LKPP JAKARTA 1 AGUSTUS 2019
RIAD HOREM & SAMUDRA GUNADHARMA
PEKERJAAN KONSTRUKSI RANCANG BANGUN (TERINTEGRASI)
DESIGN & BUILD
2014
FO KUNINGAN KUNING SELATAN
FO PERMATA HIJAU
JLKB PAKET ADAM MALIK
JLKB PAKET KOSTRAD
JLKB PAKET SESKOAL
JLKB PAKET KEBAYORAN LAMA
JLKB PAKET TAMAN PURING
JLKB PAKET TRUNOJOYO
JLKB PAKET SANTA
JLKB PAKET TANDEAN
2016
FO CIPINANG LONTAR
FO BINTARO
FO PANCORAN
UP MAMPANG - KUNINGAN
JLKB PAKET SESKOAL
JLKB PAKET KEBAYORAN LAMA
UP MATARAM
UP KARTINI
RIAD HOREM FOR DINAS BINAMARGA DKI 2014-2016
OJK, JAKARTA 24 JUNI 2019
RIAD HOREM & SAMUDRA GUNADHARMA
PEKERJAAN KONSTRUKSI RANCANG BANGUN (TERINTEGRASI)
DESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
SISTIM KONTRAKTUAL
PELAKSANAAN
PENGAWASAN PENGAWASAN
DISAIN, PELAKSANAAN & PEMELIHARAAN
PENGAWASAN
KONTRAKTUAL
TUNGGAL
DISAIN PEMELIHARAANDISAIN,
PELAKSANAAN & PEMELIHARAAN
SWAKELOLA
SKEMA EKSEKUTIF No. O1
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
DESIGN & BUILD (DB)TERINTEGRASI/ RANCANG BANGUN
BUKAN DESIGN & BUILD
DESIGN & BUILD
1 23
USULAN vs ANGGARAN
1 KONSEP DISAIN
2 DED/ TAHAPAN DED
3 DED/ TAHAPAN DED SELESAI
KESESUAIAN PERENCANAANDENGAN TEKNOLOGI KONSTRUKSI DI LAPANGAN(DESIGN DEVELOPMENT)
DISAIN PELAKSANAAN
MULAI DESAIN DAN PELAKSANAAN
DESIGN & BUILD (DB)TERINTEGRASI/ RANCANG BANGUN
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
SKEMA EKSEKUTIF No. O2
SELESAI DESAIN DAN
PELAKSANAAN
PERENCANAAN DIKERJAKAN BERSAMAAN (TERINTEGRASI) DENGAN PELAKSANAAN TERHINDAR CCO (PERUBAHAN NILAI KONTRAK) DAN PERUBAHAN WAKTU
MULAI PELAKSANAANDBB
DISAIN
PELAKSANAAN/ BUILDPERENCANAAN/ DESIGN
DESIGN – BID – BUILD (DBB) TUNGGAL/ KONVENSIONAL
AKHIRPELAKSANAAN
TENDER/ BID DBB
MULAI PERENCANAAN
AKHIR PERENCANAAN
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
SKEMA EKSEKUTIF No. O3
DESIGN TELAH TERSEDIAPELAKSANAAN TAK TERHINDAR CCO (PERUBAHAN NILAI KONTRAK) DAN PERUBAHAN WAKTU
PENGGUNA JASA
PENYEDIA JASA TERINTEGRASI (KONSTRUKSI+KONSULTAN)
PERENCANA TEKNIS (DESIGN)
SUB KONSULTAN
KONSTRUKSI (CONSTRUCTION)
SUB KONTRAKTOR
|BASIC DESIGN/CRITERIA| |PAGU ANGGARAN| |HARGA
PER SATUAN |PANJANG/LUAS|
|KONSEP DESIGN| |PENAWARAN| |LUMPSUM-
CONTRACT|
|METODE| |FIX PRICE| |TAHAPAN DED| |DED|
|ASBUILT DRAWING|
SKEMA EKSEKUTIF No. O4
DESIGN & BUILD (DB)TERINTEGRASI/ RANCANG BANGUN
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
PENGGUNA JASA
PENYEDIA JASA KONSTRUKSI
SUB KONTRAKTOR
|DED| |HPS| |LUMPSUM|
|HARGASATUAN|
|DED||PENAWARAN| |LUMSUM| |HARGA
SATUAN||SHOPDRAWING|
|METODE||REVIEW/ REVISI DED| |ADENDUM|
SKEMA EKSEKUTIF No. 05
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
DESIGN – BID – BUILD (DBB) TUNGGAL/ KONVENSIONAL
TERSEDIA DESAIN.
SPESIFIKASI
PERUBAHAN WAKTU
MULAI SELESAIPHO/FHO
HAKIKAT PELAKSANAAN KONTRAK MERUPAKAN EKSEKUSI PENGUJIAN KONSEP DESAIN
DILAPANGAN
AKIBAT BASIC/CRITERIA DESIGN BELUM MENYIKAPI KONDISI LAPANGAN MAKA RENTAN TERHADAP PENYESUAIAN WAKTU DAN KETENTUAN PENGGUNA
KONDISI LAPANGAN
MENJADI OUTPUT FISIK
PERUBAHAN KETENTUAN PENGGUNA
PPK, PENYEDIA, TIM PENGENDALI & KONSULTAN
SKEMA EKSEKUTIF No. O6
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
DESIGN & BUILD (DB)TERINTEGRASI/ RANCANG BANGUN
TERSEDIA DESAIN.
SPESIFIKASI
PERUBAHAN WAKTU
MULAI SELESAIPHO/FHO
HAKIKAT PELAKSANAAN KONTRAK MERUPAKAN EKSEKUSI PENGUJIAN DESAIN/ SPESIFIKASI
DILAPANGAN
AKIBAT DESAIN BELUM MENYIKAPI KONDISI LAPANGAN MAKA RENTAN TERHADAP PENYESUAIAN WAKTU DAN BIAYA./CCO
KONDISI LAPANGAN
MENJADI OUTPUT FISIK
PERUBAHAN BIAYA/CCO
PPK, PENYEDIA, TIM PENGENDALI & KONSULTAN
SKEMA EKSEKUTIF No. O7
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
DESIGN – BID – BUILD (DBB) TUNGGAL/ KONVENSIONAL
TENDER▪ BASIC/
CRITERIA DESIGN
▪ KETENTUAN PENGGUNA
▪ NILAI PAGU
PENAWARAN▪ KONSEP
DISAIN▪ PENAWARAN
PENYEDIA (LUMPSUM –FIX PRICED)
1DESIGN DEVELOPMENT
(PENGEMBANGAN DESAIN)
PERUBAHAN KETENTUAN PENGGUNA
KONSEP DISAIN
BASIC/ CRITERIA
DED/ TAHAPAN
34
5
FINAL CONTRACT▪ ASB DRW▪ LUMPSUM –
FIX PRICED
6
NILAI KONTRAK TETAP (LUMPSUM)
2
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
DESIGN & BUILD (DB)TERINTEGRASI/ RANCANG BANGUN
SKEMA EKSEKUTIF No. O8
TENDER▪ DED▪ SPESIFIKASI▪ NILAI PAGU
PENAWARAN▪ PENAWARAN
PENYEDIA▪ LUMPSUM▪ HARGA
SATUAN
1KONDISI LAPANGANPERUBAHAN DESAIN
DED/SPECSHOP DRMC-NOL
CCO
34
5
FINAL CONTRACT▪ ASB DRW▪ LUMPSUM▪ HARGA SAT
6
NILAI KONTRAK TETAP ATAU BERUBAH
2
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
SKEMA EKSEKUTIF No. O9
DESIGN – BID – BUILD (DBB) TUNGGAL/ KONVENSIONAL
STUDI RANCANGAN DISAINPENJELASAN TENDER PELAKSANAAN PEMELIHARAAN
SURVEY RANCANGAN
DISAIN
BASIC DESIGN CRITERIA
NILAI PROYEK/ PAGU ANGGARAN
PENINJAUAN LAPANGAN
SURVEY PELAKSANAAN
MAINTENANCE
START-UP
IMPLEMENTASI
SELESAIPROCUREMENT CONSTRUCTIONKEBUTUHAN
SURVEY STUDY
RANCANGAN
PENJABARAN
BRIEFING KONSEP DISAIN
NILAI PENAWARAN
DED/ TAHAPAN DED
CONSTRUCTION
PRA TENDER PASCA TENDER
KONSULTAN MK
SKEMA EKSEKUTIF No. 10
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
TUGAS DAN TANGGUNG JAWAB
KONSULTAN MK : PRA TENDER – PASCA TENDER
LAMPIRAN EKSEKUTIF No. 11
TIM PEMILIHAN 1/2TAHAPAN DOKUMEN, KEGIATAN & WAKTU
DESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
No DOKUMEN KEGIATAN OLEH WAKTU
1HPSBASIC DESIGN
PENGAJUAN KE SATKER PPK
PERSETUJUAN SATKER
2KAKCRITERIA DESIGN
PENGAJUAN KE PPK TIM TEKNIS
PERSETUJUAN PPK
3 DOKUMEN KUALIFIKASI PENYIAPAN TIM TEKNIS
PESETUJUAN PPK
PENYAMPAIAN TIM TEKNIS
PENGUMUMAN TIM PEMLIHAN
PEMASUKAN PENAWARAN PENYEDIA
EVALUASI TIM PEMILHAN
PENGUMUMAN HASIL EVALUASI TIM PEMILIHAN
MASA SANGGAH TIM PEMILIHAN
LAMPIRAN EKSEKUTIF No. 12
TIM PEMILIHAN 2/2TAHAPAN DOKUMEN, KEGIATAN & WAKTU
DESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
No DOKUMEN KEGIATAN OLEH WAKTU
4 DOKUMEN PEMILIHAN PENGAJUAN KE PPK TIM TEKNIS
PERSETUJUAN PPK
PENYAMPAIAN KE TIM PEMILIHAN/ PENGUMUMAN/UNDANGAN
TIM TEKNIS
UPLOAD TIM PEMILIHAN
PEMBERIAN PENJELASAN TIM PEMILIHAN
PEMASUKAN PENAWARAN PENYEDIA
EVALUASI TIM TEKNIS
PENGUMUMAN HASIL EVALUASI TIM PEMLIHAN
PEMASUKAN PENAWARAN PENYEDIA
MASA SANGGAH TIM PEMILHAN
SPPBJ TIM PEMILIHAN
PENANDATANGAN KONTRAK PPK
LAMPIRAN EKSEKUTIF No. 13
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
KONSULTAN MK TIM PEMILIHANPENYEDIA JASA TEINTEGRASI
SATUAN KERJA
PRA T
ENDER
KAKCRITERIA DESIGNPERHITUNGAN PAGUBASIC DESIGNDRAF DOK KUAL/PML
DOKUMEN KUALIFIKASIDOKUMEN PEMILIHAN
TIM PEMILIHAN 1/6TAHAPAN PRA TENDER, TENDER, KONTRAK & PELAKSANAAN KONTRAK
DESIGN & BUILD
LAMPIRAN EKSEKUTIF No. 14
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
KONSULTAN MK TIM PEMILIHANPENYEDIA JASA TEINTEGRASI
SATUAN KERJA
PENAWARAN TAHAP I
EVALUASI
TENDER
PENAWARAN TAHAP II
GUGUR
TIM PEMILIHAN 2/6TAHAPAN PRA TENDER, TENDER, KONTRAK & PELAKSANAAN KONTRAK
DESIGN & BUILD
LAMPIRAN EKSEKUTIF No. 15
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
KONSULTAN MK TIM PEMILIHANPENYEDIA JASA TEINTEGRASI
SATUAN KERJA
EVALUASI
TENDER
PERINGKAT 1PERINGKAT 2
GUGUR
USULAN PEMENANG PENETAPAN PEMENANG
TIM PEMILIHAN 3/6TAHAPAN PRA TENDER, TENDER, KONTRAK & PELAKSANAAN KONTRAK
DESIGN & BUILD
LAMPIRAN EKSEKUTIF No. 16
TIM PEMILIHAN 4/6TAHAPAN PRA TENDER, TENDER, KONTRAK & PELAKSANAAN KONTRAK
DESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
KONSULTAN MK TIM PEMILIHANPENYEDIA JASA TEINTEGRASI
SATUAN KERJA
PELA
KSANAAN K
ONTRAK
TT KONTRAKSPMK
BA ST LAPANGAN
SURVEI/INVESTIGASI LAPANGAN
(TOPOGRAFI, GEOTEKNIK DLL)
KOORDINASI INT/EKSMOBILISASI DLL
DETAIL PERENCANAAN (BANGUNAN BAWAH, ATAS, PELENGKAP & LINGKUNGAN DLL)
PERIKSAKETENTUAN KRITERIA & SPESIFIKASI
LAMPIRAN EKSEKUTIF No. 17
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
KONSULTAN MK TIM PEMILIHANPENYEDIA JASA TEINTEGRASI
SATUAN KERJA
PELA
KSANAAN K
ONTRAK
MEMENUHIPERSETUJUAN
PELAKSANAAN
PENGAJUAN TERMIN
REQUEST OF WORKS
TIM PEMILIHAN 5/6TAHAPAN PRA TENDER, TENDER, KONTRAK & PELAKSANAAN KONTRAK
DESIGN & BUILD
LAMPIRAN EKSEKUTIF No. 18
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
KONSULTAN MK TIM PEMILIHANPENYEDIA JASA TEINTEGRASI
SATUAN KERJA
PELA
KSANAAN K
ONTRAK PENGENDALIAN
UNIT MUTU DOK PENDUKUNG
MEMENUHI PERSETUJUAN
TERMIN DIBAYAR
FISIK 100% PHO
TIM PEMILIHAN 6/6TAHAPAN PRA TENDER, TENDER, KONTRAK & PELAKSANAAN KONTRAK
DESIGN & BUILD
KEGIATAN & TATA CARADESIGN & BUILD
NO URAIAN TATA CARA
1 PEMILIHAN PENGADAAN RANCANG DAN BANGUN (TERINTEGRASI) DENGAN SPSE
2 METODE PEMILIHAN PELELANGAN TERBATAS/PELELANGAN UMUM.
3 BENTUK DOKUMEN PENGADAAN PRAKUALIFIKASI
4 JENIS KONTRAK LUMP SUM
5 METODE PEMASUKAN PENAWARAN
DUA SAMPUL
6 METODE EVALUASI TEKNIS SISTEM NILAI DENGAN AMBANG BATAS MINIMUM
7 PENETAPAN PEMENANG NILAI TERENDAH DARI KOMBINASI NILAITEKNIS DAN HARGA DENGAN PERBANDINGAN30% (TEKNIS) : 70% (HARGA)
LAMPIRAN EKSEKUTIF No. 19
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
1. KERANGKA ACUAN KERJA2. CRITERIA DESIGN (PEKERJAAN KONSTRUKSI)3. BASIC DESIGN (PEKERJAAN KONSTRUKSI)4. PERHITUNGAN HPS (HARGA SATUAN) JASA KONSULTANSI MANAJEMEN
KONSTRUKSI DAN PENGGUNAAN PAGU ANGGARAN PEKERJAAN KONSTRUKSI DESIGN & BUILD (LUMPSUM)
5. DOKUMEN KUALIFIKASI6. DOKUMEN PEMILIHAN7. FORMAT EVALUASI PENAWARAN
CATATANSEBELUM MELAKUKAN PELELANGAN, POKJA ULP SUDAH MEMPUNYAI JADWAL PELELANGANNYA DAN DOKUMEN YANG DIPERLUKAN ADALAH DARI NO 1 SAMPAI NO 5, SEMENTARA NO 6 DAN NO. 7 DAPAT DISUSULKAN
LAMPIRAN EKSEKUTIF No. 20
DOKUMEN TENDERDESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
▪ LATAR BELAKANG DAN TUJUAN ADANYA KEBUTUHAN PENGADAAN INI
▪ LOKASI DARI PEKERJAAN YANG AKAN DILELANG
▪ JENIS KONTRAK YANG AKAN DILAKSANAKAN (BERDASARKAN CARA PEMBAYARANNYA, PEMBEBANAN TAHUN ANGGARAN, SUMBER PENDANAANNYA DAN JENIS PEKERJAANNYA)
▪ BESARNYA DANA ANGGARAN YANG TERSEDIA
▪ PENGGUNA ANGGARANNYA DAN PEJABAT PEMBUAT KOMITMEN
▪ METODE PELELANGAN YANG AKAN DILAKUKAN DAN WAKTU PELELANGANNYA SERTA WAKTU PELAKSANAANNYA
▪ KUALIFIKASI ATAU KLASIFIKASI DARI PERUSAHAAN YANG IKUT PELELANGAN
▪ PERSONIL YANG DIPERLUKAN MELIPUTI JABATANNYA, TUGAS DAN TANGGUNG JAWABNYA SERTA JUMLAHNYA
▪ PERALATAN YANG MENDUKUNG
LAMPIRAN EKSEKUTIF No. 21
KERANGKA ACUAN KERJA (KAK)DESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
MERUPAKAN STANDAR UKURAN NORMATIF (BATASAN MUTU, DIMENSI DLL) UNTUK MENCAPAI TUJUAN DED :
▪ MUDAH PELAKSANAAN▪ LINGKUNGAN (NYAMAN)▪ EKONOMIS▪ HEMAT ENERJI▪ MUDAH PERAWATAN
LAMPIRAN EKSEKUTIF No. 22
CRITERIA DESIGNDESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
1. PERHITUNGAN HPS (HARGA SATUAN) UNTUK JASA KONSULTANSI MANAJEMEN KONSTRUKSI
2. PENGGUNAAN PAGU ANGGARAN UNTUK PEKERJAAN KONSTRUKSI DESIGN & BUILD (LUMPSUM)
KETERANGAN▪ HARGA SATUAN, MENGACU PADA PERATURAN YANG DIKELUARKAN
OLEH BAPPENAS (PERSONIL)▪ LUMPSUM, PERHITUNGAN PAGU DENGAN MEMBANDINGKAN PADA
PROYEK SEJENIS
LAMPIRAN EKSEKUTIF No. 23
HARGA PERKIRAAN SENDIRI & PAGU ANGGARANDESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
DOKUMEN KUALIFIKASI :MEMBERIKAN BATASAN TERHADAP PERUSAHAAN SESUAI DENGAN KEMAMPUANNYA/ KLASIFIKASINYA
▪ MEMASTIKAN BAHWA PERUSAHAAN TERSEBUT MEMPUNYAI BADAN HUKUM
▪ MEMPUNYAI KEMAMPUAN KEUANGAN▪ MEMPUNYAI PENGALAMAN DALAM BIDANGNYA
LAMPIRAN EKSEKUTIF No. 24
DOKUMEN KUALIFIKASIDESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
1. Umum
2. Pengumuman Prakualifikasi
3. Instruksi Kepada Peserta4. Lembar Data Kualifikasi
5. Bentuk Pakta Integritas
6. Bentuk Formulir Isian Kualifikasi
7. Petunjuk Isian Formulir Kualifikasi
8. Tatacara Evaluasi Kualifikasi
1. Umum
2. Instruksi Kepada Peserta3. Lembar Data Pemilihan
4. Bentuk Dokumen Penawaran5. Bentuk Rancangan Kontrak6. Syarat - Syarat Umum Kontrak
7. Syarat - Syarat Khusus Kontrak
8. Persyaratan Teknis dan Gambar
9. Daftar Kuantitas Keluaran dan Harga
10. Bentuk Dokumen Lain
1. Penawaran Administrasi 2. Penawaran Teknis3. Penawaran Harga
1. Addendum Surat Perjanjian (bila ada)
2. Pokok Perjanjian3. Surat Penawaran 4. Syarat - Syarat Khusus Kontrak
5. Syarat - Syarat Umum Kontrak
6. Persyaratan Teknis dan Gambar
8. Daftar Kuantitas Keluaran dan Harga
8. Dokumen Lainnya
DOKUMEN PEMILIHAN
DOKUMEN KUALIFIKASI
DOKUMEN PENAWARAN
DOKUMEN KONTRAK
LAMPIRAN EKSEKUTIF No. 25
DOKUMEN KUALIFIKASI - KONTRAKDESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
A. PEKERJAAN PERENCANAAN TEKNIS:1. PEKERJAAN PERENCANAAN TEKNIS BERDASARKAN KRITERIA DESAIN YANG
DITETAPKAN DALAM DOKUMEN PEMILIHAN DAN SESUAI LINGKUP PEKERJAAN KONSTRUKSI PADA HURUF B DIBAWAH.
2. DALAM PELAKSANAAN PERENCANAAN TEKNIS JEMBATAN, HARUS DILAKUKAN PEMUTAKHIRAN BERDASARKAN SURVAI DETAIL DAN INVESTIGASI LAPANGAN SEBELUM PELAKSANAAN PEKERJAAN KONSTRUKSI.
B. PEKERJAAN KONSTRUKSI MELIPUTI :1. NAMA PEKERJAAN : .............
2. LOKASI : ........
3. DIMENSI/ UKURAN :
C. SUMBER DANA :1. PEKERJAAN INI DIBIAYAI DARI SUMBER PENDANAAN: ....................... TAHUN
.................. TOTAL PAGU DANA SEBESAR RP. ______________ DENGAN RINCIAN BERIKUT :a. TAHUN 20.... SEBESAR RP. _________________
b. TAHUN 20.... SEBESAR RP. _________________
c. TAHUN 20.... SEBESAR RP. _________________
d. DAN SETERUSNYA .________________________
LAMPIRAN EKSEKUTIF No. 26
SCOPE OF WORKSDESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
SSUK PASAL 27.1.
SEBELUM PELAKSANAAN PEKERJAAN KONSTRUKSI, PENYEDIA JASA HARUSMENYIAPKAN DETAIL DESAIN BERDASARKAN USULAN/PROPOSAL DESAINDALAM PENAWARAN TEKNIS DAN KRITERIA DESAIN YANG DITETAPKAN,SETELAH MELAKUKAN SURVAI DAN INVESTIGASI LAPANGAN SECARADETAIL UNTUK SEMUA PEKERJAAN UTAMA, PELENGKAP DAN PENUNJANGSERTA MEMENUHI SPESIFIKASI TEKNIS YANG DIUSULKAN.
SSUK PASAL 27.2.
PENYEDIA JASA BERTANGGUNGJAWAB DAN MENELITI DENGAN CERMATATAS KEAKURATAN DAN KELENGKAPAN INFORMASI YANG DIGUNAKANDALAM PEMBUATAN DETAIL DESAIN TERMASUK PERHITUNGANNYA. DANSEGALA PERBEDAAN, KESALAHAN ATAU KELALAIAN DALAM PEMBUATANDETAIL DESAIN MERUPAKAN TANGGUNGJAWAB PENYEDIA JASAWALAUPUN TELAH MENDAPATKAN PERSETUJUAN DARI DIREKSI TEKNISDAN/ATAU PPK.
LAMPIRAN EKSEKUTIF No. 27
TANGGUNG JAWAB DESAINDESIGN & BUILD 1/2
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
SSUK PASAL 27.4.SEMUA DESAIN, DOKUMEN TEKNIS DAN PEKERJAAN KONSTRUKSI YANGDISELESAIKAN HARUS MEMENUHI NORMA, STANDAR, PEDOMAN DAN MANUAL(NSPM) SERTA KETENTUAN LINGKUNGAN YANG BERLAKU DAN STANDAR LAINYANG DITETAPKAN DALAM DOKUMEN KONTRAK.
APABILA TERDAPAT STANDAR BARU YANG DIBERLAKUKAN SETELAHPEMASUKAN PENAWARAN, KONTRAKTOR HARUS MENYAMPAIKAN KEPADAPENGGUNA JASA MENGAJUKAN USULAN PERUBAHAN SEBAGAI PEMENUHANSTANDAR DESAIN DENGAN KETENTUAN:
✓ PENGGUNA JASA MENENTUKAN BAHWA BERUBAHAN KETENTUAN TERSEBUTDIPERLUKAN; DAN/ATAU
✓ USULAN UNTUK PERUBAHAN TERSEBUT MERUPAKAN SUATU VARIASIKONTRAK.
LAMPIRAN EKSEKUTIF No. 28
TANGGUNG JAWAB DESAINDESIGN & BUILD 2/2
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
SSUK PASAL 28.1.
PENYEDIA JASA HARUS MELENGKAPI DALAM STRUKTUR ORGANISASINYA SEBAGAI UNIT PENGENDALI MUTU (UPM) YANG MERUPAKAN SUATU UNIT TERTENTU BERANGGOTAKAN PERSONIL YANG MEMENUHI SYARAT, MEMPUNYAI TUGAS UNTUK MENGEVALUASI SECARA TERUS MENERUS PEMENUHAN MUTU PEKERJAAN YANG DISYARATKAN. UNIT PENGENDALI MUTU BERTANGGUNG JAWAB UNTUK MENGHASILKAN DAN MENYAJIKAN INFORMASI YANG DIPERLUKAN OLEH DIREKSI PEKERJAAN MELIPUTIRINCIAN DATA HASIL PENGUJIAN MUTU, KELENGKAPAN INFORMASI STATUS PEKERJAAN, MEMBERIKAN SELURUH INFORMASI YANG DIPERLUKAN TENTANG PENGELOLAAN MUTU PEKERJAAN.
SSUK PASAL 28.4.
UNIT PENGENDALI MUTU HARUS MEMBUAT LAPORAN PENGENDALIAN MUTU KEPADA PPK DAN DIREKSI PEKERJAAN SETIAP PELAKSANAAN DAN PENYELESAIAN PEKERJAAN SEBAGAIMANA TELAH DITENTUKAN DALAM KONTRAK.
LAMPIRAN EKSEKUTIF No. 29
UNIT PENGENDALI MUTUDESIGN & BUILD
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
No ITEM PEKERJAAN RENCANA (BOBOT%)KUMULATIF REALISASI
(BOBOT%)
I Main Item A 20 18
1. Sub item a12. Sub item a2
515
60100 S
II Main Item B 50 38
1. Sub Item b12. Sub Item b23. Sub item b3
102515
200 S60 S20
III Main Item C 30 25
1. Sub Item c12. Sub Item c2
1020
5070 S
Total 100 81
MODEL PEMBOBOTAN PELAKSANAAN KONTRAKDESIGN & BUILD
LAMPIRAN EKSEKUTIF No. 30
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
URAIANPEMBAYARAN/ ANSURAN
KE
KUMULATIF PRESTASI
PEKERJAAN (%)
KUMULATIF PEMBAYARAM
SEBELUM POTONGAN (%)
▪ PEMBAYARAN PRESTASI PEKERJAAN UNTUK KONTRAK LUMP SUM DILAKUKAN DENGAN CARA TERMIJN/ANGSURAN DAN PEMBAYARAN SETIAP TAHUNNYA TIDAK MELEBIHI PAGU DANA INDIKATIF YANG DITETAPKAN.
▪ PEMBAYARAN PRESTASI PEKERJAAN DILAKUKAN DENGAN CARA DENGAN KETENTUAN SEBAGAI BERIKUT
1 3 2
2 7 6
3 12 10
4 20 18
5 28 25
6 36 33
7 45 44
8 55 50
9 65 60
10 75 70
DSTNYA
LAMPIRAN EKSEKUTIF No. 31
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019
MODEL PEMBAYARAN PELAKSANAAN KONTRAKDESIGN & BUILD
SELESAI
RIAD HOREM & SAMUDRA GUNADHARMA UNTUK OJK PEKERJAAN KONSTRUKSI DESIGN & BUILD 2019