    PERHITUNGAN BIAYA SEWA SCAFFOLDING

    Jack base = 4 buah

    Main frame = 2 buah

    Crossbrace = 2 buah 1 set = Rp. 15.000,- / bulan

    Joint pin = 4 buah

    U head = 4 buah

    (Sumber : Wawancara di lapangan)

    Scaffolding pelat lantai :

    Untuk pelat lantai dengan luas ((2,7 m x 3 m) = 8,1 m2) membutuhkan :

    Jack base = 4 buah

    Main frame = 4 buah

    Crossbrace = 4 buah 2 set = Rp. 30.000,- / bulan

    Joint pin = 4 buahU head = 4 buah

    BLOK 1 BLOK 2 BLOK 3

    Lt 1 222 set Lt 1 320 set Lt 1 234 set

    Lt 2 230 set Lt 2 166 set Lt 2 234 set

    Lt 3 230 set Lt mezz 106 set Lt 3 234 set

    Lt atap 230 set Lt 3 234 set Lt atap 234 set

    Lt dek 16 set Lt atap 94 set

    Lt dek 10 set

    Penyewaan :BLOK 1 & BLOK 3 BLOK 2

    Lt 1 240 set Lt 1 320 set

    Lt 2 240 set Lt 2 200 set

    Lt 3 240 set Lt mezz 200 set

    Lt atap 240 set Lt 3 240 set

    Lt dek 240 set Lt atap 50 set

    Lt dek 50 set

    320 set = 1 bulan320 set x Rp. 15.000,- = Rp. 4.800.000,-

    240 set = 8 bulan240 set x (Rp. 15.000,- x 8 bulan) = Rp. 28.800.000,-200 set = 3 bulan200 set x (Rp. 15.000,- x 3 bulan) = Rp. 9.000.000,-

    50 set = 1 bulan50 set x Rp. 15.000,- = Rp. 750.000,-

    Total biaya = Rp. 43.350.000,-

  • 7/21/2019 Perhitungan Sewa Sacffolding

    2/4

    2

    Scaffolding balok :

    Setiap jarak 3,5 m membutuhkan :

    Jack base = 8 buah

    Main frame = 4 buah

    End frame = 4 buah 4 set = Rp. 120.000,- / bulanCrossbrace = 8 buah

    Joint pin = 8 buah

    U head = 8 buah

    BLOK 1 BLOK 2 BLOK 3

    Lt 1 596 set Lt 1 832 set Lt 1 600 set

    Lt 2 728 set Lt 2 628 set Lt 2 600 set

    Lt 3 720 set Lt mezz 552 set Lt 3 580 set

    Lt atap 620 set Lt 3 652 set Lt atap 560 set

    Lt dek 44 set Lt atap 440 set

    Lt dek 28 set

    Penyewaan :

    BLOK 1 & BLOK 3 BLOK 2

    Lt 1 600 set Lt 1 850 set

    Lt 2 730 set Lt 2 650 set

    Lt 3 730 set Lt mezz 650 set

    Lt atap 730 set Lt 3 650 set

    Lt dek 450 set Lt atap 450 set

    Lt dek 450 set

    850 set = 1 bulan850 set x (Rp. 15.000,- x 1 bulan) = Rp. 12.750.000,-

    730 set = 6 bulan730 set x (Rp. 15.000,- x 6 bulan) = Rp. 65.700.000,-

    650 set = 5 bulan650 set x (Rp. 15.000,- x 5 bulan) = Rp. 48.750.000,-

    600 set = 2 bulan600 set x (Rp. 15.000,- x 2 bulan) = Rp. 18.000.000,-

    450 set = 1 bulan450 set x (Rp. 15.000,- x 1 bulan) = Rp. 6.750.000,-

    Total biaya = Rp. 151.950.000,-

  • 7/21/2019 Perhitungan Sewa Sacffolding

    3/4

    3

    Pipe support = 1 buah (Rp. 20.000,- / bulan)

    (Sumber : Wawancara di lapangan)

    Pipe support kolom :

    Satu buah kolom membutuhkan :

    Pipe support = 8 buah (Rp. 160.000,- / bulan)

    BLOK 1 BLOK 2 BLOK 3

    Lt dasar 192 buah Lt dasar 240 buah Lt dasar 144 buah

    Lt 1 192 buah Lt 1 160 buah Lt 1 144 buah

    Lt 2 192 buah Lt 2 160 buah Lt 2 144 buah

    Lt 3 192 buah Lt mezz 112 buah Lt 3 144 buah

    Lt atap 80 buah Lt 3 176 buah

    Lt atap 168 buah

    Penyewaan :

    250 set = 1 bulan 250 buah x (Rp. 20.000,- x 1 bulan) = Rp. 5.000.000,-200 set = 12 bulan 200 buah x (Rp. 20.000,- x 12 bulan) = Rp. 48.000.000,-

    180 set = 7 bulan 180 buah x (Rp. 20.000,- x 7 bulan) = Rp. 25.200.000,-

    Total biaya = Rp. 78.200.000,-

    BLOK 1 & BLOK 3 BLOK 2

    Lt dasar 200 buah Lt dasar 250 buah

    Lt 1 200 buah Lt 1 180 buah

    Lt 2 200 buah Lt 2 180 buah

    Lt 3 200 buah Lt mezz 180 buah

    Lt atap 200 buah Lt 3 180 buah

    Lt atap 180 buah