PRESENTACIÓN EJECUTIVA V1

Embed Size (px)

Citation preview

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    1/13

    1

    1

    CPE Inventory Optimization Project

    NOVEMBER 13, 2008

    NOMBRE MATRICULA SEDE

    Marco Antonio Silva A01048110 CD. JUAREZ

    Javier Snchez Flores A00266037 SALTILLO

    Miguel Casillas Velasco A00343715 COLIMA

    Carlos Sergio Arrieta Serrato A00343714 COLIMA

    INGENIERA DE LA

    PRODUCTIVIDAD

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    2/13

    2

    2

    Inventory Optimization Report

    Points of Discussion

    Definition of the Problem

    Root Causes

    Current Process Map

    Improvement Opportunities

    Suggestions for opportunities found

    Financial Benefits

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    3/13

    3

    3

    Problem Definition

    Shipping costs in May increased $61k due toexcessive overnight shipments of CPE

    Stock requirement analysis is manual, timeconsuming, and cumbersome

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    4/13

    4

    4

    Root Causes

    Unstable Supply Chain Shipping costs in May increased $61k due to excessive

    overnight shipments of CPE> Stock-out due to:

    Delay in approving PO Delay from Vendor in getting the PO in their system Delay in normal vendor shipping time frame

    Re-Stocking analysis is manual, time consuming, andcumbersome Systems provide pieces of data that must be manually manipulated

    in Excel to obtain:> Field shipment orders> Stock replenishment quantity

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    5/13

    5

    5

    Start

    InventoryInformation Systems

    Inventory Gets the reportOf products needed for

    two week period

    SalesSales Person enter

    info. on MSS

    Inv. Ships the productto Market Site

    Inventory depletes stockfrom Warehouse Using

    the Replenishment System

    Inv. Package the Product

    Market Sites Receiveequipment

    Distribution to differentsites

    Market Sites enters equipment intoMSS as equipment Available

    Sites Receive OrdersTo install equipmentField Tech. Change MSS

    Equipment from Available to In Service

    Field Tech. Goes and InstallEquipment Field Tech. Deletes Equipment

    From MSS.

    Nuvox Bills the customer

    $

    Nuvox Bank

    RICH PICTURE OFINVENTORY SYSTEM

    (System # 1 )

    Sub- System 2

    Sub System# 3

    Current Process High Level

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    6/13

    6

    6

    Current Process

    INVENTORY HANDLING PROCESS

    Inventory goesto MSS and pullReports in order

    to find what'sneeded to be

    shipped tomarket sites

    Not Installed Report(NIR)

    TSP ScheduleDrillable Report

    Installed YTD Report(IR)

    Cleaning Reports

    Combine all TSP Reportsinto one

    Called Total TSP

    Conbine Total TSP intoNIR

    Combine IR into NIR

    Rename NIR to CPESummary Report

    CPESummaryReport issent to

    warehouseElectronically

    Warehouseverifies reportwith currentinventory(Manually)

    Warehouseprepares

    material to beshipped

    WarehousecreatesPOs of

    inventorythat will beshipped.

    Warehouseships the

    product/s tomarketsites

    Marketsites

    receiveequipmentand enter it

    into thesystem

    Financialreceives

    POs

    electronically

    POs

    approved?

    Yes

    No

    Request ofinstallation isneeded andMarket site

    assigns serial #to customer POand change theclassifications

    Market siteinstalls

    equipment

    FieldTechnicianreturn to thesystem anddelete partfrom thesystem.

    End

    Warehousereceives

    confirmationelectronically

    Warehousefax the POs

    to Supplier

    SupplierreceivesPOs and

    send back aconfirmationemail with

    delivery time

    Supplierprepares

    and sendsequipment

    Warehousereceives

    equipmentand store it

    Warehousekeeps

    copies ofopen POs

    Confirmationnotice is store

    on thecorresponding

    Open PO

    Warehouseattached

    closes thePO with the

    receiverfrom

    supplier.

    End

    Delay Process

    3 .1 .5 2 40 1 .5 3 .25

    .5 .25 40 .1 .25 40 160 2

    50.35hours/6.3 Days

    261.72hours/32.71

    Days

    Non Valueactivities

    Chance forImprovement

    Non Value, but notaffecting the

    process

    NVA= 3TNVA=3

    VA=0TVA=0

    NVA= 1.5TNVA=247.1

    VA=.5TVA=1.6

    NVA= 160TNVA=245.6

    VA=0TVA=1.1

    NVA= 40TNVA=85.6

    VA=0TVA=1.1

    NVA= 0TNVA=45.6

    VA=.25TVA=1.1

    NVA= 40TNVA=45.5

    VA=0TVA=.85

    NVA= .25TNVA=5.5

    VA=0TVA=.85

    NVA= .1TNVA=45.6

    VA=0TVA=.85

    NVA= 1.75TNVA=5.25

    VA=.75TVA=.85

    NVA= .5TNVA=3.5

    VA=0TVA=.1

    NVA= 0TNVA=3VA=.1TVA=.1

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    7/13

    77

    May situation

    April May June

    103103103 10390 9090 90

    RCP

    Demand

    90 9090 90 20620600

    Supplier Lead time increased 2 weeks.Internal Approval process was delayed 1 week from ournormal 1 week period.

    This causes overnight shipments from China and to US market

    Balance -103-206-1030000 0

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    8/13

    88

    Improvement Opportunities

    Quicker PO approval process

    Automatic shipping and re-stocking analysis

    Decrease supplier lead time

    Utilize bar code scanners to integrate with

    inventory system

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    9/13

    99

    Improvement Actions

    Develop fully automated daily report to provide re-stock amounts and field shipping details. Field Shipping detail:

    > Order #> CLLI> TSP Date> Market> Equipment

    Re-Stock Amounts> Part Number> Quantity

    Enhance CPE approval process. Decrease time from PO request to submission to Cisco:

    > Provide Harold with unilateral authority to replenish stock to approved stock levels Generate daily/weekly reports to advise executive management of capital commitment

    > Obtain SLAs from Operations/Finance approval management to work Pos quickly

    Special capital purchase circumstances, such as TitleMax, will be handled ICB

    Pursue new Cisco supply strategy to reduce lead time to delivery. Provide minimum of an 8 week notice for shipping forecasts

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    10/13

    1010

    Why Safety Stock is important

    April May June

    103103103 10390 9090 90

    RCP

    Demand

    90 9090 90 10310300

    Balance 0077180180180 0

    Safety Stock

    180

    180 26

    2 weeks ahead we see a change in demand and we place an order to compensate safetystock. 26

    Supplier has been committed to supply every week. But what if they fail? We place and

    order for material taken from safety stock.

    What if they fail another week. We use remaining stock plus the one that came in.

    This Model shows that we are covered for two week period.

    StockRecovery

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    11/13

    1111

    Contingency Plans

    We considered the possibility of alternative company tostock equipment. Based of annual cost we did notconsidered beneficial.

    We will have safety stock of 3 weeks for the following

    products:1. 2431-8

    2. 2431-16

    3. vwic-1mft-t1

    4. vwic-2mft-t15. 2432-24

    Safety stock will be distributed as follows:2 weeks on ware house1 week on the field.

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    12/13

    1212

    New Inventory Process

    Sub-System # 3

    Start

    Inv. Goes to theSystem and gets areport of what is

    needed to ship forthe market sites

    Inv. Ships productsand enters data into

    Inventory ControlSystem (ExcelSpreadsheet)

    Is there any productcolored Red?

    Create a PO forwhat is indicated inorder to replenish

    Safety stock

    Save the documentand exit.

    No

    Yes

    Fax PO to VendorAnd notify

    Financial of

    purchases made.

    Monitor POs for

    fast delivery.

    ReceiveEquipment and

    store it

    Update InventoryControl System

    End

    END

    Note: This procedure assumes

    Weekly shipments from Cisco.

  • 8/3/2019 PRESENTACIN EJECUTIVA V1.

    13/13

    1313

    Summary

    Enhanced PO approval process Automated Field distribution reporting

    Eliminated manual labor increasing accuracy

    Automated the re-stock analysis system Optimized stock levels

    Minimized capital commitment

    Decreased supplier lead time