  • 8/2/2019 PPt Llamas Itesm

    1/13

    Dr. Armando Llamas

    Center for Energy Studies

    ITESM Campus [email protected]

    Monterrey, NL april 2, 2004

    Energy price competitiveness

    mailto:[email protected]:[email protected]
  • 8/2/2019 PPt Llamas Itesm

    2/13

    CFE and LFC deliver public service.

    Pemex own generation

    Self supply: Societies created with the only purpose to generate and sell electricity

    between the society partners.

    Independent Power Producer: Private power plant over 30 MW generating

    electricity exclusively to CFE or for exportation.

    References: www.cfe.gob.mx, www.lfc.gob.mx, Prospectiva sector elctrico 2003-2012

    Gross Cap

    MW %CFE 36,971 74.4

    LFC 834.3 1.7

    Pemex 1,822 3.7

    IPP 6,756 13.6

    Selfsupply and/or

    Cogeneration3,316 6.7

    Total (%) 49,699 100.0

    Installed Capacity Mexico 2003

  • 8/2/2019 PPt Llamas Itesm

    3/13

    Fuel oil

    Natural gasCoal

    Diessel

    h = 39.7%

    168,280 GWh

    Reference: Tercer informe de labores - CFE

    Technology '02 - '03Vapor (fuel oil or gas) 76,756

    Dual 14,447

    Coal 17,093

    Combined cycle 24,679

    Turbogas 6,421

    Internal combustion 568

    IPP 28,315Total Fossil 168,280

    Hydro 19,389

    Nuclear 9,340

    Geothermal 5,728

    Wind 6

    Total non-fossil 34,463

    Total 202,743Fossil generation/ Total 83.0%

    Gross generation by technology (GWh)

  • 8/2/2019 PPt Llamas Itesm

    4/13

    TECHNOLOGYGWh Cost

    (million of pesos)

    Unit cost($/kWh)

    Vapor 78,803 48,762$ 0.62$

    CC 22,217 13,820$ 0.62$

    Turbo Gas 6,013 2,882$ 0.48$Diesel 555 811$ 1.46$

    Coal 30,030 7,527$ 0.25$Geothermal 5,396 2,002$ 0.37$

    WInd 7 7$ 1.00$Nuclear 9,747 7,934$ 0.81$

    Hydro 24,277 12,441$ 0.51$Geothermal Projects division 881$

    Civil engineering studies division 663$Generation subdivision 741$

    177,045.00 98,471$ 0.56$

    Independent Power Producers 22,657.00 7,452$ 0.33$

    TOTAL 199,702.00 105,923$ 0.53$

    Generation cost by technology 2002

    Reference: www.informacionpublica.gob.mx

  • 8/2/2019 PPt Llamas Itesm

    5/13

  • 8/2/2019 PPt Llamas Itesm

    6/13

    Ref: www.cfe.gob.mx

    High Voltage (HS) energy price in Northeast Mexico

    (Dec 2003 dollars)

    $0.00

    $0.02

    $0.04

    $0.06

    $0.08

    $0.10

    $0.12

    $0.14

    $0.16

    $0.18

    $0.20

    Dic-01

    Ene-

    02

    Feb-

    02

    Mar-

    02

    Abr-02

    May-0

    2

    Jun-

    02

    Jul-02

    Ago-

    02

    Sep-

    02

    Oct-

    02

    Nov-

    02

    Dic-02

    Ene-

    03

    Feb-

    03

    Mar-

    03

    Abr-03

    May-0

    3

    Jun-

    03

    Jul-03

    Ago-

    03

    Sep-

    03

    Oct-

    03

    Nov-

    03

    Dic-03

    Ene-

    04

    Feb-

    04

    USD/kWh

    $0.00

    $1.00

    $2.00

    $3.00

    $4.00

    $5.00

    $6.00

    USD/kW

    $/kW $/kWh peak $/kWh inter $/kWh base

    4.07 $/kW

    5.17 $/kW

  • 8/2/2019 PPt Llamas Itesm

    7/13

    Ref: www.cfe.gob.mx

    High voltage (HS) NE Nominal Pesos / kWh

    0.40

    0.45

    0.50

    0.55

    0.60

    0.65

    0.70

    0.75

    0.80

    Ene-00

    Abr-00

    Jul-00

    Oct-00

    Ene-01

    Abr-01

    Jul-01

    Oct-01

    Ene-02

    Abr-02

    Jul-02

    Oct-02

    Ene-03

    Abr-03

    Jul-03

    Oct-03

    Ene-04

    pesos/kW

    h

    Load factor = 0.6

  • 8/2/2019 PPt Llamas Itesm

    8/13

    Self supply

    Partner 1 has purchased capacity propperly selected and reasonable wheeling cost

    0.60

    0.80

    1.00

    1.20

    May-03

    Jun-03

    Jul-03

    Ago-03

    Sep-03

    Oct-03

    Nov-03

    Dic-03

    Ene-04

    Feb-04

    $/kWh

    Partner 1 CFEPartner 1 Self supplyPartner 2 CFEPartner 2 Self supply

  • 8/2/2019 PPt Llamas Itesm

    9/13

    Disadvantages of self supply

    No flexiblilty. Contracts are signed for 15 years and they are not easy tomodify.

    Wheeling in medium voltage is extremely expensive. In some cases the

    wheeling fix charge is several times more expensive than the one of

    high voltage.

    Non-written obligation to sign with CFEs union in case wheeling isrequired.

    Natural gas

    0

    2

    4

    6

    8

    10

    1997 1998 1999 2000 2001 2002 2003 2004

    dollars/MBtu

  • 8/2/2019 PPt Llamas Itesm

    10/13

    Natural gas consumption (Mft3/day)

    Total = 4854 Mft3/day

    M = 106

    Ref: Prospectiva

    del mercado de

    gas natural 2003 -

    2012.

    Cuadro 9. p.42

    Transport 2 Mft3/day

    Oil indus try 1994 Mft3/day

    Pemex Petrochemistry 295

    Mft3/dayPrivate sector 965 Mft3/day

    Public electric sector 959

    Mft3/day

    Private electric sector 546Mft3/day

    Residential 71 Mft3/dayServices 22 Mft3/day

  • 8/2/2019 PPt Llamas Itesm

    11/13

    Ref: North America The Energy Picture

    T = 1012

    Production/Demand of Natural gas (Tft3)

    1980 19902000 2010

    0

    5

    10

    15

    20

    25

    30

    Canada Mxico USA Canada Mxico USA Canada Mxico USA Canada Mxico USA

  • 8/2/2019 PPt Llamas Itesm

    12/13

    El Norte, Negocios, 23 marzo 2004

    El Norte, Negocios, 26 marzo 2004

  • 8/2/2019 PPt Llamas Itesm

    13/13

    Problems - Solutions

    Energy prices are not competitive. Mexican

    companies have no choice in the selection of the

    energy supplier. Answer: A well regualtedcompetitive market (Lester Lave) with quick

    response capability to changes and mistakes.

    The growth of the electric sector (public and

    private) is mainly based in combined cycle plants.Answer:Diversification (Oliver Probst).