Project name: BEJO VIET NAM PRODUCTION FARM Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LT, TNH LÂM ĐỒNG MONTHLY PROGRESS REPORT No.10 DECEMBER 2014 MAIN CONTRACTOR: TAN VIET TIN CONSTRUCTION CO. LTD CONTRACT PARTICULAR: 1. Site possession : 07March, 2014 2. Completion date : 25 September, 2014 3. Contract period : 203 Days ( 6.5 months ) Prepared by: TAN VIET TIN CONSTRUCTION CO. LTD Verified by Bejo’s Supervise Name: Le Nam Trung Name: Date: December, 2014 Date

MONTHLY PROGRESS REPORT No.10 – DECEMBER 2014mamibo.com/bejo/reports/M_December_2014.pdf · 51 Plastering work to internal side 20 days Sat 6/21/14 Thu 7/10/14100% 47 52 Plastering

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG

MONTHLY PROGRESS REPORT No.10 – DECEMBER 2014

MAIN CONTRACTOR:

TAN VIET TIN CONSTRUCTION CO. LTD

CONTRACT PARTICULAR:

1. Site possession : 07March, 2014 2. Completion date : 25 September, 20143. Contract period : 203 Days ( 6.5 months )

Prepared by: TAN VIET TIN CONSTRUCTION CO. LTD

Verified by Bejo’s Supervise

Name: Le Nam Trung Name: Date: December, 2014 Date

TABLE OF CONTENT Num Page Page

1 PROJECT INTRODUCTION 0 6

2 PROJECT EXECUTIVE SUMMARY 2 8

3 PLANNING REVIEW 4 12

4 PROGRESS WORKS PROGRAMME 2 14

5 WEATHER 3 17

6 MANPOWER RECORD 2 19

7 PLANT & MACHINERY RECORD 2 21

8SUMMARY OF VO 2 23

SUBMITTALS 1 24

A. C&S - SHOPDRAWING REGISTER 1 25

B. C&S - APPROVED SAMPLE/TECHNICAL DATA REGISTER 1 26

A. M&E - SHOPDRAWING REGISTER 2 28

B. M&E - APPROVED SAMPLE/TECHNICAL DATA REGISTER 2 30

10 HSE REPORT 2 32

TABLE OF CONTENT

9

1. PROJECT INTRODUCTION

P.3

PROJECT BRIEF:

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG

Owner: BEJO VIET NAM PRODUCTION FARM 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG TEL: 0633.520.337 Project management: VIETNAM PROJECT CONSULTANTS Co. LTD

Design Consultant: THIEN NAM DESIGN CONSUTANCY JSC. 12 YERSIN P10 DA LAT – LAM DONG TEL: 0633577646 Main Contractor: Tan Viet Tin Construction Co., Ltd 456 Nguyen van Luong St, Ward 12, Dist 6, Ho Chi Minh City, Vietnam Email: [email protected] Tel: +84-8.37511384 - +84-8.38756934 Fax: +84-8.37511383 Tax code: 0302227857

THE SITE ORGANIZATION CHARTPROJECT: MAIN CONTRACT PACKAGE FOR PROPOSED CONSTRUCTION AND COMPLETION FOR

BEJO VIETNAM PRODUCTION FARM

SITE

OFFICE

TVT Co.,LtdTVT Co., Ltd

BOARD OF DIRECTORS

TECHNICAL DEPT PURCHASING DEPT

SuperintendentTran Minh Ky

Võ Thanh HoaiSecurity Company

FINANCIAL DEPTADMIN DEPT

Project ManagerPham The Tai

Mobile: 0903 740 342Email: [email protected]

Safety Officer

PurchasingDo Thanh Hung

Site Engineer OfficeNguyễn Đức Đường

Mobile: 098 537 57 68Email: [email protected]

Site Engineer M&E Bui Van Tuoi

Mobile : 0982592943

QA & QCTran Dinh Tan

Mobile: 0903045628Email: [email protected]

Finishing Work

CeilingWork

ElectricSystemWork

Fire ServicesSystemWork

PlumbingSystemWork

ELVSystemWork

MasonryWork

Painting worksWood works

InfrastructureWork

Store keeperĐỗ Thanh Hưng

SurveyorVi Thanh Tien

Site ManagerLê Nam Trung

Mobile: 0903743788Email: [email protected]

Site EngineerĐỗ Thanh Hòa

Mobile: 0908 5559Email: [email protected]

2. PROJECT EXECUTIVE SUMMARY

P.8

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG  

Executive summary: 

Contract particular: 

Commencement date:  07 March, 2014 

  Completion date :         25 September, 2014 

  Contract period    :        203 days (6.5 Months) 

 

Revise Contract particular: 

 

  Commencement date:  07 March, 2014 

  Completion date :         16 January, 2015 

  Contract period    :        343 days (10.7 Months) 

  Elapsed                 :         327 days ( 10.2 months) 

  Remaining            :         16 days ( 0.5  month)  

 

3. PLANNING REVIEW

P.10

ID Task Name Duration Start Finish % Complete Predecessors

1 BEJO VIETNAM PRODUCTION FARM 343 days? Sat 2/8/14 Fri 1/16/15 99%

2 Contract Award 1 day Sat 2/8/14 Sat 2/8/14 100%3 Site hand over to TVT 1 day Sat 2/8/14 Sat 2/8/14 100%4 Site Mobilisation 12 days Mon 2/10/14 Fri 2/21/14 100% 35 Site Seting Out 3 days Wed 2/12/14 Fri 2/14/14 100% 4SS+2 days6 Site Grading & Leveling 3 days Sat 2/15/14 Mon 2/17/14 100% 57 OFFICE BUILDING 311 days? Sat 2/8/14 Mon 12/15/14 99%

8 TVT submit shop drawing for Foundation 0 days Sat 2/8/14 Sat 2/8/14 100%9 Foundation shop drawing get approval 3 days Sat 2/8/14 Mon 2/10/14 100% 810 Excavation for footings 4 days Mon 3/17/14 Thu 3/20/14 100% 6FS+27 days,911 Compact foundation 4 days Tue 3/18/14 Fri 3/21/14 100% 10SS+1 day12 Termite treatment to foundation 3 days Wed 3/19/14 Fri 3/21/14 100% 11SS+1 day13 Blinding concrete 4 days Thu 3/20/14 Sun 3/23/14 100% 12SS+1 day14 Concrete footings 7 days Sat 3/22/14 Fri 3/28/14 100% 13SS+2 days15 Concrete stump 7 days Mon 3/24/14 Sun 3/30/14 100% 14SS+2 days16 Backfiling work to foundation 7 days Thu 3/27/14 Wed 4/2/14 100% 15SS+3 days17 Backfiling work to raise up ground level 5 days Thu 4/3/14 Mon 4/7/14 100% 1618 Termite treatment to ground floor 1 day Tue 4/8/14 Tue 4/8/14 100% 1719 Plumbing work to ground floor 3 days Wed 4/9/14 Fri 4/11/14 100% 1820 Formwork to beam of ground floor slab 5 days Sat 4/12/14 Wed 4/16/14 100% 17,1921 PVC foil to ground floor slab 1 day Thu 4/17/14 Thu 4/17/14 100% 2022 Reinforcement steel to ground floor 4 days Fri 4/18/14 Mon 4/21/14 100% 2123 Electrical conduit to ground floor 10 days Sun 4/20/14 Tue 4/29/14 100% 22SS+2 days24 Concrete to ground floor 1 day Wed 4/30/14 Wed 4/30/14 100% 2325 Curing work to ground floor 7 days Thu 5/1/14 Wed 5/7/14 100% 2426 Reinforcement steel to column up to +3.600 m 6 days Thu 5/1/14 Tue 5/6/14 100% 2427 Formwork to column up to +3.600 m 6 days Fri 5/2/14 Wed 5/7/14 100% 26SS+1 day28 Concrete column to level (+3.600) 6 days Sat 5/3/14 Thu 5/8/14 100% 27SS+1 day29 Scafolding , formwork to floor +3.600 m 7 days Fri 5/9/14 Thu 5/15/14 100% 2830 Reinforcement steel to floor at +3.600 m 5 days Fri 5/16/14 Tue 5/20/14 100% 2931 Electrical conduit to floor +3.600 m 8 days Wed 5/21/14 Wed 5/28/14 100% 3032 Concrete to floor slab at level (+3.600) 1 day Thu 5/29/14 Thu 5/29/14 100% 3133 Curing work to floor at level +3.600 m 7 days Fri 5/30/14 Thu 6/5/14 100% 3234 Reinforcement steel to column up to +6.800 m 5 days Fri 5/30/14 Tue 6/3/14 100% 3235 Formwork to column up to +6.800 m 5 days Sat 5/31/14 Wed 6/4/14 100% 34SS+1 day36 Concrete column to level +6.800 m 5 days Sun 6/1/14 Thu 6/5/14 100% 35SS+1 day37 Floor slab level at +6.800 m 6 days Fri 6/6/14 Wed 6/11/14 100% 3638 Ring beam and roof beam 10 days Thu 6/12/14 Sat 6/21/14 100% 3739 Concrete staircase 15 days Fri 6/6/14 Fri 6/20/14 100% 3340 Steel structure works 120 days Mon 3/24/14 Mon 7/21/14 100%

47 Brickwork on ground floor 15 days Fri 6/6/14 Fri 6/20/14 100% 28,3348 Brickwork on First floor 20 days Sat 6/21/14 Thu 7/10/14 100% 4749 Lintel beam for brick wall 15 days Thu 6/26/14 Thu 7/10/14 100% 48SS+5 days50 Electrical conduit to floor +3.600 m 15 days Thu 6/26/14 Thu 7/10/14 100% 48SS+5 days51 Plastering work to internal side 20 days Sat 6/21/14 Thu 7/10/14 100% 4752 Plastering work to external side 20 days Fri 7/11/14 Wed 7/30/14 100% 4853 Finishing works 158 days? Fri 7/11/14 Mon 12/15/14 99%

54 Ceiling work on Ground floor & First floor 15 days Fri 7/11/14 Fri 7/25/14 100% 5155 Wall tiling work 15 days Fri 7/11/14 Fri 7/25/14 95% 5156 Floor tiling work 15 days Sat 7/26/14 Sat 8/9/14 100% 5457 Door & Window 62 days Wed 10/15/14 Mon 12/15/14 99% 56SS+10 days

58 D6(2100x700)mm, Melamine door changed to Wooden door (2100x800)mm

10 days Wed 10/15/14 Fri 10/24/14 100%

59 Approval by Hafela hardware for quotation (Asssuming) 5 days Fri 11/28/14 Tue 12/2/14 100%60 Order & Delivery by Hafele hardware on site 10 days Wed 12/3/14 Fri 12/12/14 100% 5961 Installation by hardware 3 days Sat 12/13/14 Mon 12/15/14 99% 6062 Wooden work 31 days? Wed 10/29/14 Fri 11/28/14 100% 57SS+10 days

63 Pascal to change natural teak wood to MDF veneer wood 1 day? Wed 10/29/14 Wed 10/29/14 100%64 Order & Delivery for material on site 15 days Thu 10/30/14 Thu 11/13/14 100% 6365 Installation of wooden wall 15 days Fri 11/14/14 Fri 11/28/14 100% 6466 Glazing work to partition 17 days Thu 11/20/14 Sat 12/6/14 100% 64

67 Submition the Translucent film sample for approval (Assuming)

10 days Thu 11/20/14 Sat 11/29/14 100%

68 Order & delivery for material on site 7 days Sun 11/30/14 Sat 12/6/14 100% 6769 Painting work to ceiling & wall 40 days Mon 11/3/14 Fri 12/12/14 100% 62SS+5 days70 Painting work to external side 20 days Thu 7/31/14 Tue 8/19/14 100% 5271 Resin for floor 16 days Sun 11/30/14 Mon 12/15/14 100%

72 Submition the sample for approval (Assuming) 5 days Sun 11/30/14 Thu 12/4/14 100%73 Order & delivery for material on site 5 days Fri 12/5/14 Tue 12/9/14 100% 7274 Making for first fllor 3 days Wed 12/10/14 Fri 12/12/14 100% 7375 Making for ground floor 3 days Sat 12/13/14 Mon 12/15/14 100% 7476 Electrical works 153 days Fri 7/11/14 Wed 12/10/14 100%

77 Cabling the power cable 20 days Fri 7/11/14 Wed 7/30/14 100% 54SS78 Installing lighting equipment & socket 30 days Thu 7/31/14 Fri 8/29/14 100% 7779 Thorn approval 1 day Fri 9/26/14 Fri 9/26/14 100%80 Delivery Thorn lighting to the site 70 days Sat 9/27/14 Fri 12/5/14 100% 7981 Installing the Thorn lighting 5 days Sat 12/6/14 Wed 12/10/14 100% 8082 Installing distribution board 12 days Sat 8/30/14 Wed 9/10/14 100% 7883 Installing earthing 17 days Thu 7/31/14 Sat 8/16/14 100% 78SS84 Testing the Electrical works 7 days Thu 9/11/14 Wed 9/17/14 100% 83,8285 ELV works 70 days Fri 7/11/14 Thu 9/18/14 100%

86 Cabling the ELV Cable (Tel / Data / CCTV) 25 days Fri 7/11/14 Mon 8/4/14 100% 54SS87 Installing the ELV Equipment (Tel / Data / CCTV) 38 days Tue 8/5/14 Thu 9/11/14 100% 8688 Testing the ELV works 7 days Fri 9/12/14 Thu 9/18/14 100% 8789 A/C System 135 days Fri 7/11/14 Sat 11/22/14 100%

90 Installing the power cable for A/C Split unit 20 days Fri 7/11/14 Wed 7/30/14 100% 54SS91 Installing the A/C Spilit unit 40 days Thu 7/31/14 Mon 9/8/14 100% 9092 Testing the A/C system 7 days Tue 9/9/14 Mon 9/15/14 100% 9193 Other finishing works 15 days Sat 11/8/14 Sat 11/22/14 100% 69SS+5 days94 Epoxy resin to floor 10 days Sun 11/23/14 Tue 12/2/14 100% 9395 Cleaning work 5 days Wed 12/3/14 Sun 12/7/14 100% 9496 Completion work 1 day Mon 12/8/14 Mon 12/8/14 100% 9597 GREEN HOUSE SHED 304 days Sat 2/8/14 Mon 12/8/14 100%

98 TVT submit shop drawing for Foundation 0 days Sat 2/8/14 Sat 2/8/14 100%99 Foundation shop drawing get approval 3 days Sat 2/8/14 Mon 2/10/14 100% 98

100 Excavation for footings 6 days Mon 3/17/14 Sat 3/22/14 100% 99FS+27 days101 Compact foundation 6 days Tue 3/18/14 Sun 3/23/14 100% 100SS+1 day102 Termite treatment to foundation 6 days Wed 3/19/14 Mon 3/24/14 100% 101SS+1 day103 Blinding concrete 6 days Thu 3/20/14 Tue 3/25/14 100% 102SS+1 day104 Concrete footings 9 days Sat 3/22/14 Sun 3/30/14 100% 103SS+2 days105 Concrete stump 10 days Mon 3/24/14 Wed 4/2/14 100% 104SS+2 days106 Backfiling work to foundation 10 days Thu 3/27/14 Sat 4/5/14 100% 105SS+3 days107 Backfiling work to raise up ground level 6 days Sun 4/6/14 Fri 4/11/14 100% 106108 Termite treatment to ground floor 1 day Sat 4/12/14 Sat 4/12/14 100% 107109 Plumbing work to ground floor 3 days Sun 4/13/14 Tue 4/15/14 100% 108110 Formwork to beam of ground floor slab 7 days Wed 4/16/14 Tue 4/22/14 100% 107,109111 PVC foil to ground floor slab 1 day Wed 4/23/14 Wed 4/23/14 100% 110112 Reinforcement steel to ground floor 6 days Thu 4/24/14 Tue 4/29/14 100% 111113 Electrical conduit to ground floor 5 days Sat 4/26/14 Wed 4/30/14 100% 112SS+2 days114 Concrete to ground floor 1 day Thu 5/1/14 Thu 5/1/14 100% 113115 Curing work to ground floor 7 days Fri 5/2/14 Thu 5/8/14 100% 114116 Reinforcement steel to column up to +3.600 m 10 days Fri 5/2/14 Sun 5/11/14 100% 114117 Formwork to column up to +3.600 m 10 days Sat 5/3/14 Mon 5/12/14 100% 116SS+1 day118 Concrete column to level (+3.600) 6 days Sun 5/4/14 Fri 5/9/14 100% 117SS+1 day119 Scafolding , formwork to floor +3.600 m 9 days Sat 5/10/14 Sun 5/18/14 100% 118120 Reinforcement steel to floor at +3.600 m 3 days Mon 5/19/14 Wed 5/21/14 100% 119121 Electrical conduit to floor +3.600 m 3 days Thu 5/22/14 Sat 5/24/14 100% 120122 Concrete to floor slab at level (+3.600) 1 day Sun 5/25/14 Sun 5/25/14 100% 121123 Curing work to floor at level +3.600 m 7 days Mon 5/26/14 Sun 6/1/14 100% 122124 Reinforcement steel to column up to +6.900 m 9 days Mon 5/26/14 Tue 6/3/14 100% 122125 Formwork to column up to +6.900 m 9 days Tue 5/27/14 Wed 6/4/14 100% 124SS+1 day126 Concrete column to level +6.900 m 9 days Wed 5/28/14 Thu 6/5/14 100% 125SS+1 day127 Ring beam and roof beam 12 days Fri 6/6/14 Tue 6/17/14 100% 126128 Concrete staircase 15 days Mon 6/2/14 Mon 6/16/14 100% 123129 Steel structure works 118 days Mon 3/24/14 Sat 7/19/14 100%

130 TVT submit shop drawing for Steel structure 10 days Mon 3/24/14 Wed 4/2/14 100%131 Steel structure get approval 5 days Thu 4/3/14 Mon 4/7/14 100% 130132 Manufacturing in work shop 30 days Mon 5/5/14 Tue 6/3/14 100% 131FS+27 day133 Delivery steel structure to site 5 days Wed 6/4/14 Sun 6/8/14 100% 132134 Erection on site 15 days Wed 6/18/14 Wed 7/2/14 100% 127,133135 Install gutter 5 days Thu 7/3/14 Mon 7/7/14 100% 134136 Install Roofing sheet 12 days Tue 7/8/14 Sat 7/19/14 100% 135137 Brickwork on ground floor 15 days Mon 6/2/14 Mon 6/16/14 100% 118,123138 Brickwork on First floor 20 days Tue 6/17/14 Sun 7/6/14 100% 137139 Lintel beam for brick wall 15 days Sun 6/22/14 Sun 7/6/14 100% 138SS+5 days140 Electrical conduit to floor +3.600 m 15 days Sun 6/22/14 Sun 7/6/14 100% 138SS+5 days

2/8

2/8

10/15 10/24

11/28 12/2

12/3 12/12

12/13 12/15

10/29 10/29

10/30 11/13

11/14 11/28

11/20 11/29

11/30 12/6

NA 12/12

11/30 12/4

12/5 12/9

12/10 12/12

12/13 12/15

9/26 9/26

9/27 12/5

12/6 12/10

12/8

4 7 10 13 16 19 22 25 28 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 201

Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014

Task

Critical Task

Milestone

Summary

Rolled Up Task

Rolled Up Critical Task

Rolled Up Milestone

Rolled Up Progress

Split

External Tasks

Project Summary

Group By Summary

Inactive Task

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Critical

Critical Split

Progress

Deadline

Manual Progress

THE PROPOSED CONSTRUCTION PLANNING

Page 1

Project: Bejo_Planning3.12.2014

ID Task Name Duration Start Finish % Complete Predecessors

141 Plastering work to internal side 20 days Tue 6/17/14 Sun 7/6/14 100% 137142 Plastering work to external side 20 days Mon 7/7/14 Sat 7/26/14 100% 138143 Concrete slab 7-13- A-G 32 days Tue 6/17/14 Fri 7/18/14 100%

144 Leveling work 9 days Tue 6/17/14 Wed 6/25/14 100% 137145 Crushed stone layer , 200 mm thick 9 days Thu 6/26/14 Fri 7/4/14 100% 144146 PVC foil to ground floor slab 1 day Sat 7/5/14 Sat 7/5/14 100% 145147 Reinforcement steel to floor 5 days Sun 7/6/14 Thu 7/10/14 100% 146148 Concrete floor slab with trowel finish 1 day Fri 7/11/14 Fri 7/11/14 100% 147149 Curing work to floor 7 days Sat 7/12/14 Fri 7/18/14 100% 148150 Finishing works 155 days Mon 7/7/14 Mon 12/8/14 100%

151 External staircase 10 days Tue 11/25/14 Thu 12/4/14 100% 142

152 Installation for roof sheet 10 days Tue 11/25/14 Thu 12/4/14 100%153 Internal staircase - Finishing work 14 days Tue 11/25/14 Mon 12/8/14 100% 149

154 Additional the brick wall under staircase 7 days Tue 11/25/14 Mon 12/1/14 100%155 Approval shop drawing for ladder to roof (Asssuming) 4 days Fri 11/28/14 Mon 12/1/14 100%156 Fabricate & installation 7 days Tue 12/2/14 Mon 12/8/14 100% 155157 Ceiling work for WC area 8 days Mon 7/7/14 Mon 7/14/14 100% 141158 Wall tiling work 15 days Tue 7/15/14 Tue 7/29/14 100% 141,157159 Floor tiling work 15 days Wed 7/30/14 Wed 8/13/14 100% 158160 Door & Window 65 days Sun 10/5/14 Mon 12/8/14 100% 159

161 Move the tempered glass door from Guest house 3 days Sun 10/5/14 Tue 10/7/14 100%162 Installation new steel door D4 in electrical room 9 days Wed 10/8/14 Thu 10/16/14 100% 161163 Installation new steel door in under staircase 4 days Fri 12/5/14 Mon 12/8/14 100% 152164 Insulation wall to Training , Lab room' 15 days Mon 7/21/14 Mon 8/4/14 100% 141165 Ceiling work for training & Lab area 8 days Tue 8/5/14 Tue 8/12/14 100% 164166 Partition wall to Locker room 10 days Thu 8/14/14 Sat 8/23/14 100% 159167 SS Washing sinks 15 days Thu 8/14/14 Thu 8/28/14 100% 159168 Mirror to washing sinks 8 days Fri 8/29/14 Fri 9/5/14 100% 167169 Painting work 14 days Sat 9/6/14 Fri 9/19/14 100% 142,168170 Partition to WC area 15 days Thu 8/14/14 Thu 8/28/14 100% 159171 Electrical works 80 days Mon 7/7/14 Wed 9/24/14 100%

172 Cabling the power cable 20 days Mon 7/7/14 Sat 7/26/14 100% 157SS173 Installing lighting equipment & socket 30 days Sun 7/27/14 Mon 8/25/14 100% 172174 Installing distribution board 15 days Tue 8/26/14 Tue 9/9/14 100% 173175 Installing the Lightning protection & earthing 8 days Wed 9/10/14 Wed 9/17/14 100% 174176 Testing the Electrical works 7 days Thu 9/18/14 Wed 9/24/14 100% 175177 ELV works 72 days Mon 7/7/14 Tue 9/16/14 100%

178 Cabling the ELV Cable (Tel / Data / CCTV) 30 days Mon 7/7/14 Tue 8/5/14 100% 157SS179 Installing the ELV Equipment (Tel / Data / CCTV) 35 days Wed 8/6/14 Tue 9/9/14 100% 178180 Testing the ELV works 7 days Wed 9/10/14 Tue 9/16/14 100% 179181 Other finishing works 4 days Sat 9/20/14 Tue 9/23/14 100% 169,180182 Cleaning work 2 days Wed 9/24/14 Thu 9/25/14 100% 181183 Completion work 0 days Thu 12/4/14 Thu 12/4/14 100% 182,151184 GUEST HOUSE BUILDING 302 days Mon 2/17/14 Mon 12/15/14 100%

185 TVT submit shop drawing for Foundation 0 days Mon 2/17/14 Mon 2/17/14 100%186 Foundation shop drawing get approval 3 days Mon 2/24/14 Wed 2/26/14 100% 185187 Excavation for footings 4 days Wed 3/26/14 Sat 3/29/14 100% 186FS+27 day188 Compact foundation 4 days Thu 3/27/14 Sun 3/30/14 100% 187SS+1 day189 Termite treatment to foundation 3 days Fri 3/28/14 Sun 3/30/14 100% 188SS+1 day190 Blinding concrete 4 days Sat 3/29/14 Tue 4/1/14 100% 189SS+1 day191 Concrete footings 7 days Mon 3/31/14 Sun 4/6/14 100% 190SS+2 days192 Concrete stump 7 days Wed 4/2/14 Tue 4/8/14 100% 191SS+2 days193 Backfiling work to foundation 7 days Sat 4/5/14 Fri 4/11/14 100% 192SS+3 days194 Backfiling work to raise up ground level 5 days Sat 4/12/14 Wed 4/16/14 100% 193195 Termite treatment to ground floor 1 day Thu 4/17/14 Thu 4/17/14 100% 194196 Plumbing work to ground floor 3 days Fri 4/18/14 Sun 4/20/14 100% 195197 Formwork to beam of ground floor slab 5 days Mon 4/21/14 Fri 4/25/14 100% 194,196198 PVC foil to ground floor slab 1 day Sat 4/26/14 Sat 4/26/14 100% 197199 Reinforcement steel to ground floor 4 days Sun 4/27/14 Wed 4/30/14 100% 198200 Electrical conduit to ground floor 3 days Tue 4/29/14 Thu 5/1/14 100% 199SS+2 days201 Concrete to ground floor 1 day Fri 5/2/14 Fri 5/2/14 100% 200202 Curing work to ground floor 7 days Sat 5/3/14 Fri 5/9/14 100% 201203 Reinforcement steel to column up to +3.600 m 6 days Sat 5/3/14 Thu 5/8/14 100% 201204 Formwork to column up to +3.600 m 6 days Sun 5/4/14 Fri 5/9/14 100% 203SS+1 day205 Concrete column to level (+3.600) 6 days Mon 5/5/14 Sat 5/10/14 100% 204SS+1 day206 Scafolding , formwork to floor +3.600 m 7 days Sun 5/11/14 Sat 5/17/14 100% 205207 Reinforcement steel to floor at +3.600 m 5 days Sun 5/18/14 Thu 5/22/14 100% 206208 Electrical conduit to floor +3.600 m 3 days Fri 5/23/14 Sun 5/25/14 100% 207209 Concrete to floor slab at level (+3.600) 1 day Mon 5/26/14 Mon 5/26/14 100% 208210 Curing work to floor at level +3.600 m 7 days Tue 5/27/14 Mon 6/2/14 100% 209211 Reinforcement steel to column up to +6.800 m 5 days Tue 5/27/14 Sat 5/31/14 100% 209212 Formwork to column up to +6.800 m 5 days Wed 5/28/14 Sun 6/1/14 100% 211SS+1 day213 Concrete column to level +6.800 m 5 days Thu 5/29/14 Mon 6/2/14 100% 212SS+1 day214 Ring beam and roof beam 10 days Tue 6/3/14 Thu 6/12/14 100% 213215 Concrete staircase 15 days Tue 6/3/14 Tue 6/17/14 100% 210216 Steel structure works 111 days Mon 3/24/14 Sat 7/12/14 100%

217 TVT submit shop drawing for Steel structure 5 days Mon 3/24/14 Fri 3/28/14 100%218 Steel structure get approval 5 days Sat 3/29/14 Wed 4/2/14 100% 217219 Manufacturing in work shop 25 days Wed 4/30/14 Sat 5/24/14 100% 218FS+27 day220 Delivery steel structure to site 5 days Sun 5/25/14 Thu 5/29/14 100% 219221 Erection steel structure on site 15 days Fri 6/13/14 Fri 6/27/14 100% 214,220222 Install Roof Tile 15 days Sat 6/28/14 Sat 7/12/14 100% 221223 Brickwork on ground floor 15 days Tue 6/3/14 Tue 6/17/14 100% 205,210224 Brickwork on First floor 20 days Wed 6/18/14 Mon 7/7/14 100% 223225 Lintel beam for brick wall 15 days Mon 6/23/14 Mon 7/7/14 100% 224SS+5 days226 Electrical conduit to floor +3.600 m 15 days Mon 6/23/14 Mon 7/7/14 100% 224SS+5 days227 Plastering work to internal side 20 days Wed 6/18/14 Mon 7/7/14 100% 223228 Plastering work to external side 20 days Tue 7/8/14 Sun 7/27/14 100% 224229 Finishing works 161 days Tue 7/8/14 Mon 12/15/14 100%

230 Ceiling work on Ground floor & First floor 15 days Tue 7/8/14 Tue 7/22/14 100% 227231 Wall tiling work 14 days Sun 11/30/14 Sat 12/13/14 100% 227

232 Submition the sample tile in living room for approval (Assuming)

3 days Sun 11/30/14 Tue 12/2/14 100%

233 Order & delivery for material on site 7 days Wed 12/3/14 Tue 12/9/14 100% 232234 Making the wall tiling 4 days Wed 12/10/14 Sat 12/13/14 100% 233235 Floor tiling work 15 days Wed 7/23/14 Wed 8/6/14 100% 230236 Door & Window 15 days Sat 8/2/14 Sat 8/16/14 100% 235SS+10 day237 Hardware in bath room 18 days Fri 11/28/14 Mon 12/15/14 100%

238 Approval by Hafela hardware for quotation (Asssuming) 5 days Fri 11/28/14 Tue 12/2/14 100%239 Order & Delivery by Hafele hardware on site 10 days Wed 12/3/14 Fri 12/12/14 100% 238240 Installation by hardware 3 days Sat 12/13/14 Mon 12/15/14 100% 239241 Wooden work 20 days Tue 8/12/14 Sun 8/31/14 100% 236SS+10 day242 Glazing work to partition 20 days Mon 9/1/14 Sat 9/20/14 100% 241243 Painting work to ceiling & wall 20 days Sun 8/17/14 Fri 9/5/14 100% 241SS+5 days244 Painting work to external side 20 days Mon 7/28/14 Sat 8/16/14 100% 228245 Electrical works 70 days Tue 7/8/14 Mon 9/15/14 100%

246 Cabling the power cable 25 days Tue 7/8/14 Fri 8/1/14 100% 230SS247 Installing lighting equipment & socket 30 days Sat 8/2/14 Sun 8/31/14 100% 246248 Installing distribution board 10 days Mon 9/1/14 Wed 9/10/14 100% 247249 Installing the Lightning protection & earthing 10 days Mon 9/1/14 Wed 9/10/14 100% 248SS250 Testing the Electrical works 5 days Thu 9/11/14 Mon 9/15/14 100% 249251 ELV works 38 days Tue 7/8/14 Thu 8/14/14 100%

252 Cabling the ELV Cable (Tel / Data) 15 days Tue 7/8/14 Tue 7/22/14 100% 230SS253 Installing the ELV Equipment (Tel / Data) 20 days Wed 7/23/14 Mon 8/11/14 100% 252254 Testing the ELV works 3 days Tue 8/12/14 Thu 8/14/14 100% 253255 Other finishing works 20 days Wed 8/27/14 Mon 9/15/14 100% 243SS+10 day256 Cleaning work 5 days Tue 9/16/14 Sat 9/20/14 100% 255257 Completion work 1 day Sun 9/21/14 Sun 9/21/14 100% 256,242258 CANTEEN BUILDING 304 days? Mon 2/17/14 Wed 12/17/14 98%

259 TVT submit shop drawing for Foundation 0 days Mon 2/17/14 Mon 2/17/14 100%260 Foundation shop drawing get approval 3 days Mon 2/24/14 Wed 2/26/14 100% 259261 Excavation for footings 4 days Wed 3/26/14 Sat 3/29/14 100% 260FS+27 day262 Compact foundation 4 days Thu 3/27/14 Sun 3/30/14 100% 261SS+1 day263 Termite treatment to foundation 3 days Fri 3/28/14 Sun 3/30/14 100% 262SS+1 day264 Blinding concrete 4 days Sat 3/29/14 Tue 4/1/14 100% 263SS+1 day265 Concrete footings 7 days Mon 3/31/14 Sun 4/6/14 100% 264SS+2 days266 Concrete stump 7 days Wed 4/2/14 Tue 4/8/14 100% 265SS+2 days267 Backfiling work to foundation 7 days Sat 4/5/14 Fri 4/11/14 100% 266SS+3 days268 Backfiling work to raise up ground level 5 days Sat 4/12/14 Wed 4/16/14 100% 267269 Termite treatment to ground floor of WC area 1 day Thu 4/17/14 Thu 4/17/14 100% 268270 Plumbing work 3 days Fri 4/18/14 Sun 4/20/14 100% 269271 Formwork to beam of ground floor slab of WC 5 days Mon 4/21/14 Fri 4/25/14 100% 268,270272 PVC foil to ground floor slab 1 day Sat 4/26/14 Sat 4/26/14 100% 271273 Reinforcement steel to ground floor 4 days Sun 4/27/14 Wed 4/30/14 100% 272274 Electrical conduit to ground floor 3 days Tue 4/29/14 Thu 5/1/14 100% 273SS+2 days275 Concrete to ground floor of WC area 1 day Fri 5/2/14 Fri 5/2/14 100% 274

11/25 12/4

11/25 12/1

11/28 12/1

12/2 12/8

10/5 10/7

10/8 10/16

12/5 12/8

12/4

11/30 12/2

12/3 12/9

12/10 12/13

11/28 12/2

12/3 12/12

12/13 12/15

9/21

4 7 10 13 16 19 22 25 28 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 201

Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014

Task

Critical Task

Milestone

Summary

Rolled Up Task

Rolled Up Critical Task

Rolled Up Milestone

Rolled Up Progress

Split

External Tasks

Project Summary

Group By Summary

Inactive Task

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Critical

Critical Split

Progress

Deadline

Manual Progress

THE PROPOSED CONSTRUCTION PLANNING

Page 2

Project: Bejo_Planning3.12.2014

ID Task Name Duration Start Finish % Complete Predecessors

276 Curing work to ground floor 7 days Sat 5/3/14 Fri 5/9/14 100% 275277 Reinforcement steel to column up to +5.000 m 6 days Sat 5/3/14 Thu 5/8/14 100% 275278 Formwork to column up to +5.000 m 6 days Sun 5/4/14 Fri 5/9/14 100% 277SS+1 day279 Concrete column to level +5.000 m 6 days Mon 5/5/14 Sat 5/10/14 100% 278SS+1 day280 Scafolding , formwork for gutter 7 days Sun 5/11/14 Sat 5/17/14 100% 279281 Reinforcement steel for gutter 5 days Sun 5/18/14 Thu 5/22/14 100% 280282 Concrete to gutter 1 day Fri 5/23/14 Fri 5/23/14 100% 281283 Curing work to gutter 7 days Sat 5/24/14 Fri 5/30/14 100% 282284 Steel structure works 70 days Mon 3/24/14 Sun 6/1/14 100%

285 TVT submit shop drawing for Steel structure 5 days Mon 3/24/14 Fri 3/28/14 100%286 Steel structure get approval 5 days Sat 3/29/14 Wed 4/2/14 100% 285287 Manufacturing in work shop 25 days Thu 4/3/14 Sun 4/27/14 100% 286288 Delivery steel structure to site 5 days Mon 4/28/14 Fri 5/2/14 100% 287289 Erection steel structure on site 15 days Sat 5/3/14 Sat 5/17/14 100% 288290 Install Roof Tile 15 days Sun 5/18/14 Sun 6/1/14 100% 289291 Brickwork 10 days Sat 5/31/14 Mon 6/9/14 100% 279,283292 Lintel beam for brick wall 6 days Tue 6/10/14 Sun 6/15/14 100% 291293 Electrical conduit to wall 3 days Mon 6/16/14 Wed 6/18/14 100% 292294 Plastering work to internal side 10 days Thu 6/19/14 Sat 6/28/14 100% 291,293295 Plastering work to external side 10 days Sun 6/29/14 Tue 7/8/14 100% 294296 Concrete slab for Canteen area 32 days Sun 6/29/14 Wed 7/30/14 100%

297 Leveling work 9 days Sun 6/29/14 Mon 7/7/14 100% 294298 Crushed stone layer , 200 mm thick 9 days Tue 7/8/14 Wed 7/16/14 100% 297299 PVC foil to ground floor slab 1 day Thu 7/17/14 Thu 7/17/14 100% 298300 Reinforcement steel to floor 5 days Fri 7/18/14 Tue 7/22/14 100% 299301 Concrete floor slab with trowel finish 1 day Wed 7/23/14 Wed 7/23/14 100% 300302 Curing work to floor 7 days Thu 7/24/14 Wed 7/30/14 100% 301303 Finishing works 52 days Sun 6/29/14 Tue 8/19/14 100%

304 Ceiling work in WC 6 days Sun 6/29/14 Fri 7/4/14 100% 294305 Wall tiling work 12 days Sun 6/29/14 Thu 7/10/14 100% 294306 Floor tiling work 6 days Sat 7/5/14 Thu 7/10/14 100% 304307 Door & Window 10 days Fri 7/11/14 Sun 7/20/14 100% 306308 Wooden work 12 days Mon 7/21/14 Fri 8/1/14 100% 307309 Glazing work to partition 6 days Sat 8/2/14 Thu 8/7/14 100% 308310 Painting work to internal side 6 days Fri 8/8/14 Wed 8/13/14 100% 309311 Painting work to external side 6 days Thu 8/14/14 Tue 8/19/14 100% 310312 Electrical works 55 days Sun 6/29/14 Fri 8/22/14 100%

313 Cabling the power cable 15 days Sun 6/29/14 Sun 7/13/14 100% 304SS314 Installing lighting equipment & socket 20 days Mon 7/14/14 Sat 8/2/14 100% 313315 Installing distribution board 15 days Sun 8/3/14 Sun 8/17/14 100% 314316 Installing the Lightning protection & earthing 15 days Sun 8/3/14 Sun 8/17/14 100% 315SS317 Testing the Electrical works 5 days Mon 8/18/14 Fri 8/22/14 100% 316318 Other finishing works 16 days? Fri 11/28/14 Sat 12/13/14 59% 311

319 Approved shop drawing for cabinet 1 day? Fri 11/28/14 Fri 11/28/14 100%320 Order & Delivery for material on site 10 days Sat 11/29/14 Mon 12/8/14 80% 319321 Installation of cabinet 5 days Tue 12/9/14 Sat 12/13/14 10% 320322 Cleaning work 3 days Sun 12/14/14 Tue 12/16/14 100% 321323 Completion work 1 day Wed 12/17/14 Wed 12/17/14 100% 322324 STORE & TOILET BUILDING 209 days Mon 2/17/14 Sat 9/13/14 100%

382 MAIN STORE 163 days Mon 3/3/14 Tue 8/12/14 100%

429 SEED SHED BUILDING 175 days Mon 3/3/14 Sun 8/24/14 100%

471 INFRASTRUCTURE WORKS 296 days? Thu 3/27/14 Fri 1/16/15 98%

472 Drainage system 85 days Thu 3/27/14 Thu 6/19/14 100%

473 Excavation work 40 days Thu 3/27/14 Mon 5/5/14 100% 6FS+37 days474 Compaction to base 45 days Sun 4/6/14 Tue 5/20/14 100% 473SS+10 day475 Blinding concrete 45 days Wed 4/16/14 Fri 5/30/14 100% 474SS+10 day476 Stone wall masonry 55 days Sat 4/26/14 Thu 6/19/14 100% 475SS+10 day477 Backfilling work 30 days Mon 5/5/14 Tue 6/3/14 100%478 Road 171 days? Fri 6/20/14 Sun 12/7/14 100% 472

479 Grading & leveling work 45 days Fri 6/20/14 Sun 8/3/14 100%480 Compaction to base 28 days Mon 8/4/14 Sun 8/31/14 100% 479481 Concrete road 10 days? Fri 11/28/14 Sun 12/7/14 100% 480

482 Approved shop drawing for concrete road at the main gate 5 days Fri 11/28/14 Tue 12/2/14 100%483 Excavation & backfill stone 2 days Wed 12/3/14 Thu 12/4/14 100% 482484 Formwork & reinforment bar 2 days Fri 12/5/14 Sat 12/6/14 100% 483485 Casting concrete road 1 day? Sun 12/7/14 Sun 12/7/14 100% 484486 Lightning system 46 days Tue 12/2/14 Fri 1/16/15 100%

487 Assuming appoval 1 day Tue 12/2/14 Tue 12/2/14 100%488 Delivery material 30 days Wed 12/3/14 Thu 1/1/15 100% 487489 Installing working 15 days Fri 1/2/15 Fri 1/16/15 100% 488490 Bore well - water supply system 23 days Wed 12/3/14 Thu 12/25/14 72%

491 Assuming appoval 1 day Wed 12/3/14 Wed 12/3/14 100%492 Delivery material 15 days Thu 12/4/14 Thu 12/18/14 90% 491493 Installing working 7 days Fri 12/19/14 Thu 12/25/14 30% 492494 CCTV 64 days? Mon 10/13/14 Mon 12/15/14 99%

495 Appoval 1 day? Mon 10/13/14 Mon 10/13/14 100%496 Delivery material 58 days Tue 10/14/14 Wed 12/10/14 100% 495497 Installing working 5 days Thu 12/11/14 Mon 12/15/14 90% 496498 WORK AT MAIN GATE AREA 237 days Mon 4/28/14 Sat 12/20/14 100%

499 Guardhouse 45 days Mon 4/28/14 Wed 6/11/14 100%500 Flag poles 15 days Mon 8/4/14 Mon 8/18/14 100%501 Additional Fence 71 days Tue 9/30/14 Tue 12/9/14 100%

502 Footing 15 days Tue 9/30/14 Tue 10/14/14 100%503 Ground beam 12 days Wed 10/15/14 Sun 10/26/14 100% 502504 Stone wall 12 days Mon 10/27/14 Fri 11/7/14 100% 503505 Steel frame 12 days Sat 11/8/14 Wed 11/19/14 100% 504506 Finishing work for fence 20 days Thu 11/20/14 Tue 12/9/14 100% 505507 Sliding gate 160 days Mon 7/14/14 Sat 12/20/14 100%

508 Concrete foundation 20 days Mon 7/14/14 Sat 8/2/14 100%509 Sliding gate 8 days Sun 8/3/14 Sun 8/10/14 100% 508510 Swing gate 6 days Mon 8/11/14 Sat 8/16/14 100% 509511 Motor system 47 days Tue 11/4/14 Sat 12/20/14 100%

512 Appoval 1 day Tue 11/4/14 Tue 11/4/14 100%513 Delivery material 40 days Wed 11/5/14 Sun 12/14/14 100% 512514 Installing working 6 days Mon 12/15/14 Sat 12/20/14 100% 513515 Lock gates 12 days Mon 8/4/14 Fri 8/15/14 100%516 HANDING OVER PROJECT 0 days Fri 1/16/15 Fri 1/16/15 0% 498,429,382,3

11/28 11/28

11/29 12/8

12/9 12/13

12/17

11/28 12/2

12/3 12/4

12/5 12/6

12/7 12/7

12/2 12/2

12/3 1/1

1/2 1/16

12/3 12/3

12/4 12/18

12/19 12/25

10/13 10/13

10/14 12/10

12/11 12/15

9/30 10/14

10/15 10/26

10/27 11/7

11/8 11/19

11/20 12/9

11/4 11/4

11/5 12/14

12/15 12/20

1/1

4 7 10 13 16 19 22 25 28 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 201

Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014

Task

Critical Task

Milestone

Summary

Rolled Up Task

Rolled Up Critical Task

Rolled Up Milestone

Rolled Up Progress

Split

External Tasks

Project Summary

Group By Summary

Inactive Task

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Critical

Critical Split

Progress

Deadline

Manual Progress

THE PROPOSED CONSTRUCTION PLANNING

Page 3

Project: Bejo_Planning3.12.2014

4. PROGRESS

P.13

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG

Report on overall work done till 30th December 2014. 

Month  Schedule  Actual work done 

Ahead/Delay Contract/25 September, 2014

March, 2014  3%  3%  0% ( 0 day)  0% ( 0 day) 

April, 2014  11%  10%  ‐1% (2days)  ‐1% (2days) 

May, 2014  30%  30%  ‐0% (0days)  ‐0% (0days) 

June, 2014  44%  41%  ‐3% (7days)  ‐3% (7days) 

July, 2014  65%  57%  ‐8% (16days)  ‐8% (16days) 

August, 2014  86%  72%  ‐14% (28days)  ‐14% (28days) 

September, 2014  92%  90%  ‐2% (4days)  ‐20% (40days) 

October, 2014  100%  92%  ‐8% (16days)  ‐25% (50days) 

November, 2014  95% ( New planned)  95%  ‐0% (0 days)  ‐30% (60days) 

December, 2014  99% ( New planned)  99%  ‐0% (0 days)  ‐45% (90days) 

 

 

 

5. WEATHER REPORT

P.15

6. MANPOWER SCHEDULE

P.19

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 Project Manager 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0

2 Site Manager 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 0

3 Q.A & Q.C 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 Site Engineer ( C&S ) 3 3 3 3 3 3 3 3 3 3 3 3 3 2 3 3 3 3 3 3 2 3 3 3 3 3 3 2 3 3

5 Accountant 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6 Foreman 3 3 3 3 3 3 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 3 3 3 3 3 3

7 Surveyor and Helper 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

8 Site Engineer (M&E) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

9 Labour (C&S) 27 28 28 28 28 27 18 26 26 26 25 25 25 22 23 23 23 23 23 23 23 22 22 22 22 22 22 21 22 22

10 Labour (M&E) 9 7 9 9 7 9 3 7 9 7 9 9 9 3 9 9 9 7 9 9 2 9 9 4 8 8 8 2 7 8

47 46 48 48 46 47 29 44 46 44 45 45 45 34 43 43 43 41 43 43 34 42 42 35 41 41 42 33 40 40

376 368 384 384 368 376 232 352 368 352 360 360 360 272 344 344 344 328 344 344 272 336 336 280 328 328 336 264 320 320

TAN VIET TIN CONSTRUCTION CO., LTD.456 Nguyen Van Luong ST, Ward 12, Dist 6, HCMCT: +84-8375-11384 Fax: +84-8375-11383

MANPOWER RECORD

Project : Bejo ( Viet Nam) Farm.

TOTAL

TOTAL HOURS

No. DESCRIPTION

7. LIST OF PLANT, MACHINERY AND EQUIPMENT

P.21

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

1 Welding Machine 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 32 Bar Bending Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 13 Bar Cutting Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14 Truck 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 05 Roller Compactor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 16 Heavy duty Truck 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 07 Leveling Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 18 Excavator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 19 Theodolite 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 210 Water Pump 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 411 Vibrator 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 312 Hand compaction machine 2 2 2 2 2 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 413 Mortar mixer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 114 Sawing Machine 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

TAN VIET TIN CONSTRUCTION CO., LTD.456 Nguyen Van Luong ST, Ward 12, Dist 6, HCMCT: +84-8375-11384 Fax: +84-8375-11383

Project : BEJO VIET NAM PRODUCTION FARM

No. DESCRIPTION

PLANT & MACHINERY RECORD

08. SUMMARY OF VO 

TÂN VIỆT TÍN CONSTRUCTION CO., LTD.456 Nguyen Van Luong. Dist. 6 HCMC.Fax : (08) 7511383 Tel : (08) 8.756.934 - 7.511.384Website: www.tanviettin.comEmail: [email protected]

PROJECT : BEJO VIET NAM FARM

ITEM:

1 Tempprary Toilet N.01 for worker near Pump house VO-01A 75,566,400

2 Temporary Toilet for worker near Gate 2 VO-01B 38,532,000

3 Concrete slab for irigation room VO-03 55,768,000

4 Foundation for Cool room ( Main store ) VO-04 4,558,000

5 Pump pit & Water channel VO-06 162,656,000

6 Bore hole house VO-14B 19,543,425

7 Fencing at Main gate VO-19 48,343,000

8 Cabinet - Green house shed VO-24 59,974,800

9 Gas storage, Concrete entrance for Canteen and Mainstore VO-25 25,209,600

10 Cabinet, kitchen - Guest house VO-26 136,117,210

11 Cabinet, kitchen - Office VO-27 82,058,900

12 Concrete for main entrance VO-29 51,932,467

13 2 Sub gate between canteen & Green house shed VO-30 18,870,000

14 Cabinet in bedroom - Guest house VO-31 64,628,650

15 Hardware-Office VO-28 106,858,998

Hardware-Guest house VO-28 40,502,751

Hardware-Green house shed VO-28 22,903,903

II TOTAL ( EXCLUDING VAT) 1,014,024,104

APPROVED BY BEJO VIET NAM FARMDATE : ----------/-----------/2014

TOTAL COST(VND) VO

SUMMARY THE QUOTATION

Ref Description

75566400

38532000

61258000

4558000

162656000

19543425

48343000

25898400

436,355,225.00                      

9. SUBMITTALS

P.28

NO DESIGNTION DRAWING NO TITTLE1 OTHERS SD-02 EXISTING GROUND LEVEL OF CANTEEN, MAIN STORE, SEED

PROCESSING SHEDSD-04 FINISHING LEVEL OF (INTERNAL) ROAD (4m) IN FRONT OF RAM-

UP (OF GREENHOUSE SHED)SD-05 PROPOSED THE FINISHING LEVEL OF MAIN ROAD (A TO E)SD-07 GREEN HOUSE SHED, MAIN STORE, SEED PROCESSING SHED -

GROUND FLOORSD-08 WATER CHANNEL PLAN AND DETAIL ( ALONG MAIN ROAD)SD-11 FINISHING LEVEL - INTERNAL ROAD (4M) - ALL ROAD

SD-14FINISHING LEVEL - 2M ROAD (NEAR THE FENCE) - BICYCLE ROAD

SD-23 ROOF SHEET FOR GUARD HOUSE AND TOILET & STORE

SD-25 INTERNAL ROAD DETAIL

SD-26 MAIN GATE AND GUARD HOUSE DETAIL

SD-27 IRRIGATION ROOM FLOOR SLAB

SD-28 PUMP PIT

SD-35 SOIL EXCAVATION LEVEL INTERNAL ROAD 4000 mmSD-36 ALUMINUM LOUVER FOR OFFICE BUILDING, GUEST HOUSE,

CANTEENSD-42 MAIN ROAD AND ROAD 2000 mm

SD-50 CAR & MOTOBIKE PARKING

SD-51 EXISTING SOIL LEVEL AT MOTOBIKE PARKING

SD-52 100 MM CONCRETE REMAINING FOR 4 M ROADSD-56 FLAG POLE DETAILSD-59 SIGNBOARD DETAIL FOR MAIN GATE

SD-61 ADDITIONAL FENCING NEAR MAIN GATE

2 MAIN STORE SD-12 ARCHITECTURESD-29 LOUVER AND DOOR SD-30 CEILING PLAN

SD-31 MACHINCE SLAB FOR COLD ROOM

SD-48 BEHIND ENTRANCE

3 GREEN HOUSE SHED SD-03 GROUND BEAMS AND SLAB SD-06 RAM UPSD-20 ROOF SHEET AND CANOPYSD-24 BREACING BEAM ON GREEN HOUSE SHED ROOF TOP (Rejected)

SD-33 OUTSIDE STEEL STAIRCASE GL:1 GREEN HOUSE SHEDSD-36 GALVANIZED STAIR-CASE (INSIDE)

SD-37 GREEN HOUSE SHED CEILING

SD-43SPECIFICATION AND SHOP DRAWING FOR SANDWICH PANELS IN GREEN HOUSE SHED

SD-44 LIGHT GREY RESIN FOR 2nd FLOOR

SD-53 HAND WASHING SINK

4 TOILET AND STORE SD-01 FOOTING AND GROUND BEAMSD-09 ARCHITECT SD-10 GROUND FLOORSD-16 EXISTING LEVEL

C & S SHOP DRAWING

SD-21 ENTRANCE

5 SEED PROCESSING SHED SD-13 DRAIN DETAILSD-17 BRACING BEAMS

6 CANTEEN SD-15 GROUND FLOORSD-18 DRAIN DETAIL (Omitted)SD-32 ROOF EAVES DETAIL (Rejected)SD-44 ENTRANCESD-45 GAS STORAGE

7 PUMP HOUSE SD-22 ROOF SHEET

8 GUEST HOUSE SD-46 STONE ARRANGEMENTSD-54 DETAIL CEILING AT STAIR-CASESD-62 TILING WORKS FOR TOILET WALL UNDER STAIRCASE

9 OFFICE BUILDING SD-41 ALUM DOOR FOR DOOR: D2, FIXED WINDOW: VK1, VK2

NO NAME ITEMS SUPLLIER BUILDINGS COMMENTS ATTACHED WITH STATUS SUBMITTED DATE

APPROVED DATE

MSA/TVT/001

THE CATALOG FOR STEEL BAR FORM POMINA

POMINA ALL BUILDINGS PLEASE SAMPLES FOR TESTING - RANDOM SIZES 12 MM BAR & 16 MM BAR TENSILE TEST ONLY …PLEASE PROVIDE " TAGS & CERTIFICATE".

CATALOGUES APPROVED ON CONDITION, AS NOTED

27/2/2014 27/2/2014

PICS ATTACHED

MSA/TVT/002

THE CONCRETE GRADE DESIGN 10MPa, 15MPa, 20MPa, 25MPa, 30MPa

ALL BUILDINGS SPECIFICATIONS AND TEST REPORTS

APPROVED 27/2/2014 27/2/2014PICS

ATTACHED

MSA/TVT/003

BACKFILL SOIL FOR FACTORY AND ROAD

FOUNDATION, GROUND SLAB, ROAD

PLEASE GIVE COPY OF DELIVERYNOTES TO BEJO (GEOFF) THESE DELIVERY NOTE SHALL TONAGE (AMOUNT OF SOIL + DATE DELIVERY)

SAMPLES APPROVED 4/3/2014 4/3/2014

PICS ATTACHED

MSA/TVT/004

GALVANIZE STEEL TO BE USED FOR FOOTING SYSTEM

TIEN PHONG ADD BUILDINGS CATALOGUES APPROVED21/3/2014 21/3/2014

PICS ATTACHED

MSA/TVT/005

ANTI-TERMITE TREAMENT CHEMICAL

FOUNDATION & GROUND FLOOR FOR ALL BUILDINGS

TEST REPORTS APPROVED 24/3/2014 24/3/2014PICS

ATTACHED

MSA/TVT/006

ANCHOR BOLTS M16, ANCHOR BOLTS M20.

SUBCONTRACTOR - BMB

ALL BUILDINGS STEEL STRUCTURE

SAMPLES APPROVED 1/4/2014 1/4/2014PICS

ATTACHED

MSA/TVT/007

INSULLATION 1 SIDE ALU-POLYNUM (REFER TO SAMPLES)

CAT TUONG ROOFING SYSTEM FOR ALL BUILDINGS ( MAINSTORE AND SEED PROCESSING SHED)

SAMPLES + TEST REPORTS + CATALOGUES

APPROVED 1/4/2014 1/4/2014

PICS ATTACHED

MSA/TVT/008

SKYLIGHGT TO BE USED FOR ROOFING SYSTEM

NAM VIET MAIN STORE AND SEED PROCESSING SHED

COLOR OPAL CATALOGUES (COLOR CHART)

APPROVED 1/4/2014 2/4/2014PICS

ATTACHED

MSA/TVT/009

PAINTING FOR STEEL STRUCTURE

DONASA ALL BUILDINGS (MAIN STORE AND SEED PROCESSING SHED)

COLOR NO 3076 SILVER CATALOGUES APPROVED 1/4/2014 2/4/2014

PICS ATTACHED

MSA/TVT/010

COLOUR CHART TO BE USED FOR MAIN STORE AND SEED PROCESSING SHED DOOR

TNP & HD MAIN STORE AND SEED PROCESSING SHED

M9029A TO BE USED OVERHEAD DOOR SLIDING DOOR MADE OUT OF PANELSO HAVE PANEL COLOR

CATALOGUES APPROVED 20/5/2014 20/5/2014PICS

ATTACHED

MSA/TVT/011

WELDMESH TO BE USED FOR GROUND FLOOR

SONG HOP LUC

CATALOGUES + SPECIFICATION + TEST

APPROVED 28/5/2014 4/8/2014PICS

ATTACHED

MSA/TVT/012

HOLLOW AND SOILD BRICKS ALL BUILDINGS SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED

MSA/TVT/013

NATURAL STONE TO BE USED FOR WATER CHANNEL

LOCAL WATER CHANNEL

SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED

MSA/TVT/014

CONCRETE BLOCK MAIN STORE SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED

MSA/TVT/015

TILES ROOFING LAMA CANTEEN, GUEST HOUSE, OFFICE BUILDING

L104 - CHARCOAL TO BE USED CATALOGUES, SPECIFICATION, SAMPLE

APPROVED AND APPROVED ON CONDITION, AS NOTED

5/6/2014 10/6/2014PICS

ATTACHED

MSA/TVT/016

ROOF SHEET'S COLOUR CHART HOA SEN GREEN HOUSE SHED, GUARD HOUSE, TOILET, PUMP HOUSE.

BBL01 TO BE USED SAMPLES APPROVED 9/6/2014 9/6/2014PICS

ATTACHED

MSA/TVT/017

ROOF AND WALL SHEET HOA SEN MAIN STORE, SEED PROCESSING SHED.

BBL01 TO BE USED SAMPLES APPROVED 4/4/2014 4/4/2014PICS

ATTACHED

MSA/TVT/018

PVC SHEET TVT GROUND FLOOR - ALL BUILDINGS

SAMPLES APPROVED 1/6/2014 1/6/2014 PICS ATTACHED

MSA/TVT/019

DOWER BAR D16 TVT CONSTRUCTION JONT - ALL BUILDINGS

SAMPLES APPROVED 20/6/2014 20/6/2014PICS

ATTACHED

MSA/TVT/020

WALL SHEET'S COLOUR CHART HOA SEN SAME COLOR WITH FOOR SHEET BMB

SAMPLES APPROVED 9/6/2014 9/6/2014 PICS ATTACHED

MSA/TVT/021

INTERNAL AND EXTERNAL PAINTING

SONATA GUEST HOUSE, OFFICE, GREEN HOUSE SHED, CANTEEN, TOILET & STORE, GUARD HOUSE, PUMP HOUSE.

CATALOGUES, SPECIFICATION.

APPROVED 16/7/2014 4/8/2014

PICS ATTACHED

MSA/TVT/022

TILES FOR FLOOR AND WALL AMERICAN HOME VIET NAM

GREEN HOUSE SHED, CANTEEN, TOILET AND STORE

MICHIGAN 2525 FOR SHOWER AREAS + MICHIGAN 02-2540 FOR OTHERS MORE CATALOGUES/ SAMPLES REQUIRED

CATALOGUES, SPECIFICATION.

APPROVED 29/7/2014 19/8/2014PICS

ATTACHED

MSA/TVT/023

EPS SANDWICH PANEL , 50 MM THICKNESS

VIET NAM MAIN STORE CATALOGUE + SAMPLE

APPROVED 31/7/2014 1/8/2014 PICS ATTACHED

MSA/TVT/024

ALUM CEILING ALUKING OFFICE AND GUEST HOUSE'S TOILET

COLOR TO BE AK009 AS PER SPEC BY HKAP3

CATALOGUE AND SAMPLE

APPROVED 14/8/2014 19/8/2014PICS

ATTACHED

MSA/TVT/025

SINGLE FLUSH WOODEN DOOR (MDF TEAK VENEER). DOUBLE FLUSH GLASS DOOR

VIET NAM OUTSIDE GUEST HOUSE, INSIDE OFFICE AND GUEST HOUSE

SAMPLES APPROVED 18/8/2014 25/8/2014PICS

ATTACHED

MSA/TVT/026

PHENOLIC PARTITION SHED , 10 mm THICKNESS IN WC

THIEN QUY GREEN HOUSE SHED, CANTEEN, TOILET AND STORE

COLOR AS PER SAMPLE STAINLESS STEEL SERIES OT.10B

CATALOGUE AND SAMPLES

APPROVED 18/8/2014 19/8/2014PICS

ATTACHED

MSA/TVT/027

PAINTING COLOR INTERNAL AND EXTERNAL BY THIEN NAM ARCHITECTURE DESIGNER

SONATA ALL BUILDING EXCLUDED COLORS SELECTED BY HKAP3 FOR INTERNAL DESIGN. INTERNAL SI206 EDWARDIAN LACE TO BE USED

CATALOGUE APPROVED 18/8/2014 19/8/2014PICS

ATTACHED

MSA/TVT/028

COMPOUND STONE VU HIEP PHAT

OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN.

HP120 GUEST HOUSE BOTTOM PART, SEE MARKED * THIS ONE IN CATALOGUES FOR COLUMNS OFFICE

CATALOGUE + SAMPLES

APPROVED 19/8/2014 22/8/2014PICS

ATTACHED

MSA/TVT/029

SPECIFICATION AND SHOP DRAWINGS FOR THE SANDWICH PANEL IN GREEN HOUSE SHED 100 mm AND 50 mm THICKNESS

METECNO VIET NAM

LAB ROOM GREEN HOUSE SHED

FIRE RATED PANELS TO BE STEEL SHEET BOTH SIDES.

CATALOGUE + SHOP DRAWING + SPECIFICATION

APPROVED 25/8/2014 29/8/2014PICS

ATTACHED

C & S SUBMISSION

MSA/TVT/030

TEAK NATURE WOOD 23 mm THICK (STAIR-CASE). TEAK NATURE WOOD 155 mm THICK (WALL AREA INSIDE)

VIET NAM OFFICE BUILDING, GUEST HOUSE.

SAMPLES APPROVED 25/8/2014 25/8/2014PICS

ATTACHED

MSA/TVT/031

MARBLE 67 (800 × 800 × 20) mm 

THICK. (GROUND FLOOR) . GRANIT 28 

(600 × 300 × 20)mm THICK (BALCONY 

AREA). GRANIT 95 20 mm THICK 

(BOTTOM DOOR). 

VIET NAM OFFICE BUILDING, GUEST HOUSE.

SAMPLES APPROVED 25/8/2014 25/8/2014

PICS ATTACHED

MSA/TVT/032

CERAMIC TILE (250 × 400) mm AT 

KINCHEN WALL AREA. CERAMIC TILE 

(300 × 300) mm AT WASHING FLOOR 

AREA.

VIET NAM CANTEEN, GREEN HOUSE SHED

GREEN HOUSE SHED GROUND FLOOR: WASHING ROOM, TOILET, HALL, CHANGING ROOM

SAMPLES APPROVED 28/8/2014 30/8/2014PICS

ATTACHED

MSA/TVT/033

MDF TEAKWOOD FINISHING MALAYFLOOR

TRAINNING ROOM STAGE

MODEL DIAMOND CODE 788 (MALAYFLOOR)

SAMPLE APPROVED 9/9/2014 10/9/2014 PICS ATTACHED

MSA/TVT/034

PINE WOOD CANTEEN THE COLOR IS TOO LIGHT. MATERIALS CAN BE ORDERED BUT NEED ON SITE DARKER VERNIS FINISHING

SAMPLES APPROVED 24/09/2014 26/9/2014PICS

ATTACHED

MSA/TVT/035

GRANITE STONE FOR SIGNBOARD

MAIN GATE SUBMIT SAMPLE OF LETTERING ON GRANITE STONE

SAMPLE APPROVED 10/10/2014 11/10/2014 PICS ATTACHED

MSA/TVT/036

NATURAL STONE BROWN/ COPPERISCH

GUEST HOUSE COLUMNS

SAMPLE APPROVED 11/10/2014 11/10/2014 PICS ATTACHED

MSA/TVT/037

SLIDING DOOR HARDWARE D9 IN BATHROOM

GUEST HOUSE CATALOGUE APPROVED 13/10/2014 16/10/2014 PICS ATTACHED

MSA/TVT/038

DOOR HARDWARE HAFELE OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN.

CATALOGUE NOT APPROVED YET

18/10/2014PICS

ATTACHED

MSA/TVT/039

CERAMIC TILE (300 × 300) mm PORCELAIN

GUEST HOUSE TOILET FLOOR

SAMPLE APPROVED 18/10/2015 22/10/2014 PICS ATTACHED

MSA/TVT/040

VIET CERAMIC - GSB05 GUEST HOUSE KITCHEN WALL

SAMPLE APPROVED 18/10/2016 23/10/2014 PICS ATTACHED

MSA/TVT/041

WHITE-BLACK TILES/ 30Y01, 30Y06

OFFICE TOILET SIZE 100 × 100 SQUARE APPROVED ON CONDITION, AS NOTED

18/10/2017 22/10/2014PICS

ATTACHED

MSA/TVT/042

AM EXPOXICATE 403SM - RAL 7046, 7047

OFFICE, GREEN HOUSE SHED

BY PASCAL HKAP3 SAMPLE APPROVED 10/11/2014 12/11/2014 PICS ATTACHED

MSA/TVT/043

TEMPERED GLASS 10 mm THICK OFFICE, GUEST HOUSE, CANTEEN

SPECIFICATIONS AND TEST REPORTS

APPROVED 10/11/2014 12/11/2014PICS

ATTACHED

MSA/TVT/044

CEMENT BOARD CEILING, GYPROC REGULAR BOARD, MOISTURE RESISTANT, BOARD

OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN, TOILET & STORE

SAMPLES NOT APPROVED YET

18/10/2020

PICS ATTACHED

MSA/TVT/045

MDF MELAMINE FOR OFFICE & GUEST HOUSE CABINET

OFFICE AND GUEST HOUSE

SAMPLE APPROVED 22/10/2014 22/10/2014 PICS ATTACHED

MSA/TVT/046

PINE WOOD FOR CABINET GREEN HOUSE SHED

SAMPLE APPROVED 22/10/2014 22/10/2014 PICS ATTACHED

MSA/TVT/047

POLYCARBONATE EXTERNAL STAIRCASE ROOF GREEN HOUSE SHED

SAME MATERIALS TO BE USED AS EXISTING ROOF

CATALOGUE, SAMPLE

REJECTED 22/10/2014 23/10/2014PICS

ATTACHED

MSA/TVT/048

WHITE MARBLE OFFICE STAIRCASE

AS PER SIGNED SAMPLE SAMPLE APPROVED 6/11/2014 6/11/2014 PICS ATTACHED

MSA/TVT/049

STONE FOR KITCHEN COUNTER AND MELAMIN FOR CABINET

OFFICE, GUEST HOUSE

BY PASCAL HKAP3 SAMPLES APPROVED 10/11/2014 12/11/2014 PICS ATTACHED

NO DESIGNATION DRAWING NO TITLE

0MAIN DISTRIBUTION BOARD - MDB

TEST REPORT

GALVANOMETER TEST REPORTS

COMPLETE SHOP DRAWING

1 OTHERS M&E/TVT - 008 POWER SUPPLY MASTER PLAN

M&E/TVT - 027 LOCATION INSTALLATION GROUNDING FOR DISTRIBUTION BOARD

M&E/TVT - 029 WATER SUPPLY MASTER PLAN

M&E/TVT - 030 CCTV MASTER PLAN AND SINGLE LINE CCTV

M&E/TVT - 031 SINGLE LINE TEL AND DATA (OVERVIEW)

M&E/TVT - 039 LIGHTING, SOCKET, DATA IN GUARD HOUSE

M&E/TVT - 043 LIGHTNING SYSTEM FOR BUILDING FROM IRRIGATION ROOM UNTIL MAIN ROAD AND SEED PROCESSING SHED

M&E/TVT - 045 MOTOR FOR SLIDING SYSTEM( SYSTEM SLIDING GATE) MAIN GATE

2 CANTEEN M&E/TVT - 007 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 015 POWER SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 016 DATA & TEL SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 023 LIGHTING LAYOUT PLAN FOR CANTEEN

M&E/TVT - 028 WATER DRAIN FROM ROOF TO GROUND

3 MAIN STORE M&E/TVT - 018 POWER SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 024 LIGHTING LAYOUT PLAN

M&E/TVT - 034 SINGLE LINE FOR MDB ( MAIN DISTRIBUTION BOARD)

M&E/TVT - 035 WATER DRAIN FROM ROOF TO GROUND

M&E/TVT - 040 WASTE WATER AND WATER SUPPLYM&E/TVT - 041 GREASE TRAP

4 GUEST HOUSE M&E/TVT - 005 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 020 POWER SOCKET OUTLET AND DATA & TEL SOCKET LAYOUT PLAN

M&E/TVT - 021 LIGHTING LAYOUT PLAN

M&E/TVT - 032 WATER DRAIN FROM ROOF TO GROUND

5TOILET AND STORE

M&E/TVT - 006 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 017 LIGHTING AND POWER SOCKET OUTLET LAYOUT PLAN

6GREEN HOUSE SHED

M&E/TVT - 003 WATER SEWAREGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 009 POWER SOCKET LAYOUT PLAN

M&E/TVT - 010 DATA AND TEL SOCKET LAYOUT PLAN

M&E/TVT - 019 LIGHTING AND LIGHTING POSITIONING AND SINGLE LINE LAYOUT PLAN

M&E/TVT - 037 WATER DRAIN FROM ROOF TO GROUND

M&E/TVT - 038 SINGLE LINE FOR DB7 (GREEN HOUSE)

M & E SHOP DRAWINGS

M&E/TVT - 044 EXHAUST AIR SYSTEM

7 OFFICE BUILDING M&E/TVT - 004 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 011 POWER SOCKET LAYOUT PLAN

M&E/TVT - 012 DATA AND TEL SOCKET LAYOUT PLAN

M&E/TVT - 022 LIGHTING LAYOUT PLAN

M&E/TVT - 033 WATER DRAIN FROM ROOF TO GROUND

M&E/TVT - 042 AIR-CONDITION

8 SEED PROCESSING SHED

M&E/TVT - 025 WATER SUPPLY PLAN

M&E/TVT - 026 LIGHTING AND SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 036 WATER DRAIN FROM ROOF TO GROUND

NO NAME ITEMS SUPLLIER BUILDINGS COMMENTS ATTACHED WITH STATUS SUBMITTED DATE

APPROVED DATE

MES/TVT - 001

PVC PIPE TO BE USED FOR WATER SEWAREGE AND WATER SUPPLY SYSTEM

BINH MINH ALL BUILDINGS ENSURE AROMATIC SOLVENTS ARE NOT USED TO GLUE THE PIPEWORK

CATALOGUE + SAMPLE

APPROVED ON CONDITION, AS NOTED

24/3/2014 24/3/2014

MES/TVT - 002

PVC CONDUIT TO BE USED FOR ELECTRICAL SYSTEM

VANLOCK ALL BUILDINGS WHERE ARE THE 'CUPS' FOR FIXING CONDUITS TO WALLS

CATALOGUE + SAMPLE

APPROVED ON CONDITION, AS NOTED

24/3/2014 24/3/2014

MES/TVT - 003

SAMPLE CABLE FOR ALL BUILDINGS CADIVI ALL BUILDINGS SAMPLE APPROVED 21/4/2014 26/4/2014

MES/TVT - 004

CATALOGUE CCTV ALL BUILDINGS CAMERA SNB-5000, SLA-M 3180DN, HOUSING SHB-4200H, SURGE SUPPRESSOR, EPMP 1000 INTERGRATED RADIO.

CATALOGUES APPROVED 16/5/2014 25/7/2014

MES/TVT - 005

LIGHTING PARAGON CHANGING ROOM OF GREEN HOUSE SHED

LIGHTING PIFL228 FOR SOWING AREA, LIGHTING PCFA236 FOR CHANGING ROOM, SEED CLEANING AREA, GERMINATION ROOM, CONTROL ROOM, EXTENDTION OFFICE PHASE 1, PHYTO LAB, SAMPLING ROOM, GERMINATION LAB, POLLEN EXSTRACTION, SUPERVISER ROOM. DOWNLIGHT PRDH70E27 FOR TOILET 1-FLOOR. EXIT LAMP PEXA13SW FOR TRAINING ROOM, EMERGENCY LAMP PEMA25SW FOR CHANGING ROOM.

CATALOGUE APPROVED 9/6/2014 8/8/2014

MES/TVT - 006

CATALOGUES SANITARY EQUIPMENT

CAESAR GREEN HOUSE SHED, TOILET AND STORE, CANTEEN

WATER CLOSET CD1340 + TAP BS304, UNIRAL U0262 + TAP BF412G, LAVABO LF 5236 + TAP BF053, FLOOR DRAIN ST1010B, COAT HANGER Q8807, SOAP HOLDERS ST823V, TOILET PAPER HOLDERS Q7714V, XI PHONG BF 602, WO34-1, SHOWER BFV-28S are to be used. SHOWERHEAD TO BE RE-SUBMITTED

CATALOGUE SELECTIVITY APPROVED, AS NOTED

9/6/2014 15/7/2014

MES/TVT - 007

CATALOGUES SOCKET, SWITCH SCHNEIDER MAIN STORE, GREEN HOUSE SHED, SEED PROCESSING SHED, TOILET & STORE

SWITCH ONE WAY: F50M1-5, SWITCH TWO WAY: F50-2M1-5, COVER: FG1051, FG1052, FG1053, POWER SOCKET: F1426ESM, DATA AND TEL SOCKET: F50RJ5EM

CATALOGUES APPROVED 9/6/2014 25/7/2014

MES/TVT - 008

CABLE TRAY DONG NAM A GREEN HOUSE SHED, SEED PROCESSING SHED

FOR MAINSTORE AND SEED PROCESSIING SHED CABLE TRAYDUCT TYPE TO BE USED 100×50 AND NO COVER.. DIMENSION ACCORDING SHOP DRAWING.

CATALOGUE AND SAMPLE

APPROVED 19/6/2014 23/7/2014

MES/TVT - 009

SOLAR POWER SINGAPORE CAMERA. OUTDOOR

CATALOGUES APPROVED 8/7/2014 29/8/2014

MES/TVT - 010

WATER HEATER ARISTON GUEST HOUSE ARISTON VERO IM-4522EP (BẠC) TO BE USED CATALOGUE APPROVED 10/9/2014 11/9/2014

MES/TVT - 011

NETWORK ALL BUILDINGS CAT 6A TO BE USED. AP-SWITCH - MODULES TO BE LEFT OUT.

CATALOGUE APPROVED 11/8/2014 9/9/2014

M & E SUBMISSION

MES/TVT - 012

TRUNKING SOCKET L&S GREEN HOUSE SHED

FA 100/40 100 mm × 40mm × 2 mm. FA 

100/60 100 mm × 60 mm × 2 mm.

CATALOGUE APPROVED 4/9/2014 4/9/2014

MES/TVT - 013

ROAD LAMP POLE LU GIA IN SITE 73-F1-010 + KATO 0516010250 CATALOGUE APPROVED 16/8/2014 19/8/2014

MES/TVT - 014

BRASS FITTING VIET NAM ALL BUILDINGS SAMPLE APPROVED 23/8/2014 23/8/2014

MES/TVT - 015

WALL DECORATIVE LIGHTING CHINA GUEST HOUSE CATALOGUE NOT APPROVED YET

26/8/2014 REJECTED. BEJO WILL SUPPLY

MES/TVT - 016

DOWNLIGHT FOR BATHROOM PHILIP GUEST HOUSE CATALOGUE APPROVED 26/8/2014 1/9/2014

MES/TVT - 017

POLE FOR CAMERA LU GIA IN SITE 8 METER POLE TO BE USED CATALOGUE APPROVED 29/8/2014 12/9/2014

MES/TVT - 018

LAVOBO CAESAR MAINSTORE CATALOGUE APPROVED 1/9/2014 1/9/2014

MES/TVT - 019

LAVABO STAINLESS STEEL HA TIEN LAB ROOM AT GREEN HOUSE SHED

CATALOHUE APPROVED 1/9/2014 1/9/2014

MES/TVT - 020

MACHINE AIR CONDITION DAIKIN OFFICE BUILDING

TO BE SURE ALL COMPONENT SUCH AS DUCTS + UNITS FIT IN CEILING AND SPACE

CATALOGUE APPROVED 16/9/2014 18/9/2014

MES/TVT - 021

FAN AIR EXHAUST PANASONIC GUEST HOUSE FV-20AUG TO BE USED CATALOGUE APPROVED 16/9/2014 16/9/2014

MES/TVT - 022

LIGHTNING EQUIPMENT GREEN HOUSE SHED

CATALOGUE APPROVED 22/10/2014 5/11/2014

MES/TVT - 023

SOCKET 3 PHASE SEED PROCESSING SHED

CATALOGUE APPROVED 22/10/2014 23/10/2014

MES/TVT - 024

MOTOR FOR SLIDING SYSTEM MAIN GATE CATALOGUE APPROVED 22/10/2014 3/11/2014

MES/TVT - 025

TV K+ GUEST HOUSE CATALOGUE APPROVED 25/10/2014 25/10/2014

11. HSE REPORT 

Suger
Text Box
10. HSE REPORT

No Description As for this month Accumulated

1 Total Exposure Hour 10672 10580M/H

2 Reported Safety Cases 0

A. Fatalities 0 0

B. Lost Workday Cases 0 0

C. Medical Treatment 0 0

D. Restricted Word Cases 0 0

E. First Aid Cases 0 0

F. Motor Fleet Accidents (Light/ Heavy) 0 0

G. Near Miss Incidents 0 0

H. Fires 0 0

I. Major Property Damage 0 0

3 Total Lost Time Injuries (A + B) 0 0

4 Total Reportable Cases (A + B + C + D) 0 0

5 Total No Lost Time 10672 10580M/H

HSE REPORT

The Safety supervisor of TVT, We compliance with safety policy by the Government. Contractor is implementing all possible safety procedures and tight control of subcontractor's workers to maintain high safety standard at Site. Workers trained in basic safety by monitoring building safety.