Trainee .........................................................................................................3 5.4 Attainment Target .......................................................................................3

    6 Preparation ...............................................................................................3 6.1 Establishment of the Training Program .....................................................3 6.2 Venue Arrangements ...................................................................................4 6.3 Invitation of Trainees ..................................................................................4 6.4 Preparation of Materials..............................................................................4

    7 Implementation ........................................................................................4 7.1 Points to be learned during training ...........................................................4 7.2 Key lecture points ........................................................................................4

    8 Amendment of the manual .......................................................................4

  • LIST OF ANNEXES

    ANNEX 1 : List of already-drafted training materials ANNEX 2 : Learning points by training item for planning and

    civil structure design ANNEX 3 : Samples of training material

  • 1

    1 General Proponents of micro-hydropower projects for rural electrification should draft an

    appropriate project plan based on site conditions in order to effectively make use of the limited water resources and ensure project sustainability. From the same perspective, administrative organizations are also required to adequately evaluate the submitted plan and give proper instructions to the proponents. Accordingly, sufficient understanding of planning technique for micro-hydropower project is essential for both the proponents and the assessors.

    This manual is intended to present the key points in organizing and implementing the training on micro-hydropower technology. Some basic training materials have been included to reduce the trainers burden for preparatory work.

    2 Scope This manual shall be used for the planning, implementation, and evaluation of

    micro-hydropower technology training.

    3 Objectives (1) Assist training organizers and trainers in planning, preparing, and

    implementing the training on micro-hydropower technologies effectively, and (2) Maximize the training effect by providing the key points to be noted during

    conducting lectures.

    4 Implementation structure 4.1 Implementation structure

    The following figure shows the implementation structure of the training. Figure 1 Implementation structure of the training

    Organizer

    Organizations concerned to micro-hydropower development for rural electrification

    Trainer

    Trainee

    Assignment of trainers

    Training implementation for specific technical field

    Dispatch of trainees

    InvitationTrainee nomination

    Trainer Trainer

    Trainee Trainee Trainee

  • 2

    4.2 Roles and responsibilities The training roles and responsibilities of the planning, preparation and

    implementation components have been summarized in the following table.

    Table 1 Roles and responsibility of persons concerned

    5 Outline of the Training 5.1 Purpose

    The purposes of micro-hydropower technology training are to:

    (1) deepen the knowledge of experienced technical staff who have been involved in micro-hydropower development, and

    (2) develop the knowledge of new technical staff who will be engaged in micro-hydropower development in the near future.

    Appropriate training implementation enables technical staff to adequately design and evaluate new micro-hydropower projects and establish the rehabilitation plans for existing plants.

    5.2 Trainer

    Each trainer shall be assigned to a specific technical field, such as planning and designing for civil, electrical, mechanical facilities. Trainers shall be those who have participated in past micro-hydropower development training. However, the organizer can also invite technical staff who have served as trainers in outside organizations.

    Trainers will be responsible for preparing training materials in the technical field of which they have respectively been put in charge. Examples of the technical materials are attached to this manual for reference.

    Component Role

    Organizer

    Assignment of trainers Arrangement of venue, equipment

    (accommodation for trainees if necessary) Sending invitation letter calling for traiees

    Trainer

    Preparation of training materials Implementation of training for specific technical

    field in charge Evaluation of trainees

    Trainee Participation in training Implementation of future training for specific

    technical in their organizations

    Organization concerned

    Nomination of trainees

  • 3

    5.3 Trainee Trainees shall be invited from among the stakeholders, such as the DOE field

    office, ANEC, LGU, etc., organizations which have promoted micro-hydropower development for rural electrification. The organizer will determine the number of trainees taking into account the training effects.

    Further, basic knowledge of mathematics is required for all trainees to ensure smooth progress. In the end, trainees will also be required to disseminate the knowledge that they have acquired during training.

    5.4 Attainment Target

    Final targets to be attained for the proponents and the assessor are described respectively as follows:

    to develop the project plan on the basis of the site reconnaissance results and handle the basic design of equipment in a proper manner, and

    to properly evaluate the project plan that the proponents have drafted, and offer constructive instructions and advice.

    6 Preparation 6.1 Establishment of the Training Program

    The following table shows an example of a 5-day training program which includes the over-all contents concerning micro-hydropower development from a preliminary study used for site selection to basic designs used for civil and electro-mechanical equipment. The organizer can arrange the training program to meet available time frames and stakeholders needs. For instance, the trainings on civil structures design and electro-mechanical equipment design can be organized separately for people possessing different academic backgrounds such as civil, electric, and mechanical engineering.

    Table 1 Example of program for 5-day training Date Training item

    AM Map study Day 1 PM Planning

    AM Site reconnaissance Day 2 PM Design of civil structures

    AM Practice of map study Day 3 PM Practice of civil structure design

    AM Turbine / Driving system Day 4 PM Generator / Control system

    AM Electrical equipment and protection system / Distribution system Day 5 PM Practice of electro-mechanical equipment design

  • 4

    6.2 Venue Arrangements The organizer shall arrange an appropriate venue taking into account the

    availability and expected number of the trainees. Necessary training equipment, such as the PC, projector, and microphone, shall also be prepared. The trainees are asked to prepare the calculator for practice of planning and designing, if necessary.

    6.3 Invitation of Trainees

    In order to summon and finalize candidates based on their area of specialty and prior experience, an invitation letter specifying trainee requirements will be sent by the organizer to the stakeholders in advance.

    6.4 Preparation of Materials

    The trainers shall prepare in advance the training materials in their charge. The materials that are attached to this manual are listed in ANNEX1. The organizer and trainers shall upgrade these materials as well as adding new ones.

    7 Implementation 7.1 Points to be learned during training

    The trainers shall proceed with the lectures step by step so that the trainees can thoroughly absorb the fundamental points of each training item, which are shown in ANNEX2.

    7.2 Key lecture points

    One-on-one lectures may turn out to be a tedious proposition for both the trainers and trainees. Hence, the trainers shall encourage the trainees to actively participate in the following ways:

    Interspersed periodic questioning of the trainees to confirm their understanding, Introduction of examples and case studies, Homework for lecture review, On-hand practice to deepen knowledge and understanding, Discussion among the trainees, and Presentations by the trainees on how to utilize their newly acquired knowledge, Wrap-up meeting.

    Such methods will enable trainees to apply their acquired knowledge in planning and actual development. Conducting examinations before and after the training is an effective method in evaluating the level of capacity building and also reveals the training effects.

    8 Amendment of the manual The DOE shall review this manual annually, and amend it, if necessary, according

    to the surrounding circumstances in rural electrification of the country. The amended manual shall be fully authorized among the DOE and approved by Director of Energy Utilization Management Bureau of the DOE.

  • List of already-drafted training materials

    Items Contents Outline of hydropower Catchment area Map study Duration curve and identification of potential site Functions of main structures for micro-hydropower plant Layout of main structures Planning Selection of main structures location Outline of site reconnaissance Measurement of river flow Site reconnaissance Measurement of head Intake weir Intake and settling basin Headrace Head tank Penstock Powerhouse

    Design of civil structures

    Head loss calculation Basics of hydraulics Turbine types Characteristics of turbine Turbine

    Basic design of turbine Basics of generator Classification of generator Generator Basic design of generator Basics of automatic control Frequency control Control system Voltage control Major factors Transformer Switch gear Arrester Instrument transformer Single line diagram

    Electrical equipment and protection system

    Protection system Distribution method Components Route selection Distribution system

    Voltage drop estimation

    ANNEX1

  • i

    Learning points by training item for planning and civil structure design

    Items Contents Learning points Outline of hydropower Concept of hydropower

    Concept of catchment area Relationship between discharge and catchment area Catchment area Catchment area estimation using topographical map Concept of duration curve Maximum/firm discharge identification using duration curve

    Map study

    Duration curve and identification of potential site Potential site identification using topographical

    map Functions of intake weir and intake Functions of settling basin Functions of headrace Functions of head tank and penstock

    Functions of main structures for micro-hydropower plant

    Functions of turbine and generator Layout of main structures Concept of basic layout for main structures

    Appropriate location of weir, intake, and settling basin Appropriate location of powerhouse

    Planning

    Selection of main structures location

    Appropriate location of headrace route Objectives and survey items of site reconnaissanceOutline of site

    reconnaissance Information gathering and planning for site reconnaissance Measurement of river flow On-site measuring method of river flow

    Site reconnaissance

    Measurement of head On-site measuring method of head Type and structure of intake weir Design concept for intake weir Intake weir Calculation technique for intake weir dimensioning Structure of intake and settling basin Design concept for intake and settling basin Intake and settling basin Calculation technique for intake and settling basin dimensioning Type and structure of headrace Design concept for headrace Headrace Calculation technique for headrace dimensioning Structure of head tank Design concept for head tank Head tank Calculation technique for head tank dimensioningDesign concept for penstock Penstock Calculation technique for penstock dimensioning

    Powerhouse Structure of powerhouse by turbine type

    Design of civil structures

    Head loss calculation Calculation technique for head loss

    ANNEX2

  • ii

    Learning points by training item for electro-mechanical equipment design

    Items Contents Learning points Principle of continuity Bernoullis theorem Basics of hydraulics Concept of potential, pressure, and velocity head Structure, features, and applicable range by turbine type Turbine types Concept of turbine selection chart Concept of specific speed Applicable range of specific speed by turbine typeCharacteristics of turbine Turbine efficiency by turbine type Flow of turbine basic design

    Turbine

    Basic design of turbine Calculation technique for turbine specifications Principle of operation of AC generator Relationship between voltage and rotational speedMain structure of generator Basics of generator Type of excitation system

    Classification of generator Classification of AC generator Flow of generator basic design

    Generator

    Basic design of generator Calculation technique for generator specifications Concept of feedback control Basics of automatic control Reaction of P-control, I-control, and PI-control Characteristics of frequency and active power control Frequency control Concept of speed governor and dummy load governor Characteristics of voltage and reactive power control

    Control system

    Voltage control Concept of automatic voltage controller

    Major factors Concept of major factors Transformer Type and functions of transformer Switch gear Type and functions of switch gear Arrester Functions of arrester Instrument transformer Type and functions of instrument transformer Single line diagram Standard composition of single line diagram

    Type and functions of protection relay

    Electrical equipment and protection system

    Protection system Standard arrangement of protection relay Distribution method Classification of distribution method

    Design and installation concept of pole Components Design and installation concept of guy wire Route selection Concept of distribution line route selection

    Calculation technique for resistance and inductance of conductor

    Distribution system

    Voltage drop estimation Calculation technique for voltage drop of distribution lines

  • 1Training on

    Micro Hydropower

    Development

    1-1 2

    DATE 2008

    Outline of HydropowerCatchment AreaIdentification of Potential SitesDuration CurveFunctions of Main StructuresLayout of Main StructuresSelection of Main Structures' LocationOutline of Site ReconnaissanceMeasurement of River FlowMeasurement of HeadIntake WeirIntake and Settling BasinHeadraceHead tankPenstock and SpillwayPower HouseHead Loss

    AM

    AM TurbinePM Driving System

    GeneratorControl SystemProtection System

    PM

    Nov. 10

    AM

    PM

    CONTENTS

    Examination: Design of Electrical & Mechanical Equipment

    BASIC COURSE: Map Study

    BASIC COURSE: Planning

    ADVANCE COURSE: Site Reconnaissance

    ADVANCE COURSE: Design of Civil Structures

    Practice Activity for Map StudyPractice Activity for Civil DesignExamination: Planning & Design of Civil Structures

    Design of Mechanical Equipment

    Curriculum for the Training on Micro-Hydropower Development

    Nov.13

    Design of Electrical EquipmentAMNov.14

    Nov.11

    AM

    PM

    PMNov.12

    1-2

    3

    Training on

    Micro Hydropower

    Development

    Basic Course (1ST part)

    EPIFANIO G. GACUSAN DOE - REMDAVR, Department of Energy, 10 November 2008

    1-3 4

    Training on Micro Hydropower Development

    Basic Course

    Map Study

    OUTLINE OF HYDROPOWER

    1-4

  • 5What is Hydropower?Energy of Falling Stone:

    Ouch!

    1-5 6

    What is Hydropower?Energy of Falling Stone:

    Ouch!

    Ouch!

    1-6

    7

    What is Hydropower?Energy of Falling Stone:

    Ouch!

    Ouch!

    1-7 8

    What is Hydropower?Energy of Falling Stone

    depends on

    Height Weight of the Stone

    Energy of Hydropower

    Height Weight of the Water

    Head Discharge

    Height

    1-8

  • 9Training on Micro Hydropower Development

    Basic Course

    Map Study

    CATCHMENT AREA

    1-9 10

    Hydropower depends on Head and Discharge

    Catchment Area

    Depends on Catchment Area

    Rainfall

    For Generating Power

    SayangMottainai

    Discharge

    1-10

    11

    10621045

    Height 20 m x 5 =100m

    Scale: 1/50,000

    On map : Accrual

    1 cm : 500 m

    Short Distance = Steep

    Long Distance = Gentle

    980

    960

    940

    920

    900

    880

    860

    840

    820

    800

    780

    760

    1-11 12

    10621045

    Catchment Area

    1-12

  • 13

    h

    b

    A

    A = ( b x h ) /2

    1-13 14

    10621045

    1-14

    151-15 161-16

  • 17

    Training on Micro Hydropower Development

    Basic Course

    Map Study

    DURATION CURVE & IDENTIFICATION OF POTENTIAL SITE

    1-17 18

    Duration Curve

    0 100 200 300 365

    R

    i

    v

    e

    r

    F

    l

    o

    w

    (

    m

    3

    /

    s

    )

    140

    100

    60

    R

    i

    v

    e

    r

    F

    l

    o

    w

    (

    m

    3

    /

    s

    )

    Flow Duration CurveActual River Flow

    ArtJimmy

    ArtJimmy

    Change the Order

    1-18

    19

    Duration CurveGauging Station: ABC (CA=30km2) Latitude@@@

    Period:1990.1 2000.1 Longitude@@@

    25%(95day) 50%(183day) 75%(274day)100%(365day

    )90%(328day)

    95%(346day)

    0.5

    1.0

    1.5

    R

    i

    v

    e

    r

    F

    l

    o

    w

    (

    m

    3

    /

    s

    ) Depends on Chatchment Area and Rainfall

    Depends on Planning

    Maximum Discharge/Design Discharge

    Firm Discharge = 95 % Firm

    1-19 20

    Duration Curve : How to Identify Maximum Discharge

    40% 50% 70%

    0.5

    1.0

    1.5

    R

    i

    v

    e

    r

    F

    l

    o

    w

    (

    m

    3

    /

    s

    )

    60% 80%

    C

    o

    n

    s

    t

    r

    u

    c

    t

    i

    o

    n

    C

    o

    s

    t

    /

    k

    W

    h

    Percentage of Duration

    40 % 50 % 60 % 70 % 80 %

    For Mini/Large Hydro : Comparison of Unit Cost in Each Case

    1-20

  • 21

    Duration Curve : How to Identify Maximum Discharge

    Maximum and Firm Discharge in Hydropower Plant

    0.00.20.40.60.81.01.21.41.61.82.02.2

    0 10 20 30 40 50 60 70 80 90 100 110

    Percentage of Firm/Maximum Discharge (%)

    U

    n

    i

    t

    F

    i

    r

    m

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    /

    1

    0

    0

    k

    m

    2

    )

    Large

    Small MiniMicro

    For Micro Hydro : Initial Stage

    Firm Discharge = 1.0 m3/s/100km2

    Max. Discharge = Firm Discharge

    1-21 22

    Duration Curve : How to Identify Firm/Max. DischargeFor Micro Hydro : Pre-Feasibility Study

    Maximum and Firm Discharge in Hydropower Plant

    0.00.20.40.60.81.01.21.41.61.82.02.2

    0 10 20 30 40 50 60 70 80 90 100 110

    Percentage of Firm/Maximum Discharge (%)

    U

    n

    i

    t

    F

    i

    r

    m

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    /

    1

    0

    0

    k

    m

    2

    )

    Micro

    Vegetation

    Rich Forest

    Bare Ground

    Over 3000mm

    Annual Rainfall

    Aprx.2000 mm

    57

    Average rain fall line

    1-22

    23

    Duration Curve : How to Identify Firm/Max. DischargeFor Micro Hydro : Detail Study

    Measurement River Flow at the Site

    It will be Trained in Advance

    Course

    1-23 24

    Good Potential Site (Technically)1. Short Distance and High Head

    Portion A B C D

    Profile of River

    1-24

  • 25

    1. Short Distance and High Head ; How to Know ?

    E.L

    520

    500

    480

    460

    440

    420

    400

    380

    L1L1

    L3L2

    L4 L5

    L6500400

    L1 L2 L3 L4 L5 L6

    1-25 26

    1. Short Distance and High Head ; How Short? How High?

    Indicator : L/H (Distance/Head)

    Head and Waterway Length

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000

    Waterway Length (m) L

    H

    e

    a

    d

    (

    m

    )

    H

    Micro L/H

  • 29

    E.L

    520

    500

    480

    460

    440

    420

    400

    380

    L1L1

    L3L2

    L4 L5

    L6500400

    L1 L2 L3 L4 L5 L6

    1. Short Distance and High Head ; How to find out ?

    Assumed Head : 40 m

    1000m2 cm

    1000m1000m1000m 1000m1000m

    N.GOK

    OKN.G

    N.G

    RR1-29 30

    1. Short Distance and High Head ; How to find out ?

    E.L

    520

    500

    480

    460

    440

    420

    400

    380

    L1L1

    L3L2

    L4 L5

    L6500400

    L1 L2 L3 L4 L5 L6

    Assumed Head : 60 m

    3 cm 1500 m

    1500 m1500 m1500 m1500 m

    N.GOK

    N.G

    N.G

    1-30

    31

    Good Potential Site (Technically)

    2. Bigger Catchment Area is better if the L/H is evenAssumed Head : 40 m

    10621045

    1-31 32

    Good Potential Site (Technically)

    3. Power Output must be balanced with DemandFor Micro Hydro : Initial Stage

    100 HH X 200 W/ HH = 20 kWFirm Discharge = 1.0 m3/s/100km2

    Demand ; Based on Social SurveyMax. Discharge = Firm Discharge

    Practical Hydropower OutputP = 9.8 x Q x H x

    Where, P = Power output (kW)Q = Discharge (m3/s) = Head (m) = Combined efficiency (0.5)

    Q = P / (9.8 x H x )= 20 / (9.8 x H x 0.5 )

    0.0760200.1040200.202020

    Q (m3/s)H (m)P (kW)

    Required Catchment Area = 20 km2

    C.A=10 km2

    C.A=7 km2

    1-32

  • 33

    Good Potential Site (Technically)4. Near the Demand Area

    Voltage Drop is within 10 % without Step up T/F

    Radius 1km (2cm on the Map)

    Demand site

    0 1.0 2.0 3.0 4.0 5.0 km

    1-33 34

    Good Potential Site (Technically)

    5. Gentle Slope is Convenient for Headrace and Powerhouse

    A

    A

    Section A-A

    B

    B

    Section B-B1-34

    35

    Examples

    1-35 36

    0 1.0 2.0 3.0 4.0 5.0 km

    Output 10 kW Head 60 m

    1-36

  • 37

    0 1.0 2.0 3.0 4.0 5.0 km10 kWP

    60 mH

    0.035 m3/sQ

    3.5 km2C.A

    22 kWP

    60 mH

    0.075 m3/sQ

    7.5 km2C.A

    25 kWP

    40 mH

    0.125 m3/sQ

    12.5 km2C.A

    35 kWP

    40 mH

    0.180 m3/sQ

    18.0 km2C.A

    55 kWP

    60 mH

    0.185 m3/sQ

    18.5 km2C.A

    10 kWP

    60 mH

    0.035 m3/sQ

    3.5 km2C.A

    12 kWP

    60 mH

    0.040 m3/sQ

    4.0 km2C.A

    1-37 38

    Items Contents

    Project Name Ambabag Mini-Hydropower Project

    Location Barangay Ambabag, Pindungan, Kiangan, Ifugao

    Coordinates Intake : N-164734.92, E-1210535.22

    Powerhouse: : N-164737.32,E-1210620.28)

    Catchments Area 20.2 km2

    Elevation of the Intake E.L. 494.2 m

    Tailrace Water Level E.L. 403 m

    Gross Head 91.2m

    Effective Head 80 m

    Required Max. Discharge 0.32 m3/s

    Maximum Output 200 kW

    Annual Energy Generation 1,490 MWh

    Construction Cost Approximate. 42 Million pesos

    Plant Factor 85 %

    Result of Map Study (Example)

    1-38

    39

    Thank you Very Much !!!!

    1-39

  • 1Training on

    Micro Hydropower

    Development

    Basic Course (2nd part)

    2-12

    Training on Micro Hydropower Development

    Basic Course

    Planning

    Functions of Main Structures

    2-2

    3

    Main Structures for Micro/Mini Hydropower

    Head-tankFore bay

    Headrace

    Demand

    2-34

    Intake Weir Settling Basin

    Headrace

    Head-tank

    Penstock

    Powerhouse

    TailraceSpillway

    2-4

  • 5Intake Weir and Intake

    The Intake weir a barrier built across the river used to divert water through an opening in the riverside (the Intake opening) into a settling basin.

    2-56

    Function of Intake Weir

    Intake

    If no Intake Weir Insufficient Inflow Many Sedimentations into Intake

    2-6

    7

    Function of Intake Weir

    to Divert the River Flow into the Intake to prevent the Sediment/silts to pass through

    Flush Gate (Stop Logs)

    2-78

    Function of Intake

    Weir Crest

    Flood Water Level

    Q over Q

    Flood Water Level

    Big Flow = Structures will be Damaged

    Orifice with Spillway

    Control Gate

    to Control Inflow2-8

  • 9Settling BasinSettling Basin-The settling basin is used to trap sand or suspend the silt from the water before entering the penstock.

    2-910

    IntakeHeadrace

    Spillway

    High Velocity Low Velocity

    Flush Gate

    Function of Settling Basin

    to trap sand or suspend the silt from the water2-10

    11

    HeadraceHeadrace-A channel leading the water to a head tank. The headrace follows the contour of the hillside so as to preserve the elevation of the diverted water.

    2-1112

    H

    e

    a

    d

    L

    o

    s

    s

    Settling Basin Headrace Headtank

    Slope =Gentle

    Function of Headrace

    Gentle Slope Small Head Loss = Big Output

    Big Size of Headrace = High Cost

    Steep Slope Small Size of Headrace =Low Cost

    Big Head Loss =Small Output

    Settling Basin Headrace Headtank

    Slope =Steep

    H

    e

    a

    d

    L

    o

    s

    s

    to convey water into the head-tank

    Micro=1/100 to 1/300

    Mini=1/200 to 1/1,000

    2-12

  • 13

    Head-tank (Forebay Tank)Head-tank - Pond at the top of a penstock or pipeline; serves as final settling basin, maintains the required water level of penstock inlet and prevents foreign debris entering the penstock.

    2-1314

    Penstock

    Penstock - .A close conduit or pressure pipe for supplying water under pressure to a turbine.

    2-14

    15

    Water Turbine and GeneratorA water turbine is a machine to directly convert the kinetic energy of the flowing water into a useful rotational energy while a generator is a device used to convert mechanical energy into electrical energy.

    2-1516

    Thank you Very Much!

    2-16

  • 1Training on

    Micro Hydropower

    Development

    Basic Course (3rd part)

    3-1 2

    Training on Micro/Mini Hydropower DevelopmentTraining on Micro Hydropower Development

    Basic Course

    Planning

    Layout of Main Structures

    3-2

    3

    HeadtankHeadrace

    Main Structuresfor Micro/Mini Hydropower plants

    3-3 4

    1. Short Penstock

    Basic Layout

    3-4

  • 52. Long Penstock

    Basic Layout

    3-5 6

    3. Middle-Length Penstock

    Basic Layout

    3-6

    7

    Training on Micro/Mini Hydropower Development

    Basic Course

    Planning

    Selection of Main Structures Locations

    3-7 8

    CRITERIA

    1. Narrow River Width

    2. Preferably at Straight Portion of the River

    3. Has Space for Settling Basin

    4. Easy to Combine with Headrace

    Apropriate location forthe weir, intake and settling basin

    3-8

  • 9AB

    C

    DE

    Criteria

    1. Narrow River Width

    2. Preferably at Straight Portion of the River

    3. Has Space for Settling Basin

    4. It is easy to combine with Headrace

    A,B,D,E

    A,B

    appropriate location forthe weir, intake and settling basin

    A,B,E

    A3-9 10

    CRITERIA

    1. Gentle River Bank

    2. The Water Flood Will Have No Great Impact at the River Bank

    3. Has a Wide Cross Section of the River (Low Flood Water Level)

    4. Ridge is Better (Geologically Strong and Stable)

    Appropriate location forPower house

    3-10

    11

    D

    FA

    BC

    E

    Criteria

    1. Gentle River Bank

    2. The Water Flood Will Have No Great Impact at the River Bank

    3. Has a Wide Cross Section of the River (Low Flood Water Level)

    4. Ridge is better (Geologically Strong and Stable)

    B,C

    C

    C,D

    Appropriate location forPower house

    B,C,F

    3-11 12

    CRITERIA

    1. Gentle Slope

    2. Stable Geological Condition

    3. Accessible

    Please consider & recommend based on your experience of irrigation cannel

    Appropriate location forHeadrace route

    3-12

  • 13

    MARAMING SALAMAT!!!

    Thank You Very Much!!!!

    Arigato!!!

    3-13

  • 1Training on

    Micro Hydropower

    Development

    Advance Course (1st part)

    4-12

    Outline of Site Reconnaissance

    Measurement River Flow

    Measurement of Head

    Training on Micro/Mini Hydropower Development

    Advance Course

    Site Reconnaissance

    4-2

    3

    Outline of Site Reconnaissance Objective

    To roughly evaluate the feasibility of the project To get necessary information for planning

    Items to be investigated Potential capacity of the project site

    - Measurement of river flow- Measurement of head

    Topographical and geological condition of the sites for the structure layout

    Accessibility to the site Power demand in the load center Distance from the load center to the power house Ability of the local people to pay for electricity Willingness of the local people for electrification

    4-34

    Information Gathering Prepare 1/50,000 scale maps to check the location, catchment

    area, villages, access road and topography of the project sites. Gather available information on accessibility to the site, the

    weather conditions, social stability, and so on. Make copies of the 1/50,000 scale maps and route maps

    enlarged by 200 to 400%. Prepare checklists and interview sheets for site survey.

    Planning of preliminary site survey Make a plan and schedule for site survey considering

    accessibility to the sites and the weather conditions. Allow sufficient time in the schedule since most of sites are

    located in remote and isolated areas

    Preparation of Site Reconnaissance

    4-4

  • 5Equipment Equipment Route map Altimeter Topographic map GPS (portable) Reconnaissance schedule Camera, film Checklist Current meter (Float,) Interview sheet Distance meter, measure tape

    Geological map Hand level (Hose)Aerial photographs Convex scale (2-3m)Related reports Hammer

    Clinometers Field notebook Knife Scale Scoop Pencil Torch, flashlight Eraser Sampling baggage Colored pencil Label

    Section paper CompassStopwatchBatteries

    Necessary Goods for Site Reconnaissance

    4-56

    Major Items of Site Reconnaissance Investigation of potential capacity River flow measurement Head measurement

    Investigation for layout and design of facilities Intake siteWaterway route Powerhouse site Transmission/distribution line route

    Investigation of demand forecast Other outline surveys

    4-6

    7

    Measurement River Flow Reason for direct measurements:

    Since the catchment area of micro-hydro power is relatively small, the river flow at micro-hydro sites is site-specific.

    Some rivers dries up during dry season Without checking the actual flow, we cannot be confident of

    the potential capacity of the projects. Purpose:

    To get enough data to accurately predict river flow at the project site

    To check the minimum river flow during dry season (Micro) To prepare the duration curve (Mini & Large)

    Method: Current meter method Float method Bucket method Weir measuring method

    4-78

    Micro-Hydro Mini-HydroFlowchart to check Minimum Flow/ Duration Curve

    Water Level DischargeH Q

    (m) (m3/s)XXX 0.230 0.111YYY 0.550 1.734ZZZ 0.300 0.272

    WWW 0.380 0.600

    Date

    Installation of Staff Gauge(Base Point)

    Selection of MeasurementPoint

    Measuring of Cross Section

    Measuring of Cross SectionalArea(A)

    Measuring of Velocity /Speed(V)

    Calculation of Discharge(Q=A x V)

    Record the water levelon Staff gauge (H)

    A

    n

    o

    t

    h

    e

    r

    d

    a

    y

    a

    t

    l

    e

    a

    s

    t

    3

    t

    i

    m

    e

    s

    r

    e

    p

    e

    a

    t

    DailyRecord

    (Hd)

    Calculation of Rating Curve

    Calculation of DailyDischarge

    Calculation of DurationCurve

    Micro-Hydro

    G

    G G

    G

    G

    4-8

  • 91

    2

    3

    4

    5

    Installation of Staff Gauge

    R

    R

    4-910

    Electromagnetic Current Meter Propeller Current Meter

    Actual Measurement

    4-10

    11

    30cmNumber of

    Segmrntation: (i) 1 11 RemarkDistance from left

    bank: Lcm 0 520

    Water Depth:D c14.0 0.0

    Area of Segmantation:Ac

    H V H V H V H V H VDepth from Surface: H

    (cm) 0.2 5.60 12.00 5.80 28.00 6.60 47.0 7.00 17.0 3.20 13.0

    Velocity : V (cm/s)0.4 11.20 10.00 11.60 20.00 13.20 47.0 14.00 13.0 6.40 6.0

    0.8 22.40 10.00 23.20 8.00 26.40 26.0 28.00 9.0 12.80 2.0Average Velocity:

    Va c/ Total

    Discharge ofSegmantation:q (m3/s

    272.528

    50

    2,950 3,425 3,325

    30.0

    350

    33.0 35.0

    250

    2,500

    2 4 6 87

    450

    3

    100

    5

    200 300

    9

    400

    10

    150

    22.0

    1,510

    41.0 16.028.0 29.030.0

    40.00 13.00

    Flow Measurement Field SheetName of Location: Date:Time: Staff gauge

    7.00

    26.667 55.067 137.000 43.225 10.570

    10.67 18.67

    Record Sheet of Measurement River Flow

    4-1112

    Float Measuring Method

    4-12

  • 13

    h1 0.00h2 0.45h3 0.50h4 0.57h5 0.60h6 0.62h7 0.65h8 0.60h9 0.50h10 0.35h11 0.00

    Total 4.84Average 4.84/11= 0.44 m

    h1 h2 h3 h4 h5 h6 h7 h8 h9 h10h11

    L=10m

    L/10 L/10 L/10 L/10 L/10 L/10 L/10 L/10 L/10 L/10

    A=havarage x L = 0.44 x 10.00 = 4.40 m2

    Measuring of Cross Sectional Area

    Measurement of Cross Sectional Area

    4-1314

    L=2WL=2W

    W

    Cross Sectional Area ; A

    Cross Sectional Area ; B

    Cross Sectional Area ; C

    Measurement of Velocity

    4-14

    15

    0.5 m

    Vmean

    Vmean Vmean

    Vm = 0.45Vmean Vm = 0.25Vmean

    Vmean

    Vm = 0.85Vmean Vm = 0.65Vmean

    Concrete channel which cross section is uniform

    Small stream where a riverbed is smooth

    Shallow flow (about 0.5) Shallow and riverbed is not flat

    R

    R

    4-1516

    Calculation of Rating Curve

    y = 3.0993x - 0.3947

    0.0

    0.20.4

    0.6

    0.8

    1.01.2

    1.4

    1.61.8

    2.0

    0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 0.55 0.60 0.65 0.70

    Water Level (m)S

    q

    u

    a

    r

    e

    R

    o

    o

    t

    o

    f

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    Calculation of Rating CurveRating Curve

    0.10

    0.15

    0.20

    0.25

    0.30

    0.35

    0.40

    0.45

    0.50

    0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 0.55 0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.95 1.00

    Discharge (m3/s)

    W

    a

    t

    e

    r

    L

    e

    v

    e

    l

    (

    m

    )

    Q=9.579*H2-2.428H+0.154

    R

    R

    4-16

  • 17

    Calculation of Daily Discharge

    R

    Discharge of Ambangal Brook at Intake (20.2km2)

    0.00.20.40.60.81.01.21.41.61.82.02.22.42.62.83.03.23.43.63.84.04.24.44.64.85.0

    5/19/06 6/18/06 7/18/06 8/17/06 9/16/06 10/16/06 11/15/06 12/15/06 1/14/07 2/13/07 3/15/07 4/14/07 5/14/07 6/13/07 7/13/07

    Date

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    Daily Discharge

    R

    4-1718

    Discharge of Ambangal Brook at Intake (20.2km2)

    0.00.20.40.60.81.01.21.41.61.82.02.22.42.62.83.03.23.43.63.84.04.24.44.64.85.0

    5/19/06 6/18/06 7/18/06 8/17/06 9/16/06 10/16/06 11/15/06 12/15/06 1/14/07 2/13/07 3/15/07 4/14/07 5/14/07 6/13/07 7/13/07

    Date

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    Daily DischargeDuration Curve at Intake Site (C.A.=20.2km2)

    0.00.20.40.60.81.01.21.41.61.82.02.22.42.62.83.03.23.43.63.84.04.24.44.64.85.0

    0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

    Percentage (%)

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    Calculation of Duration Curve

    4-18

    19

    Head measurement

    Water-filled tube method Easy to handle No need for a skilled engineer Relatively accurate

    H1

    H3

    H4

    H5

    H6

    H2

    Head

    Head = H1+H2+H3+H4+H5+H6

    H1 = B1-A1

    B1

    H1

    A1

    4-1920

    Result of head measurementDate :

    No. Hi=Bi-Ai(meters)1 0.852 0.863 0.864 0.915 0.996 0.757 0.308 0.909 0.70

    10 0.7411 2.3012 0.66

    10.82

    Location :

    0.70 1.36Total Height (meters)=

    1.00 1.740.20 2.50

    1.00 1.901.00 1.70

    1.00 1.751.00 1.30

    1.00 1.911.00 1.99

    1.00 1.861.00 1.86

    Ai(meters)

    Bi(meters)

    1.00 1.85

    4-20

  • 21

    Head measurement (Easy Way)Using Water Bottle

    H

    H

    HH

    H

    H

    HHead=nxH

    H

    4-2122

    Date :

    No. Hi=Bi-Ai(meters)1 0.852 0.863 0.864 0.915 0.996 0.757 0.308 0.909 0.70

    10 0.7411 2.3012 0.66

    10.82

    Location :

    0.70 1.36Total Height (meters)=

    1.00 1.740.20 2.50

    1.00 1.901.00 1.70

    1.00 1.751.00 1.30

    1.00 1.911.00 1.99

    1.00 1.861.00 1.86

    Ai(meters)

    Bi(meters)

    1.00 1.85

    Result of head measurement

    Using Water Bottle : 1.56 m x 7 times 0.15= 11.07 m

    4-22

    23

    Thanks !!!!

    4-23

  • 1Training on

    Micro Hydropower

    Development

    Advance Course (2nd part)

    5-1 2

    Intake Weir

    Intake and Settling Basin

    Headrace

    Head-Tank

    Penstock

    Powerhouse

    Head Loss Calculation

    Training on Micro Hydropower Development

    Advance Course

    Design of Civil Structures

    5-2

    3

    Basic Equation for Civil Design: Important

    Q = A x VQ: Discharge (m3/s)A: Cross sectional area of water (m2)V: Velocity of water (m/s)

    V = Q / A

    A = Q / V AV

    1 secondV

    A

    1 second

    meters/

    meters/

    5-3 4

    2-1 Intake Weir(1) Type of Intake Weir (refer to Manual p5-2 to 5-4)

    Foundations: GravelFloating concrete

    Foundations: Bedrock

    Concrete gravity

    Application ConditionOutline DrawingType of Weir

    5-4

  • 52-1 Intake Weir(2) Example of the Intake Weir

    Designed as Gravity TypeDestroyed by Flood ,due to lack of strength of the foundation

    Re-designed as Floating Type

    5-5 6

    2-1 Intake Weir(3) Design of the Weir Height

    Conditions into consideration (Manual p-5-4 to P5-6 ) Minimizing the Height

    High High Cost & Wide Affected AreaLow Low Cost & Small Affected Area

    Smooth Removal of Sediment

    Weir Height is depend on Slope of the Riverbed

    5-6

    7

    2-1 Intake Weir(3) Design of the Weir Height

    L

    ic

    ir d2

    d1

    hi

    B

    Width of Inlet (B) Height from river bed to bed of inlet (d1) Water depth of inlet (hi) Slope of settling basin (ic) Slope of River (ir) Length of settling basin (L) Height from river bed to bed settling basin (d2)

    5-7 8

    2-1 Intake Weir(3) Design of the Weir Height

    L

    ic

    ir d2

    d1

    hi

    D1 = d1 + hi

    D2 = d2 + hi+ L x (ic ir)

    D1 > D2 Weir Height = D1D2 > D1 Weir Height = D2

    B

    5-8

  • 92-1 Intake Weir(3) Design of the Weir Height

    Design Discharge (Q) 0.220 Width of Inlet (B) 0.550 meters Height from river bed to bed of inlet (d1) 0.500 meters Water depth of inlet (hi) 0.400 Velocity at inlet (Vi) 1.000 'D1=d1+hi 0.900 Slope of settling basin (ic) 0.050 (1/20) Slope of River (ir) 0.100 (1/10) Length of settling basin (L) 10.000 Height from river bed to bed settling basin (d2) 0.500 D2=d2+hi+L*(ic-ir) 0.400

    Weir height from original river bed 0.900 meters

    : Values which are decided on other factors: Common values for design (refer to "Manual"): Values depend on natural condition

    D1>D2

    D1 = d1 + hi

    D2 = d2 + hi+ L (ic ir)

    Example (Steep river)

    5-9 10

    2-1 Intake Weir(3) Design of the Weir Height

    D1 = d1 + hi

    D2 = d2 + hi+ L (ic ir)

    Example (Gentle river) Design Discharge (Q) 0.220 Width of Inlet (B) 0.550 meters Height from river bed to bed of inlet (d1) 0.500 meters Water depth of inlet (hi) 0.400 Velocity at inlet (Vi) 1.000 'D1=d1+hi 0.900 Slope of settling basin (ic) 0.050 (1/20) Slope of River (ir) 0.010 (1/100) Length of settling basin (L) 10.000 Height from river bed to bed settling basin (d2) 0.500 D2=d2+hi+L*(ic-ir) 1.300

    Weir height from original river bed 1.300 meters: Values which are decided on other factors: Common values for design (refer to "Manual"): Values depend on natural condition

    D2>D1

    5-10

    11

    2-1 Intake Weir

    Important H x 3.0 L1+ L2 + L3 + L4 + L5 + L6 + L7

    800 1,200 3,9001,000

    6,900

    1.0

    1

    EL.497.200 m

    EL.496.000 m

    1

    ,

    2

    0

    0

    1

    ,

    5

    0

    0

    7

    0

    0

    8

    0

    0

    500400

    500400

    5,100

    1

    ,

    5

    0

    0

    GabionH x B x L =0.6 x 0.8 x 1.0m)

    Masonry Concrete

    Reinforced Concrete (t=25cm)

    0.8 1.00.6 1.0 m

    H

    L1

    L2

    L3L4 L5

    L6

    L7

    1.0 1.5 m 1.0 1.5 m

    0.5 m

    Common Values

    Flood water level

    5-11 12

    2-2 Intake and Settling Basin

    Intake

    Intake weir

    Protect wall

    Image of Intake ( Side Intake Type)

    5-12

  • 13

    2-2 Intake and Settling Basin

    Concepts of the design

    The dimension of the intake should be designed that thevelocity of inflow at the intake is 1.0 or less m/s.

    The ceiling of the intake should be designed with allowance of 10-15cm from the water surface.

    The height and area of the intake should be designed with the minimum size.

    5-13 14

    2-2 Intake and Settling BasinProtect wall

    Intake Weir

    Flush gate (Stop-log)

    Intake

    b

    hidh

    Vi

    Q = A x V

    V = Q / A Vi = Q / (b x hi)1.0 m/s dh=0.1-0.15m

    Intake ( Side Intake Type)

    5-14

    15

    2-2 Intake and Settling BasinSettling Basin

    Spill way Flush gate

    5-15 16

    2-2 Intake and Settling BasinSettling Basin(1) Design of Spillway

    Flood Water Level

    Water Level of Spillway

    Normal Water Level

    sp

    p

    Ai

    hi

    dh

    dh

    hi

    bi

    H

    Q f1= Ai Cv Ca (2 g H ) 0.5

    Q f2= Cs hsp1.5 Bsp

    Ai= hi x bi

    Q f1= Q f2

    0.667 0.6 9.8

    1.8

    5-16

  • 17

    2-2 Intake and Settling BasinSettling Basin(1) Design of Spillway (Example)

    Flood water level from crest of spillway (Ht) 2.000 from flood mark Area of intake (Ai) 0.303 dh=0.15m f 0.500 Cv=1/(1+f) 0.667 Ca 0.600 Cs 1.800 Width of spillway of settling basin (Bsp) 3.000

    H Qf1 Qf2 Qf1-Qf21.900 0.738 0.171 0.5681.800 0.719 0.483 0.2361.742 0.707 0.708 (0.001)1.700 0.698 0.887 (0.189)1.600 0.678 1.366 (0.689)1.500 0.656 1.909 (1.253)

    : Values which are decided on other factors: Common values for design (refer to "Manual"): Values depend on natural condition

    0.3000.4000.500

    Qf1=Ai x Cv x Ca x (2 x 9.8 x H)^0.5 Qf2=Cs x Bsp x hsp^1.5

    hsp0.1000.2000.258

    Usually hsp < 0.3m

    5-17 18

    2-2 Intake and Settling Basin

    Conduit sectionWidening section

    Settling section

    Bb

    1.02.0

    Dam

    SpillwayStoplog Flushing gate

    Intake

    Headrace

    Bsp

    hs

    h

    s

    p

    +

    1

    5

    c

    m

    h0

    1

    0

    1

    5

    hi

    ic=1/201/30

    IntakeStoplog

    bi

    Sediment Pit Flushing gate

    (2) Dimension of settling basinCommon Values

    Lw=B-b

    Depends on site condition

    b=bi

    Decided Values

    Un-known Values

    hs=hi+(Lc+Lw)*ic

    5-18

    19

    Where,

    l : minimum length of settling basin (m)

    hs : water depth of settling basin (m)

    U : marginal settling speed for sediment to be settled (m/s)

    usually around 0.1 m/s for a target grain size of 0.5 1 mm.

    V : mean flow velocity in settling basin (m/s)

    usually around 0.3 m/s

    V = Qd/(Bhs)

    Qd: design discharge (m3/s)

    B : width of settling basin (m)

    2-2 Intake and Settling Basin(2) Dimension of settling basin

    l x hs L= 2 x l U V

    5-19 20

    2-2 Intake and Settling Basin

    (2) Dimension of settling basinLl x hs L= 2 x l U V

    Design Discharge (Q) 0.220 Width of Intake (bi = b) 0.550 Length of conduit section (Lc) 2.000 Length of widening section (Lw) 0.950 Width of settling basin (B) 1.500 hi 0.400 ic 0.050 1/20 hs=hi+(Lc+Lw) x ic 0.548 U 0.100 V=Q/(B*hs) 0.300

    1.339 B1.500 Bact

    Vact =Q/(Bact*hs) 0.268 l=(Vact/U) x hs 1.467Ls=2 x l 2.933Length of basin= Ls 3.000

    Width of settling basin (B=Q/(V x hs))

    : Values which are decided on other factors: Common values for design (refer to "Manual"): Values depend on natural condition: Decided Values

    5-20

  • 21

    2-3 Headrace

    (1) Type of Headrace

    Open Type

    Closed Type

    No-Lining type

    Lining type

    Pipe type

    Box type

    5-21 22

    2-3 Headrace

    H

    e

    a

    d

    L

    o

    s

    s

    Settling Basin Headrace Headtank

    Slope =Gentle

    Micro=1/100 to 1/300

    (2) Dimension of Headrace (Open Type)

    Dimension of headrace depends on Discharge and Slope

    5-22

    23

    Values for Deign

    h

    b

    A

    bLength of red-line : P

    1

    m

    Slope =1/m: SL

    Q

    Q= A R 2/3SL 1/2 n

    Q : design discharge for headrace (m3/s)

    A : area of cross section (m2)

    R : R=AP (m)

    P : length of wet sides (m).

    SL : longitudinal slope of headrace (e.g. SL= 1/100=0.01)

    n : coefficient of roughness (for concrete =0.015)

    A= b x h

    5-23 24

    Example

    Q=0.220m3/s SL=1/250=0.004Condition for calculation

    Designers setting

    b= 0.550 m

    Q : design discharge for headrace (m3/s)

    A : area of cross section (m2)

    R : R=AP (m)

    P : length of wet sides (m) refer to next figure.

    SL : longitudinal slope of headrace

    n : coefficient of roughness (for concrete =0.015)

    A= b x h

    0.550

    0

    .

    5

    5

    0

    0

    .

    3

    3

    5

    A

    p

    r

    .

    0

    .

    2

    A P R R2/3 Qi

    b x h b+2 x h A/P Q= A R 2/3SL 1/2 n

    0.100 0.063 0.055 0.750 0.073 0.175 0.0410.200 0.063 0.110 0.950 0.116 0.237 0.1100.300 0.063 0.165 1.150 0.143 0.274 0.1910.335 0.063 0.184 1.220 0.151 0.283 0.2200.400 0.063 0.220 1.350 0.163 0.298 0.2770.500 0.063 0.275 1.550 0.177 0.316 0.366

    SL1/2h

    5-24

  • 25

    2-3 Headrace8

    0

    0

    2

    5

    0

    1

    5

    0

    600250 250160 160

    1,380

    8

    5

    0

    2

    5

    0

    Mortar Plaster t=5cm

    Masonry Concrete

    4

    7

    0

    D8

    D9

    150 600 150

    0.5

    1.0

    3

    3

    0

    4

    7

    08

    0

    0

    2

    5

    0

    1

    5

    0

    2

    0

    0

    8

    5

    0

    1

    ,

    0

    5

    0

    5-25 26

    2-4 Head-tank (Fore-bay -tank)

    Spill way

    Flush Gate

    Screen

    5-26

    27

    2-4 Head-tank (Fore-bay -tank)

    0.5

    1.0

    dsc

    As

    d

    Bspw

    hc

    h0h>1.0

    S=12

    1.020.0

    1.02.0

    3050cm

    B-b

    Headrace

    3050cm

    Ht

    Spillway

    Screen

    SLe

    h0=H*0.1Sle0.5H*Refer to 'Reference 5-1'hc=(Qd2)(B2)}1/3=1.1g=9.8d=1.273(QdVopt0.5 Vopt:Refer to 'Reference 5-2'Vsc=Asdsc=BLdsc10secQdB,dsc:desided depend on site condition.

    Common Values

    Decided Values

    Un-known Values

    0.5

    1.0

    dsc

    As

    d

    Bspw

    hc

    h0h>1.0

    S=12

    1.020.0

    1.02.0

    3050cm

    B-b

    Headrace

    3050cm

    Ht

    Spillway

    Screen

    SLe

    h0=H*0.1Sle0.5H*Refer to 'Reference 5-1'hc=(Qd2)(B2)}1/3=1.1g=9.8d=1.273(QdVopt0.5 Vopt:Refer to 'Reference 5-2'Vsc=Asdsc=BLdsc10secQdB,dsc:desided depend on site condition.

    dsc < h

    5-27 28

    2-4 Head-tank (Fore-bay-tank)Example

    Q=0.220m3/sB= 2.000 m

    Condition for calculationDesigners setting

    Vsc > 10 x QAs = B x L = 8.000 m2

    L= 4.000 m dsc = 10 x Q/As =2.20/8=0.275mh = 0.335m

    Calculation

    dschCheck

    Change B or L No

    hc={(Q2)(gB2)}1/3

    : 1.1 g : 9.8

    Yes

    5-28

  • 29

    2-5 Penstock

    5-29 30

    Lp

    Head Tank

    Power

    Hp

    Ap = Hp Lp

    Powerhouse

    2-5 Penstock Diameter of penstockExampleQ : Discharge 0.220 m3/s

    Lp: Total length of penstock

    80.0m

    Hp: Head from Head-tank to C/T

    20.0m

    Ap=Hp/Lp=0.25

    Vopt= 2.3 m/s

    D=1.128 x (Q/Vopt)0.5

    =1.128 x (0.22/ 2.3)0.5

    =0.348 0.350 m

    0.500.600.700.800.901.001.101.201.301.401.501.601.701.801.902.002.102.202.302.402.502.602.702.802.903.003.103.20

    0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40

    Average angle of penstock Ap

    O

    p

    t

    i

    m

    u

    m

    v

    e

    l

    o

    c

    i

    t

    y

    V

    o

    p

    t

    (

    m

    /

    s

    )

    D=1.273(QVopt)0.5

    D:diameter of pipe(m)Q: design discharge(m3/s)Vopt: optimum velocity(m/s)

    1.128

    5-30

    31

    2-5 Penstock Thickness of penstock

    t0 = + t (cm)Pd

    2at0 = + t (cm)

    Pd2a

    and t0=0.4cm or t0(d+80)40 cm

    t0: minimum thickness of pipe

    P: design water pressure i.e. hydrostatic pressure + water hammer (kgf/cm2) ,

    in micro-hydro scheme P=1.1hydrostatic pressure.

    for instance, if the head which from headtank to turbine is 25m,

    P=2.51.1=2.75 kgf/cm2.

    d: inside diameter (cm)

    a: admissible stress (kgf/cm2) SS400: 1300kgf/cm2

    : welding efficiency (0.850.9)

    t : margin (0.15cm in general)

    5-31 32

    2-6 Powerhouse (for impulse turbine)

    Flood Water Level(Maximum)

    20cm

    boSection A-A

    20cmb

    bo: depends on Qd and He

    3050cm

    3050cm

    HL3(see Ref.5-3)

    hc={ }1/31.1Qd

    2

    9.8

    A

    A

    Afterbay Tailrace cannel Outlet

    5-32

  • 33

    2-6 Powerhouse (for refection turbine)

    Section A-A

    1.5d3

    Flood Water Level(Maximum)3050cm

    23

    d3

    2

    0

    c

    m

    1.15d3

    1.5d3

    Hs

    Hsdepens on characteristic of turbine

    HL3(see Ref.5-3)

    hc={ }1/31.1Qd

    2

    9.8

    A

    A

    5-33 34

    2-6 Powerhouse (with tailrace gate)

    Pump

    Gate

    HL3

    Flood Water Level (Maxmum)

    5-34

    35

    2-7 Calculation of Head Loss

    Hg He

    HL1HL2

    HL3

    Forebay

    Penstock

    Settling Basin

    Headrace Intake

    PowerhouseTailrace

    H

    He = Hg (HL1 + HL2 + HL3 )

    Where: He - Effective Head

    Hg - Gross Head

    HL1 - Loss from intake to head-tank (fore-bay)

    HL2 - Loss at penstock

    HL3 - Installation head and Loss at tailrace

    5-35 36

    Hg He

    HL1 HL2

    HL3

    Forebay

    Penstock

    Settling Basin

    Headrace Intake

    Powerhouse Tailrace

    H

    2-7 Calculation of Head Loss

    (1) Calculation of HL1: Loss from intake to head-tankElevation of crest of intake weir : ELs

    Elevation of water level at head-tank : ELe

    HL1= ELs-Ele

    5-36

  • 37

    2-7 Calculation of Head Loss

    Hg He

    HL1HL2

    HL3

    Forebay

    Penstock

    Settling Basin

    Headrace Intake

    PowerhouseTailrace

    H

    Flood Water Level(Maximum)

    3050cm

    3050cm

    HL3(see Ref.5-3)

    { }9.8

    A

    Afterbay Tailrace cannel Outlet

    HL3

    (2) Calculation of HL3:Loss at tailrace

    5-37 38

    (3) Calculation of HL2:Loss at penstock2-7 Calculation of Head Loss

    (a) Friction LossFriction loss (Hf) is one of the biggest losses at penstock.

    Hf = f pp2 2gp

    f - Coefficient on the diameter of penstock pipe . f= 124.5n2Dp1/3

    Ap - Cross sectional area of penstock pipe. (m2) Ap = 3.14Dp24.0 Vp - Velocity at penstock (m/s) Vp = Q Ap

    Q - Design discharge (m3/s) Lp - Length of penstock. (m)Dp - Diameter of penstock pipe (m) g=9.8n = Coefficient of roughness (steel pipe: n=0.12, plastic pipe: n=0.011)

    5-38

    39

    (3) Calculation of HL2:Loss at penstock

    2-7 Calculation of Head Loss

    (b) Inlet Loss

    He = f ep2 2gfe : Coefficient on the form at inlet. Usually fe = 0.5 in micro-hydro scheme

    (c) Valve Loss

    Hv = f vp2 2gfv = 0.1 ( butterfly valve)

    HL2=1.1 x (Hf + He + Hv)

    5-39 40

    Thank You !!!!

    5-40

  • 1Training on

    Micro Hydropower

    Development

    Reference

    6-1 2

    Optimum/Appropriate

    Installed Capacity of

    Mini Hydropower Plant

    6-2

    3

    Optimum Installed Capacity

    Generation Side Condition Demand Side Condition

    Conditions for Optimum Installed Capacity

    6-3 4

    Daily Discharge Jun 2006-May 2008 (C.A=20.2km2)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    J J A S O N D J F M A M J J A S O N D J F M A MD

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    1- Generation Side Condition

    (1) Discharge at the Site

    6-4

  • 540% 50% 70%

    0.5

    1.0

    1.5

    R

    i

    v

    e

    r

    F

    l

    o

    w

    (

    m

    3

    /

    s

    )

    60% 80%

    C

    o

    n

    s

    t

    r

    u

    c

    t

    i

    o

    n

    C

    o

    s

    t

    /

    k

    W

    h

    Percentage of Duration

    40 % 50 % 60 % 70 % 80 %

    For Mini/Large Hydro : Comparison of Unit Cost in Each Case

    Duration Curve : How to Identify Max. Design Discharge

    6-5 6

    Duration Curve at Intake Site (C.A.=20.2km2)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

    Percentage (%)

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    Duration Curve

    (2) Duration Curve, Max. Discharge and Plant Factor

    A

    D

    Area of (A-b-c-C-D)Discharge Plant Factor= =

    Area of (A-B-C-D)76.69%

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    D

    i

    s

    c

    h

    a

    r

    g

    e

    P

    l

    a

    n

    t

    F

    a

    c

    t

    o

    r

    (

    %

    )

    B

    C

    b

    c

    Discharge Plant Factor

    Maximum Design

    Discharge = 0.8 m3/s

    Average Discharge in the Power Plant = Maximum Design Discharge x Discharge Plant Factor=0.8 m3/s x 0.7669 = 0.613 m3/s

    Average Output = 9.8 x Average Discharge x Head x efficiency

    Annual Generation (kWh) = Average Output x 365 days x 24hr

    6-6

    7

    (2) Duration Curve, Max. Discharge and Plant Factor

    Duration Curve at Intake Site (C.A.=20.2km2)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

    Percentage (%)

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    D

    i

    s

    c

    h

    a

    r

    g

    e

    P

    l

    a

    n

    t

    F

    a

    c

    t

    o

    r

    (

    %

    )

    Discharge Plant Factor

    Duration Curve

    1.20m3/s64.45 %

    1.02m3/s

    69.95 %

    0.81m3/s

    76.69 %

    0.67m3/s

    81.24 %

    0.50m3/s

    86.46%

    0.37m3/s

    91.27%

    0.21m3/s

    96.56%

    6-7 8

    (3) Max. Output and Annual Generation in each CaseCondition : Effective Head = 100 meters

    Total Efficiency = 76 %

    Note : = 365days x 24hrs x x

    DurationPercentage

    (%)

    MaximumDischarge

    (m3/s)

    Max.

    Output(kW)

    Plant Factor

    (%)

    Annual Generation

    (MWh/year)

    30 1.20 920 64.45 5,19440 1.02 780 69.95 4,78050 0.81 620 76.69 4,16560 0.67 510 81.24 3,62970 0.50 380 86.46 2,87880 0.37 280 91.27 2,23990 0.21 160 96.56 1,353

    6-8

  • 9(4) Optimum Capacity based on Unit Generation Cost (Philippines)

    Source : DOE-REMD

    6-9

    Unit Construction Costy = -24773Ln(x) + 314639

    80,000

    100,000

    120,000

    140,000

    160,000

    180,000

    200,000

    220,000

    240,000

    260,000

    0 200 400 600 800 1000 1200 1400 1600 1800 2000

    Installed Capacity (kW)

    U

    n

    i

    t

    C

    o

    n

    s

    t

    r

    u

    c

    t

    i

    o

    n

    C

    o

    s

    t

    (

    P

    h

    p

    /

    k

    W

    )

    10

    (4) Optimum Capacity based on Unit Generation Cost(Philippines)

    DurationPercentage

    (%)

    MaximumDischarge

    (m3/s)

    Max.Output(kW)

    Plant Factor(%)

    Annual Generation

    (MWh/year)

    UnitConstruction

    Cost(Php/kW)

    TotalConstruction

    Cost(Php)

    =Unit Generation

    Cost(Php/kWh)

    30 1.20 920 64.45 5,194 145,579 133,932,488 25.78540 1.02 780 69.95 4,780 149,668 116,741,283 24.42550 0.81 620 76.69 4,165 155,356 96,320,447 23.12560 0.67 510 81.24 3,629 160,194 81,698,911 22.51070 0.50 380 86.46 2,878 167,483 63,643,592 22.11380 0.37 280 91.27 2,239 175,048 49,013,540 21.89490 0.21 160 96.56 1,353 188,912 30,225,875 22.334

    Optimum Installed Capacity

    21.000

    22.000

    23.000

    24.000

    25.000

    26.000

    20 30 40 50 60 70 80 90 100Duration Percentage (%)

    U

    n

    i

    t

    G

    e

    n

    e

    r

    a

    t

    i

    o

    n

    C

    o

    s

    t

    (

    P

    h

    p

    /

    k

    W

    h

    )

    Other Indexa. Cost/Benefitb. IRR

    6-10

    11

    (4) Optimum Capacity based on Unit Generation Cost (Japan)

    Unit Construction Cost y = -565.48Ln(x) + 5306.5

    600

    800

    1,000

    1,200

    1,400

    1,600

    1,800

    2,000

    2,200

    2,400

    2,600

    0 200 400 600 800 1000 1200 1400 1600 1800 2000

    Installed Capacity (kW)

    U

    n

    i

    t

    C

    o

    n

    s

    t

    r

    u

    c

    t

    i

    o

    n

    C

    o

    s

    t

    (

    1

    0

    0

    0

    J

    P

    Y

    /

    k

    W

    )

    Source : TEPSCO

    6-11 12

    (4) Optimum Capacity based on Unit Generation Cost(Japan)

    DurationPercentage

    (%)

    MaximumDischarge

    (m3/s)

    Max.Output(kW)

    Plant Factor(%)

    Annual Generation

    (MWh/year)

    UnitConstruction

    Cost(JPY/kW)

    TotalConstruction

    Cost(JPY)

    =Unit Generation

    Cost(JPY/kWh)

    30 1.20 920 64.45 5,194 1,447,453 1,331,656,923 256.37640 1.02 780 69.95 4,780 1,540,802 1,201,825,930 251.45250 0.81 620 76.69 4,165 1,670,622 1,035,785,782 248.67760 0.67 510 81.24 3,629 1,781,065 908,343,366 250.26870 0.50 380 86.46 2,878 1,947,452 740,031,745 257.12780 0.37 280 91.27 2,239 2,120,139 593,638,969 265.17590 0.21 160 96.56 1,353 2,436,591 389,854,514 288.059

    Optimum Installed Capacity

    240

    250

    260

    270

    280

    290

    300

    20 30 40 50 60 70 80 90 100Duration Percentage (%)

    U

    n

    i

    t

    G

    e

    n

    e

    r

    a

    t

    i

    o

    n

    C

    o

    s

    t

    (

    J

    P

    Y

    /

    k

    W

    h

    )

    6-12

  • 13

    Reference : Comparison of Unit Construction Cost

    Comparison of Unit Construction Cost

    0

    100,000

    200,000

    300,000

    400,000

    500,000

    600,000

    700,000

    800,000

    900,000

    1,000,000

    1,100,000

    1,200,000

    0 200 400 600 800 1000 1200 1400 1600 1800 2000

    Installed Capacity (kW)

    U

    n

    i

    t

    C

    o

    n

    s

    t

    r

    u

    c

    t

    i

    o

    n

    C

    o

    s

    t

    (

    P

    h

    p

    /

    k

    W

    )

    Philippines

    Japan

    6-13 14

    Reference : Comparison of Duration Curve

    Duration Curve C.A=20.2km2

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    0 10 20 30 40 50 60 70 80 90 100

    Percentage of Date (%)

    U

    n

    i

    t

    D

    i

    s

    c

    h

    e

    r

    g

    e

    (

    m

    3

    /

    s

    /

    1

    0

    0

    k

    m

    2

    ) Based on Statistical Analysis

    Based on Actual Data

    6-14

    15

    2- Demand Side Condition

    Demand Area

    Big Capacity of the Grid Enough Other Power Source

    Small Capacity of the Grid Insufficient Other Power Source

    6-15 16

    Daily Discharge Jun 2006-May 2008 (C.A=20.2km2)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    J J A S O N D J F M A M J J A S O N D J F M A M

    D

    i

    s

    c

    h

    a

    r

    g

    e

    (

    m

    3

    /

    s

    )

    30%

    40%

    50%60%

    70%80%

    90%

    2- Demand Side Condition

    Fluctuation of the Generated Power

    920kW

    780kW

    610kW

    520kW

    390kW270kW

    160kW

    6-16

  • 17

    2- Demand Side Condition

    0.2

    0.4

    0.6

    0.8

    D

    i

    s

    c

    h

    a

    50%60%

    70%80%

    90%

    610kW

    520kW

    390kW270kW

    160kW

    Existing Power Source

    Fluctuation is relatively Small

    Most of Generated Power can be Sold

    Optimum Installed Capacity depends on Generation Side Condition

    (1) Big Demand Area

    6-17

    High Load Factor

    Selling Electric Generation (kWW)Load Factor=

    Electric Generation of the Plant (kWh)

    18

    2- Demand Side Condition

    (2) Small Demand Area

    Existing Power Source

    0.2

    0.4

    0.6

    0.8

    D

    i

    s

    c

    h 50%60%

    70%80%

    90%

    610kW

    520kW

    390kW270kW

    160kW

    Fluctuation is relatively Big

    Some of Generated Power can not be Sold

    Optimum Installed Capacity depends on Demand Side Condition

    6-18

    Low Load Factor

    19

    Construction CostDepends on

    Installed CapacitykW

    ProfitDepends on

    Sold Annual GenerationkWh

    Over Installed Capacity High Cost & Low Profit

    6-19 20

    MARAMING SALAMAT!!!

    Thank You Very Much!!!!

    Arigato!!!

    6-20

  • DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    Review Training forReview Training forMicroMicro--hydropower Technologieshydropower Technologies

    Electric and Mechanical EquipmentElectric and Mechanical Equipment

    2DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    TurbineTurbine

    3DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    ContentsContents

    1. Basics of hydraulics

    2. Turbine types

    3. Characteristics of turbine

    4. Basic design of turbine

    4DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.1 Principle of continuity1.1 Principle of continuity

    Discharge is constant at any section of the pipe regardless of change in the sectional area.

    Q1 = Q2 (Q=constant)

    A1 X V1 = A2 X V2*Q (m3/s) = A (m2) X V (m/s)

    In other words, if the section area of the pipe is reduced, the velocity will be increased.

    Discharge: Q1Sectional area: A1Velocity: V1

    Discharge: Q2Sectional area: A2Velocity: V2

    Water flowWater flow

    PipePipe

    1. Hydraulics

  • 5DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.2 1.2 Bernoulli's theoremBernoulli's theorem

    Close

    Reference levelPotential head: z (m)

    Pressure head:p / w (m)

    Pressure energy:p (kg/m2)= w (kg/m3) X z (m)

    w: unit weight of water

    Pressure head: z = p / w (m)

    Total head =(Potential head)+(Pressure head)= z + (p / w)

    No flow

    Total head

    1.2.1 1.2.1 Energy of water without discharge (v=0 m/s)Energy of water without discharge (v=0 m/s)

    1. Hydraulics

    6DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.2 1.2 Bernoulli's theoremBernoulli's theorem

    Open

    Reference levelPotential head: z (m)

    Kinetic energy:(1/2) X (w/g) X v2 = w X zg: gravity acceleration 9.8 (m/s2)

    Velocity head: z = v2 / 2g (m)

    Total head =(Potential head)+(Pressure head)+(Velocity head)= z + (p / w) + (v2/2g)

    Flow velocity v (m/s)

    Total head

    1.2.2 1.2.2 Energy of water with discharge (vEnergy of water with discharge (v0 m/s)0 m/s)(not considering head loss)

    Pressure head:p / w (m)

    Velocity head:v2 / 2g (m)

    1. Hydraulics

    7DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.2 1.2 Bernoulli's theoremBernoulli's theorem1.2.3 Bernoulli1.2.3 Bernoullis theorems theorem

    Sum of potential head, pressure head, and velocity head is constant at any section of the pipe.

    (Potential head) + (Pressure head) + (Velocity head) = Constant

    z + (p / w) + (v2 / 2g) = Constant

    If the flow velocity is increased due to reduction of the sectional area, the pressure will be decreased.

    Total head H = hA + (pA / w) + (vA2/2g)= hB + (pB / w) + (vB2/2g)

    1. Hydraulics

    8DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.2 1.2 Bernoulli's theoremBernoulli's theorem

    Open

    Reference levelPotential head: z (m)

    Ref.Head loss consists of friction loss hf, inlet loss he, valve loss hv, etc.

    hf=f X (Lp/Dp) X (v2/2g)he=fe X (v2/2g)hv=fv X (v2/2g) ho=510% X (hf+he+hv)

    Total head =(Potential head)+(Pressure head)+(Velocity head)+(Head loss)= z + (p / w) + (v2/2g) + Hloss

    Flow velocity v (m/s)Total head

    1.2.4 1.2.4 Energy of water with discharge (vEnergy of water with discharge (v0 m/s)0 m/s)(considering head loss)

    Velocity head:v2 / 2g (m)

    Pressure head:p / w (m)

    Head loss: Hloss (m)

    1. Hydraulics

  • 9DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.2 1.2 Bernoulli's theoremBernoulli's theorem

    1.2.5 Calculation of net head on site (1)1.2.5 Calculation of net head on site (1)

    Penstock pressure P (kgf/cm2): measured by pressure gauge

    Pressure gauge height h (m): measured by tape

    Discharge Q (m3/s): measured by ultrasonic flow meter

    Penstock outside diameter Dpo (m): measured by tape

    Available data on site:

    Pressure gauge Ultrasonic flow meter

    Pressure gauge

    PenstockTurbineCenter

    h

    Height of pressure gauge h

    1. Hydraulics

    10DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.2 1.2 Bernoulli's theoremBernoulli's theorem 1. Hydraulics

    1.2.5 Calculation of net head on site (2)1.2.5 Calculation of net head on site (2)

    Gross head Hg (m) = Ps (kgf/cm2) X 10 + (pressure gauge height h)Ps: readout of the pressure gauge under suspension (inlet valve closed)

    Penstock inside diameter Dp (m):Estimated based on the nominal size of the penstock

    Penstock sectional area A (m2) = (XDp2)/4

    Flow velocity v (m/s) = Q / A

    Net head He = (Pressure head) + (Velocity head) + (Potential head)= (Po X 10) + (v2 / 2g) + (pressure gauge height h)

    Po: readout of the pressure gauge in operation

    Head loss Hloss (m) = (Gross head Hg) (Net head He)

    11DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    1.2 1.2 Bernoulli's theoremBernoulli's theorem 1. Hydraulics

    1.2.5 Calculation of net head on site (3)1.2.5 Calculation of net head on site (3)

    Exercise

    Measurements on site Penstock pressure Ps: 1.266 kgf/cm2 (under suspension) Penstock pressure Po: 0.956 kgf/cm2 (in operation) Pressure gauge height h: 0.25 m Discharge Q: 0.0533 m3/s (53.3 L/s) Penstock inside diameter Dpi: 0.2 m

    Please calculate gross head Hg, net head He, and head loss Hloss. Gross head Hg (m) = Penstock sectional area A (m2) = Flow velocity v (m/s) = Velocity head Hv (m) = Net head He (m) = Head loss Hloss (m) =

    12DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    2.1 Types of turbine2.1 Types of turbine 2.Turbine types

    The runner rotates by impulsive force of water jet with the velocity head, which has been converted from the pressure head at the time of jetting from the nozzle

    Pelton turbine Crossflow turbine* Turgo-impulse

    Impulse turbine:Impulse turbine:

    The runner rotates by reactive force of water with the pressure head

    Francis turbine Propeller turbine (Kaplan, Bulb, Tubular, etc.)

    Reaction turbine:Reaction turbine:

    *Crossflow turbine has characteristics of both impulse and reaction turbine

  • 13DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    2.Turbine types2.1 Types of turbine2.1 Types of turbine

    2.1.1 2.1.1 PeltonPelton turbineturbine Water jet from the nozzles acts

    on the buckets, and the runner is rotated by the impulsive force

    Horizontal-shaft Pelton turbine can be applied to micro/small hydropower project

    Suitable for run-of-river project, especially with high-head and less head change

    Applicable range Output: 100 5,000 kW Discharge: 0.2 3 m3/s Head: 75 400 m

    14DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    2.Turbine types2.1 Types of turbine2.1 Types of turbine

    2.1.2 2.1.2 CrossflowCrossflow turbineturbine Arc shape runner blades are

    welded on the both side of iron plate discs

    Simple structure, easy O&M, andreasonable price

    Suitable for rural electrification project using micro hydropower plant

    Applicable range Output: 50 1,000 kW Discharge: 0.1 10 m3/s Head: 5 100 m

    15DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    2.Turbine types2.1 Types of turbine2.1 Types of turbine

    2.1.3 Francis turbine2.1.3 Francis turbine Water flow brought from the

    penstock flows into the runner through casing and guide vane

    Wide applicable range of head and discharge

    Horizontal-shaft Francis turbine can be applied to micro/small hydropower project

    Applicable range Output: 200 5,000 kW Discharge: 0.4 20 m3/s Head: 15 300 m Spiral casing

    Guide vane

    16DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    2.Turbine types2.1 Types of turbine2.1 Types of turbine

    2.1.4 Tubular turbine2.1.4 Tubular turbine One of propeller turbines tubular

    casing

    Wide applicable range of head and discharge

    Suitable for low-head sites

    Applicable range Output: 50 5,000 kW Discharge: 1.5 40 m3/s Head: 3 18 m

    Generator

    Propeller RunnerGuide Vane

    (Wicket Gate)

    Timing Belt

    Draft Tube

  • 17DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    2.Turbine types2.2 Turbine selection chart2.2 Turbine selection chart

    Discharge (m3/s)

    N

    e

    t

    h

    e

    a

    d

    (

    m

    )

    18DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    3.Characteristics3.1 Specific speed3.1 Specific speed

    3.1.1 Definition of specific speed Ns3.1.1 Definition of specific speed Ns

    Ns = Nt X (Pt1/2 / H5/4)

    where,

    Ns: Specific speed (m-kW)Nt: Turbine rotational speed (min-1)Pt: Turbine output (kW)H: Net head (m)

    Specific speed is a numerical value expressing the classification of runners (turbine types) correlated by the tree factors of head H, turbine output Pt, and rotational speed Nt. It represents the runner shape and characteristics of turbine.

    LargeSmall Ns

    Change in shape of reaction runner

    Axial flowdiagonal flowRadial flow

    19DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    3.Characteristics3.1 Specific speed3.1 Specific speed

    3.1.2 Specific speed of 3.1.2 Specific speed of CrossflowCrossflow turbineturbine

    Ns = Nt X (Pt1/2 / H5/4)

    where,

    Ns: Specific speed (m-kW)Nt: Turbine rotational speed (min-1)Pt: Turbine output (kW)H: Net head (m)

    Inlet width: bo

    Diameter: D

    1. Turbine output Pt is proportional to discharge Q, i.e. inlet with bo.

    2. Net head H is proportional to diameter D.

    Specific speed Ns of Crossflowturbine represents the shape of runner (bo / D)

    LargeSmall Ns (bo/D)Change in shape of Crossflow runner

    20DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    3.Characteristics3.1 Specific speed3.1 Specific speed

    3.1.3 Applicable range by turbine type3.1.3 Applicable range by turbine type

    Applicable range of Ns is empirically determined by turbine type, which is limited by process limitation (narrow inlet), mechanical strength limitation (high speed machine), and cavitation characteristics.

    NOTE:As for Crossflow turbine, Pt for Ns calculation is defined as follow;

    Pt = Pr / (bo / D) Pr: Turbine output per unit (kW)

    200900Propeller turbine500Tubular turbine

    50350Francis turbine90110Crossflow turbine825Pelton turbine

    Applicable specific speedNs (m-kW)Turbine type

  • 21DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    3.Characteristics3.2 Turbine efficiency3.2 Turbine efficiency

    In the process of converting hydraulic energy (input) into rotational energy (output) by a turbine, hydraulic and mechanical losses occur. Turbine efficiency is defined as the proportion of the output to the input.

    t = {Pt / (9.8 X Q X H)} X 100 (%)

    where, t: Turbine efficienby (%)Pt: Turbine output (kW)9.8QH: Theoretical power (kW) (i.e. Turbine input)Q: Discharge (m3/s)H: Net head (m)

    3.2.1 Definition of turbine efficiency 3.2.1 Definition of turbine efficiency tt

    22DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    3.Characteristics3.2 Turbine efficiency3.2 Turbine efficiency

    At the stage of basic design, the following figures can be used as turbine efficiency by turbine type in order to estimate the turbine output.

    NOTE:As for Crossflow turbine manufactured locally, 40-50% of efficiency can be applied in consideration of fabrication quality of the work shop.

    3.2.2 Turbine efficiency for basic design3.2.2 Turbine efficiency for basic design

    82Propeller turbine

    84Tubular turbine

    84Francis turbine

    77Crossflow turbine

    82Pelton turbine

    Turbine efficiencyt (%)Turbine type

    23DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    4.Basic design4.14.1 Flow chart of basic designFlow chart of basic design

    Design net head: HDesign discharge: Q

    Selection ofapplicable turbine type

    Calculation of applicable maximum specific speed

    Calculation of maximum rotational speed

    Selection of turbine rotational speed

    Recalculation ofspecific speedEstimation of

    turbine output

    Turbine type:Design net head H (m):Design discharge Q (m3/s):Frequency F:Rotational speed Nt:Specific speed Ns:Turbine efficiency t (%):

    refer to Turbine selection chart (see Clause 2.2)

    4.1.1

    4.1.2

    4.1.3

    4.1.4

    4.1.5

    Input

    Output

    24DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    Turbine output Pt is estimated using design head H and discharge Q, which derived from the result of planning and civil designing.

    Pt = 9.8 X Q X H X t (kW)

    Turbine efficiency t listed in Clause 3.2.2 can be applied to the above calculation at the stage of basic design.

    4.1.1 4.1.1 Estimation of turbine outputEstimation of turbine output

    4.Basic design4.14.1 Flow chart of basic designFlow chart of basic design

    ExampleTurbine type: H-shaft FrancisNet head H: 45 mDischarge Q: 2.5 m3/sFrequency F: 50 Hz

    Please estimate the turbine output.Estimated turbine efficiency t: % (see 3.2.2)Estimated turbine output Pt =

    == kW

  • 25DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    Applicable maximum specific speed Nsmax is empirically determined by turbine type, which derived from the following formulas.

    4.1.2 4.1.2 Calculation of applicable maximum specific speedCalculation of applicable maximum specific speed

    4.Basic design4.14.1 Flow chart of basic designFlow chart of basic design

    ExampleTurbine type: H-shaft FrancisNet head H: 45 mDischarge Q: 2.5 m3/sFrequency F: 50 Hz

    Please calculate Nsmax.Applicable max. specific speed Nsmax

    === m-KW

    {(2,000/(H+20))+30}Francis turbine

    {(2,000/(H+20))+50}Propeller turbine

    2,000/(H+16)Tubular turbine

    3,200 X H-2/3H-shft Francis turbine

    650 X H-0.5Crossflow turbine

    85.49 X H-0.213Pelton turbine

    Applicable maximum specific speed NsmaxTurbine type

    26DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    Maximum rotational speed Nmax is derived by applying the calculated Nsmax to the following formula for specific speed.

    Ns = Nt X (Pt1/2 / H5/4) (m-kW)

    Ntmax = Nsmax X (H5/4 / Pt1/2) (min-1)

    4.1.3 4.1.3 Calculation of maximum rotational speedCalculation of maximum rotational speed

    4.Basic design4.14.1 Flow chart of basic designFlow chart of basic design

    ExampleTurbine type: H-shaft FrancisNet head H: 45 mDischarge Q: 2.5 m3/sFrequency F: 50 Hz

    Please calculate Ntmax using estimated Pt.Applicable max. rotational speed Ntmax

    = = = min-1

    Calculated Nsmax in Clause 4.1.2

    27DOEDOE--JICA Rural Electrification Project forJICA Rural Electrification Project forSustainability Improvement of Renewable Energy Development in ViSustainability Improvement of Renewable Energy Development in Village Electrificationllage Electrification

    In case that turbine is directly connected with generator, turbine rotational speed Nt is selected from the following standard rotational speed, which is the maximum value less than Ntmax.

    4.1.4 4.1.4 Selection of turbine rotational speedSelection of turbine rotational speed

    4.Basic design4.14.1 Flow chart of basic designFlow chart of basic design

    ExampleTurbine type: H-shaft FrancisNet head H: 45 mDischarge Q: 2.5 m3/sFrequency F: 50 Hz

    Please select appropriate Nt considering Ntmax (note the rated frequency).

    min-1 of turbine rotational speed is selected because

    500600750

    1,0001,500

    50Hz

    600720900

    1,2001,800

    60Hz

    2420181614

    Nos. of poles

    250300333375429

    50Hz

    40083601030012

    45065144

    60HzNos. of poles*

    * Number of generator rotor