56
MMZG 538 Toyota Production System Rajiv Gupta BITS Pilani January 2014 Session 4

MM ZG538-L5

Embed Size (px)

DESCRIPTION

MM ZG538-L5

Citation preview

  • 5/28/2018 MM ZG538-L5

    1/56

    MMZG 538 Toyota Production

    System

    Rajiv Gupta

    BITS PilaniJanuary 2014

    Session 4

  • 5/28/2018 MM ZG538-L5

    2/56

    Module 1 Recap of Session 4

    Module 2 Value Stream Mapping Example (contd)

    Lean Principles

    Module 3 Value Stream Mapping Example (contd)

    Future State Map

    Module 4 Types of layouts and material flow

    Module 5 Design of machine cells

    Module 6 Summary and wrap up

    2

  • 5/28/2018 MM ZG538-L5

    3/56

    Session 4

    Begin Module 1

    Recap of Session 3

    3

  • 5/28/2018 MM ZG538-L5

    4/56

    Recap

    Material flow is integral to TPS as it affects the lead

    times and inventories on the shop floor

    The principal reasons for intermittent movement of

    materials is batch manufacturing, long set-up timesand an attempt to reduce per unit costs

    Product type layouts were used in mass

    manufacturing for high volume parts. Process

    layouts were meant for low volume job shops.

    4

  • 5/28/2018 MM ZG538-L5

    5/56

    Recap

    Group layouts were developed as a hybrid between

    product and process layouts. They were efficient in

    terms of flow and could be used for low to medium

    volumes of families of products Typically, value is added to parts for less than one

    percent of the time it spends in the plant. However,

    the majority of improvement efforts are focused on

    improving this one percent. There is a largerpotential for benefits by looking at the remaining

    time the part spends in the system.

    5

  • 5/28/2018 MM ZG538-L5

    6/56

    Recap

    Value Stream Mapping is a macro level charting

    technique that highlights the discontinuities in flow in a

    system. It can be used as a tool to significantly improve

    material flow and system throughput

    Value Stream Mapping is applicable to both

    manufacturing, as well as non-manufacturing processes.

    By analyzing the current state maps and applying lean

    principles, we can greatly reduce discontinuities in

    material and information flow.

    6

  • 5/28/2018 MM ZG538-L5

    7/56

    Session 4

    End of module 1

    7

  • 5/28/2018 MM ZG538-L5

    8/56

    Session 4

    Begin Module 2

    Value Stream Mapping Example (contd)

    Lean Principles

    8

  • 5/28/2018 MM ZG538-L5

    9/56

    9

    Lean Principles

    Takt time = Available time per shift/Customer demand rate per shift

    = 27600 sec/460 pcs

    = 60 sec/pc

    i.e., we need to produce at the rate of one part every 60 secs.

    In practice we may set the production rate a little higher to allow

    for changeover time and equipment down time and delays

    1. Avoid over-productionproduce to takt time

  • 5/28/2018 MM ZG538-L5

    10/56

    10

    Lean Principles

    2. Develop Continuous Flow

    One piece at a time

    Little or no inventory between operations

    Operations linked to each other

  • 5/28/2018 MM ZG538-L5

    11/56

    11

    Lean Principles

    3. Where continuous flow is not possible, use supermarket

    pull

    - Used when operations are far apart

    - Used when an operation is done at a supplier- Used when operations are not balanced

    - Used when process is unreliable

    Customer

    ProcessSupplying

    Process

    Supermarket

    KanbanKanban

  • 5/28/2018 MM ZG538-L5

    12/56

    Lean Principles

    Customer Process goes to supermarketand withdraws what it needs

    This withdrawal triggers a kanban, which

    is a signal to the supplier process toreplenish that product

    The supermarket links the customer

    process to the supplier process preventingindependent scheduling of the 2processes

    12

  • 5/28/2018 MM ZG538-L5

    13/56

    13

    Lean Principles

    4. Schedule only one process- It is called the pace maker

    - Linked to the customer order

    - Downstream processes have to be continuous flow

    Process 1 Process 2Process 3 Process 4

    Pace maker

  • 5/28/2018 MM ZG538-L5

    14/56

    14

    Lean Principles

    5. Level Production Mix

    O X

    O X O X O X O X O

  • 5/28/2018 MM ZG538-L5

    15/56

    Lean Principles

    6. Create Initial Pull

    - At the pacemaker

    - Small consistent amount of work

    - Could be a container or a bin

    15

  • 5/28/2018 MM ZG538-L5

    16/56

    Initial Pull

    16

    Decide on a pitch which represents consistent incremental work.

    Let us say that the takt time = 30 seconds and the pack size is 20

    pieces, then the pitch will be 30 seconds x 20 pieces = 10 minutes

    So your production schedule will give the pacemaker instruction to

    produce one pack quantity every 10 minutes.

    Also every 10 minutes, you will take away one finished pitch quantity

  • 5/28/2018 MM ZG538-L5

    17/56

    17

    7:00 am 7:10 am 7:20 am 7:30 am 7:40 am

    O O

    X

    OO

    X

    Load Leveling Box

  • 5/28/2018 MM ZG538-L5

    18/56

    Session 4

    End of module 2

    18

  • 5/28/2018 MM ZG538-L5

    19/56

    Session 4

    Begin Module 3

    Value Stream Mapping Example (contd)

    Future State Map

    19

  • 5/28/2018 MM ZG538-L5

    20/56

    Key Questions For The Future

    State1. What is the takt time?

    2. Will you build to a finished goods supermarket from

    which the customer pulls, or directly to shipping?

    3. Where can you use continuous flow processing?4. Where will you need to use supermarket pull systems?

    5. Which will be the pacemaker process?

    6. How will you level the production mix at the pacemaker

    process?7. What increment of work will you consistently release to

    the pacemaker process?

    8. What process improvements will be necessary?

    20

  • 5/28/2018 MM ZG538-L5

    21/56

    Question 1: What will be the takt time?

    Available time per shift = 28,800 secs

    1200 secs (for 2 10-minute breaks) =

    27,600 secs

    Customer demand per shift = 460 pieces

    Takt time = 27,600/460 = 60 secs

    21

  • 5/28/2018 MM ZG538-L5

    22/56

    Question 2: Should the company build to a

    finished goods supermarket or directly to

    shipping?

    22

  • 5/28/2018 MM ZG538-L5

    23/56

    23

    Future State Map

    Dispatch

    L

    R

    Customer

    Demand

    Weld+Assy

    First Step- Build to supermarket

    FutureDirect to shipping

  • 5/28/2018 MM ZG538-L5

    24/56

    Question 3: Where can the company

    introduce continuous flow?

    24

  • 5/28/2018 MM ZG538-L5

    25/56

    25

    Future State Map

    Blank Weld Weld Assy Assy

    60

    1 s

    39 s

    46 s

    62 s

    40 s

    Operators reqd = 187/60

    = 3.12

    3 or 4

    Apply Kaizen to reduce

    Total work content to 168 sec

    Operators reqd = 168/60

    = 2.8

    Use 3 operators

  • 5/28/2018 MM ZG538-L5

    26/56

    26

    Future State Map

    WeldWeld

    Assy

    Assy

    Improve welder setup time

    Improve welder uptime

    Weldchangeover

    Welderuptime

    Work content

    < 168 secs

  • 5/28/2018 MM ZG538-L5

    27/56

    27

    Future State Map

    C/T = 56 sec

    C/O = 0

    Up =100%

    Blanking

    Dispatch

    L

    R

    Customer

    Demand

    Weld+Assy

  • 5/28/2018 MM ZG538-L5

    28/56

    Question 4: Where will supermarket pull

    be used?

    28

  • 5/28/2018 MM ZG538-L5

    29/56

    29

    60

    L

    R

    Stamping

    Batch

    LH = 600

    RH = 320

    1.5 days Weld + Assembly

    C/T = 56 sec

    C/O = 0

    Up =100%

  • 5/28/2018 MM ZG538-L5

    30/56

    Question 5: Which single point should

    receive the production schedule

    (pacemaker)?

    Question 6: How should production be

    leveled at the pacemaker?

    Every part every day

    Every part every pitch

    30

  • 5/28/2018 MM ZG538-L5

    31/56

    Question 7: What consistent amount of workshould be released to the pacemaker

    process?

    Question 8: What process improvements arenecessary?

    Elimination of changeover time in welding

    Improvement of uptime of the second weldingprocess

    Reduction of waste in assembly cell to bring total

    work content to 168 seconds

    Reduction of setup time at the stamping press 31

  • 5/28/2018 MM ZG538-L5

    32/56

    32

    Stage Coils Blanks Weld/

    Assy

    WIP

    FG Prod

    LT

    Inv

    Turns

    Before 5d 7.6 d 6.5 d 4.5 d 23.6 d 10

    After 2 d 1.5 d 0 4.5 d 8 d 30

  • 5/28/2018 MM ZG538-L5

    33/56

    Session 4

    End of module 3

    33

  • 5/28/2018 MM ZG538-L5

    34/56

    Session 4

    Begin Module 4

    Layout types and material flow

    34

  • 5/28/2018 MM ZG538-L5

    35/56

    Lathe

    Lathe

    Lathe

    Drill

    Drill

    Drill

    Milling

    Milling

    Milling

    Process Layout

    Lathe Drill Lathe

    Drill Milling Grind

    Lathe Grind

    Product Layout 35

  • 5/28/2018 MM ZG538-L5

    36/56

    Product Layouts

    Product layouts were designed to maximize flow,

    but for high volume products

    The machines were special purpose and

    automation was hard automation, i.e, the systemwas designed for a specific part and volume

    The system was inflexible

    It was easy to supervise

    Scheduling was relatively easy

    Lead times were generally short

    WIP was low36

  • 5/28/2018 MM ZG538-L5

    37/56

    Process Layouts

    Process layouts were used for low volume

    products

    Machines were general purpose and parts

    requiring processing could be produced on anymachine of a particular type, e.g., lathe, etc.

    Supervision and scheduling were more difficult

    Lead times were long

    WIP was high

    37

  • 5/28/2018 MM ZG538-L5

    38/56

    Lathe Milling

    Lathe Drill

    Lathe Drill

    Milling

    Milling Milling Drill

    Grind Grind

    Group 1

    Group 2

    Group 3

    Group Layouts

    38

  • 5/28/2018 MM ZG538-L5

    39/56

    Group Technology

    Attributed to Mitofanov, a machinist, who was

    looking for similarities in part shapes

    Group technology was the forerunner to

    machine cells Initial applications were in coding and

    classification of parts for reducing redundant

    effort in part design

    John Burbidge devised Production Flow Analysis

    to group parts that needed similar routings and

    the machines into cells

    39

  • 5/28/2018 MM ZG538-L5

    40/56

    Machine Cells

    Machine Cells A group of machines used to complete a sequence of

    operations on a family of parts

    The parts in a family does not have high volumes, but

    the family has sufficient volume to justify thededication of the machine cell

    By restricting the movement of each part to a smallarea, material handling and control is easier,inventories are low and therefore lead times short.This gives the machine cells the efficiency of productlayouts

    40

  • 5/28/2018 MM ZG538-L5

    41/56

    Machine Cells

    Machine Cells Unlike product layouts, group layouts/machine cells

    have the ability to accommodate a family of parts

    Due to this, when product mix and volumes change,

    the machine cell is able to absorb the fluctuation. Thismakes the group layout/machine cell flexible like theprocess layouts

    Machine cells are easy to supervise and schedule

    WIP and lead times tend to be low

    41

  • 5/28/2018 MM ZG538-L5

    42/56

    Session 3

    End of module 4

    42

  • 5/28/2018 MM ZG538-L5

    43/56

    Session 3

    Begin Module 5

    Design of machine cells

    43

  • 5/28/2018 MM ZG538-L5

    44/56

    Machine Cells

    Machine Cells

    Machines are arranged typically in a U-shaped layout

    Each operator is assigned multiple machines,not of the same type

    Input and output stations tend to be near eachother next to a transportation aisle

    Components are delivered either to the firststation and moved with the product, ordelivered by a water spider to each station

    44

  • 5/28/2018 MM ZG538-L5

    45/56

    Machine Cells

    Machine Cells

    Generally the machining capacity is morethan required.

    As production volume changes, adjustment ismade to the staffing of the machine cell. Thismakes the machine cells flexible in terms ofproduct mix and volumes

    By making a group of workers responsible forthe complete production of a part, there is agreater sense of satisfaction for the workers

    45

  • 5/28/2018 MM ZG538-L5

    46/56

    Machine Cells

    Machine Cells

    Due to better communication within the cell, ifthere is a quality problem, it is detected

    quickly and adjustments made to preventfurther defectives from being produced

    46

  • 5/28/2018 MM ZG538-L5

    47/56

    Machine Cells

    Input

    Output

    Mach 1Mach 2

    Mach 3

    Mach 4 Mach 5

    Example of a machine cell with 2 operators

    47

  • 5/28/2018 MM ZG538-L5

    48/56

    Machine CellsMachine Cells

    Input

    Output

    Mach 1Mach 2

    Mach 3

    Mach 4 Mach 5

    Example of a machine cell with 1 operator

    48

  • 5/28/2018 MM ZG538-L5

    49/56

    49

  • 5/28/2018 MM ZG538-L5

    50/56

    50

  • 5/28/2018 MM ZG538-L5

    51/56

    Machine Cell Design

    The number of operators and the assignment of

    machines to the operators depends on the manual work

    content, the walking times and the takt time

    Takt time determines the pace at which the cell should

    complete one piece

    The sum of the manual times and the walking times

    should be less than or equal to the takt time

    When more than one operators are used, the largest

    sum of the manual times plus the walk times should beless than or equal to the takt time

    51

  • 5/28/2018 MM ZG538-L5

    52/56

    Session 4

    End of module 5

    52

  • 5/28/2018 MM ZG538-L5

    53/56

    Session 4

    Begin Module 6

    Summary and wrap up

    53

  • 5/28/2018 MM ZG538-L5

    54/56

    Summary

    Lean principles are used to analyze Current State

    VSMs

    When creating Future State maps, the attempt is

    reduce, or eliminate discontinuities in the flow

    The VSM will indicate areas where Point Kaizen is

    needed in order to achieve smoother flow

    Machine cells are a hybrid between product and

    process layouts Machine cells have the advantages of efficiency of

    product layouts and flexibility of process layouts

    54

  • 5/28/2018 MM ZG538-L5

    55/56

    Summary

    Machine cells require multi-skilling of operators

    Due to the improved communication in of

    machine cells, quality of products is improved

    Due to the completion of all or most productionof a part within a cell, there is greater worker

    satisfaction

    In the design of machine cells, we need to

    establish the number of workers based on takt

    time and the manual time required

    As the production volume changes, the number

    of workers can be adjusted55

  • 5/28/2018 MM ZG538-L5

    56/56

    End Module 6

    Summary and wrap up

    56