28
Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement, Acquisition and Analysis

Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Embed Size (px)

Citation preview

Page 1: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Reliability Demand Response Product February 25, 2011

John GoodinLead, Demand ResponseMarket Design & Regulatory Policy

Jill PowersManagerEnergy Measurement, Acquisition and Analysis

Page 2: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Today’s Discussion

• Why the Reliability Demand Response Product (RDRP)

• Product Foundation- Proxy Demand Resource Product

• What is RDRP and How is it being Implemented?

Slide 2

Page 3: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

WHY RDRP?Today’s Discussion

Page 4: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

RDRP addresses long standing concerns with emergency demand response programs.

• Emergency demand response programs can only be utilized under extreme conditions but account for a significant amount of resource adequacy requirements (nearly 4%).

• Dispatching these resources outside of ISO markets and systems can suppress price signals.

Slide 4

CPUC initiated a settlement proceeding as part of its demand response efforts to address these concerns.

Page 5: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

The settlement resolved these concerns and defined requirements for reliability demand response product.

• Limits the quantity that can satisfy the resource adequacy requirement to 2% of the ISO all-time system peak.

– Transitions from the current ˜ 4% to the 2% limit as follows:

• Allows emergency resources to be available at a Warning Notice in advance of a Stage 1 or Stage 2 emergency.

Slide 5

RA Qualifying Emergency Demand Response

2012 2013 2014 & Beyond

3% 2.5% 2%

Page 6: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

RDRP integrates emergency DR programs into the ISO market.

• Product can be offered by any demand response provider

• Eligible to set the locational marginal price

• Like a generator, dispatched by location and MW quantity

• Enables economic energy bids in the day-ahead

• In real-time, bids limited to ISO bid cap and 95% of bid cap

• Sets availability limits of 15 times and/or 48 hours per term

Slide 6

Page 7: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

RDRP helps complete package of solutions for wholesale market demand response.

Slide 7

Page 8: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

PRODUCT FOUNDATION-PROXY DEMAND RESOURCE

Today’s Discussion

Page 9: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Participating Load ProductLong-standing CAISO DR Model

Slide 9

DLAP

• Load Serving Entity (LSE) and Demand Response Provider (DRP) act as single entity

• PL “Load” scheduled and settled at Custom LAP (CLAP)

• “Pseudo gen” used to offer A/S capacity and RT energy resource at CLAP

• PL load and pseudo generation resources treated independently in the DA scheduling process

PL(CLAP)

LSE(Default LAP)

Didn’t satisfy FERC Order 719 that enabled the LSE and DRP to be distinct entities

Page 10: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

CAISO Needed New Demand Response Solutions

• Integrate DR into the CAISO Market– Enable easier integration of retail DR programs– Increase DR participation in the wholesale markets

• Provide a Model that Enabled “Direct Participation”– Allow Demand Response Provider (DRP) to participate

independent of the load-serving entity (LSE)– Comparable treatment allowing Day-Ahead, Real-Time

Energy and Ancillary Service (AS) market participation– Enable DR all hours/days of the year

Slide 10

Page 11: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Proxy Demand Resource (PDR)New Demand Response model Launched August 10, 2010

• Load serving entities (LSE) load continues to forecast bid at the DLAP.

• Demand response provider (DRP) bids the demand response portion of the load into the ISO markets as a separately defined proxy demand resource (pseudo generator).

• The LSE and the DRP could be the same entity or two separate entities.

Slide 11

DRPPDR

LSEDLAP

Proxy Demand Resource

Provides Direct Participation and Simplification of Forecasting/Scheduling

Page 12: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Proxy Demand Resource Implementation Elements

• CAISO Agreement• Establish Resources• Registration• Market Participation• Baseline

– Measurement of PDR Performance• Settlement

– Demand Response Provider– Load Serving Entity

Slide 12

Page 13: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Slide 13

Proxy Demand Resource ImplementationHigh-Level Process Integration

Page 14: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

New DR System to Support PDRLeveraging UISOL’s DRBizNet Framework

14

Manage PDR/RDRP registration process

High-Level PDR Resource Registration Process Flow with DRS Enhanced LSE /UDC Review Process Functionality

CAISO

CAISO

UDC

UDC

LSELSE

DRP

DRP

YES

NO

YES

NO

UDC Reviews Registration Detailwith opportunity to

provide review comments

Additional information

Needed by CAISO from DRP

CAISO Deny

LSE Reviews Registration Detailwith opportunity to

provide review comments

Provide PDR Resource ID

to DRP

Update Master File & notify DRP of Effective Date

Auto Complete Review

CAISO Approves

CAISO Review

Review Complete before 10

business days

DRP begins Baseline Meter Data Submittal

DRP submits Registration for

Review

DRP begins RDT Process

DRP Enters/Edits

Resource Registration

Data

Begin Registration

All events are available on

the DRS event search screen

Track underlying load locations

PDR/RDRP interval meter data management

Consolidated PDR/RDRP events (outages, awards, dispatches)

Automated baseline calculations

Performance Measurement calculations and Default Load Aggregation (DLA) management

Page 15: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Market

15

Market Participation

DailyMeter Data

Submission for PDR or DA

RDRP; after the fact for RT only

RDRP resources

BaselinePerformance Measurement

Default Load Adjustment

Settlement

Post-Market Activities

PDR/RDRP ProcessesHigh Level Sequential Activity Flow

Secure Agreements

Registration Process

Begin: Provideend use load location info

End: ReceiveMarket Resource ID

for PDR

AccessDRS

DemandResponse System

Submit 45 days of historic meter dataEstablishing PDR

Baseline

Pre-Market Activities

Page 16: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Slide 16

Agreements

• Demand Response Provider establishes agreements prior to participating in the ISO Wholesale Energy Markets– Agreement with Load Serving Entity (LSE) – Agreement with Utility Distribution Company (UDC)– Agreement with ISO (DRP and SC)

“Above the Line” – Within the CAISO

“Below the Line” – Outside the CAISO

Wholesale Market Participation as PDR or RDRPSettlement of PDR or RDRP Performance with DRPSettlement of DLAP Load incorporating DLA with LSE

Any Other Contractual Arrangements Between the DRP & LSE

Page 17: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Slide 17

– A Registration is composed of one or more locations in a single Sub-Lap

– Location refers to a retail customer location uniquely identified by a UDC account number

– LSE and UDC have opportunity to review Registration information through DR System and provide CAISO with input on its accuracy

– CAISO makes final approval of registration

Manage Registration Process

DRP creates Registrations to establish a PDR or RDR resource

DRP uses the DR System to submit service locations and registration information for LSE/UDC review and ISO approval.

PDR/RDRR Constrained to Single Sub-LAP

Page 18: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Sub-LAPs

Page 18

• 23 Sub-LAPs within CAISO Control Area

• Low to no congestion between PNodes within Sub-LAP

• Historically, congestion interfaces between Sub-LAPs

Page 19: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

WHAT IS RDRP AND HOW IS IT BEING IMPLEMENTED?

Today’s Discussion

Page 20: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

RDRP Qualifications

• Availability

– All year/24x7, as resource is available

– Summer and winter terms

– 15 events and/or 48 hours/per term

– Min run time ≤ 1 hour and max run time ≥ 4 hours

– Advance notice + ramp to max curtailment must be ≤ 40 minutes

• RDRP resources:

– Min load reduction (single or aggregate) of 0.5 MW

– Contained within a sub-LAP

Slide 20

Page 21: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

RDRP Qualifications (cont’d)

• Dispatch– Real-time: based on emergency operating procedures

• Operating reserve shortage (ISO market/dispatch)• CAISO transmission emergency (ISO market/dispatch)• Local T&D emergency (utility dispatch/ISO notification)

– Marginal market clearing and dispatch– Discrete or “block” dispatch option available

•Address “firm service level” interruptible customers• Metering

– Hourly interval data for Day-ahead participation– Up to 15 minute interval ‘reads” for real-time participation

•Must be provided to ISO as 5-minute SQMD

Slide 21

Page 22: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

RDRP Market Participation

• RDRR can bid into the following markets:– Day-Ahead energy market (economic bids)

• Marginal clearing only in day-ahead– Real-Time market (reliability dispatch only)

• Marginal Dispatch, or• Discrete dispatch option available in real-time

– No A/S or Residual Unit Commitment participation

Slide 22

Market Systems used for bidding as well as for collecting market results and receiving dispatch instructions in Real-Time.

Page 23: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

RDR Resource (RDRR) ModelingMarket Systems and Applications

RDRR/PDR modeled in the network as a generator

Slide 23

Pre-defined RDRR in Sub-LAP

• Pre-modeled and pre-assigned a Generation Distribution Factor (GDF) by the CAISO

Custom RDRR in Sub-LAP

• DRP submits for a customized RDRR by selecting buses and defining the GDF to the selected buses

Page 24: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Baseline Methodology

• RDRR Meter Data Submission Process – Day-Ahead participation- requires daily submission

• Including initial 45 days of historical usage for establishing initial baseline data

– Real-time participation only- requires submission of all current and historic meter data after the event by T+5B

• Performance of the RDRR is determined using a customer baseline calculation– 10-in-10 non event day baseline methodology– Rules for selection of baseline days – Symmetrical 20% multiplicative adjustment

Slide 24

DRS used for Meter Data Submission, Baseline Calculations, DR Performance Measurement and DLA

Page 25: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Settlement Process

• DRS source of DR Performance Measurement used by SaMC for settlement of DRP’s RDR resources

• Default Load Adjustment provided by DRS to SaMC for settlement of LSE’s DLAP Load

• RDRR settled as a proxy generator– PDR paid at Day-Ahead or Real-Time LMP

• Market Participants receive a settlement statement 7 business days after the trade date

Slide 25

Page 26: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Simple Settlement Example with Default Load Adjustment

Slide 26

Settlement Assumptions:

RDRR Performance MeasurementAdj Baseline – Actual = 2MW

2 MWDLA2 MW

LSE Adjusted Meter Quantity 2 MW DLA + 8 MW Actual

= 10 MW

8 MW

Add RDRRPerformance to LSE

DLAP

LSE paid for 0 MW (Scheduled – Actual)

DRP paid for 2 MW (Expected = Performed)

No Double Payment for Demand Response

LSE DA Schedule = 10MWRDRR DA Award = 2MW

DLA

ACTUAL

Page 27: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Slide 27

RDRP to be Implemented Spring 2012PDR experiences that carry over to RDRP implementation

• Multiple User Accessibility to DRS

• Real Time Adjustment to DR Performance Measurement– Conversion of “Hourly Baseline DR Performance Measurement” to a 10

minute performance measurement for RT market activity

Challenges – Candid Comments from CAISO Implementation Team

Request greater visibility of calculation information

Updating API to allow greater upload/download functionality

DRS Enhancements – Always wanting more…

Request for more/different baseline types; part of CAISO Tariff

Challenge to assess need and best fit

Baseline Methodology – Desire for more options

Page 28: Reliability Demand Response Product February 25, 2011 John Goodin Lead, Demand Response Market Design & Regulatory Policy Jill Powers Manager Energy Measurement,

Contact Information

John GoodinLead, Demand Response

Market Design & Regulatory Policy(916) 608-7154

[email protected]

Jill PowersManager, Energy Measurement Acquisition & Analysis

Market Services(916) 608-5781

[email protected]

Slide 28