Rab Rtbl Bwk b Kabupaten Luwu Utara

Embed Size (px)

DESCRIPTION

RAB RTBL

Citation preview

  • SATUANKERJA :DINASPEKERJAANUMUMTAHUNANGGARAN :2012PROGRAM :PERENCANAANTATARUANGLOKASI :KAB.LUWUUTARAPEKERJAAN :PENYUSUNANRENCANATATABANGUNANDANLINGKUNGAN(RTBL)

    BWKBKEC.MASAMBAKAB.LUWUUTARAWAKTUPELAKSANAAN :90(SEMBILANPULUH)HARIKALENDER

    No.Item JUMLAH(Rp)1 3

    I 81,650,000.00RpI.1 66,000,000.00RpI.2 10,550,000.00RpI.3 TENAGAPENDUKUNG 5,100,000.00Rp

    II 31,987,000.00RpII.1 2,880,000.00RpII.2 24,107,000.00RpII.3 5,000,000.00Rp

    JUMLAH 113,637,000.00RpPPN 11,363,700.00RpTOTAL 125,000,700.00RpDIBULATKAN 125,000,000.00Rp

    Makassar,17September2012Penawar:

    CV.MUTAHIR

    Hj.DARMAWATI,SHDirektris

    Terbilang:SeratusDuaPuluhLimaJutaRupiah

    BIAYALANGSUNGNONPERSONILMOBILISASI&DEMOBILISASITENAGAAHLIBIAYAOPERASIONAL/FASILITASKANTOR

    REKAPITULASIRENCANAANGGARANBIAYA

    TRANSPORTASIDANAKOMODASI

    URAIANJENISBIAYA2

    BIAYALANGSUNGPERSONILPERSONILTENAGAAHLITENAGASUBPROFESIONAL

  • SATUANKERJA :DINASPEKERJAANUMUMTAHUNANGGARAN :2012PROGRAM :PERENCANAANTATARUANGLOKASI :KAB.LUWUUTARAPEKERJAAN :PENYUSUNANRENCANATATABANGUNANDANLINGKUNGAN(RTBL)

    BWKBKEC.MASAMBAKAB.LUWUUTARAWAKTUPELAKSANAAN :90(SEMBILANPULUH)HARIKALENDER

    ORANGBULAN

    I BIAYALANGSUNGPERSONIL 81,650,000.00RpI.1 PERSONIL/TENAGAAHLI

    1.AhliMuda 1 3 3 5,000,000.00Rp 15,000,000.00Rp 2.AhliPratama 4 3 12 4,250,000.00Rp 51,000,000.00Rp

    Jumlah 66,000,000.00Rp

    I.2 TENAGASUBPROFESIONALCAD/CAMOperator 1 3 3 1,850,000.00Rp 5,550,000.00Rp AssistantProfesionalStaf 1 3 3 1,300,000.00Rp 3,900,000.00Rp Surveyor 2 0.5 1 1,100,000.00Rp 1,100,000.00Rp

    Jumlah 10,550,000.00Rp

    I.3 TENAGAPENDUKUNGComputerOperator 1 3 3 850,000.00Rp 2,550,000.00Rp StafAdministrasi 1 3 3 550,000.00Rp 1,650,000.00Rp Driver 1 3 3 300,000.00Rp 900,000.00Rp

    Jumlah 5,100,000.00Rp

    II BIAYALANGSUNGNONPERSONIL 31,987,000.00RpII.1 MOBILISASI&DEMOBILISASITENAGAAHLIA PerjalananLokalAntarKab/Kota

    1.AhliMuda 1 2 2 650,000.00Rp 1,300,000.00Rp 2.AhliPratama 4 2 2 400,000.00Rp 800,000.00Rp

    B PerjalananLokalKeDaerah1.AhliMuda 1 2 2 250,000.00Rp 500,000.00Rp 2.AhliPratama 4 2 2 140,000.00Rp 280,000.00Rp

    Jumlah 2,880,000.00Rp II.2 BIAYAOPERASIONAL/FASILITASKANTORA BiayaOpasionalKantor

    1.BiayaSewaKantor ls 3 1 1,000,000.00Rp 3,000,000.00Rp 2.BiayaListrik,AirdanTelepon ls 3 1 1,000,000.00Rp 3,000,000.00Rp 3.ATK ls 3 1 500,000.00Rp 1,500,000.00Rp 3.BiayaOperasionalKomputer ls 3 1 750,000.00Rp 2,250,000.00Rp

    B BiayaPeralatanUtama1.AlatSurveyLainnya ls ls 1 500,000.00Rp 500,000.00Rp 2.Measurement&DraftSet ls ls 1 500,000.00Rp 500,000.00Rp

    C BiayaPelaporan1.LaporanPendahuluan 5 Exp 250,000.00Rp 1,250,000.00Rp 2.LaporanAntara 5 Exp 250,000.00Rp 1,250,000.00Rp 3.LaporanAkhir 10 Exp 350,000.00Rp 3,500,000.00Rp 4.AlbumPetaA3 5 Exp 530,000.00Rp 2,650,000.00Rp 5.Ekspose 3 kali 1,500,000.00Rp 4,500,000.00Rp 6.CDDokumentasi 10 bh 20,700.00Rp 207,000.00Rp

    Jumlah 24,107,000.00Rp II.3 TRANSPORTASIDANAKOMODASI

    1.SewaKendaraanRoda2(dua) 3 3 12 125,000.00Rp 1,500,000.00Rp 2.SewaKendaraanRoda4(empat) Ls Ls 1 3,500,000.00Rp 3,500,000.00Rp

    Jumlah 5,000,000.00Rp

    JUMLAHHARGA(Rp)

    RINCIANBIAYA

    VOLUMENOITEM

    WAKTUHARGASATUAN(Rp)

    JUMLAHURAIANBIAYA