16
20150320 1 PLANT DESIGN AND ECONOMICS Zahra Maghsoud (3) Process operation Revenues آTotal product cost ل ﺰ ﻨﻪ ﺗ ﻟGross profit ﻧﺎﺧﺎﻟﺺ ﺳﻮدNet profit after taxes, insurance ﺑﻴﻤﻪ و ﻣﺎﻟﻴﺎت ﻛﺴﺮ از ﭘﺲ ﺧﺎﻟﺺ ﺳﻮدDepreciation اﺳﺘﻬﻼكGross profit after depreciation اﺳﺘﻬﻼك ﻛﺴﺮ از ﭘﺲ ﻧﺎﺧﺎﻟﺺ ﺳﻮدNet cash flow ﻧﻘﺪ ﭘﻮل ﺟﺮﻳﺎنRepayment of borrowed capital وام ﺑﺎزﭘﺮداﺧﺖWorking capital ﮔﺮدش در ﺳﺮﻣﺎﻳﻪ ﻣﺤﺼﻮل ﺗﻮﻟﻴﺪTotal capita ﻛﻠﻲﺮﻣﺎﻳﻪ ﻓﺮوش از ﺣﺎﺻﻞﻣﺪآ درل ﻣﺤﺼﻮﻴﺪﻨﻪCash flow for industrial operations ﺳﺮﻣﺎﻳﻪ در ﭘﻮل ﺟﺮﻳﺎن ﺻﻨﻌﺘﻲ ﮔﺬاري2 Capital source ﮔﺬار ﺳﺮﻣﺎﻳﻪ ﭘﻮل ﺻﻨﺪوقOther investments دﻳﮕ ﻫﺎي ﻫﺰﻳﻨﻪBonds and other capital input ﻋﻘﺪ ﻃﺮﻳﻖ از ﺳﺮﻣﺎﻳﻪ آوري ﺟﻤﻊ ﻣﺤﺼﻮﻻت ﻓﺮوش ﭘﻴﺶ و ﻗﺮاردادLoans وامStock ﺳﻬﺎم ﻓﺮوشStockholders' dividends ﺳﻬﺎﻣﺪاران ﺳﻮدFixed capital ﺛﺎﺑﺖ ﺳﺮﻣﺎﻳﻪal

PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

  • Upload
    vantruc

  • View
    227

  • Download
    3

Embed Size (px)

Citation preview

Page 1: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

1

PLANT DESIGN AND ECONOMICS

Zahra Maghsoud(3)

Process operationRevenuesآ

Total product costل ل ت نه ز

Gross profitسود ناخالص

Net profit after taxes, insuranceسود خالص پس از كسر ماليات و بيمه

Depreciationاستهالك

Gross profit after depreciationسود ناخالص پس از كسر استهالك

Net cash flowجريان پول نقد

Repayment of borrowed capital

بازپرداخت وام

Working capitalسرمايه در گردش

توليد محصول

Total ca

pita

سرمايه كلي

درآمد حاصل از فروش هزينه توليد محصول

Cash flow for industrial operations

جريان پول در سرمايه گذاري صنعتي

2

Capital sourceصندوق پول سرمايه گذار

Other investments

هزينه هاي ديگر

Bonds and other capital inputجمع آوري سرمايه از طريق عقد قرارداد و پيش فروش محصوالت

LoansStockوام

فروش سهام

Stockholders' dividends

سود سهامداران

Fixed capitalسرمايه ثابت

alس

Page 2: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

2

FACTORS AFFECTING INVESTMENT ANDPRODUCTION COSTS

3

Sources of Equipment

In many cases standard types of tanks reactors or other In many cases, standard types of tanks, reactors, or other equipment are used, and a substantial reduction in cost can be made by employing idle equipment or by purchasing second‐hand equipment. 

If new equipment must be bought, several independent quotations should be obtained from different manufacturers.

When the specifications are given to the manufacturers, the chances for a low cost estimate are increased if the engineer does not place overly strict limitations on the design.

FACTORS AFFECTING INVESTMENT ANDPRODUCTION COSTS

4

2. Price Fluctuations

In our modern economic society prices may vary widely from one In our modern economic society, prices may vary widely from oneperiod to another, and this factor must be considered when thecosts for an industrial process are determined.

It would obviously be ridiculous to assume that plant operators orsupervisors could be hired today at the same wage rate as in 1995.

Page 3: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

3

FACTORS AFFECTING INVESTMENT ANDPRODUCTION COSTS

5

3. Company Policies

Policies of individual companies have a direct effect on costs For Policies of individual companies have a direct effect on costs. For example, some concerns have particularly strict safety regulations and these must be met in every detail.

Accounting procedures and methods for determining depreciation costs vary among different companies. 

The company policies with reference to labor unions should be considered, because these will affect overtime labor charges and the type of work the operators or other employees can do.

FACTORS AFFECTING INVESTMENT ANDPRODUCTION COSTS

6

4. Operating Time and Rate of Production

The fixed costs remain constant and the total product cost increases as the rate of production increases.

The point where the total product cost equals the total income is known as the break‐even point. 

Page 4: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

4

FACTORS AFFECTING INVESTMENT ANDPRODUCTION COSTS

7

An ideal production  rate for this chemical processing plant would be approximately 450,000 kg/month, because this represents the point of maximum net earnings.

By considering sales demand along with the capacity and operating characteristics of the equipment, the engineer can recommend the production rate and operating schedules that will give the best economic results.

FACTORS AFFECTING INVESTMENT ANDPRODUCTION COSTS

8

5. Governmental Policies

the chemical engineer should understand the effects of the chemical engineer should understand the effects of governmental regulations on costs. 

Each company has its own methods for meeting these regulations, but changes in the laws and alterations in the national and company economic situation require constant surveillance if optimum cost conditions are to be maintained.p

Page 5: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

5

Total capital investment (TCI)

Fixed capital(FCI) Working capital (WC)

I di t tDi t t Indirect costsDirect costs

offsite(OSBL)onsite(ISBL)

•land•Buildings•Yard improvement and service facilities

•Raw materials•Finished products•Salaries& wages•Raw-material purchases•Taxes payable

9

•Purchased equipment•Purchased equipment installation•Instrumentation & control •Piping•Electrical equipment & material

•Engineering& supervision •Construction expenses and contractor’s fee•Legal expenses

Project cost & influence of design decisions 10

As a project proceeds from initial concept through detailed design to start up:

costs begin to be accumulated, particularly once procurement and construction get underway

the ability of the design engineer to influence project cost decreases 

Page 6: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

6

Accuracy of cost estimation

11

The accuracy of an estimate depends on:

The amount of design detail available.g

The accuracy of the cost data available.

The time spent on preparing the estimate.

In the early stages of a project, only an approximate estimate will be required, and justified, by the amount of information available.

The Association for the Advancement of Cost Estimating International (AACE International) is the professional association representing the cost engineering profession in the United States. 

Accuracy of cost estimation

12

AACE International classifies capital cost estimates into five types according to their accuracy and purpose:according to their accuracy and purpose:

1. Order of magnitude±30‐50 %

2. Preliminary±30 %

3. Definitive±10‐15 %

4. Detailed±5 10 %±5‐10 %

5. Check estimates

±5‐10 %

Page 7: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

7

Accuracy of cost estimation

13

1.Order of magnitude estimates (‘‘ballpark estimate,’’ ‘‘guesstimate,’’ ‘‘Class 5 estimate’’), accuracy typically ± 30–50%, 

usually based on the costs of similar processes and requiring essentially no design information. These are used in initial feasibility studies and for screening purposes.

2.Preliminary (‘‘approximate,’’ ‘‘study,’’ ‘‘feasibility,’’ ‘‘Class 4’’) estimates, accuracy typically ± 30%, which are used to make 

coarse choices between design alternatives. They are based on limited cost data and design detail.

Accuracy of cost estimation

14

3.Definitive (‘‘authorization,’’ ‘‘budgeting,’’ ‘‘control,’’ ‘‘Class 3’’) estimates, accuracy typically ± 10–15%. These are used for the 

authorization of funds to proceed with the design to the point where an accurate and more detailed estimate can be made. 

In a contracting organization this type of estimate could be used with a large contingency factor to obtain a price for tendering especially with experience, and where a company has cost data available from similarexperience, and where a company has cost data available from similar projects. Normally, however, an accuracy of about ± 5% would be needed 

and a more detailed estimate would be made, if time permitted. 

Page 8: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

8

Accuracy of cost estimation

15

4.Detailed estimates (‘‘quotation,’’ ‘‘tender,’’ ‘‘firm estimate,’’ ‘‘contractor’s estimate,’’ ‘‘Class 2 estimate’’), accuracy ± 5–10%, which are used for project cost control and estimates for fixed price contracts. 

These are based on the completed (or near complete) process design, firm quotes for equipment, and a detailed breakdown and estimation of the construction cost. By this stage the contractor can usually present a list of all the items that must be purchased and can make a firm commitment to the client.

5.Check estimates (‘‘tender,’’ ‘‘as‐bid,’’ ‘‘Class 1 estimate’’), accuracy ± 5–10%. This is based on a completed design and concluded negotiations on procurement of specialized items and long lead‐time items.

16

ESTIMATING INFORMATION GUIDE

Plant Design and Economics for Chemical Engineers, M. S. Peters and K. D. Timmerhaus, Ch 6, page 161

Page 9: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

9

The cost of making a cost estimate 

17

Improving a cost estimate is itself a cost!

Cost Index

18

The prices of the materials of construction and the costs of labor are subject to inflation. j

Cost indices relate present costs to past costs, and are based on data for labor, material, and energy costs. 

A cost index is merely an index value for a given point in time showing the cost at that time relative to a certain base timeshowing the cost at that time relative to a certain base time.

Page 10: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

10

Cost Index

19

Cost indexes can be used to give a general estimate, but no index can take into account all factors, such as special technological advancements or local conditions.

The common indexes permit fairly accurate estimates if the time period involved is less than 10 years.

Cost Index

20

To get the best estimate, each job should be broken down into its components, and separate indices should be used for labor and p pmaterials. 

It is often more convenient to use the composite indices published for various industries in the trade journals These are weightedfor various industries in the trade journals. These are weighted average indices combining the various components of costs.

Page 11: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

11

Different types of cost indices

21

Journal of Chemical Engineering 

“The Chemical Engineering Plant Cost Index (CEPCI)” or “CE” The Chemical Engineering Plant Cost Index (CEPCI)  or  CE  

“Marshall and Swift index” or “(M&S equipment cost index)”

Oil and Gas Journal

“Nelson‐Farrer Refinery Construction Index” or “NF index”

Journal of Engineering News Record

Construction cost index

Journal of Process Engineering Journal of Process Engineering

Monthly cost indices

The Chemical Engineering Plant Cost Index (CEPCI or CE)

22

The four major components of this index are weighted by percentage in the following manner: 

equipment machinery and supports: 61 equipment, machinery, and supports: 61

erection and installation labor: 22

buildings, materials, and labor: 7 

engineering and supervision: 10 

The major component, equipment: 

fabricated equipment: 37 

process machinery: 14

pipe, valves, and fittings; 20 

process instrument and controls; 7 

Pumps and compressors: 7 

electrical equipment an materials: 5 

Structural supports, insulation, and paint: 10

All are based on 100=1959‐1957

Page 12: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

12

The Chemical Engineering Plant Cost Index (CEPCI)

23

http://www.che.com

24

Example 1: A centrifuge cost $95,000 in 1998. What is the cost of the same centrifuge in third quarter of 2004? Use the CE index.g q

Page 13: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

13

Marshall and Swift cost index

The Marshall and Swift (formerly known as Marshall and Stevens) equipment index is found in each issue of the magazine Chemical 

25

q p gEngineering and is normally divided into two categories:

The all‐industry equipment index

The process‐industry equipment index

The Marshall and Swift indexes are based on an index value of 100 for the year 1926. These indexes take into consideration the cost of machinery and major equipment plus costs for installation, fixtures, tools, office furniture, and other minor equipment.

Nelson‐Farrer Refinery Construction Index

For oil refinery and petrochemicals projects, the Oil and Gas Journal publishes the Nelson‐FarrerR fi C t ti I d (NF i d )

26

Refinery Construction Index (NF index). http://www.ogj.comhttp://www.ogj.com

The Nelson‐Farrer index is on a U.S. Gulf Coast basis rather than U.S. average and is more reliable than the CE index for the types of equipment used in hydrocarbon processing.

base year 1946 =100 The discovery of oil and gas deposits along the coast and offshore, combined with easy access to shipping, have made the Gulf Coast the heart of the U.S. petrochemical industry. The coast contains nearly 4,000 oil platforms.

U.S. Gulf Coast

Page 14: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

14

Construction cost index

The journal of Engineering News Record publishes a monthly construction cost index. 

27

This is based on civil engineering projects. This index has been published since 1904 and is the oldest of all the indices.

For international projects, the journal of Process Engineering publishes monthly cost indices for several countries, including the United States, United Kingdom Japan Australia and many of the EU countriesUnited Kingdom, Japan, Australia, and many of the EU countries.

Use  of cost indices

28

The Chemical Engineering Plant Cost Index is based on four major components, which are weighted as follows:p g

equipment, machinery, and supports: 61

erection and installation labor: 22

buildings, materials, and labor: 7 

engineering and supervision: 10 

Anyone who feels this index does not best represent his situation can make up his own index by weighing the components and/or subcomponents differently.

Page 15: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

15

Example 2

In June, 1969, the indexes for the major components in the Chemical

29

Use  of cost indices

In June, 1969, the indexes for the major components in the Chemical Engineering Plant Design Index were:

equipment, machinery, and supports: 115.9

erection and installation labor: 127.0

buildings, materials, and labor: 121.5 

engineering and supervision: 109.8

Suppose the proposed plant costs consisted mainly of warehouses and construction labor. Assume the ratios are as follows

equipment, machinery, and supports: 35

erection and installation labor: 35

buildings, materials, and labor: 20 

engineering and supervision: 10

CE  cost index (C.I.)equipment, machinery, and supports: 61 erection and installation labor: 22 buildings, materials, and labor: 7  engineering and supervision: 10 

C.I.=120.3 C.I.=118.2

Use  of cost indices

All cost indices should be used with caution and judgment. The longer the period over which the correlation is made, the more 

30

g punreliable the estimate. 

Between 1970 and 1990, prices rose dramatically. Prices then grew at a more or less steady 2 to 3% per year until 2003, when high demand for fuels projects and high energy prices caused another period of steeper price inflation. 

Page 16: PLANT DESIGN AND ECONOMICS - Personal Datamaghsoud.profcms.um.ac.ir/imagesm/1148/course-source/presentatio… · Marshall and Swift cost index The Marshall and Swift (formerly known

2015‐03‐20

16

Use  of cost indices

The same are data plotted relative to the 1990 value of each index.

31

The NF index starts to accelerate ahead of the M&S and CE indices as fuels sector activity led price inflation from 2000 onward.

For use with chemical‐plant investment estimates, the Marshall and Swift equipment cost indexes and the Chemical Engineering plant cost indexes are recommended. 

The Nelson‐Farrar refinery construction index has shown a very large increase with time and should be used with caution and only for refinery construction.