Weekly Progress Report # 70
SVCHAIL-2
PREPARED BY: 2016
AJAZ UL KABIRProject Manager- Qassim Group
SEC EHVPD , COA , SVC Hail-2‐Mobile : 054 112 2637 , Email : [email protected]
REVIEWED BY:ABDULRAHMAN AL-KADI
Group Leader- QassimExtra High Voltage Projects Department- COA
Mobile : 050 489 6906 , Email : [email protected]
26October
Dynamic Reactive Power Compensation at Hail-2 (9031) & Al-Jouf-2 380kV SubstationsSEC CONTRACT NO. 4400003963/00
AIM/ OBJECTIVE: CONTRACT DETAILS:
SEC intends to improve rapid voltage support at Hail-2 (9031) and Al-Jouf-2 380kV Substations of SEC network by providing Conventional or Hybrid Static VAR Compensator Systems (SVC). The SVCs at Hail-2 (9031) shall be connected to spare 380kV Breaker. CB position for SVC at Al-Jouf-2 .380kV Substation will be provided by Al-Jouf-2 380kV Substation Contractor.
• Project Name ……………………….. DYNAMIC REACTIVE POWER COMPENSATION AT HAIL-2 (9031) & AL-JOUF-2 380KV SUBSTATIONS
• Contract No ………………………… 4400003963/00
• Owner ………………………………. SAUDI ELECTRIC COMPANY - COA
• SEC Project Manager ……………… ENGR. AJAZ UL KABIR
• Contractor ………………………...... SIEMENS LTD.
• Address ……………………………... SIEMENS COMPANY LIMITED, P.O.BOX 9510, RIYADH 11423, KSA
• Contractor Project Manager ………. ENGR. REHAN ULHAQUE
• Contract Effective Date ……………. 03-JUNE-2014
• Contract Value ……………………... SAR 463,840,000.00
PROJECT DESCRIPTION & CONTRACT INFO
SVC HAIL-2
• Technical Completion Certificate (TCC) : 02-JUNE-2016• Preliminary Acceptance Certificate (PAC) : 02-AUGUST-2016• Final Acceptance Certificate (FAC) : 02-NOVEMBER-2016
TIME LINE
SVC HAIL-2
Jun-14
Jun-14
Jun-14
Jun-16
Aug-16
Nov-16
SVS set up2x SVC PLUS2x TSC
32kV
380 kV
15% at 450 MVA +/-5%
Q at 32 kV (1.0 pu)2 x (0\+143.1 Mvar) cap 2 x (-75\+81.9 Mvar)
Ik=63kA
SVC PLUSSVC PLUS
TSC TSC
Installation of +450MVAr (Capacitive) & -150MVAr (Indutive) 380kV SVC System
SVC CONNECTION DIAGRAM
SVC HAIL-2
PROJECT SIGN BOARD• Contract Signing : June 03, 2014
• Kick off Meeting : June 24, 2014
• Site Handover : June 26, 2014
• TCC: June 02, 2016
• PAC: August 02, 2016
• FAC: November 02, 2016
SVC HAIL-2
CONTROL ROOMProtection & Control System / SAS / Alarms / Metering (SIEMENS)
Electrical:
Progress - SlowWitnessing with CSD Engineer started from 19/03/2016 and in progress for • SAS OLT – 100% completed• SCADA Closed Loop Test: Start from 18/10/2016 – 55%
completed
• SAS SAT: In Progress - 90% completed
• Kirk interlocking interlock completed.
• Final Trip Test completed.
• Snag Clearance in Progress
• Post Energization Test (to be done after Energization of SVC Transformer & 13.8kV Auxiliary System) : Need 14 Working Days to put SVC in service
SVC HAIL-2
SVC HAIL-2HVAC & FPS
Electro-Mechanical:
• Testing of Fire alarm & Fire fighting with ISD completed.
• Fire Hydrant System testing with ISD Completed.
• HVAC installation works – 100% completed
• Internal Air balancing testing works in progress
• Testing works for HVAC panel control room in progress
Dynamic & Static Reactive Power Compensator at Al Jouf-2, 380kV Substation
Contractor Date of award TCC Handed Over Ex Energize dateSIEMENS 03.06.2014 02.06.2016 26.06.2014 15/10/2016
COMMISSIONING STATUS
(98.5 % completed)
EQUIPMENT REMARKS
(Delivery status – 100 % completed)
EXPECTED BUILDING READINESS BUILDING EXP. DELIVERY SUPPLIER EQUIPMENT S/N
Witnessing with CSD – 100% completedOLT – 100% completedCLT – % completed
Delivered and Installed Foundations completed Outdoor Foundations 30-12-2015 SIEMENS SVC Equipment's 1
Witnessing with CSD – 100% completed Delivered and Installed Foundations completed Transformer Foundation 15-12-2015 SIEMENS 450MVA Power Transformer's 2
Witnessing with CSD – 99% completed Delivered and Installed Building and foundation are
ready Control Building 15-12-2015 ALFANAR, KSA & SIEMENS 13.8kV Switchgear & RMU 3
Witnessing with CSD – 100% completed Delivered and Installed Foundation ready Transformer Foundation 15-02-2016 UTEC, KSA Auxiliary Transformer /
Grounding Transformer 4
Witnessing with CSD – 100% completed Delivered and Installed
Building Ready Control Building
15-01-2016 TBD Protection System 5
Witnessing with CSD – 100% completed Delivered and Installed 15-12-2015 HEPOCKEE &
BENNING Battery & Battery Charger 6
Witnessing with CSD – 100% completed Delivered and Installed 30-12-2015 TBD AC / DC Panel 7
HV Cable termination completed Delivered and Installed Steel structure installed Trench and duct bank
ready 25-10-2015 TBD & LS Cable Steel Structures, Cables and Earthing Materials 8