PS1-PR1-15

Embed Size (px)

Citation preview

  • 8/3/2019 PS1-PR1-15

    1/4

    Development Plan of

    Korean Energy Management System

    Jinsu Lee*, Seokha Song**, Sunghak Kim***

    Abstract Korea Power Exchange (KPX) is currently under the developing an EnergyManagement System. This paper reports on the development plan of the Korean Energy

    Management System (K-EMS). In addition to the basic EMS functions such as SCADA,

    Automatic Generation Control, Economic Dispatch, Network Analysis and Dispatcher Training

    Simulator, the K-EMS will also have market related function, Dispatch Optimal Schedule. The K-

    EMS will be developed as 3 phases such as Base-line EMS, Proto-type EMS and finally Full-scale

    EMS through 5 years.

    Keywords:Energy Management System, SCADA, Automatic Generation Control, EconomicDispatch, Network Analysis, Dispatcher Training Simulator.

    1. Introduction

    The Korea Power Exchange is the electricity market

    operator and independent system operator for the Korea

    electric power grid. As of April 2, 2001, following the

    government-driven restructuring plan and under the

    Electricity Business Act of Korea, the KPX was founded as

    a core organization responsible for management of thenewly introduced competitive electricity market in Korea.

    The objective of the KPX is to manage the electricity

    market in a reasonable and transparent manner so that

    power producers and suppliers can participate in the market

    with equal rights.

    Korea electricity market has been in operation since

    April 2, 2001. As the first stage of competition, generation

    sectors have been in competition and they submit dispatch

    offers. This Cost Based Pool price consists of System

    Marginal Price and Capacity Payment. The System

    Marginal Price reflects the production costs of the lastgenerator brought into operation and this ensures that actual

    generation cost is paid. The Capacity Payment is paid to all

    generators that submitted offers, whether or not dispatched,

    for capital cost recovery. In the Cost Based Pool market,

    generators can submit capacity offers but price offers are

    not allowed. Generators are obliged to provide the details of

    their production costs. This information is then used by the

    KPX to determine the lowest rate schedules for both setting

    market prices and dispatching the generations.

    KPXs system peak load for 2005 was 54,631 MW and

    its installed generating capacity in August 2005 was 61,737

    MW. KPX operates a network of transmission lines with

    voltage levels ranging from 154 kV, 345 kV to 765 kV. The

    KPX power system is not connected to any other utilities at

    the present time, although there is a future possibility of

    interconnection with the North Korean power system. KPXalso serves the Che-Ju Island, which is connected to the

    main land by an HVDC link.

    KPXs National Control Center dispatches the generation

    resources, monitors and controls the 345kV and 765kV

    transmission system, and monitors and directs the operation

    of the looped 154kV transmission system. KPX has two

    control centers, the primary and the backup site, separately

    located for mutual backup.

    2. K-EMS Hardware Architecture

    The K-EMS will be configured using standard hardware

    products. All processors in the K-EMS system will be

    configured as dual redundant for very high availability and

    scalability.

    2.1 Processors

    The application processors (also referred to as hosts or

    servers) execute a variety of K-EMS application programs,

    such as Supervisory Control and Data Acquisition

    (SCADA), Automatic Generation Control (AGC), and

    Network Analysis (NA). Application processors typically

    serve as the centralized source of database, display, and

    * Information Technology Department, Korea Power Exchange,

    Korea.([email protected])

    ** Information Technology Department, Korea Power Exchange,

    Korea.([email protected])

    *** Information Technology Department, Korea Power Exchange,

    Korea.([email protected])

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/3/2019 PS1-PR1-15

    2/4

    report definitions. Most program and database development

    will be performed on an application processor.

    The communication processors (also referred to as front-

    end processors) retrieve, transmit, and process data to and

    from remote sources, particularly RTUs and remote

    computer systems. Communication processors typically

    operate on data definitions and other parameters down

    loaded from application processors. Data retrieved and

    processed from sources may be stored in a communication

    processor, which then distributes the data to other

    processors periodically or on demand.

    Workstations are processors primarily used to present

    displays and process user requests.

    2.2 Main Memory

    The main memory of each processor, including

    workstations, will have sufficient memory capacity to

    satisfy the requirements of all system functions under

    normal and peak conditions. At least twenty-five percent

    (25%) of each delivered main memory shall be spare

    capacity.

    The main memory of each processor will be available for

    data storage, program execution, and all input/output

    operations without restrictions. The main memory of each

    delivered processor and workstation will be expandable to

    two times the size of the delivered memory in the field

    solely by card or circuit module additions.

    2.3 Processor Utilization

    The K-EMS will support all functions using no more

    than 40% of the processing capability of each application

    processor and no more than 60% of the processing capacity

    of each communication processor under the normal

    conditions. The K-EMS will support all functions described

    in this Specification using no more than 60% of the

    processing capability of each application processor and no

    more than 70% of the processing capacity of eachcommunication processor under the normal conditions and

    the ultimate data capacity.

    2.4 Local Area Networks

    Where a local area network is used to connect processors

    to other processors or other devices to processors, the LAN

    will be non-proprietary, conforming to the ISO8802/IEEE

    802 series standards. LAN interfaces will preclude LAN

    failure if a processor, device, or LAN interface fails. LAN

    interfaces will also allow reconfiguration of the LAN and

    the attached devices without disrupting operations.

    2.5 Consoles

    A console may consist of one or more workstations

    driving one or more monitors, a single keyboard, and a

    cursor positioning device. The user will be able to switch

    the keyboard and cursor positioning device, as a unit,

    among all the monitors at a console via pushbuttons or

    other controls.

    2.6 Mapboards

    A hybrid mapboard consisting of multiple rear projection

    display units, computer-based chart recorders, digital

    indicators, and time displays will be provided with K-EMS.

    2.7 RTU Communication Interfaces

    RTU communications will use the IEC 60870-5, or DNP3.0 as designated by the Programmer for each

    communication channel. There will be no restriction on the

    assignment of a protocol to any single channel, except that

    individual channels need support only one protocol. The K-

    EMS will also support other industry accepted RTU

    protocols. The RTU communication speed will be 9600 bits

    per second or faster.

    2.8 Communication Interface with Other Systems

    The K-EMS will exchange data with KPX's corporate

    system and other remote computer systems. The K-EMS

    will support the data link protocols such as X.25, TCP/IP,

    ICCP, IEC 61850 and IEC 61970 in order to exchange data

    with existing and new computer systems.

    3. K-EMS Application Software

    K-EMS will apply a state-of-the-art technology of

    modern power system application.

    3.1 Supervisory Control and Data Acquisition

    The Supervisory Control and Data Acquisition (SCADA)

    function will provide real-time data collection from RTUs

    or Regional Control Centers (RCCs) located at substations

    and power plants. Through communication path between

    TFE and field RTUs, real-time data from power plants and

    high voltage substation above 345kV will be directly

    collected at every two seconds. Real-time data from 154kV

    substation will also be collected through Communication

    Interface server and local RCC system at every ten seconds.

    3.2 Automatic Generation Control

  • 8/3/2019 PS1-PR1-15

    3/4

    The Automatic Generation Control (AGC) will provide

    supplementary control that automatically adjusts the power

    output levels of generating units within KPX control area.

    AGC will include load frequency control, economic

    dispatch, frequency scheduling, reserve computation, and

    production cost monitor.

    AGC will be implemented for up to 1,000 generating

    units and be capable of controlling multiple control areas

    such as Che-Ju Island. Most of the generating units will be

    controlled by a setpoint representing the units desired

    generation output. The remaining old type generating units

    will be controlled by variable length raise/lower pulses

    representing the change in the units desired generation.

    The allocation of control to generating units will be

    executed at every four seconds.

    3.3 Network Analysis

    The Network Analysis (NA) functions will monitor the

    operation of KPX electric system, analyze electric system

    for power system security problems, and determine

    corrective and preventive control strategies which are used

    by the system operator to minimize the impact of existing

    power system security problems on reliable and economic

    operation.

    The NA functions will include State Estimator,

    Transmission Loss Sensitivity Factors, Contingency

    Analysis, Security Enhancement, Voltage Var Dispatch,

    Power Flow, and Short Circuit Analysis, etc.Real-time network application will be executed

    following the successful completion of the SE.

    3.4 Dispatch Optimal Schedule

    This dispatch engine will employ Security-Constrained

    Economic Dispatch with Network Security Analysis and

    Network Constrained Dispatch applications. In constrained

    dispatch, in addition to all the input data used in

    unconstrained dispatch, transmission limits are considered

    under normal and contingency conditions. The solution ofthe constrained dispatch satisfies the demand, network

    constraints and system constraints.

    3.5 Dispatcher Training Simulator

    The Dispatcher Training Simulator (DTS) function will

    include features for use in DTS operators for normal,

    emergency, and restorative control of the KPX power

    system. The DTS will support a power system model that

    will simulate the power system in a realistic manner

    including static and dynamic simulation of the power

    system and response to simulated events, a control center

    model that will provide an exact representation of the K-

    EMS, and instructor control features.

    The DTS will be isolated from the on-line K-EMS, but

    will have the capability to obtain data from the K-EMS

    during its initialization.

    4. Development Schedule

    K-EMS development project had been started in

    November, 2005 and will have been completed in October,

    2010. The K-EMS will be developed by three phases.

    4.1 Base-line EMS

    The Base-line EMS will be developed in 30 months from

    the starting point of the project. It will include the essential

    EMS functions as follows;

    SCADA

    Economic Dispatch

    Load forecasting

    State Estimator

    Power Flow

    Transmission Loss Factor

    4.2 Proto-type EMS

    The Proto-type EMS will be developed in 44 months

    from the starting point of the project. The following

    functions are developed and integrated with the Base-lineEMS functions into the Proto-type EMS.

    Advanced SCADA Functions

    Optimal Power Flow

    Security Constrained Economic Dispatch

    Voltage Var Dispatch

    4.3 Full-scale EMS

    The Full-scale EMS will be developed in 60 months from

    the starting point of the project. The following functions are

    developed and integrated with the Proto-type EMSfunctions into the Full-scale EMS.

    Dispatch Optimal Schedule Functions

    Security Enhancement

    Available Transfer Capability

    Short Circuit Analysis

    Contingency Analysis

    Dispatcher Training Simulator

    5. Conclusion

    There has been a great progress in an information

    technology in recent years. The electricity industry has

  • 8/3/2019 PS1-PR1-15

    4/4

    adopted those advanced technology to its various fields.

    This is same to EMS technology.

    This paper briefly described the development plan of

    Korean Energy Management System. After completion of

    the K-EMS development project, KPX, as an independent

    system operator, will operates its power system using K- E

    MS for the more optimal control and more reliable

    operation of the generation and the transmission network in

    Korea.

    AcknowledgementsThe development of Korean Energy Management System

    is supported by electricity power industry R&D project of

    the Ministry of Commerce, Industry and Energy (MOCIE)

    in Korea.

    References[1] Korea Power Exchange, "Technical Specification of

    the K-EMS," vol. 2, 2006.

    [2] Very Large Power Grid Operators, "EMS Architectures

    for the 21st Century", 2005 Very Large Power Grid

    Operators International Working Group #2.