Upload
nirav-parmar
View
222
Download
0
Embed Size (px)
Citation preview
7/31/2019 Pro Report Sidhi cement
1/52
GUJRAT SIDDHI CEMENT LIMITED
INDEX
Sr Subject Page
1 Acknowledgement 2
2 Introduction 3
3 Production flow Diagram 6
4 Mines 7
5 Crusher 11
6 Stacker & Declaimer 14
7 Rawmill 16
8 C.F Silo 18
9 Preheater 19
1
0
Kiln 24
1
1
Cooler 28
12
Clinker storage 29
1
3
Cement mill 32
1 ESP 33
1
7/31/2019 Pro Report Sidhi cement
2/52
GUJRAT SIDDHI CEMENT LIMITED
4
15 Packing plant 34
16
Instrumentation used incement plant.
36
1
7
Plant Interlocking diagram 48
1
8
Heartily thanks to 51
2
7/31/2019 Pro Report Sidhi cement
3/52
GUJRAT SIDDHI CEMENT LIMITED
ACKNOWLEDGEMENT
This is the acknowledgement for those
personalities who have helped me directly or indirectly
to organize my training, helped me during my training
period and to make my training report. I am alsothankful to all staff members of automation division,
who have helped me to clear my doubts & concepts.
3
7/31/2019 Pro Report Sidhi cement
4/52
7/31/2019 Pro Report Sidhi cement
5/52
GUJRAT SIDDHI CEMENT LIMITED
Preheater
Kiln
Cooler
Clinker Storage
Cement Mill Clinker yard
Cement Silo
Packing Plant
5
7/31/2019 Pro Report Sidhi cement
6/52
GUJRAT SIDDHI CEMENT LIMITED
6
7/31/2019 Pro Report Sidhi cement
7/52
GUJRAT SIDDHI CEMENT LIMITED
7
7/31/2019 Pro Report Sidhi cement
8/52
GUJRAT SIDDHI CEMENT LIMITED
2 MINES####################################################
2.1 INTRODUCTION:
The lime stone
2.2
MINING:
Here in the GSCL Lime Stone Mine mining is done in two
methods:
1. Conventional Mining
2. Surface Mining
1. CONVENTIONAL MINING
These explosives and detonators are stored is called the
magazine. First of all the top soil is removed with the bulldozer.
This soil is transported to the mines only when ordered, otherwise it
is heaped at the mines.
The drilling machine is used to make holes upto the depth of
10 m and 150 mm diameter. It also takes samples of soil at various
levels for the assessment of the soil. According to the kind of earth
i.e., soft or hard the placing of explosive is decided.
If the soft earth is charge with an explosive, then the gases
pass through the porous soil and hole is not blasted, hence
explosive is wasted.
8
7/31/2019 Pro Report Sidhi cement
9/52
GUJRAT SIDDHI CEMENT LIMITED
It is very important to ram and compact the earth after piling
explosive. Otherwise it might explode in the air. Even the rock
develops the cracks, so if the drilling machine is used in the area it
might get stuck up in crack.
The blast explosive is of 125 mm and 83 mm Diameter. It is
class 2 explosive weighting 6.25 kg. The 83 mm Diameter
explosive is Aqua dyne, also manufactured by IDL Chemicals. It
has weigh of 2.77 kg.
The explosive have following compositions:Nitrate - 60 %
Ag Powder - 10 %
Water - 10 %
Nitroglycerine - 20 %
These explosive are Nitroglycerine based explosive and they
are in a thick paste form and contains salver. The cost is Rs.18/kg.
When we observed the blasting there were 19 holes of depth
10 m each, so 35x15x10x1.5 tons of limestone is acquired against
the usage of 1500 kg of explosive used.
Here the holes blasting affective area are 34 m long and 15 m
wide. The power factor ranges from 3 to 5 which are consideredless.
A detonating chord is used to connect these holes to each
other. These are made up to Penta Ethylene Tetra Nitrate coater
with plastic. A one meter long chord contains 10 gm of PETN. This
is used in a chord form so that the contact is not broken. It fires at
the rate of 6000 m/sec.
9
7/31/2019 Pro Report Sidhi cement
10/52
GUJRAT SIDDHI CEMENT LIMITED
A detonator is used to connect these holes and complete the
circuit. The wire is made of steel which is covered with plastic.
This wire is ignited. An Ohms meter is used to check whether the
circuit is completed or not. Then the dynamo is charged and the redlight on it lights frequently and fire button is pressed, and blast
occurs.
The place where the stone and it is 60 cm thick stacking of
explosives and detonators are done separately. In the case of
accidents if explosives ignite, they just burn, but if detonators
ignite, they explode.
The explosives are stacked on a wooden platform, 6 inch
above the ground, so that no harm is caused by rats also. Special
care is taken not to use any iron material in the magazine, instead of
iron, Cu is used. The stacking is done only upto 1.2 m. A red line is
marked almost about 2.5 m above the ground which marks themaximum storage capacity. A passage is left between the stacks, so
that if one starts burning the others might be removed.
These magazines have special Z type ventilators for the
purpose of security. These are also made from Cu.
The vehicle used for carrying the explosives is made from Al.It has a partition between back part and front part and also a
silencer in front, so there will not any chance of fire.
2. SURFACE MINING:
10
7/31/2019 Pro Report Sidhi cement
11/52
GUJRAT SIDDHI CEMENT LIMITED
Mining lime stone with surface miner is of very recent origin
in India and it has got definite advantages over conventional
mining.
First of all the mining with surface miner eliminates totally
drilling and blasting. Surface miner performs in site crushing while
mining, which cases out the problems encountered in transportation
of limestone to crusher.
The system needs no separate loading arrangement and the
machine loads the material directly to he trucks or dumpers. Theneed for haul road maintenance is drastically reduced, since the
mine surface with the surface miner is very gradual and uniform.
The biggest advantage with surface miner is that it eliminates
primary crushing, since the product size will be maximum 150 mm
and 50 % will be less than 75 mm.
Surface miner provides scope of selective mining and hence
gives greater opportunity for exploiting the reserve where
contamination is more and where conventional mining is not
possible. The elimination of drilling and blasting provides
environmental friendly mining operations with utmost safety for the
mine operators.
11
7/31/2019 Pro Report Sidhi cement
12/52
GUJRAT SIDDHI CEMENT LIMITED
3 CRUSHER##########################################
Apron Feeder
It comprises of specially fabricated frame on which two heavy
duty endless link assemblies are wounded. The apron flights are of
rolled steels and are bolted on the chains and are used for conveying
the material. The drive arrangement is a D.C. motor and a gear ox
connected to the drive shaft of the apron feeder. The link assembly
and the flight are supported and guided on the top of the frame by
deck rollers. The drive shaft has two sprocket hub assemblies which
mesh with the link assemblies and drive the apron feeder. On the
return end of the apron conveyor is the tail wheel assembly for
guiding the link assembly.
1. Scraper Chain Conveyor
The scraper conveyor consists of a trough assembly within
with a scraper chain assembly travels. The round link chain and
fabricated scraper flight runs on scraper trough while conveying the
spillage load on trough support assemble while returning.
Actual conveying of spillage is done by the bottom strand by
scraping material alone the trough bottom plate. The drive
arrangement consists of an A.C. electric motor and shaft mounted
12
7/31/2019 Pro Report Sidhi cement
13/52
GUJRAT SIDDHI CEMENT LIMITED
reduction gear box which directly rotates the drive shaft. At the rear
end, the scraper tail wheel assembly guides the round ling chain
assembly.
2. Impactor
The crusher is Impactor Cursher. Crushing is done by impact
and it is a dynamic operation.
The main size reduction is carried out by striking i.e., by
impact of the impeller bars to the crusher feed. The purpose of thebreaker plates arranged inside crusher is to function as deflecting
plated. The material thrown against them is reflected back into
crushing compartment, where it is again hit by the impeller bars,
until it leaves the crusher through slot between rotor and lower edge
of breaker plate.
By the impact of material against roller plates and materialgets crushed and then material is supposed to crush by chunking
against each other. The material is ground to the size of 50-60 mm
in first phase.
There are three types of impact plates
1: front impact2: rear impact
3: grinding lower
13
7/31/2019 Pro Report Sidhi cement
14/52
GUJRAT SIDDHI CEMENT LIMITED
CONVEYOR BELT:
The crushed material from is convening through many
numbers of belt conveyor.
The material is feeded to stacker through conveyor BC 4A
and BC 4B.
14
7/31/2019 Pro Report Sidhi cement
15/52
GUJRAT SIDDHI CEMENT LIMITED
3 STACKER & RECLAIMER####################################################
3.1 STACKER :
The stacker type SU is used to stack raw material at the yard.
The stacker runs on the rails fixed at the right hand side of the pile
in longitudinal direction. The material are stacked with a certainhomogenizing effect normally according to Chevron method or
longitudinal stack piling method, with help of Boom stacker.
Chevron method is a roof like stock piling method.
The stacker consists of two main parts:
1. Tripper
2. Jib
1. TRIPPER:
Tripper and jibs are linked together and are provided with
RBCs. For the traveling of stacker four drive motors are provided
which are attached with jibs rollers through gear boxes. The tripperis fitted with four wheels which are mounted in wheel casing.
15
7/31/2019 Pro Report Sidhi cement
16/52
GUJRAT SIDDHI CEMENT LIMITED
1. JIB:
The stacker consists of a mobile rotable frame and a stacker
capable of lifting in the vertical plane. The hydraulic equipmentserves to move the stacker jib in step from the lower to the upper
working position. While the stacker lift the stacker jib according to
the height of the pile.
3.2 RECLAIMER:
The bridge scraper is used for homogenization of particular
materials at longitudinal store and for conveyance of material from
piles to outgoing conveyor belt.
Reclaimer has a long scrapper chain through which
homogenized material is transported to outgoing conveyor. Harrow
carriage has cross conveyors on it and cross conveyors have
horrows on it. Horrows move horizontally by horrow carriage. The
horrows cut the stack horizontally and material falls down and from
the stacker chain material gets collected. The scrapper chain moves
ahead and material comes on conveyor belt and further goes to
additive silos.
Thus, reclaimer has an important role for homogenization ofmaterial. And it helps to achieve good quality of final product.
16
7/31/2019 Pro Report Sidhi cement
17/52
GUJRAT SIDDHI CEMENT LIMITED
4 RAW MILL####################################################
4.1 INTRODUCTION:
Lime stone, clay, Iron ore fed into mill. The chemical
composition of raw materials is controlled by computer calculations
based on analyses of raw materials, as well as actual amount of
compositions of meal in the homogenizing silo.
During transport to mill inlet, magnetic objects are removed by
a magnetic separator, which is mounted over belt conveyor. Metal
detectors are also built in as further protection. If a metal is
detected, a pneumatically operated gate is activated for discharge of
a portion of materials containing metal piece. Another metal
detector is placed near box feeder, where belt stops for manualremoval if a metal is detected.
The box feeder at mill inlet operates as a buffer and as an air
sluice to reduce false air intake. After box feeder, raw material
drops on rotary grinding table. Here, they are thrown under rollers
by rotary movement of table, and ground. The grinding table is
driven by mill main motor.
The material might contains some moisture upto 4%. This is
dried by hot kiln exit gases supplied through nozzle ring
surrounding grinding table.
The reflected material from mill is returned to mill inlet. The
ground and dried materials i.e., raw meal are carried by air flow to
17
7/31/2019 Pro Report Sidhi cement
18/52
GUJRAT SIDDHI CEMENT LIMITED
dynamic separator. Here, coarse particles are returned to grinding
table while finer particles pass for separator in dedusting cyclones.
There are a number of oil pumps for Lubrication and cooling
of gr unit and bearing of grinding table. Grinding pressure between
three rollers and grinding table. A constant and correct lubrication
of bearing in three rollers.
There are nozzles installed in front of rollers and on grinding
table, for use when temperature or grinding process makes it
necessary. Here, in raw mill hot gas blow is taken from kiln string.It helps material to dry and thus to less moisture content. Yet
moisture content remains 0.5%, which is necessary for easy
operation.
The mill is automatically stopped when very strong vibrations
occur. The air flow to mill is supplied by fan. A gas recirculation
duct with damper is also installed to ensure sufficient constant air
flow. The air from mill fan is drawn through ESP.
The raw meal produced is carried by fluxosides and elevators
to C.F. silo for storage. The dust precipitated in ESP and
transported to C.F. silo.
The most important feature of raw mill is that instead of balls,it has rollers. There are three rollers of 50 tons each around centre
shaft. The production of a ball mill cant exceed more than 150
tons, where as the kiln needs 450 tons of raw meal. The production
of raw mill is 500 tons/hours.
18
7/31/2019 Pro Report Sidhi cement
19/52
GUJRAT SIDDHI CEMENT LIMITED
CONTROLLED FLOW SILO :
FLS have developed a new, continuously operated silo for
blending and storage of cement raw mix, called C.F. silo. It extractsmaterial simultaneously at different rates from a number of outlets
in silo bottom.
The C.F. silo bottom is divided into seven identical hexagonal
sectors. Each of these sectors is divided into six triangular sub
sectors. Thus, the bottom consists of a total of 42 sub sectors. These
sub sectors represent 42 individual areas from which are provided
with aerating units. These 42 separate sub sectors represent 42
individual areas from which material can be extracted accurately to
a predetermined program.
In actual operation, homogenization is performed by using
three of seven discharge outlets simultaneously, each bloweraerating only one sub sector at a time.
The raw meal flow stream from extraction points of part silos
is then blended in a tank placed after silo.
19
7/31/2019 Pro Report Sidhi cement
20/52
GUJRAT SIDDHI CEMENT LIMITED
5 PRE-HEATER####################################################
5.1 PREHEATER AND CALCINER:
A decisive factor in heat economy of cement dry production process
was development of preheater. With this, it was possible to obtain very low
exit gas temperature of about 250oC which were not attainable before.
ADVANTAGESOF PREHEATER:
The kiln dimensions can be considerably reduced.
The calciner can be supplied with combustion air from clinker
cooler at a temperature of approximately 900oC. Since control
devices are located in gas stream behind preheater.
The process control allows for a suitable margin of safety
against overheating, even at a calciner stage of 90-95%.
The high degree of calcinations and regular feeding of kiln
ensure stable kiln operation without kiln upset conditions.
The characteristic feature of calciner is through blending of
raw mix and fuel prior to introduction of combustion air and
subsequent initiating of combustion process. The combustion air isdrawn from clinker cooler at a temperature of about 900oC. The air
flows from inlet to outlet of calciner, with only a low pressure drop.
The heat generated in calciner is utilized partly to raise raw
mixture temperature to calcining level and to implement actual
calcining process. The preheater here has a double string-kiln string
20
7/31/2019 Pro Report Sidhi cement
21/52
GUJRAT SIDDHI CEMENT LIMITED
and calciner string 6-stage preheater with low pressure type
cyclones.
Kiln string: 3x6 m + 3x6.3 m cyclone.
Calcining string: 1x2x5.4 m + 1x7.5 m + 2x7.8 m + 2x8 m
By using separate strings for kiln and calciner important
operational advantage of independent and accurate draught control
is obtained.
The raw meal feed is extracted from the C.F. silo into feed bin.The feed control is based on schenck impact weigher concept. The
feed bin is placed on load cells.
After the feeding system, raw meal is transported to the
preheater inlet by means of elevators and air slides. At preheater
inlet, feed is split into two preheater strings in such a way that
outlet temperatures are equalized.
The preheater is operating as a counter current heat exchanger
with raw meal passing downwards by gravity and air going
upwards by the INDUCED DRAUGHT (ID) fans.
After fifth stage of the calciner string and sixth stage of kilnstring, combined raw meal enters calciner vessel. Here, about 55%
of fuel is fired. The combustion for the calciner is hot atmosphere
air drawn from coolax cooler through a separate tertiary air duct
mixed with combustion has from kiln. The calciner is designed for
a gas retention time of more than 3 seconds. In calciner, raw meal
will be calcined to about 90-95%.
21
7/31/2019 Pro Report Sidhi cement
22/52
GUJRAT SIDDHI CEMENT LIMITED
The material from calciner is routed onwards to four cyclone
stage of calciner string from where it slides into kiln.
Part of gases leaving top stage of preheater cyclones is taken toraw mill for drying and transporting raw material before it is taken
to bag house.
5.2 BAG HOUSE:
Reversible air bag house has an important role to deal with
environmental pollution problems. As the whole pre heater system
works on the negative draft system by ID Fans, the air goes upward
direction.
These gases contains material or particle form material and if
they are directly send or vented out on the air, then pollution
problems will occur and even lot of material loss will be there in the
manufacturing process, so it is very necessary to do something with
this.
The system consists of a sixteen compartments bag houses
with associated safety device.
Support structures By using separate strings for kiln and
calciner important operational advantage of independent and
accurate draught control is obtained.
The raw meal feed is extracted from the C.F. silo into feed bin.
The feed control is based on schenck impact weigher concept. The
feed bin is placed on load cells.
22
7/31/2019 Pro Report Sidhi cement
23/52
GUJRAT SIDDHI CEMENT LIMITED
After the feeding system, raw meal is transported to the
preheater inlet by means of elevators and air slides. At preheater
inlet, feed is split into two preheater strings in such a way that
outlet temperatures are equalized.
The pre heater is operating as a counter current heat exchanger
with raw meal passing downwards by gravity and air going
upwards by the INDUCED DRAUGHT (ID) fans.
After fifth stage of the calciner string and sixth stage of kiln
string, combined raw meal enters calciner vessel. Here, about 55%of fuel is fired. The combustion for the calciner is hot atmosphere
air drawn from coolax cooler through a separate tertiary air duct
mixed with combustion has from kiln. The calciner is designed for
a gas retention time of more than 3 seconds. In calciner, raw meal
will be calcined to about 90-95%.
The material from calciner is routed onwards to sixth cyclone
stage of calciner string from where it slides into kiln.
Part of gases leaving top stage of preheater cyclones is taken to
raw mill for drying and transporting raw material before it is taken
to bag house.
These gases contains material or particle form material and ifthey are directly send or vented out on the air, then pollution
problems will occur and even lot of material loss will be there in the
manufacturing process, so it is very necessary to do something with
this.
Reversible air bag house has an important role to deal with
environmental pollution problems. As the whole preheater system
23
7/31/2019 Pro Report Sidhi cement
24/52
GUJRAT SIDDHI CEMENT LIMITED
works on the negative draft system by ID Fans, the air goes upward
direction.
24
7/31/2019 Pro Report Sidhi cement
25/52
GUJRAT SIDDHI CEMENT LIMITED
6 KILN####################################################
6.1 INTRODUCTION:
The kiln is 75 m long and it have 4.75 m diameter. The kiln is
supported on three types of 2 rollers each. It rotates at a speed of 3
to 4 rpm. The burning zone temperature in kiln is around 1400-
1500oC. Pulverized coal is used as fuel in kiln and calciner. The
fuel supply rate to kiln installation is determined on basis of an
evaluation of clinker quality and current status of kiln.
The exit gas analysis is done for evaluation of combustion
process. The smoke gases must not contain any unburnt substances
i.e., C or Co. They may cause fire and also waste latent heat of
unburnt part of gases. A certain surplus air is supplied during thecombustion process, because of inadequate air is supplied, smoke
may contain unburnt gases.
There are alarm limits set up to monitor CO and O2 levels in
exist gases. If due to any reason there is a blockage in cyclones, kiln
is shut down.
The lubrication between supporting rollers and kiln type must
be provided by means of dry graphite lubrication. Providing an oil
bath can prove fatal as kiln is almost floating in air.
Usually refractory lining of kiln is replaced if the thickness of
bricks is reduces to half of its original size due to wear. Hence, kiln
shell must not be overheated. If kiln shell temperature rises above
25
7/31/2019 Pro Report Sidhi cement
26/52
GUJRAT SIDDHI CEMENT LIMITED
400-500oC, affected area must be cooled by means of fans. There
are 14 fans for this purpose.
In event of a further rise in temperature kiln must be shut
down for a repair of lining. A radiation pyrometer (scanner) has
been installed for purpose of checking condition of kiln lining
during operation.
If there are any hot spots observed, kiln motor is run at lowest
speed until temperature of hot spot has been reduced. In burning
zone, the temperature reaches upto 1400oC and clinkerization
occurs.
BURNING PROCESSIN KILN:
For burning purpose firing is done in kiln. The firing is done
through nozzle, coal is fired, reaching temperature of flame upto
1800oC and maintaining temperature in kiln upto 1400-1500oC of
material.
KILN SPEED:
Slowing kiln will heat kiln up through out its length. It will
also increase draft, which will tend to reduce rate of heating in
burning zone and increase temperature at feed end.
Speeding kiln up will have opposite effect. When a kiln is
slowed down for longer period of time, increase in draft should be
controlled by regulating damper, to avoid overheating of feed end,
fuel rate is decreased.
26
7/31/2019 Pro Report Sidhi cement
27/52
GUJRAT SIDDHI CEMENT LIMITED
The kiln should be controlled by change in fuel rate, as sight
increase in fuel which is not enough to overheat burning zone will,
if left on long enough, heat up feed end and correct slowly dropping
back end temperature.
CHEMICAL PROCEDURE:
During burning and decarbonation of carbonates of Mg and Ca
and removal constitutional water, there are schematically three
consecutive stage of clinker mineral formation. During burning of
first stage upto 990oC all aluminium oxide reacts with lime,generating monocalcium alluminate silica also starts to combine
with lime generating dicalcium silicate. At this phase of clinker
compounds dicalcium silicate concentration is low.
At second stage of formation, when the material is heated to a
range from 1190oC to 1400oC, monocalcium alluminate formed
during first stage is further saturated with lime reacts with iron
oxide creating dicalcium alluminoferrit which is also called
browmmillerite. Formation of dicalcium silicate which started first
stage is now being completed.
At third stage, material reaches temperature above 1285oC, at
this stage of clinker formation, known exothermal effect occurs,which produces generally 120-150 kcal/kg clinker. The rapid
heating of material by this effect causes clinker to behave in this
kiln section similar to fluidized material, thus increasing the
transport velocity of material which can disturb the regular kiln
operation. The partially fused condition of material permits one part
of dicalcium silicate to be saturated with remainder of the
27
7/31/2019 Pro Report Sidhi cement
28/52
GUJRAT SIDDHI CEMENT LIMITED
uncombined lime, and thus be converted to tricalcium silicate. The
formation of clinker is completed with third stage.
28
7/31/2019 Pro Report Sidhi cement
29/52
GUJRAT SIDDHI CEMENT LIMITED
7 COOLER
####################################################
7.1 COOLER:
The cooler receives approximately 145oC. Hot clinker from
rotary kiln, cooling clinker down to a temperature which is
approximately 80oC at a production of 6500 t/day.
Some of thermal energy contained in clinker is simultaneously
recuperated. The thermal energy is transmitted to cooling air which
is subsequently utilized in kiln and calciner.
Grate-1 is designed as CFG system while grate 2 and 3 are
designed as RFT system. From kiln outlet, clinker drops down onto
the inclined grate plates, latter being alternately stationary andmoveable.
CONTROLLED FLOW GRATE:
The airstreams to first grates is very powerful so that clinker is
well distributed across the entire width of the grates. This will
prevent clinker from being backed together at very hightemperature.
The air flow is adjusted so that clinker is kept bubbling on
surface of layer. Hence, heat recuperation will be optimized.
A controlled flow means that air is fed to grates, individually
controlled to smaller units of grate. This is accomplished by means
29
7/31/2019 Pro Report Sidhi cement
30/52
7/31/2019 Pro Report Sidhi cement
31/52
GUJRAT SIDDHI CEMENT LIMITED
many cases, high temperature of clinker leaving cooler does not
allow direct grinding, because hot clinker causes high grinding
temperatures, which impair not only mill operation but also cement
quality so, far cooling and as a production buffer clinker is stored invarious storage facilities.
The storage time of a good quality clinker, stored in protected
facilities does not influence grinding process nor the quality of
cement. Even clinker stored for many years in dead space of clinker
holes did not show a drop in quality.
Here, for purpose of clinker storage, they have a clinker yard
erected with aluminium sheets and a clinker silo of R.C.C. The
bottom diameter of silo is 80mts and capacity is 400,000 tons. From
the clinker yard, it is taken to cement mill with help of trucks,
whereas from silo, it is taken via conveyor belt, clinker is also
stored in open space. Size of clinker is 2 to 25mm.
31
7/31/2019 Pro Report Sidhi cement
32/52
GUJRAT SIDDHI CEMENT LIMITED
32
7/31/2019 Pro Report Sidhi cement
33/52
GUJRAT SIDDHI CEMENT LIMITED
8 CMENT MILL
####################################################
8.1 INTRODUCTION:
Cement clinker and 2-5% raw gypsum is ground together to
form cement. The purpose of grinding mills:-
Creation of larger reactive surface, so that clinkerminerals can react with water.
Controlling of setting properties of cement by adding
gypsum.
At L&T, there are four cement mills of capacity 133 t/hr. It
consists of two chambers divided by double wall. This wall allows
particles of 4 mm size to pass through. About 27 % of volumeconsists of grinding media. The first chambers has high chrome ball
of 60 to 90 mm diameter whereas second chamber has 15-20 mm
diameter high chrome balls In first chamber grinding takes place
due to impact and in second due to attrition. The product is taken to
air separator where coarse particle are recirculated to mill. The mill
converts majority of energy input into heat. Gypsum is dehydratedat 130oC at high temperature. Gypsum loses its property as cement
setting retarded and becomes false set cement. Hence temperature
inside mill is 70-80oC. For this water is injected into hottest part of
mill where it evaporates instantly. Water is carried into mill by
compressed air through a simple nozzle which breaks up water into
very small drops; from where material goes to air separator.
33
7/31/2019 Pro Report Sidhi cement
34/52
GUJRAT SIDDHI CEMENT LIMITED
8.2 ELECTOSTATIC PREICIPITATOR:
In plate type electric precipitator, only electrical precipitation
is employed. This ESP is used after and Cement Mill.
In addition to precipitation by action of the electrical dust
collection also precipitation of a certain quantity of dust particle by
action of gravity as well as direction and by impact. During the
elimination of every supply, the electrical precipitator works as thedust settling chamber with collection of 30 to 70 %.
The size and velocity with which the dust is attracted by the
collecting electrodes is of importance for the collection efficiency.
High resistivity and is difficult to remove from the collecting
electrodes and often it may cause a detrimental operating condition
known as return throw of sparks or as back ionization.
ESP is less efficient than bag house, as it fails to work at high
temperature.
34
7/31/2019 Pro Report Sidhi cement
35/52
GUJRAT SIDDHI CEMENT LIMITED
9 PACKING PLANT####################################################
9.1 INTRODUCTION:
A rotary packing machine is used here having 6 filling spouts.
This machine completes 2.5 rotates per minute. Hence filling 30
bags/minutes or 1800 kg/hour.
The spouts are mounted at the bottom of cylindrical container.
The manual work comprises of placing the empty bags on the
spouts as they pass it. Fluidized cement flows into the rotating
container. At the bottom of the container. Certain amount of
fluidized air is added to the cement to increasing flowability
through the filling spouts into the bags.
Each spout has its own weighing device. By the time the spout
finished one rotation 50 kg of cement is filled into the bag. It is
dropped off on the conveyor belt. All the extra cement falls in the
hopper from where it is transported to the cement silo.
In case of transportation by ship, they are carried to the jettythey are slide down and loaded in to the trucks standing underneath.
35
7/31/2019 Pro Report Sidhi cement
36/52
GUJRAT SIDDHI CEMENT LIMITED
36
7/31/2019 Pro Report Sidhi cement
37/52
GUJRAT SIDDHI CEMENT LIMITED
10 INTRUMENTATIONUSEDIN
CMENTMANUFACTURINGPROCESS####################################################
1) Lime Stone Crusher and stacker :
As the control material is required to feed the crusher. Apron
feeder is used and the speed of apron feeder is controlled by VFD
(Variable Frequency Drive) and discharge of the crushed material
flow to the belt is measured by belt wave. The material is taken to
the lime stone stacker through number of belts proximity type
speed monitors are provided in each belt.
There are three micro logic 1000 mini PLCs has been used
for controlling the stacker for making the limestone pile.
2) Limestone Reclaimer & raw mill grindings :
Limestone stacker is used to reclaim the material for pile for
feeding to raw mill for fine grinding. Reclaiming speed iscontrolled by 2 dc motor which is controlled by thyristor control
panel and skewing of Reclaimer is controlled by varying the
correction speed by field weakening system of dc motor and
required reclaimed material can be controlled by varying the
speed of these dc motors which can be vary from 0-3m/hr. for
cutting the material the hydraulic harrow having to & fro motion is
37
7/31/2019 Pro Report Sidhi cement
38/52
GUJRAT SIDDHI CEMENT LIMITED
there which is controlled by hydraulic system and the cylinder
having four meter stroke length for string and on the moment the
proximity switches are used harrow speed can also be varied with
the hydraulic proportional valve which is controlled system.
There are three mini PLCs used for logic control for lime stone
reclaiming and as there two harrow are used, one each side which is
controlled by min PLCs. There is online redundant PLCs are
supervised in case operational PLCs fails. The materials are cuts by
harrow slides down which is dragged by chain drive. It leaves
discharging material on the belt proximity type speed monitoring
is provided for monitoring the speed of bucket chain drive. The
chain drive discharge the materials on the belt & to the third.
Finally the material discharges into raw mill box feeder hopper. All
the three belts which is carrying the material from reclaimer to raw
mill to raw mill hopper and provided by proximity type speedmotors. The function of these motors is to stop the system in case
the belt jamming and belt is getting shared of to avoid further
damages of the system. Box feeder hopper is having capacity of 70
tones which is weigher by three load cells having the capacity of
47 tones each and they are 120 degree apart in the periphery of the
hopper. In order to have equal load distribution on all three loadcells. As shielding cables is connected across three load cells. To
protect three load cells shielding cable is connected by across each load
cell against the welding current. Care is also taken during welding jobs on
such places by giving earthen point directly to the place where welding is
done. The required quantity of the material on volumetric basis is fed to the
vertical raw mill by controlling the box feeder speed. Box feeder speed is
38
7/31/2019 Pro Report Sidhi cement
39/52
GUJRAT SIDDHI CEMENT LIMITED
controlled by 11 kw VFD. The grinding capacity of vertical raw3 mill is 325
tones/hr.
As the raw mill is vertical beam. Raw mill consists of a gear box, a
grinding rollers and 2000kw dry motor(ac induction motor).
Motor:motor rating is 2000 kw induction sleeping motor. 6.65 Kv H.T
motor which is during the grinding table through gearbox.
Gear box: Gear box is very heavy duty gear box hence sufficient lubrication
is required. In case of failure of this oil lubrication system the gear and
bearing can get damage hence bearing temperature are measured by pt100rtd
which trips the system. If oil flow to the gear box becomes less than the
desired value.
Grinding table: Grinding table is rotating on six static show bearings and
these bearings oil supplied by two high hydraulic pressure pumps in
order to maintain the continuous oil film between static show
bearing and grinding table go down surface in order to avoid metal
to metal contact to ensure the required pressure and flow to these
static show bearing six thermal type oil. Oil flow transmitter and
six pressure switches. On oil flow monitor and one pressure
switch for each vein. This system ensures the continuous oil flow
and pressure to the static show bearing in case of abnormality inthe oil flow and pressure & the system trips in order to protect the
static show bearing. The oil show discharged temperature is also
monitored in order to maintain the required viscosity. There are
three grinding rollers placed 120 degree apart connected by yolk at
the centre and outer end of each roller is connected to hydraulic
39
7/31/2019 Pro Report Sidhi cement
40/52
GUJRAT SIDDHI CEMENT LIMITED
cylinders. The complete hydraulic system is provided to control
the moment of the roller against grinding table.
Pumping starts up in the roller which is in varied condition. Thematerials before rollers are brought down. Sufficient quantity of
material is fed which is judged by differential pressure across the
mill. For grinding the material the rollers are brought down to the
table and as the table are rotating rollers are also free to rotate so
whatever comes in between roller and the table gets crushed down.
The crushed material flies up also with the hot gases connected tothe inlet and going inside the mill at the periphery of grinding mill
through mill. The crushed material is lifted along with hot gases
which possess through static separator where the converse material
is separated out and travel further and coarse material comes down
for further grinding. The outlet temperature is measured by
pt100rtd.
3)C.F silo
As consistent quality of material is required for stable operation
C.F silo is used for homogizing the material in the top layers are
getting discharged from 7 extraction points. As quantity of
materials from 10-20% this discharging phenomenon converts its
different quality of horizontal layers into vertical layers hence we
are getting different quality of layers into vertical layers from
40
7/31/2019 Pro Report Sidhi cement
41/52
GUJRAT SIDDHI CEMENT LIMITED
different extraction points. These extracted material goes to wave
bin where again it is getting mixed with the help ofcompressed air
supplied from the bottom of wave bin. Therefore we are getting
consistent quality from the bin.
OPRATION:
For the homogenizing the C.F silo there are 7 air slides connected
to each discharged points getting air in sequence which is
programming. Controlled by PLC there are 7 pneumatic gates at the
discharge point which are also operated in sequence and are being
controlled by PLC for level measurement of C.F silo on eco type
radar has been put. There is one more pedal type level switch which
is provided for monitoring high level of C.F silo.
4) KILN FEEDING SYSTAEM :
There are 2 outlets at the bin from where controlled desired
material flow is fed to kiln pre heater one for P.C stream and
one for P.H stream to sank impact flow meter are used for the
system. The capacity of P.C feeder is 130 tones/hr where as
the capacity of P.C feeder is 240 tones/hr. Dozing valves are
provided as final element to control the flow.. Before the
dozing valve to pneumatic gates are provided for total material
41
7/31/2019 Pro Report Sidhi cement
42/52
GUJRAT SIDDHI CEMENT LIMITED
cut off the material discharge from these feeders fed to the P.C
& P.H stream by conveying through air slides and elevators at
the discharge of the elevator there is one y-shoot diverter
which can feed the material towards the C.F silo back to the
system when it is in operation or to the system hence the total
material from P.H & P.C feeder is carried by elevator there is
one splitter gate is provided by which the material again splits
to P.H & P.C streams in the same ratio from deferens. t feeder
4) PRE HEATING SYSTEM:
In the P.H stream ,flame is second the gases light from cooler
through the kiln and P.H & P.C duct cyclones. The material flow
is from top to bottom and hot gases flow in the P.H system is
from bottom to top hence the heat exchange takes place and the
material is separated out from the cyclone and goes to the P.Cstream & P.C stream goes to P.C where again the burn coal fixed
to maintain the temperature around 900 degree Celsius. The total
material from P.C goes to the
Cyclone of P.C stream and to the kiln inlet during this process
80-90% of calcinations takes place before it reaches to the kilnand if material comes into. The extreme temperature of
1400degree Celsius is maintained for burning process. So after
the burning process in the kiln the material from powder to
nodules. Finally it drops to the cooler. There are number of
instruments used in the process. Each stage material temperature
ad gas temperature are measured with the k-type thermocouple
42
7/31/2019 Pro Report Sidhi cement
43/52
GUJRAT SIDDHI CEMENT LIMITED
down to the transmitter. From here mV generated by the
transmitter is converter to 420 million. After each transmitter
repovided to PLC analog input cords. Each stage is also provided
,2 pressure points ,2 draft points, One at the cyclone outlet
number order to know stable flow of material if any restriction
forms into the coating formation into the system can be deducted
by pressure defense at outlet of each strings.
CO & O2 analyzers have been provided know the proper
combustion of the gases in the P.C for getting the sample fromthe stream to gas analyzers probes are provided to have the
continuous sampling to the analyzer and cleaning panel, O2
analyzer is based on the principle of infrared observation.
The entire kiln rotated from 0-4.5rpm with the help of 670kw
D.C motor which is being controlled by thyristor based 6 pulseD.C drive. The kiln is driven by the mechanism of gear box,
pinion and pair of this continuous lubrication girth system where
it is controlled by mini PLC mounted in the local plc mounted in
the local panel there is one kiln thruster driven by hydraulic
power system to control the float of kiln. In normal operation the
float of kiln is controlled + - 5mm in abnormal condition if floatof kiln is rises to + - 10mm as alert alarm is generated to system
and when it is reached to + - 15mm system is given the rippling
command to the kiln to know the float of the kiln. Assembly is
provided which is attached to one of the leveling of the kiln
through roller. Emergency limit switch is also provided to quit
the kiln operation in switch assembly there are 3 supporting
43
7/31/2019 Pro Report Sidhi cement
44/52
GUJRAT SIDDHI CEMENT LIMITED
roller is moving through bearing which has the controller oil
lubrication temperature of each bearing is also measured with pt
100rtds Abnormal rising temperature rising on any of its roller
bearing trip the kiln operation for safety of the roller bearing
there is one kiln same scanner is provided which scans the entire
kiln 8 times a second. Hence the temperature of each point of its
kiln surface, each recorded or stored into the computer. For the
system coating thickness as the condition of kiln linings is
monitored on continuous basis. Kiln lining migration is measured
on continuous basis with the help of proximity switch at each
lining which gives 1 pulse in the complete rotation is continuous
indication. In case of hot zone forms just below the lining which
can not be deducted by kiln. Shell temperature scanner red spot
forms just below the lining which cannot be deducted by kiln
shell temperature scanner which will result very local k liningmigration which can damage or crack the kiln lining if in
condition continuous for longer period.
5) GRATE COOLER :
The entire cooler is divided into three moving grates. Each
grete is having the number of fix end moving plates which can
44
7/31/2019 Pro Report Sidhi cement
45/52
7/31/2019 Pro Report Sidhi cement
46/52
GUJRAT SIDDHI CEMENT LIMITED
conveyor. The speed of gratecooler is controlled by under
grate pressure in order to have proper bed of material over the
grate. In order to have proper distribution of cooling air to
grates. Each fan flow is controlled by damper and VFD. The
excess air to the cooler is a part of hot gas from cooler is taken
to the vertical coal mill for raw cool grinding.Excess air to the
cooler is taken out through cooler ESP. This is done by
maintaining killer hood draught at the desired level by
controlling cooler vent fan. Speed which is controlled by
thyristor control panel to know or to monitor the burning zone
temperature on continuous basis pyrometer is used. Condition
inside the kiln and the momentum of kiln by CCTV camera
burning flame is also being monitored. The secondary air to
kiln temperature and the tertiary air to P.C vessel temperature
is also measured and the third drive water spray. Steam is alsoprovided which controls the excess air exit temperature and
that clinker temperature at the discharge of the cooling.
6) CEMENT GRINDING AND PACKING:
There are two ball mill type cement mill. Each mill is
having three hoppers. One for clinker, second for gypsum and
third for fly ash. Feeding of cement mill is controlled by belt
wave feeder and for PPC grinding with clinker 2-5% gypsums
fed with clinker . The quantity of gypsum is maintained in
order to have setting time of cement. For manufacture PPC 20-
46
7/31/2019 Pro Report Sidhi cement
47/52
GUJRAT SIDDHI CEMENT LIMITED
30% fly ash is also added. There are two chambers in the
cement mill. In first chamber mix of 80mm, 60mm,70mm
manganese balls are used as grinding media for coarse of
grinding and in the second chamber 10-15mm diameter
slippers are grinding media or finer grinding. Flow of air
through mill is created by cement mill ESP fan. Cement mill
discharges the material for the cement in the screw conveyor
carrid through belt conveyor through lift. From the air lift is
carried to the cement silos. Cement temprature in the mill is
controlled by internal water spray in the cement mill. Jamming
of cement mill is controlled by phosphate which detects the
jamming by sound level which is created by grinding process.
For both the cement mill tuning bearing temprature
measurement is provided. In case abnormal high temprature of
tuning bearing it trips the system continuous oil lubrication forcement mill tuning bearing is also provided and to ensure
continuous sufficient oil flow to the bearing being monitored
with the help of capacitance type proximity switches which
ensure the oil level on oil flow tray over the bearing the mill is
driven by 3600kw ac induction motor through symmetric gear
box and the rotation of cement mill is around 22rp.in the gearbox oil lubrication is also ensured by oil switches. Bearing
temperature of oil box is also measured on continuous basis.
There is continuous vibration monitors at the input shaft of
symmetric gear box. The grinded cement by cement mill
stored in four silos having capacity of 5000tonnes. Each and
every fine cement goes to the air collected in ESP is also fed
47
7/31/2019 Pro Report Sidhi cement
48/52
GUJRAT SIDDHI CEMENT LIMITED
back to belt and to the cement silos. For packing there are five
fourteen spouts mechanical type of packing machines are
there. These machines are packing the cement in 50kg bags
which are loaded on the trucks through the belt conveyor. The
speed of packer (rotary packer) is controlled by D.C drive.,
48
7/31/2019 Pro Report Sidhi cement
49/52
GUJRAT SIDDHI CEMENT LIMITED
11 BLOCK DIAGRAM OF PLANT
INTERLOCK
#####################################
######
49
7/31/2019 Pro Report Sidhi cement
50/52
GUJRAT SIDDHI CEMENT LIMITED
1. Crusher.
2. BC 4A, BC 4B.
3. Stacker.
4. Reclaimer.
5. BC 8.
6. Raw mill.
7. ESP.
8. Drag chain.
9. Air Slider.10. PC & PH.
11. Kiln.
12. Air slider.
13. LO 2 & LO 5 (Coal Silos).
14. Coal mill.
15. Cooler.
16. Clinker Silo.
17. Clinker storage yard.
18. Cement mill 1.
19. Cement mill 2.
20. LO-1& Lo-2(Cement Silos).
21. LO-3& LO-4(Cement Silos).
22. Packing plant.23. Gypsum feeding.
24. Fly ash feeding.
25. Bucket elevator.
50
7/31/2019 Pro Report Sidhi cement
51/52
GUJRAT SIDDHI CEMENT LIMITED
DESCRIPTION-
Same color indicates same group of interlocking. If any
One unit in the same group will shut of, Then all the unit from
The same group will be shut of .
GRUPS -
1. Crusher, BC 4A, BC 4B, Stacker
2. Reclaimer, BC 5, BC 8, Raw mill, ESP, Raw mill hydraulic
plant.
3. PC, PH, Cooler, Bucket elevator.
4. Coal mill, Air slider.
5. Cement mill-1.
6. Cement mill-2
7. Packing plant.
51
7/31/2019 Pro Report Sidhi cement
52/52
GUJRAT SIDDHI CEMENT LIMITED