RENCANA ANGGARAN BIAYA
Pekerjaan Perencanaan Jalan HK 2
Lokasi :Kalimantan Tengah
Waktu : 5 bulan
A BIAYA LANGSUNG PERSONIL
1 Staf Profesional
No PosisiPengalaman Jumlah Bulan
M.MBilling Rate
Profesional Personil Kerja Rp
1 Ketua Tim/Team Leader 6 TH 1 5.00 5.00 12,000,000.00
Pekerjaan Desain/Review Desain
2 TA Jalan Raya 4 TH 3 5.00 15.00 10,000,000.00
3 TA Jembatan 4 TH 1 5.00 5.00 10,000,000.00
4 TA Mekanika Tanah 4 TH 1 3.00 3.00 10,000,000.00
5 TA Geodesi 4 TH 1 3.00 3.00 10,000,000.00
JUMLAH
2 Teknisi
No PosisiJumlah Bulan
M.MBilling Rate
Personil Kerja Rp
1 Juru Ukur Senior 4 TH 1 3.00 3.00 3,000,000.00
2 Juru Ukur 4 TH 3 3.00 9.00 2,500,000.00
3 Kepala Juru Gambar/CAD 1 5.00 5.00 3,000,000.00
4 Juru Gambar/CAD 5 5.00 25.00 2,500,000.00
JUMLAH
3 Tenaga Penunjang
No PosisiJumlah Bulan
M.MBilling Rate
Personil Kerja Rp
1 Office Administrator 1 5.00 5.00 1,500,000.00
2 Operator Komputer 1 5.00 5.00 950,000.00
3 Sekretaris 1 5.00 5.00 950,000.00
4 Office Boy 1 5.00 5.00 800,000.005 Sopir 1 5.00 5.00 800,000.00
JUMLAH
JUMLAH Sub Total :
:
5/9/2018 RAB konsultan HK2 - slidepdf.com
http://slidepdf.com/reader/full/rab-konsultan-hk2 2/5
T o t a l
Rp
60,000,000.00
150,000,000.00
50,000,000.00
30,000,000.00
30,000,000.00
320,000,000.00
T o t a l
Rp
9,000,000.00
22,500,000.00
15,000,000.00
62,500,000.00
109,000,000.00
T o t a l
Rp
7,500,000.00
4,750,000.00
4,750,000.00
4,000,000.004,000,000.00
25,000,000.00
-
5/9/2018 RAB konsultan HK2 - slidepdf.com
http://slidepdf.com/reader/full/rab-konsultan-hk2 3/5
B BIAYA NON PERSONIL
1 Mobilisasi & Demobilisasi
No Posisi Personil Perjl.Rate T o t a l
Rp Rp
1 Ketua Tim/Team Leader 1 2.00 500,000.00 1,000,000.00
Pekerjaan Desain/Review Desain
2 TA Jalan Raya 3 2.00 400,000.00 2,400,000.00
3 TA Jembatan 1 2.00 400,000.00 800,000.00
4 TA Mekanika Tanah 1 2.00 400,000.00 800,000.00
5 TA Geodesi 1 2.00 400,000.00 800,000.00
JUMLAH 5,800,000.00
2 Perjalanan Dinas
No Posisi Personil TripRate T o t a l
Rp Rp
1 Ketua Tim/Team Leader 1 2.00 5,000,000.00 10,000,000.00
Tenaga Ahli
2 TA Jalan Raya 3 10.00 5,000,000.00 ###
3 TA Jembatan 1 10.00 5,000,000.00 50,000,000.00
4 TA Mekanika Tanah 1 3.00 5,000,000.00 15,000,000.00
5 TA Geodesi 1 3.00 5,000,000.00 15,000,000.00
JUMLAH ###
3 Sewa Kantor
No Jenis Jumlah BulanRate T o t a l
Rp Rp
1 Sewa Kantor 1 5.00 2,500,000.00 12,500,000.00
JUMLAH 12,500,000.00
4 Lain - Lain
No Jenis BulanRate T o t a l
Rp Rp
1 Telepon / Fax 5.00 1,250,000.00 6,250,000.00
2 ATK 5.00 1,500,000.00 7,500,000.00
3 Sewa Kendaraan roda 4 x 2 10.00 5,000,000.00 50,000,000.00
4 Sewa Kendaraan roda 2 5.00 1,000,000.00 5,000,000.00
JUMLAH 68,750,000.00
5/9/2018 RAB konsultan HK2 - slidepdf.com
http://slidepdf.com/reader/full/rab-konsultan-hk2 4/5
5 Pelaporan
No Jenis UkuranJumlah Satuan Total
uku)/(Se Rp. Rp.
1 Laporan desain A4 3.00 600,000.00 1,800,000.00
2 Album Gambar A3 3.00 3,000,000.00 9,000,000.00
JUMLAH 10,800,000.00
5/9/2018 RAB konsultan HK2 - slidepdf.com
http://slidepdf.com/reader/full/rab-konsultan-hk2 5/5
REKAPITULASI HARGA
Pekerjaan : Perencanaan Jalan HK 2
Lokasi : Kalimantan Tengah
Waktu : 5 bulan
No I T E M T O T A L
A BIAYA LANGSUNG PERSONIL Rp. 454,000,000.00
1 Staf Profesional Rp. 320,000,000.00
2 Teknisi Rp. 109,000,000.00
3 Tenaga Penunjang Rp. 25,000,000.00
B BIAYA NON PERSONIL Rp. 337,850,000.00 0.43
1 Mobilisasi & Demobilisasi Rp. 5,800,000.00
2 Perjalanan Dinas Rp. 240,000,000.00
3 Sewa Kantor Rp. 12,500,000.004 Lain - lain Rp. 68,750,000.00
5 Laporan Rp. 10,800,000.00
JUMLAH Rp. 791,850,000.00
PPN 10 % Rp. 79,185,000.00
T O T A L Rp. 871,035,000.00
TOTAL DIBULATKAN Rp. 871,035,000.00
Terbilang :