“Remediation of Historically Polluted Areas in Sarkandaugava”
Progress from April 2014 till March 2015
2
Topics of Presentation
The territories of the Project
Progress - Site I and Site II
Progress - Site III
Factors impacted Project implementation
Publicity and Swissness
3
The territories of the Project Site I (2,6 ha) - territory of “WOODISON TERMINAL” Ltd, “Ovi” Ltd and
“Eko Osta” Ltd Site II (2,9 ha) - territory of “VL Bunkerings” Ltd Site III (2,5 ha)- territory of “OVI Riga” Ltd
4
Progress - Site I and Site II
Remediation works are on-going according to the schedule
In April 2014 the construction permit was received and remediation works were started
Construction supervision is performed during all works’ period
Till end of February (2015) 289,4 tons or 32% from target set in the Logframe of floating oil products in groundwater were pumped out
Surface-active substance injection in wells was performed
In April and in October 2014 the Riga Environmental Board made a control visit at the project sites
5
Progress - Site III In May 2014 both agreements for remediation works and construction
supervision were signed
The pilot project was successfully performed from June till December 2014
In December, 2014 report about pilotproject was received by Contractor and Engineer approved submitted pilot stage final report and recommended to continue the preparation for the further implementation of the remediation project
According to agreement and FIDIC regulations construction supervision was performed all period
Till end of February (2015) 52,83 tons or 9,85% from target set in the Logframe of floating oil products in groundwater were pumped
In the summer 2015 it is planned to receive the construction permit and to start remediation works
6
Factors impacted Project implementation
The co-financing of project in amount of 856 678 CHF from the state budget was approved by the Cabinet of Ministers on 25 November 2014
The Project Budget and Logframe is planned to be updated according to the results of the pilot project in April 2015
7
Publicity and Swissness
Publications made in SES’s and MoEPRD web page
In October, 2014 project was submitted for the Energy Globe Award
Swiss expert provided consultations about procurement documentation of remediation works