Process Maddah

Embed Size (px)

Citation preview

  • 8/10/2019 Process Maddah

    1/263

    Process Engineering Procedure

    In

    Oil, Gas & Petrochemical Projects

    By A.R.Maddah

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    2/263

  • 8/10/2019 Process Maddah

    3/263

  • 8/10/2019 Process Maddah

    4/263

    TERMINOLOGY

    Company or Employer/Owner:

    Refers to one of the related and/or affiliated companies of the Iranian ministryof petroleum such as National Iranian Oil Company (NIOC), National Iranian

    Gas Company (NIGC), National Petrochemical Company (NPC), etc.

    f a r a go st a r a nf a r a go st a r a n

    2:\Engineering Company

  • 8/10/2019 Process Maddah

    5/263

  • 8/10/2019 Process Maddah

    6/263

  • 8/10/2019 Process Maddah

    7/263

    2:\Engineering Company Accounting

    Budget-&-Control

    Construction Supervision

    Engineering

    Estimating

    HR-Communication

    Information Technology

    Management

    Procurement

    Projects Proposals

    Support-Services

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    8/263

    2:\Engineering Company

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    9/263

    2:\Engineering CompanyEngineering

    Process

    Mechanic

    HSE

    Civil-Structure-Architecture

    Piping

    Electrical

    Instrument

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    10/263

    3:\Process DepartmentProcess

    Process Dept.Manager

    Process Senior Engineer

    Process Engineer

    Process Senior Draftsman

    Process Draftsman

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    11/263

    3:\Process Department

    Process Departments Activities in the following engineering stages:

    1. Proposal Preparation (PP)

    2. Feasibility Study (FS)

    3. Basic Engineering (BE)

    4. Detail Engineering (DE)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    12/263

    A- Documented ActivitiesA- Documented Activities

    B- Non Documented ActivitiesB- Non Documented Activities

    f a r a go st a r a nf a r a go st a r a n

    Process Departments Activities

    3:\Process Department

  • 8/10/2019 Process Maddah

    13/263

    A- Documented Activities (BE & DE)

    Design Basis & Criteria

    P&ID

    BFD,PFD, UFD

    Chemical & Utility Summary Table

    Control Philosophy

    Electrical Load Summary Table

    Equipment Process D/S

    CV, BDV, PSV Process D/S

    ESD Concept / Block Diagram

    Flare Load Summary TableBasic Design Package

    Preliminary Operating Manual

    Equipment List

    Trip & Alarm Set Point

    Stream Process Condition List

    f a r a go st a r a nf a r a go st a r a n

    3:\Process Department

  • 8/10/2019 Process Maddah

    14/263

    A- Documented Activities Continued (DE only)

    Preparation ofInsulation Schedule

    Preparation of

    Relief & Drainage Diagram

    Preparation ofInterconnecting Diagrams

    Preparation of

    As Built P&IDs

    Technical Bid Evaluation

    f a r a go st a r a nf a r a go st a r a n

    3:\Process Department

  • 8/10/2019 Process Maddah

    15/263

    B- Non Documented Activities (BE & DE)

    Hazop Study

    Cooperation in Preparing

    of Plot Plan

    Project Information Gathering, site visit

    Attending Project Meeting with ClientForeign Partner & Licensor

    Process Simulation

    Line Sizing &

    Hydraulic Calculation

    Equipment Sizing & Rating

    Tie-in List

    Information

    Completion of LDT

    f a r a go st a r a nf a r a go st a r a n

    3:\Process Department

  • 8/10/2019 Process Maddah

    16/263

    B- Non Documented Activities Continued (DE only)

    Basic Package Endorsement

    Cooperation with Inst. Dep.

    For DCS / PLC Design

    Completion of Equipment

    and Instrument D/S

    Heat Tracing Calculation

    Vendors Bid Evaluation

    Checking & Incorporating

    Equipment Sizing & RatingModel Review

    Cooperation with Piping Dep.

    For Tie-in List, Special Items,

    f a r a go st a r a nf a r a go st a r a n

    3:\Process Department

  • 8/10/2019 Process Maddah

    17/263

    ProjectEngineering

    Procurement

    Construction

    Commissioning

    EPCC

    3:\Process Department

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    18/263

    4:\Standards

    1.Whatre standards?

    2.Why do we apply standards?

    -Improvement in qualification of design and operating condition-Increase of safety

    -Decrease of design and selection of material

    -Selection of proper way for procurement

    -Work Uniformity

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    19/263

    4:\Standard\International Standards

    ANSI

    AmericanNational StandardInstitute

    API

    American Petroleum Institute ASME

    The American Society ofMechanical Engineers

    ASTM

    The American Society forTesting andMaterial

    ISAThe Instrumentation System andAutomation Society

    NACE

    National Association ofCorrosion Engineers

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    20/263

    NFPA

    National Fire Protection Association

    DIN

    Deutshes Institute furNormung BSI

    British Standards Institution

    ISO

    International Organization forStandardization

    TEMATubularExchangerManufactures

    AWWA

    American WaterWorks Association

    4:\Standard\International Standards

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    21/263

    4:\Standard\International Standards\Iranian Standards

    IPSIranian Petroleum Standard

    NPCS

    National Petrochemical Company Standard

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    22/263

    API-RP-520: Sizing, Selection, and Installation Of Pressure-Relieving Devices

    in Refinery

    API-RP-521: Guide For Pressure-Relieving and Depressuring System

    API-STD-2000: Venting Atmospheric and Low-Pressure Storage Tanks

    API-RP-14E: Recommend Practice for Design and Installation of Offshore

    Production Platform Piping System

    API-STD-530: Calculation of Heat-Tube Thickness in Petroleum

    API-TP-555: Process Analyzer

    4:\Standard\International Standards\API

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    23/263

    IPS-E-PR-750: Engineering Standard For Process Design of Compressor

    IPS-E-PR-330: Engineering Standard For Process Design of Compressor Air

    System

    IPS-E-PR-440: Engineering Standard For Process Design of Piping System

    IPS-E-PR-308: Engineering Standard For Process Design for Numbering

    System

    IPS-E-PR-700: Engineering Standard For Process Design for Process Design

    of Crude Oil Electrostatic Desalter

    4:\Standard\International Standards\IPS

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    24/263

    NFPA 11: Foam Extinguishing System

    NFPA 12: Standard on Carbon Dioxide Extinguishing System

    NFPA 13: Standard for the Installation of Sprinkler System

    NFPA 15: Standard for Water Spray Fixed System for Fire Protection

    NFPA 72E: Automatic Fire Detector

    NFPA 20: Standard for the Installation of Centrifugal Fire Pump

    4:\Standard\International Standards\NFPA

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    25/263

    4:\Standard\Iranian Standard Codes For Process

    Drawing

    IPS

    IPS-E-PR-170 PFD Symbol Document Numbering

    IPS-E-PR-230 P&ID Symbol

    NPCS

    NPCS-ES-PR-01 PFD/P&ID SYMBOLS

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    26/263

    BFD

    Simulation

    PFD

    UFD

    Process Description

    Heat & Material Balance

    P&ID Process Design Criteria

    5:\Process Activities

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    27/263

    Line List

    Stream Process Condition

    Utility Consumption

    Chemical Consumptions Data Summary

    Technical bid Evaluation

    Instrument Data Sheet

    Equipment Data Sheet Process Data For Piping Special Item

    5:\Process Activities

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    28/263

    5:\Process Activities\Terminology

    Process Units: Units which have direct roles in main process of plant.

    Utility Units: Units which dont have direct roles in main process of plant

    and are the producers of utility services which are utilized in ProcessUnits.

    Operating Condition: It Specifies the Normal Condition (Of Pressure,Temp., Flow, Level,) in Which Equipments, piping and units work.

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    29/263

    Definition:

    These diagrams (BFD) are schematic documents representing whole process

    of the project generally in different units which are introduced in blocks

    containing the title of each unit.

    Objective:

    The objective of these diagrams is to basically show the sequence of the

    process in a simple way.

    Process

    Engineer

    Process Lead

    Engineer

    5:\Process Activities\BFD(BlockFlowDiagram)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    30/263

    5:\Process Activities\BFD(BlockFlowDiagram)

    Block Flow Diagram ofLPG Plant

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    31/263

    BFD

    Contract

    Technical Proposal

    Preliminary Eng. Study

    5:\Process Activities\BFD(BlockFlowDiagram)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    32/263

    PROCESS ACTIVITIES

    BFD

    5:\Process Activities\BFD(BlockFlowDiagram)

  • 8/10/2019 Process Maddah

    33/263

    Definition:

    Process Flow Diagram (PFD) mainly defines:

    a) A schematic representation of the sequence of all relevant operations

    occurring during a process and includes information considered

    desirable for analysis.

    b) The process presenting events which occur to the material(s) to convertthe feedstock(s) to the specified products.

    5:\Process Activities\PFD(ProcessFlowDiagram)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    34/263

  • 8/10/2019 Process Maddah

    35/263

    Contents of PFD:

    Including:

    PFD shall comprise but not limited to the following items:

    1. All process lines, utilities and operating conditions including item numberessential for material balance and heat and material balance.

    2. Type and utility flow lines which are used continuously within the battery

    limits.

    3. Equipment diagrams to be arranged according to process flow, designation,

    and equipment number.4. Simplified control instrumentation pertaining to control valves and the likes

    to be involved in process flows

    5:\Process Activities\PFD

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    36/263

    5. Major process analyzers

    6. Operating conditions around major equipment.

    7. Heat duty for all heat transfer equipment.

    8. Changing process conditions along individual process flow lines, such asflow rates, operating pressure & temperature, etc.

    9. Material balance table.

    5:\Process Activities\PFD

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    37/263

    Excluding:

    The following items are generally not be shown on PFD, except in specialcases:

    1. Minor process lines which are not usually used in normal operation andminor equipment, such as block valves, safety/relief valves, etc.

    2. Elevation of equipment.

    3. All spare equipment.

    4. Heat transfer equipment, pumps, compressor, etc., to be operated in parallelshall be shown as one unit.

    5. Piping information such as size, orifice plates, strainers, and classificationinto hot or cold insulated of jacket piping.

    5:\Process Activities\PFD

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    38/263

    6. Pressure condition which must be determined by hydraulic calculation,such as discharge pressure of pump and compressor.

    7. Instrumentation not related to automatic control.

    8. Drivers of rotating machinery except where they are important for controlline of process condition.

    9. Any dimensional information on equipment, such as internal diameter,height, length, and volume. Internals of equipment shall be shown only ifrequired for a clear understanding of the working of the equipment.

    5:\Process Activities\PFD

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    39/263

    GENERAL DRAFTING INSTRUCTIONS

    1. ScalePFDs should not be drafted to scale. However, their size should be

    compatible with that of equipment drawings.

    2. Flow Direction

    As a rule, PFDs should be drawn from the left to the right in accordancewith process flows.

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    40/263

  • 8/10/2019 Process Maddah

    41/263

    c)All electrical, computer and instrument

    signals

    Thickness = 0.3 m

    b) Secondary process lines and utility line

    Thickness = 0.5 mm

    a) Main process lines

    Thickness = 0.8 mm

    4. Kind Of Lines

    As a rule, Process lines, utility lines, and loop lines for instrument should be

    drawn according to IPS-E-PR-230 as follows:

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    42/263

    5. Line Crossover

    Where two lines cross each other, the horizontal line should be drawn as a

    continuous line in all cases. This shall not apply to loop lines for instruments.

    c) Where one main line crosses one loop linefor an instrument

    b) Where one main line crosses onesecondary process and utility lines

    a) Where two main process lines cross

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    43/263

    6. Denotation of Lines at Battery Limit Tie-In Points

    a) Process lines

    From Item No. and/ To Item No. and/

    or Dwg. No. or Dwg. No.

    b) Utility lines COOLING WATER

    Names of fluids should be given in parentheses above the utility lines.

    Name of these fluids should be as abbreviation according to IPS-E-PR-308

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    44/263

    7. Direction of Flow

    The direction of flow should be indicated by arrows. In principle all flow

    lines should be denoted by arrows located at the inlet of equipment, and at

    the corners of the lines. Where a process line is long, however, the process

    flow may be denoted by arrows located at intermediate points.

    The number of arrows used to denote one process flow line is not

    restricted. However, care should be taken not to clutter the drawing with

    excessive arrows.

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    45/263

    8. Division of PFD

    Where a PFD must be divided into two or more sheets, it should be

    divided at portions where division is easiest from the process standpoint

    and each divided section should be drawn on a separate sheet.

    9. Other Trains

    Where there are two or more identical trains of process flows, one

    representative train may be given in the PFD and the others omitted.

    However, notations pointing out such omissions must be clearly indicated

    in the titles of all relevant PFDs to avoid confusion.

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    46/263

    10. Title

    The title should be given in the title block at the lower right-hand corner of

    the PFD.

    11. Legend

    The legend may be given in separate schematic drawing to which reference

    shall be made if necessary.

    12. SizeThe size of PFD should normally be A1 (594 mm 841 mm).

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    47/263

    Minimum Information Requirements For Equipments

    1. Designated streams

    a) Stream numbers should be serially denoted by Decimal numbers.b) Fluid name.

    c) Total flow rate.

    d) Density and/or molecular mass (weight) if required.

    e) Operating pressure and temperature if required.

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    48/263

    5:\Process Activities\PFD\Drafting

    2. Heat exchangers

    a) Identification number and service name.

    b) Operating heat duty.

    c) Inlet and outlet temperatures on both shell and tube sides.

    3. Furnaces

    a) Identification number and service name.

    b) Operating absorbed heat duty.

    c) Inlet and outlet operating temperatures on tube side.

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    49/263

    4. Reactors

    a) Identification number and service name.

    b) Inlet and outlet operation temperature.

    c) Inlet and/or outlet pressure.

    5. Columns

    a) Identification number and service name.

    b) Tray numbers, operating temperature and pressure for top and bottom trays

    and also for special trays such as feed and draw-off, etc.

    c) Trays shall be numbered from bottom to top.

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    50/263

    6. Drums

    a) Identification number and service name.

    b) Operating temperature.

    c) Operating pressure.

    7. Pumps

    a) Identification number and service name.

    b) Normal operating capacity and differential pressure.

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    51/263

    5:\Process Activities\PFD\Drafting

    8. Compressors and blowers

    a) Identification number and service name.

    b) Normal operating capacity and differential pressure.

    9. Tanks

    a) Identification number and service name.

    b) Operating temperature.

    c) Operating pressure.

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    52/263

  • 8/10/2019 Process Maddah

    53/263

    PFD Modification

    1. First Issue (FI):

    Release for proposal (Conclusion of estimate, study)

    -Main equipment (Tagged)

    -Main Process Lines

    -Battery Limit

    -Main control concept (control & switch)

    -Package unit Limits

    5:\Process Activities\PFD Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    54/263

    2. Issued For Approval (IFA):

    Release for Basic Engineering (Conclusion of fixed price bid)

    In addition to contents 1.-Important valve ( isolation, manual control)

    -Essential process shutdown circuits

    -Important start up lines

    -Definition of heat exchanger type

    5:\Process Activities\PFD Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    55/263

    3. Issued For Design (IFD):

    Release for Basic Engineering Development (Conclusion of verification

    Phase and Basic Eng.)

    -Content as 1. & 2. however adjusted to the contract conditions

    5:\Process Activities\PFD Modification

    f a r a go st a r a nf a r a go st a r a n

    4. Approved For Design (AFD):

    Release for Detail Engineering (End of Basic Eng.)

    -Crosscheck with P&ID, release detail engineering

  • 8/10/2019 Process Maddah

    56/263

    5. Issued For Construction (IFC):

    Release for Detail Engineering Development

    -Crosscheck with P&ID, release for purchase of bulk material

    5:\Process Activities\PFD Modification

    f a r a go st a r a nf a r a go st a r a n

    6. Approved For Construction (AFC):

    Release for Construction phase (End of Detail Eng)

    -Final issue of PFD in Detail phase

    7. As Built (ASB):

    End of construction

    -Includes all of the changes in commissioning and construction phase

  • 8/10/2019 Process Maddah

    57/263

    f a r a go st a r a nf a r a go st a r a n

    PROCESS ACTIVITIES

    BFD

    PFD

    5:\Process Activities\PFD

  • 8/10/2019 Process Maddah

    58/263

    Heat and Material Balance Table:

    The basis for preparation of this Table is process description accompanied by

    the specified contract requirements such as separation percent or outlet

    required pressure or any other specification of Feed and Products. This table is

    generally prepared by process simulation soft wares like HYSYS, PROII and

    etc.

    5:\Process Activities\PFD\H&M Balance

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    59/263

    5:\Process Activities\PFD\H&M Balance

    Contents :

    Stream information: Stream No., name of stream, flow rate, composition.

    Operating conditions: Operating temperature and pressure.

    Basic physical properties: Molecular mass (weight), API gravity, Relative

    Mass Density (Specific Gravity) or (Sp.Gr.), etc.

    Data concerning hydraulic calculation: Density, viscosity, etc. if required

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    60/263

    5:\Process Activities\PFD\H&M Balance

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    61/263

    f a r a go st a r a nf a r a go st a r a n

    PROCESS ACTIVITIES

    H&M BALANCE

    BFD

    PFD

    5:\Process Activities\H&M Balance

  • 8/10/2019 Process Maddah

    62/263

    Definition:

    These diagrams (UFD) are generally similar to Process Flow Diagrams but theyare related to the Utility parts (streams) of the process which give services to themain process lines for different purposes.

    These diagrams are normally not simulated by softwares to reach the above-mentioned specifications of streams (To prepare Heat and Material Balance).

    The Symbol Diagram of UFDs are the same as PFDs.

    5:\Process Activities\UFD

    (UtilityFlowDiagram)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    63/263

  • 8/10/2019 Process Maddah

    64/263

    1.ModificationModification and revision is defined separately for every sheet of a UFD

    FI , IFA , IFD , AFD , IFC , AFC , ABS

    2.Revision

    A new revision indicates the change of a document. The revision is defined by

    number & alphabets, which by subsequent revision shall be consecutively raised

    from a starting point.

    Numbers Rev.1,2,

    Alphabets Rev.A,B,

    5:\Process Activities\UFD Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    65/263

    f a r a go st a r a nf a r a go st a r a n

    PROCESS ACTIVITIES

    H&M BALANCE

    BFD

    PFD

    UFD

    5:\Process Activities\UFD

  • 8/10/2019 Process Maddah

    66/263

    Output ofSimulation by

    Process

    Engineer

    It is drawn

    byDraftsman

    Checked byProcess

    Senior

    Engineer

    Approved by

    Process Dep.

    Manager

    Process Lead Engineer

    5:\Process Activities\PFD & UFD

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    67/263

    5:\Process Activities\PFD\Drafting

    f a r a go st a r a nf a r a go st a r a n

    PFD, UFD, H&M Balance

    Contract (Symbol & Legend)

    Codes/ Std./ Eng. Practice

    Licensor Comments

    Final Doc. Of Equipment Vendor

    Technical Proposal

    Simulation ResultsBasic Design

    Design Basis & Criteria

    Preliminary Eng. Study

  • 8/10/2019 Process Maddah

    68/263

    Purposes:

    Decreasing of calculation time

    Heat & Material Balance Table

    Prediction of optimum arrangement of equipment for PFD

    production

    Pinch study

    Designing of equipment

    5:\Process Activities\Simulation (ND)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    69/263

    Applications Cases:

    Proposal Preparation (PP)

    Feasibility Study (FS)

    Basic Engineering (BE)

    Detail Engineering (DE)

    5:\Process Activities\Simulation (ND)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    70/263

    Terminology:

    Simulation

    Design

    Rating

    5:\Process Activities\Simulation (ND)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    71/263

    Simulations Software:o PRO /II

    o HYSYS

    o HEXTRAN

    o HX-NET

    o HTRI

    o Visual Flow

    o INPLANT

    o PIPE-PHASEo Pipe Sys

    o PROMAX

    5:\Process Activities\Simulation (ND)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    72/263

    f a r a go st a r a nf a r a go st a r a n

    PROCESS ACTIVITIES

    H&M BALANCE

    BFD

    PFD

    UFD

    SIMULATION

    5:\Process Activities\Simulation

  • 8/10/2019 Process Maddah

    73/263

    5:\Process Activities\Process Description

    f a r a go st a r a nf a r a go st a r a n

    Objective:

    Process Description , describes technical information, that determines

    operating conditions and explains major principles of plant process

    Process Description is prepared at two stages :

    1.Proposal Preparation (PP)

    2.Basic Engineering (BE)

  • 8/10/2019 Process Maddah

    74/263

    5:\Process Activities\Process Description

    f a r a go st a r a nf a r a go st a r a n

    1.Proposal Preparation (PP)

    -After the study of bid documents from client, a short process descriptionwill prepared.

    -This process description should be based on BFD

    -In this stage , process description covers the minimum requirement toexplain major principles, operating condition and purpose of each defined

    block in BFD

  • 8/10/2019 Process Maddah

    75/263

    5:\Process Activities\Process Description

    f a r a go st a r a nf a r a go st a r a n

    2.Basic Engineering (BE)

    -Preliminary process description (from client) will be completed during thisstage

    -In order to prepare detailed process description , PFD,UFD and H&MBalance should be used to extract necessary data such as temperature,

    pressure, operating condition and main process loop control.

    -In addition , process description includes duty of each equipment, majorprinciples of plant or sub unit , feed and product condition to/from each unit.

  • 8/10/2019 Process Maddah

    76/263

    5:\Process Activities\Process Description

    f a r a go st a r a nf a r a go st a r a n

    Process Description

    Contract

    Licensor Basic Design

    Technical ProposalBFD , PFD ,UFD

  • 8/10/2019 Process Maddah

    77/263

    f a r a go st a r a nf a r a go st a r a n

    PROCESS ACTIVITIES

    H&M BALANCE

    BFD

    PFD

    UFD

    SIMULATION

    PROCESS DESCRIPTION

    5:\Process Activities\Process Description

  • 8/10/2019 Process Maddah

    78/263

    5:\Process Activities\Basic Design

    f a r a go st a r a nf a r a go st a r a n

    Basic Design (Design Basis)

    This document shows the basic parameters that process engineers apply in

    designing of plant.

  • 8/10/2019 Process Maddah

    79/263

    5:\Process Activities\Basic Design

    f a r a go st a r a nf a r a go st a r a n

    Basic Design (Design Basis) Consists of below items,

    1. Feed and Product Specification

    - General Specification

    - Plant Capacity

    - Feed

    - Product

  • 8/10/2019 Process Maddah

    80/263

    5:\Process Activities\Basic Design

    f a r a go st a r a nf a r a go st a r a n

    Basic Design (Design Basis) Consists of below items,

    2. Utility Specification

    - HP,MP,LP Steam

    - Plant & Instrument Air

    - Nitrogen

    - Water (Potable,Plant,DEMIN,)

    - Fuel (Oil,Gas)

  • 8/10/2019 Process Maddah

    81/263

  • 8/10/2019 Process Maddah

    82/263

    5:\Process Activities\Basic Design

    f a r a go st a r a nf a r a go st a r a n

    Basic Design (Design Basis) Consists of below items,

    4. Emissions and Waste

    - List of Expected Gaseous Emissions

    - List of Expected Liquid Effluents

    - List of Expected Solid Wastes

  • 8/10/2019 Process Maddah

    83/263

  • 8/10/2019 Process Maddah

    84/263

    5:\Process Activities\Basic Design

    f a r a go st a r a nf a r a go st a r a n

    Basic Design (Design Basis) Consists of below items,

    6. Environmental Data

    - Site Data

    Location, Elevation above Sea Level, Earthquake Spec.

    and

    - Climatic Data

    Air Temperature, Air Humidity, Barometric Pressre,

    Wind, Rain and Snow Fall

  • 8/10/2019 Process Maddah

    85/263

    5:\Process Activities\Basic Design

    f a r a go st a r a nf a r a go st a r a n

    Process Design Basic

    Contract Licensor Basic Design

    Technical Proposal

  • 8/10/2019 Process Maddah

    86/263

    f a r a go st a r a nf a r a go st a r a n

    PROCESS ACTIVITIES

    H&M BALANCE

    BFD

    PFD

    UFD

    SIMULATION

    PROCESS DESCRIPTION

    DESIGN BASIS

    5:\Process Activities\Design Basis

  • 8/10/2019 Process Maddah

    87/263

    Definition:

    The Piping and Instrument Diagram (P&ID), based on the Process Flow

    Diagram (PFD), represents the technical realization of a process by means ofgraphical symbols for equipment and piping together with graphical symbols

    for process measurement and control functions.

    5:\ Process Activities \P&ID

    (Piping & Instrument Diagram)

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    88/263

    Terminology:

    Design Conditions: Design Pressure and Temperature are used to determine theminimum permissible thickness or Physical characteristics of each Equipment

    or Piping item.

    Low Level: A condition (Press,Temp, Flow, Liq. Level) in a process componentless than the minimum operating condition.

    High Level: A condition (Press,Temp, Flow, Liq. Level) in a processcomponent in excess of the maximum operating condition.

    5:\ Process Activities \P&ID\TerminologyTerminology

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    89/263

    Control Valve: These are automatic valves used for controlling parameters like

    Press., Temp., Flow rate, Their power medium is normally Instrument Air

    (pneumatic actuators)

    Failure: Improper performance of a device or equipment item that prevents

    completion of its design function.

    Fail Open / Closed (Control Valve): The safe position of a valve which will shift

    to upon loss of the power medium.

    Normal Position (Valve): The position of a valve in Normal Condition of the

    process (N.O. , N.C.)

    5:\ Process Activities \P&ID\TerminologyTerminology

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    90/263

    5:\ Process Activities \P&ID\TerminologyTerminology

    Plant Shutdown: The shutting in of all process stations of a Plant Production

    process and all support equipment for the process.

    Process Shutdown: The isolation of a given process station from the process

    by closing appropriate SDVs to shut-in flow to the process station or divert

    flow to another process station.

    Shutdown Valve (SDV): An automatically operated Normally Closed valve

    used for isolating a process station.

    Emergency Shutdown System (ESD): A system of stations which when

    activated initiate plant shutdown.

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    91/263

    Flare: A means of safety disposing of waste gases through the use of

    combustion. With a flare the combustion is carried out at the top of a pipe or

    stack where a the burner and igniter are located.

    Relief System: A system containing mechanical overpressure protection

    devices (press. safety valves) on the equipment, relieving in to a collection /

    disposal system.

    5:\ Process Activities \P&ID\TerminologyTerminology

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    92/263

    Pressure Safety Valve (PSV): A pressure relief device designed to open andrelieve excess pressure and to reclose and prevent the further flow of fluidafter normal conditions have been restored.

    Depressurization: When metal exposed to fire on one side with vapor on theother side, the metal temp. may reach a level at which metal rupture due tostress may occur, even though the press. does not exceed the allowableoverpressure. An emergency depressurization (blow down) system is providedto avoid such an occurrence.

    5:\ Process Activities \P&ID\TerminologyTerminology

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    93/263

    Blow down Valve :

    An automatically operated normally

    open valve used to vent the pressure

    from a process station on shutdown.

    5:\Process Activities \P&ID\TerminologyTerminology

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    94/263

    Drain System:

    This is the configuration which drains liquids

    from vessels or piping systems after

    depressurization (via valves) in to a system

    of vessel and piping.

    5:\Process Activities \P&ID\TerminologyTerminology

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    95/263

    Vent: A pipe or hatch on a vessel that opens to the atmosphere.

    Battery Limit: Generally is used for showing the exact margin of a specific unit.

    (Process or Utility Units)

    5:\Process Activities \P&ID\TerminologyTerminology

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    96/263

    Contents:

    Piping System

    Equipments

    Control Items

    Automatic and Manual Valves

    All Item Numbers

    All Item Required Information

    Vent and Drain Systems

    Notes

    Packages

    Tie-In Points

    5:\Process Activities \P&ID\Contents

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    97/263

    P&ID Symbols:P&ID Symbols:

    P&ID Equipment SymbolsP&ID Equipment Symbols

    P&ID General SymbolsP&ID General Symbols

    P&ID Instrument Symbols (Typical HookP&ID Instrument Symbols (Typical Hook--Up)Up)

    P&ID Instrument Symbols (Valve Symbol)P&ID Instrument Symbols (Valve Symbol)

    5:\Process Activities \P&ID\Symbols

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    98/263

    Gate valve (basic symbol)

    Globe valve

    Check valve (general)

    Gate valve behind off

    Angle valveBall valve

    Four way valve

    Gate valve with body bleed

    Butterfly valve

    Hydraulic control

    Metering cock

    Needle valve

    Plug valveS=solenoid valve

    R= Manual reset when indicated

    Diaphragm valve

    DESCRIPTIONSYMBOL

    5:\Process Activities \P&ID\Symbols

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    99/263

    Main process line (arrow indicates Direction of flow )

    Heat traced pipe line

    Underground pipeline

    Existing line

    Future line

    Vendor package

    Jackated or double containment pipeline

    Line crossing (connected )

    DescriptionSymbol

    5:\Process Activities \P&ID\Symbols

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    100/263

    5:\Process Activities \P&ID\Symbols

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    101/263

    5:\Process Activities \P&ID\Symbols

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    102/263

    Drafting

    1. General rules

    Drafting shall be in accordance with the requirements outlined in this Standard.The drafting must be of sufficiently high quality to maintain legibility when

    the drawing is reduced to an A3 size sheet.

    2. Drawings sheet sizes

    Diagrams shall be shown on A0 size (841 mm 1189 mm) tracing paper. A1

    size (591 mm 841 mm) may be used for simple P&IDs as per Companys

    approval.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    103/263

    3. Drawing title block

    The following requirements shall be shown on the title block of each drawing (Next

    Page):

    - revision table;

    - main Companys name (e.g., National Iranian Oil Company);

    - name of Company Relevant Organization, (if any), (e.g., Refineries Engineering and

    Construction);

    - name of refinery or plant (in English and Persian words);

    - Contractors name;

    - drawing title;

    - Companys project No.;

    - Contractors job No. (optional);

    - Contractors drawing No. (optional);

    - Companys drawing No.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    104/263

    Title block sizes and drawing dimensions shall be as follows

    180 190

    130 175

    100 155

    75 120

    A0 = 841 1189

    A1 = 594 841

    A2 = 420 594

    A3 = 297 420

    TITLE BLOCK SIZE (INCLUDING REVISION

    TABLE)WIDTH (mm) LENGTH (mm)

    DRAWING DIMENSIONS

    (mm mm)

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    105/263

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    106/263

    4. Line widths

    To obtain a clear representation, different line widths shall be used. Main flow

    lines or main piping shall be highlighted.

    The following line widths shall be applied:

    0.8 mm for main process lines;

    0.5 mm for other process lines; utility lines, and underground lines;

    0.5 mm for graphical symbols for equipment and machinery, except valves

    and fittings and piping accessories; 0.5 mm for rectangular boxes for illustrating Unit operations, process

    equipment, etc.;

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    107/263

    0.5 mm for subsidiary flow lines or subsidiary product lines and

    for energy carrier lines and auxiliary system lines;

    0.4 mm for class changes designation;

    0.3 mm for graphical symbols for valves and fittings and pipingaccessories and for symbols for process measurement and

    control functions, control and data transmission lines;

    0.3 mm for all electrical, computer and instrument signals;

    0.3 mm for reference lines;

    Line widths of less than 0.3 mm shall not be used.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    108/263

    5. Line spacing

    The space between parallel lines shall not be less than twice the width of the

    heaviest of these lines. A spacing of 10 mm and more is desirable between

    flow lines.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    109/263

    6. Direction of flow

    In general, the main direction of flow proceeds from left to right and from

    top to bottom. Inlet and outlet arrows are used for indicating the inlet and

    outlet of flows into or out of the diagram.

    Arrows are incorporated in the line for indicating the direction of the flows.If necessary for proper understanding, arrows may be used at the inlets to

    equipment and machinery (except for pumps) and upstream of pipe

    branches. If a diagram consists of several sheets, the incoming and outgoing

    flow lines or piping on a sheet may be drawn in such a manner that the lines

    continue at the same level when the individual sheets are horizontally

    aligned.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    110/263

    7. Connections

    Connections between flow lines or pipelines shall be drawn as shown in

    Figs. 1 and 2below:

    Figs. 3 and 4 show two flow lines or pipelines, which are not connected:

    Fig1 Fig2

    Fig3 Fig4

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    111/263

    8. Equipment Location Index

    Piping & Instrument Diagrams shall be divided intoequivalent intervals (each in 50 mm) eitherin length or width.The intervals shall be designated with numbers from 1 to 23 in

    length and alphabets from "A" to "P" in width. Equipmentlocation on each diagram shall be addressed by the relevantcoordinates where required. In upper right-hand area of theflow diagram under title of "Item Index" all main equipmentshall be listed by equipment number, alphabetically andnumerically and equipment location coordinates. In a separate

    sheet apart from P&IDs, an "Item Index" shall be prepared tosummarize all equipment of the Unit/Plant with referenceP&IDs and equipment location.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    112/263

    9. MINIMUM INFORMATION TO BE SHOWN ON P&ID DIAGRAMS

    General

    Each P&ID shall present all information as required herein below during

    implementation of a project in detailed design phase. Extent of information

    shown on each P&ID in the basic design stage shall be agreed by Company inadvance.

    Vendor supplied packages with an outline of the main components shall be

    shown in a dashed/dotted box. Letter "PK" referring to package shall be

    indicated adjacent to each equipment and instrument of the package.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    113/263

    Equipment, instruments or piping which are traced or jacketed, shall be shown.

    The identification number and service presentation shall be shown for eachpiece of equipment. This information shall be indicated in or adjacent to

    towers, drums, heaters, tanks and heat exchangers, etc.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    114/263

  • 8/10/2019 Process Maddah

    115/263

    A .Fixed Equipments, TanksThe following requirements shall be shown:

    Drawing

    a) all nozzles, manways, instrument connections, drains, vents, vortex breakers, and

    safety/relief valve connections;b) all internals such as steam coils, air spargers, tank heaters and etc.

    Equipment descriptiona) equipment item number (this number also appears adjacent to the tank);

    b) service;

    c) inside diameter and height;

    d) nominal capacity, in (m);e) design pressure and temperature;f) indication of insulation.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    116/263

    A .Fixed Equipments Vessels, Towers, DrumsThe following requirements shall be shown:

    Drawing

    a) changes of shell diameter (if any); b) top and bottom trays, and those trays which are necessary to locate feed, reflux and

    product lines;

    c) all draw-off trays with tray number;

    d) all nozzles, manholes, instrument connections, drains, vents, pump-out and steam-out, vortex breakers, and safety/relief valve connections,sample connection

    e) skirt or legs, top and bottom tangent lines;

    f) elevations above base line to bottom tangent line of column or to bottom of horizontaldrum;

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    117/263

    Drawing (For Vessels, Towers, Drums) :

    g) the position of high high liquid level (HHLL), high liquid level (HLL), normal liquid

    level (NLL), low liquid level (LLL) and low low liquid level (LLLL);

    h) all flanged connections; [all connections whose purpose is not readily evident shallindicate the purpose (e.g., spare inlet, catalyst draw-off, etc.).];

    i) catalyst beds, packings, demisters, chimney trays, distributors, grids, rotating discs,mixers, cyclones, tangential inlet and all other internals;

    j) water drop-out boots;

    k) maintenance blinds for the vessel nozzles.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    118/263

    Important Notes (For Vessels, Towers, Drums) :

    a) All nozzles and connections indicated on the equipment data sheet shall be shownin their correct positions.

    b) All indications shall be such that the consistency in the dimensions is considered,although not necessarily to scale.

    c) Numbering of the trays shall be from bottom to top.

    d) Height of the vessel bottom tangent line shall be indicated.

    Self standing : Skirt heightElevated vessel: Minimum required height shall be shown as "min. ....".

    e) A valved drain for all columns and vessels shall be indicated.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    119/263

  • 8/10/2019 Process Maddah

    120/263

    Equipment Description (For Vessels, Towers, Drums) :

    The following requirements shall be described under equipment description:

    a) vessel item number (this number will also appear adjacent to the vessel);

    b) service; c) size [inside diameter(s) and tangent to tangent length];

    d) design pressure (internal/external) and design temperature;

    e) indication of insulation;

    f) line number of vessel trim (this applies to LG & LC connections, vents, sample

    connections, etc.);

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    121/263

    A .Fixed EquipmentsFired Heaters, Boilers, Incinerators

    The following requirements shall be shown:

    Drawing

    a) all nozzles, instrument connections, drains, vents and damper(s);

    b) ducting arrangement including damper actuators where required;

    c) waste heat recovery system (if present), such as economizer, air preheater,

    forced draft fan, induced draft fan,etc.;

    d) decoking connections;

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    122/263

    Drawing

    e) detail of one complete set of burners for each cell and total burner number requiredfor each type of burner;

    f) tube coils schematically in correct relative positions and all skinpoint thermocouples;

    h) logic diagram of shut down system (heat off sequence);

    i) number of passes and control arrangement;

    j) blow-down and steam-out connections;

    k) testing facilities;

    l) convection section (where applicable).

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    123/263

    A .Fixed Equipments,Heat Exchangers, Coolers, ReboilersThe following requirements shall be shown:

    a) all nozzles, instrument connections, drains and vents, chemical cleaning

    connections and safety/relief valves as indicated on the equipment data sheet;

    b) spectacle blinds for the isolation;

    c) elevations required for process reason (e.g., reboilers, condensers, etc.);

    d) the position of high liquid level (HLL), normal liquid level (NLL) and lowliquid level (LLL) for kettle type reboilers;

    f) direction of flow in each side of exchanger.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    124/263

    Important notes (For Heat Exchangers, Coolers, Reboilers)

    Due considerations should be made for proper indication in the following requirements:

    a) Generally, direction of flow shall be downflow for cooled media and upflow forheated media.

    b) Isolation valves shall be provided on inlet and outlet lines where maintenance canbe performed on the exchanger with the Unit operating. Provision of by-passing isrequired for this case.

    c) Shell and channel piping shall be provided with a valved vent connection and a drainconnection unless venting and draining can be done via other equipment.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    125/263

    Important notes (For Heat Exchangers, Coolers, Reboilers)

    e) An inlet and outlet, temperature indicator shall be provided on each exchanger (oneither shell or tube side) so that to facilitate checking of heat balance aroundexchanger.

    Type of temperature indicator shall be as follows:

    - A board mounted temperature indicator (TI) shall be provided at the inlet and outletof all shell and tube process/process exchanger.

    - For water coolers, the water side outlet shall be provided with a local TI only. Theshell side in and out shall be provided with board mounted TIs.

    - Thermowells (TWs) shall be provided between each shell side and tube side of thesame services when the exchangers are in series.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    126/263

    Equipment description (For Heat Exchangers, Coolers, Reboilers)

    a) equipment item number (this number also appears adjacent to the equipment);

    b) service;

    c) duty (kJ/s);

    d) shell side design pressure and temperature;

    e) tube side design pressure and temperature;

    f) indication of insulation.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    127/263

    B. Rotary MachineriesPumps

    The following requirements shall be shown:

    Drawing

    a) all nozzles including instrument connections;

    b) pump suction valve and strainer, and discharge valve and check valve. Provision of

    wafer type check valve should be avoided unless otherwise specified;

    c) pump drains and vents piping.

    d) the type of pump;

    e) pump auxiliary system connections such as, cooling water, seal oil and lube oil, steam,etc.;

    h) pressure gage located on the discharge of each pump; the gage shall be installed

    between the pump discharge nozzle and the check valve;

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    128/263

    Equipment description (For pumps)

    a) pump item number (this number also appears below the pump);

    b) service;

    c) capacity, (m/h, dm/h for injection pumps);

    d) differential pressure, (kPa);

    e) relative density (specific gravity) of pumped fluid at pumping temperature;

    f) indication of insulation and tracing;

    g) miscellaneous auxiliary piping (CW, seal oil, etc.).

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    129/263

    B. Rotary Machineries, Air Fin Coolers

    The following requirements shall be shown:

    Drawing a) all nozzles and instrument connections;

    b) blinds for the isolation;

    c) any automatic control (fan pitch control or louver control) and any alarm (vibrationalarm, etc.);

    d) configuration of inlet and outlet headers and the branches. Only one bundle andfan shall be shown; total number of fans and bundles shall be indicated. When

    multiple bundles are required, headers arrangement as separate detailed sketchshall be indicated;

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    130/263

    e) steam coil and condensate recovery system (if required);

    f) isolation valves (if required); isolation valves shall be provided in corrosive andfouling services where individual bundles can be repaired and maintained with theUnit operating;.

    g) valved vent and valved drain connection for each header, vent header should beconnected to closed system for volatile services;

    h) a board mounted TI at inlet and outlet, (the TI will monitor the process side of eachair fin service). If multiple bundles to be used for fouled services, provide TWs on theoutlet of each bundle.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    131/263

    Equipment description (For Air Fin Cooler)

    a) equipment item number (this number will also appear adjacent to the equipment);

    b) service;

    c) duty (kJ/s);

    d) tube side design pressure (internal and external) and design temperature.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    132/263

    B. Rotary Machineries Compressors and BlowersDrawing

    a) type of compressor or blower;

    b) start-up facilities (i.e., inert gas purge system);

    c) safety/relief valves;

    d) suction and discharge valves;

    e) suction strainer (filter) and discharge check valve;

    f) suction and discharge pulsation dampener where required;

    g) valved vents and casing drains;

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    133/263

    Drawing (For Compressor and Blowers)

    h) winterization (steam or electrical tracing on suction piping) where required;

    i) lube and seal oil / sealing system and cooling water systems detail arrangement;

    j) interstage coolers where required;

    k) surge protection (where required);

    l) inlet and outlet nozzles;

    m)all instrument connections.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    134/263

    Description for Compressors and Blowers

    a) equipment item number and stage (this number also appears below thecompressor);

    b) service:

    c) capacity, (Nm/h);

    d) suction pressure, and temperature, [kPa (g)], (C);

    e) discharge pressure, and temperature, [kPa (g)], (C);

    f) miscellaneous auxiliary piping (CW, lube, oil, seal oil / sealing system, etc.);

    g) gas horse power, (kW).

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    135/263

    B. Rotary Machineries Steam and Gas Turbine Drivers

    Drawing

    a) all nozzles and connections;

    b) detail of all auxiliary systems for steam turbine drivers such as steam supply,condensate return, surface condenser and etc.;

    c) detail of lube oil, cooling water, etc.;

    d) all instrumentations such as PI, TI, etc.;

    e) safety/relief valves; relief valves shall be located between the discharge nozzle andthe outlet isolation valve;

    h) vent line to atmosphere at turbine exhaust; the vent is required for the start-up/testoperation of the turbine.

    5:\Process Activities \P&ID\Drafting

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    136/263

    1.ModificationModification and revision is defined separately for every sheet of a P&ID

    FI, IFD , AFD , IFC , AFC , ABS

    2.RevisionA new revision indicates the change of a document. The revision is defined by

    number & alphabets, which by subsequent revision shall be consecutively raised

    from a starting point.

    Numbers Rev.1,2,

    Alphabets Rev.A,B,

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    137/263

    GeneralAs the P&I Diagram contains a large amount of plant design information, its revision

    will have a great effect on the subsequent engineering works.

    Accordingly for the purpose of minimizing the revisions and avoiding unnecessary

    works, the steps for preparing the P&I Diagrams shall be established. The followingsteps should be realized in preparing the P&I Diagrams. Upon the information which

    can be prepared as engineering work proceeds, steps 2, 3 and 4 may be combinedor extended to more steps as required.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    138/263

    PFD Modification

    1.First Issue (FI):

    Through step 1, the basic design philosophy concerning those basic items for the

    preparation of P&IDs such as mode of indication, applicable standards, numberingsystem, valve arrangement and those other basic items on which agreements

    shall be made by the Company prior to the preparation of the P&ID should be

    clarified.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    139/263

    The basic items which should be taken into consideration in step 1 are listed hereinbelow but should not be limited to the following items:

    a) Vellum and drafting

    - size and vellum of drawing;

    - title;- drafting;

    - arrangement;- equipment description;

    - interconnection.

    b) Numbering System

    - drawing No.;

    - equipment No.;

    - instrument tag No.;

    - line No.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    140/263

    c) Symbol

    - equipment;

    - piping components;- instrument symbol;

    - process stream symbol;

    - utility symbol.

    d) Valve arrangement around equipment

    - valve arrangement for drain, vent and purge;

    - valve arrangement for steam-out;- sizes of the nozzles for installing the instruments;

    - valve arrangement around the heater and exchanger;- valve arrangement around the pump and compressor;

    - valve arrangement around the steam turbine.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    141/263

    e) Piping

    - piping classification standards;

    - valve arrangement at the battery limit;- valve arrangement for drain, vent, purge and steam-out on piping;

    - valve arrangement around the steam trap;

    - valve arrangement around the sample point/sample connections;- blow-down;

    - valve type selection criteria/standards;- strainer type selection standards;

    - pipe line sizing

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    142/263

    f) Instrumentation

    - valve arrangement around the control valve;

    - valve arrangement around the safety/relief valve;

    - valve arrangement around other instruments;

    - instrument type selection standards;- software linkage and DCS presentation.

    g) Miscellaneous

    - winterizing and heat conservation;

    - recovery of steam condensate;

    - disposal of drains and waste water effluent

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    143/263

    \ A i i i

  • 8/10/2019 Process Maddah

    144/263

    Results of hazard analysis and operability (HAZOP) study (if any) note :contractor shall

    perform the HAZOP study (if required by the owner) using PFD, P&ID and plot plantogether with equipment data sheets and related safety equipment checklist.

    Contractor shall provide information about the reported accidents in similar processunits in the world during HAZOP meetings.

    The Contractor should prepare both the draft of the basic items for preparation of the P&IDiagrams and all necessary operation and safety features as mentioned above to

    Companys review and approval before issuance of official revision of P&I Diagram forengineering start.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

    5 \P A i i i

  • 8/10/2019 Process Maddah

    145/263

    2. Issued For Design (IFD):

    Release for Basic Engineering

    Step 2,

    The following information as minimum requirement shall be reviewed and completed at this

    stage:

    1) Equipment

    - number of equipment;

    - type of equipment;- equipment No. and name

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

    5 \P A i i i

  • 8/10/2019 Process Maddah

    146/263

    2) Piping

    - size of main piping;

    - winterizing/heat conservation requirement;- valve type;

    - provision of drain and vent;

    - provision of purge, steam-out, chemical injection and water injection connections andvalving;

    - line No.;- utility services connected to each equipment, piping and packaged Unites.

    3) Instrumentation

    - type of instrument and location of the primary element;

    - location and discharge destination of the safety/relief valve;- location, type and valve functioning (failure action) of the control valve;

    - measurement and control method;- instrument tag No.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    147/263

    5 \P A ti iti \ difi i

  • 8/10/2019 Process Maddah

    148/263

    3. Approved For Design (AFD):

    Release for End of Basic Engineering

    Step 3,

    The purpose of issuing the P&I Diagrams , is the Companys approval on the basis of

    detailed design for piping layout.The minimum information which should be added on the P&ID at this stage shall be as

    follows:

    1) Equipment

    - elevation of equipment;

    - size of equipment;

    - internal of equipment.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

    5 \P A ti iti \P&ID M difi i

  • 8/10/2019 Process Maddah

    149/263

    2) Piping

    - line class;

    - miscellaneous piping size (except around the safety/relief valve and control valve);- thermal and cold insulation;

    - correct orientation of piping around equipment.

    3) Instrumentation

    - size of main control valves;

    - additions and revisions on the basis of detailed design.

    4) Vendors packaged uni ts

    - The details of some available information concerning the Vendors shall be indicated.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

  • 8/10/2019 Process Maddah

    150/263

    5 \P A ti iti \P&ID M difi i

  • 8/10/2019 Process Maddah

    151/263

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

    2) Instrumentation

    - sizes of the safety/relief valves;

    - sizes of the control valves;- details concerning level transmitters and level gages;

    - logic diagram for heaters, incinerators, compressors, and all other main equipment(where applicable).

    - Consequences of details of cause and effect tables.

    3) Vendors information

    - The necessary information concerning the Vendors, equipment shall be indicated.

    5 \P A ti iti \P&ID M difi ti

  • 8/10/2019 Process Maddah

    152/263

    5. Approved For Construction (AFC):

    End of Detail EngineeringStep 5,

    The P&I Diagram shall be issued for construction after completion of the followingactivities:

    - piping material table;- piping class and all relevant job specifications;

    - all job specifications and standard drawings in relation to the preparation of P&I

    Diagrams;- logic diagram of the main equipment;

    - hydraulic of system;- size of all piping, valves and instrumentation components;

    - vendors information.

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

    5 \P A ti iti \P&ID M difi ti

  • 8/10/2019 Process Maddah

    153/263

    5:\Process Activities\P&ID Modification

    f a r a go st a r a nf a r a go st a r a n

    6. As Built (ASB):

    End of construction

    Step 6,

    - The P&I Diagram as-built shall be prepared in accordance with the results of linechecking and the final edition of the field sketches.

    - The specified piping and instrument take-off and branch points shall be observed

    as strictly as possible and shall be implemented on the P&I Diagram.

  • 8/10/2019 Process Maddah

    154/263

    5:\Process Activities\P&ID

  • 8/10/2019 Process Maddah

    155/263

    5:\Process Activities\P&ID

    Piping & Inst. Diagram (P&ID)

    Contract

    Codes/ Std./ Eng. Practice

    Licensor Comments

    Plot Plan

    Technical Proposal

    Process Calculation

    Inst./Equipment

    Piping Material Specification

    Design Basis & Criteria

    Licensor Basic Design

    PFD

    f a r a go st a r a nf a r a go st a r a n

    5:\Process A ti iti \P&ID

  • 8/10/2019 Process Maddah

    156/263

    f a r a go st a r a nf a r a go st a r a n

    PROCESS ACTIVITIES

    H&M BALANCE

    BFD

    PFD

    UFD

    SIMULATION

    PROCESS DESCRIPTION

    DESIGN BASIS

    P&ID

    5:\Process Activities\P&ID

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    157/263

    5:\Process Activities\Design Criteria

    SCOPE

    PURPOSE

    MECHANICAL DESIGN CONDITIONS

    EQUIPMENT DESIGN CRITERIA

    PIPING

    f a r a go st a r a nf a r a go st a r a n

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    158/263

    5:\Process Activities\Design Criteria

    1.0 SCOPE

    These design criteria cover the general requirements for the process design ofoil, gas

    and petrochemical plants.

    Cases or applications not specifically covered by these criteria shall be handled on an

    individual basis. All applicable codes and standards shall apply to these cases.

    f a r a go st a r a nf a r a go st a r a n

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    159/263

    5:\Process Activities\Design Criteria

    2.0 PURPOSE

    Basic Engineering

    The purpose of this document in BASIC Engineering is to: Standardize and group preferred options and alternatives.

    Establish and correlate a source of basic information of typically multidiscipline interestsfor easy access and common reference.

    Serve as minimum basic sizing criteria.

    Detailed Engineering

    The purpose of this document in DETAILED Engineering is to:

    Clarify the options selected for equipment design during BASIC Engineering Define the minimum requirements for completion of DETAILED

    Engineering

    f a r a go st a r a nf a r a go st a r a n

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    160/263

    5:\Process Activities\Design Criteria

    3.0 MECHANICAL DESIGN

    CONDITIONS

    Design Pressure

    Design Temperatures

    f a r a go st a r a nf a r a go st a r a n

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    161/263

    5:\Process Activities\Design Criteria

    f a r a go st a r a nf a r a go st a r a n

    3.1 Design Pressure

    3.1.1 Pressure Vessel

    The design pressure for pressure vessel (equipment fabricated according to ASME

    VIII) shall generally be as follows:

    MOP + 7%>69

    MOP + 10%18 to 69

    MOP + 1.8 bar1.7 to 18

    3.5 barg0 to 1.7

    Full Vacuum + 3.5 barg (if external pressure is

    Atmosphere)

    Under Vacuum

    Minimum Design Pressure (barg)Maximum Operating

    Pressure MOP(barg)

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    162/263

    5:\Process Activities\Design Criteria

    3.1.2 Compressors

    Suction Side Design Pressure

    The design pressure of the equipment and piping at the compressor suction should be

    calculated based on table presented for pressure vessel. The MOP is the higherpressure of the following:

    MOP = (Suction pressure + Discharge pressure)/2

    f a r a go st a r a nf a r a go st a r a n

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    163/263

    5:\Process Activities\Design Criteria

    Discharge Side Design Pressure

    Centrifugal Compressor

    At the discharge of a centrifugal compressor:

    MOP + 1 bar, for MOP 10 barg,

    MOP + 10%, for MOP > 10 barg.

    Reciprocating compressor

    At the discharge of a reciprocating compressor:MOP + 2 bar, for MOP 20 barg

    MOP + 10%, for MOP> 20 barg

    *PSVs are required.

    f a r a go st a r a nf a r a go st a r a n

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    164/263

    3.1.3 Pumps

    Centrifugal Pumps

    Generally the pump circuit is designed for the shut-off pressure of the pump and whereno PSVs are provided for protection of the circuit. The shut-off pressure, or design

    pressure, is the highest of the following:

    Shutoff pressure = Normal suction pressure (NSP) + 1.25 of differential pressure atmaximum specified fluid density.

    Or

    Shutoff pressure = Maximum suction pressure (MSP) + differential pressure atmaximum specified fluid density.

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    165/263

    Normal and Maximum suction pressure (MSP) is calculated as follows:

    NSP = upstream equipment Operating pressure + NLL of upstream equipment

    MSP = upstream equipment PSV set pressure (design pressure) + HHLL of upstreamequipment

    Notes:

    In the case of two pumps in series, the design pressure shall be determined using thedesign pressure of the first pump as the maximum suction pressure of the secondpump.

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    166/263

    b) Positive Displacement Pumps

    At discharge of positive displacement pumps:

    MOP + 1 bar for MOP 10 barg

    MOP + 10% for MOP > 10 barg

    PSVs are required.

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    167/263

    3.1.4 Heat Exchangers

    The same method used for pressure vessel should be applied for heat exchangers.

    If a control valve or block valve is installed downstream of a heat exchanger:

    The design pressure of the exchanger = the upstream equipment design pressure.

    If a control valve or block valve is installed upstream of an exchanger (No valve ondownstream of exchanger):

    The design pressure of the exchanger = design pressure of the downstreamequipment at the entry point + 1.25 times the maximum pressure drop in the systembetween the inlet of the exchanger and the inlet of the downstream equipment + statichead (if any).

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    168/263

    An exchanger on the discharge side of a gas driven compressor shall have a designpressure equal to or greater than the setting of the PSV for the system.

    Exchanger operating under a vacuum shall be designed for full vacuum.

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    169/263

    3.1.5 Storage Tanks

    Atmospheric and near atmospheric tanks

    - If the specific gravity of stored liquid is lower than 1.0, the design pressure ofatmospheric storage tanks with open vent or without gas blanketing shall be designed

    full of water + 50 mm water column.

    - If the specific gravity of stored liquid is higher than 1.0, the design pressure ofAtmospheric storage tanks (open vent or without gas blanketing) shall be designed fullofproduct + 50 mm product column.

    For atmospheric storage tanks with gas blanketing, the design pressure of atmosphericstorage tanks shall be designed full of water + 150 mm water column and -50 mmwater column for vacuum condition.

    API STD 2000 also describes the pressure and vacuum design requirement ofatmospheric tanks put in this category.

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    170/263

    Other storage tanks (Spheroid, etc.)

    Depending on the type of tank, higher design pressures could be specified. This shall

    be treated on a case-by-case basis depending on tank type but if storage tank has a

    design pressure higher the 1.0 barg, it categorized as pressure vessel (pressurized

    storage tank).

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    171/263

    3.1.6 Pipelines

    For pipelines, the design pressure is a function of the MOP and a design factor which

    depends on the location. Process Engineer determines the MOP only; normally it is thedesign pressure of the last equipment upstream of the pipeline plus the hydrostatic

    pressure due to the pipeline profile.

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    172/263

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    173/263

    3.2 Design Temperatures

    - The design temperatures shall be generally specified as follows, for determination of

    design temperature using the following table it is necessary to specify the lower andupper limit of operating temperature of the equipment

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    174/263

    5:\Process Activities\Design Criteria

    To be specified according to selected material and process

    requirements.Above 343 C

    Max. Op. Temp. + 25 C

    orExceptional operating temp.Between 60 C and 343 C

    85 C (min)

    or

    Exceptional operating temp.

    Between 0 C and 60 C

    Higher Limit :

    Min. Op. Temp.5 CBetween -29 C and 0 C

    - 45 CBetween -39 C and -30 C

    -100 CBetween -100 C and -40 C

    Min. Op. Temp.Less than -100C

    Lower Limit:

    Design Temperature (C)Operating Temp. (C)

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    175/263

    Notes:

    - Exceptional operating temperature is to be considered for operations durationexceeding a total of 100 hours per year.

    - 85 C is the minimum design temperature due to solar radiation.- The design temperature of equipment located downstream of air cooler or trim coolershall be specified as larger of:

    Operating temperature +25 C

    Or

    Inlet operating temperature of upstream cooler

    5:\Process Activities\Design Criteria

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    176/263

    5:\ ocess c v es\ es g C e a

    4.0 EQUIPMENT DESIGN

    CRITERIA

    Pump

    Compressor

    Heater

    Vessel

    Heat exchanger and Cooler

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    177/263

    g

    4.1 Pumps

    All pumps, where their failure would cause a plant shutdown or unsafe conditions, shall

    have a spare installed. One spare unit of a pump should be considered unless stated

    otherwise.

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    178/263

    g

    - The minimum margin between the normal and rated flow for a pump shall be asfollows:

    +15% of normal flowReciprocating and rotary

    +30% of normal flowMetering

    +20% of normal flowChemical Injection

    +10% of normal flowLoading / Transfer

    +10% of normal flowExport (continuous operation)

    +10% of normal flowUtility+10% of normal flowOther Process

    +25% of normal flowReflux, pump around and reboiler pumps

    Rated FlowType of pump

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    179/263

    g

    - The static head used in calculating the suction pressure is measured from either:

    The lowest operating liquid level in the suction vessel if this will initiate a shutdown ofthe pump when that level is reached (e.g. LSLL),

    or,

    The bottom tangent line for vertical vessels or the bottom invert line for horizontalvessels if no level-initiated pump shutdown is in place,

    to one of the following lower elevations:

  • 8/10/2019 Process Maddah

    180/263

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    181/263

    g

    - The equivalent length and frictional line losses may be calculated using theappropriate Line-sizing program. otherwise, the suction line equivalent length may beestimated from the pipe diameter d (inches) as follows:

    Pumping temperature < 150 C, Le= 8d + 30 m

    Pumping temperature 150 C, Le= 12d + 30 m

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    182/263

    g

    - Suction line sizing for reciprocating pumps shall take into account acceleration head

    by:

    Ha = L V N C / 9.8 K

    L suction pipe length, m

    V suction velocity, m/s

    N,C constant from GPSA

    K Cp/Cv

    Ha acceleration loss, m

    Reciprocating pumps shall have pulsation dampers on the suction and discharge side

    where liquid pulsation should be minimized from process and operation view points.

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    183/263

    g

    4.2 Compressors

    - All compressors, where their failure would cause a plant shut-down or unsafeconditions, shall have a spare installed. One spare unit of a compressor should beconsidered unless stated otherwise.

    - Normally a 10% margin on maximum capacity will be used for sizing of compressors.

    - The variation of gas compositions, molecular weight, Cp/CV, etc., and the operatingconditions (mainly suction and discharge temperature, pressure, and flowrate) shall betaken into account to determine the sizing case.

    - Corrosive compounds in the gas (such as sulfur oxides, hydrogen sulfides, acidiccompounds, chlorides, etc.), are to be specified by the Process Engineer as these may

    determine the selection of materials by the vendor.

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    184/263

    g

    - The following table gives an approximate value of the polytropic efficiency ofcentrifugal compressors:

    0.7712700-340000

    0.74850-12700

    0.63170-850

    Average Polytropic Eff ic iencyNominal Capacity

    (m3/hr)

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    185/263

    g

    4.3 Heaters

    - The design margin on Fired Heaters and Furnaces is 10% on heat duty.

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    186/263

    4.4 Vessels

    - The basis of sizing is the critical or terminal velocity VT (m/s), calculated from:

    VT = K [(l -g)/ g]

    where

    l , g = liquid density, vapor density (kg/m3)

    For vertical vessel vapor velocity shall be less than terminal velocity. The factor 0.85 isrecommended to calculated vapor velocity from terminal velocity.

    For horizontal vessel higher vapor velocity may be used to meet acceptable L/D, butliquid droplet separation shall be checked. The upper limit of vapor velocity forhorizontal vessels is re-entrainment velocity.

  • 8/10/2019 Process Maddah

    187/263

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    188/263

    K = 3.6 m/s

    CD = Exp (8.411 2.243 X + 0.273 X2 1.865 10-2 X3 + 5.20110-4 X4)

    Where

    X = Ln ( )

    Dp is assumed as follows:

    General services: 200 micron

    Flare K.O. drum: 600 micron

    Note: Dp, m , kg/m3 , cp

    K value without Mist Eliminator:

    D

    P

    C

    D

    2

    V

    VL3PV

    8 )(D1013.0

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    189/263

    - The following hold up should be considered for vessel sizing:

    200 mm minimum, butmust allow for time

    required to close ESD orXV or stop pump

    200 mm minimum, butmust allow for time

    required to close ESD orXV or stop pump

    Vessel Tangent

    Line to LLLL

    at least 2 minutes

    with 200 mm minimum

    at least 2 minutes

    with 200 mm minimumLLLL to LLL

    determined by the following table

    with a 350 mm

    minimum

    determined by the following table

    with a 350 mm minimumLLL to HLL

    at least 2 minutes

    with 200 mm minimum

    at least 2 minutes

    with 200 mm minimumHLL to HHLL

    Horizontal VesselsVertical VesselsLevels

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    190/263

    - The minimum liquid hold-up times between LLL and HLL are as follows:

    Greater volume of5 (below normal interface level) or10

    (between water HLL-LLL)

    Water Boot:

    5 (with a pump)

    3 (without a pump)Other Drums:

    10Atmospheric De-Gassing Drum

    5 (with or without a pump)c) Product to Exchanger or Storage Tank

    5b) Product to other Column

    5a) Product to next Process

    Fractionation Tower Bottoms:

    5Reflux Drum

    10 (with or without a pump)b) to other Equipment:

    10a) to a Heater

    Feed Surge Drum:

    Time (minutes)Service

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    191/263

    - The following design criteria shall be used for nozzle sizing:

    Inlet Nozzle:Horizontal No demister pad mVm2 1000

    Vertical No demister pad mVm2 1500Horizontal / Vertical Demister pad mVm2 6000

    Horizontal / Vertical Demister pad gVg2 3750

    Gas outlet nozzle:

    gVg2 3750Liquid outlet nozzle:

    V 1 m/secLiquid outlet nozzle

    The minimum nozzle diameter shall be 50 mm (2 in.).

    Where:

    is fluid density in kg/m3V is fluid velocity in m/sec

  • 8/10/2019 Process Maddah

    192/263

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    193/263

    - Number of Manways shall be determined according to the followings:

    Vessels

    A single manway shall be provided for vessel length or height less than 6 m.

    For other vessels (length or height > 6 m), a minimum of two manways shall be

    provided; one manway each 6 m for longer or taller vessel.

    If vessel is equipped with internals (baffle, etc.), one manway shall be provided foreach compartment.

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    194/263

    - Number of Manways shall be determined according to the followings:

    Trayed Columns

    Manways shall be provided at the top, below the bottom tray, at the feed tray and

    At any other tray at which removable internals are located.

    Manways shall also be provided at intermediate points so that the maximum spacing ofmanways does not exceed 15 trays. This shall be reviewed on a case-by-case basis.Tray spacing with manway between internal shall be at least 900 mm.

  • 8/10/2019 Process Maddah

    195/263

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    196/263

    - The drain specification shall be determined on the following basis:

    a) Drain Location

    The drain of the vessel shall be connected:

    To the outlet line at low point for vertical vessel

    Directly on the vessel for horizontal vessel

    Directly on the vessel for vertical vessels, where the outlet line extends inside the

    vessel

    5:\Process Activities\Design Criteria

  • 8/10/2019 Process Maddah

    197/263

    b) Drain Sizes

    Vent and drain diameter shall be determined as follows:

    46V>420

    44220 < V 420 or D > 6000

    4375 &