RTA Nad Al Sheba Paper Full

Embed Size (px)

Citation preview

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    1/10

    GeneralDubai, one of the seven emirates

    was just a small fishermen colony,

    about fifty years ago (Fig.1a). But in

    the past 35 years, i.e. after theformation of United Arab Emirates

    (UAE), Dubai has developed by

    leaps and bounds. Dubai has

    become a hub for foreign Investors.

    Dubai is known for its modern

    structures, rapidly growing

    civilization, foreign-tourism and

    trade. It is one of the seven

    emirates of the UAE where

    maximum investment and

    developments have taken place.

    Ambitious projects like Burj-Arab

    tower (Burj-Khallifa), Burj-Dubai,

    Palm-Island, World-Island and

    several other upcoming projects

    (See Fig.1b) challenged the entire

    engineering community. The local

    government authorities are coming

    up with projects that continuously

    challenge the engineer and

    modernize the habitat in Dubai.

    But since 2007, Dubai is

    experiencing very challenging

    situation because of the global

    slow-down.

    Prestressed Concrete Bridges for Nad-al-

    Sheba Race Course Development Project,Dubai- Lessons Learnt

    AFCONS infrastructure Limited (which is the Infrastructure wing of

    M/s Shapoorji & Pallonji Group) recently executed its first bridge

    project in Dubai. It consisted of three prestressed concrete bridges

    at Nad-al-Sheba (horse and camel) Race Course, for Roads and

    Transport Authority (RTA) Dubai. During the execution, the team

    members faced various problems and creative solutions were devised.

    However, the project was completed in record time, fetching

    appreciation from the client. Various techniques adopted and other

    technical details of the project are presented in this paper.

    Vivek G. Abhyankar,Sr. Manger (Design),

    AFCONS Infrastructure limited, Mumbai

    Figure 1a: A scene of old Dubai

    160 NBM&CW MARCH 2012

    Concrete Bridges

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    2/10

    NBM&CW MARCH 2012 161

    Concrete Bridges

    Afcons, being one of the

    pioneering construction companiesof marine structures in India and

    getting diversified in other sectors

    of construction like Infrastructure,

    Nuclear and Industrial etc., was

    keen to participate in the

    international bid floated by RTA, for

    the development of Nad-Al-Sheba

    race course. As the tender was on

    International level, construction

    companies all over the world had

    participated in it. But finally RTA

    shortlisted Afcons, as the technical

    and financial bids were most

    competitive. Though it was not anew experience for the company to

    work on foreign soils, the

    responsibility to fulfill the

    expectations of RTA was a

    challenge before the project team.

    (Afcons already had a considerable

    experience in International projects

    at locations such as Mauritius,

    Madagascar (Africa), Ruwais (Abhu-

    Dabhi), Iraq etc., but mostly in the

    marine sector.) As RTA was

    considered as a strict client to work

    with, Afcons was alert during eachphase of construction.

    RTA, formerly known as Dubai

    Municipal Corporation had stringent

    norms of construction. The entire

    project was monitored by experts

    from various parts of the world

    under the shed of M/s Africon and

    Al-Burj. Invariably the projects with

    RTA are not given the Time and

    Cost extension. The contractor

    delaying on the projects may even

    get black-listed, and will not beallowed to perform any project in

    future in UAE. Officers from Britain,

    Switzerland, Sudan, Pakistan, Iraq,

    Sri Lanka were appointed by the

    company to execute the work. The

    client also had a team of competent

    engineers with focused scope.

    The overall project of Nad-al-

    Sheba race course development

    had four parts (packages) namely

    construction of roads and bridges,

    construction of water canal from sea

    till the race course (for navigation

    of visitors from other emirates), andconstruction of Main structures /

    stadium, and development of

    adjoining areas. Amongst these the

    first package of construction of

    roads and bridges was executed

    by Afcons. The overall work gave

    lots of learning to the organization

    and entire site team. The author of

    this paper is one of these teammembers. Hence the lively

    experience shared by him &

    presented in the paper would be of

    interest to all.

    Briefs About the

    ProjectNad-al-sheba race course (See

    Fig.1c) is located to the south of

    world famous Al-Burj-tower. Sea

    shore is also very close from the

    race course. The areas like Camel

    market, falcon house are very closefrom the project site.

    The scope of work for Afcons

    included construction of three

    approach Bridges (namely MDN-1A,

    MND-3D and the Main Bridge) to

    the race course and construction of

    main roads within the enter area

    (See Fig.19, showing entire

    alignment, scope of work),

    construction of canal, partly below

    the main bridge.

    The fourth bridge, approaching

    to the Race course building, called

    VIP bridge (No. 2c in Fig. 19) was

    a separate package in this tender.

    The tendering of VIP Bridge was

    done after processing first package.

    The VIP was constructed by M/s

    Figure 1b: A few modern structures (existing / coming up) in Dubai

    Figure 1c: Nad-Al-Sheba Race course - birds eye view

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    3/10

    162 NBM&CW MARCH 2012

    Concrete Bridges

    Balfour Beatty (See Fig.2). Another

    package was to construct the

    approach water canal. The

    construction of canal was done by

    M/s Dutco. The construction ofStadium building was executed by

    M/s Mydan. For the roads and

    bridges in the scope of Afcons, the

    structural design was provided by

    M/s Al-Burg and the Project

    management consultant. For the VIP

    bridge the design was provided by

    a team consisting of M/s DNEC,

    together with Africon UAE, Dutco

    Balfour Beatty LLC, and Petrofab

    Intl. FZC.

    In the present paper, the works

    executed by Afcons only are

    described in detail. The key detailsof all the three Bridges are

    described below.

    Link-1A, Link-1B were completely

    reduced from the current works

    because of financial crises. Later

    the South wing also reduced

    partially.

    Concrete grade used:

    Super structure M40

    Substructure M40

    Reinforcement Grade used: Fe500

    Project Duration: 19 months

    Project cost: 498 M Dirham (after

    Revision of scope)

    PilingThe piles were driven using

    Casagrande pile driving rigs. The

    freshly driven bores were stabilized

    using polymer solution instead of

    conventional bentonite slurry. This

    helped in maintaining a clean site.

    A steel liner was used to stabilize

    the top 10m of the freshly driven

    bore. The designed capacity of each

    pile below pier cap was 450 MT

    and 600 MT below the Abutments.

    As welding of rebars was not

    allowed, couplers were used for

    reinforcements in the piles, after

    approval from PMC, Client and

    testing lab. (Figs 3-15 show the

    project at various stages of

    construction). Table 1 shows

    quantities involved and the time

    cycle for construction of 18 m long

    piles in this project.

    Figure 2: The VIP bridge (recently completed by Ms/ Dutco Balfour Beatty LLC)

    (a) Night View on VIP Bridge(b) Fish bone shape Steel frames

    used in the VIP bridge

    Project Technical Details

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    4/10

    NBM&CW MARCH 2012 163

    Concrete Bridges

    Figure 3a: (Left) Rebar cage for piles getting ready, (right) final rebar cage for typical pile

    Figure 3b: (Left) Pile Driving in progress, (Right) Pile-cap formwork by M/s RMD Kwikform

    (i) Pile cutting device, to obtain desiredpile-cutoff level

    (ii) Freshly cut pile before finishing (iii) Cut pile just after finishing

    Figure 3c: Pile cutting

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    5/10

    164 NBM&CW MARCH 2012

    Concrete Bridges

    Figure 3d: Reinforcements of the Piers are fitted by dedicated Rebar team and View of Pier immediately after de-shuttering

    Figure 3e: Typical View of Pier Formwork supplied by M/s Anvem

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    6/10

    NBM&CW MARCH 2012 165

    Concrete Bridges

    Figure 4, 5: RMDK formwork / staging for the bridge deck and Densely reinforced Prestressed concrete section

    Figure 6. 7: Workers engaged in placing the Reinforcements and cable ducts at place and Typical View of Inner Bridge Formwork(M/s RMD Kwikform type)

    Figure 8, 9: Bridge Expansion J oints and Bearings

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    7/10

    166 NBM&CW MARCH 2012

    Concrete Bridges

    Figure 10, 11: Concreting of the bridge structure and Bitumen Road in progress

    Figure 12: MDN-1A- view of portion of completed bridge(note the white epoxy coating)

    Figure 13: Large width deck slab (

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    8/10

    NBM&CW MARCH 2012 167

    Concrete Bridges

    Construction HurdlesWhen Afcons received a work order

    for this project in August 2009, it

    was a very pleasant moment.

    Immediately the organization started

    initial mobilization of resources

    (man, material and machinery),

    considering the importance of this

    work. Here it is worth mentioning

    that all the major works associated

    with Infrastructure growth in UAE

    are directly monitored by the

    Ministry. Soon after acquiring the

    site, the site team noticed the

    clouds of Recession in all the

    trades in Dubai, including the

    construction projects. The team

    noticed that most of the Mega-projects were on the verge of

    getting Hold tag. The big projects

    like Lagoons were already closed.

    This created an unstable feeling

    within the project team members.

    After two months of initial

    mobilization, the Project team

    started working at site (Oct-Nov

    2008). In UAE the Project offices

    usually open at 6:30am / 7:00am

    and close down the work at around

    4:00pm, due to extreme heat. This

    was a time of rainy season in UAE.

    The rains imposed constraints in

    the road construction and

    underground works. This time was

    utilized by the technical team

    members, to minutely study the

    Construction drawings, prepare

    action plans, study the methods

    followed in close by projects by

    other International construction

    companies, etc. During this study,the team noticed various missing

    information / errors at a few places.

    The same was discussed with

    PMC, and queries were raised in

    the form of RFI. The clients were

    soon got flooded with many RFIs.

    Hence consultant had to appoint

    dedicated engineer to sort all the

    RFI. Considering the fast tack nature

    of project, Afcons team raised query

    / request to client (RTA) to pay

    attention to this matter. On this RTA

    instructed the contractor and

    consultant both to solve the matter

    at the earliest without affecting the

    time and cost estimate. Soon the

    consultant informed the contractor

    that there are certain changes

    expected to take place in the

    engineering details, under re-

    engineering.

    In Dubai it is mandatory for any

    party executing the works to have

    Approval with Dubai municipal

    Corp. To avoid any further delays

    in approval (leading to wastage of

    time) the organization decided toappoint an approved agency for

    construction of piling activity. Various

    approved companies were

    scrutinized and M/s Swiss Bore was

    finalized to start the work. As per

    original contract, the bored cast-in-

    situ pile of 1000 mm diameter and

    32 m depth were to be constructed.

    Immediately after constructing thefirst pile, the same was asked to

    be load tested (using the Kentledge

    method) by the PMC (see Fig.16).

    The 32m pile showed very high

    capacity during the test hence PMC

    and client asked to perform one

    more of 24m deep pile (the 24m

    depth was estimated by

    interpolation, though it was not an

    exact approach, it was fairly logical

    for friction piles in uniform strata

    as exists in places like Dubai).

    Soon the 24m pile was driven

    and tested. The 24m also passed

    the required load and settlement

    criteria. The site team was asked

    to proceed ahead with the piling of

    bridge MDN-1A with 24m depth.

    Soon the PMC started pressurizing

    the contractor to further reduce the

    length of the pile to 18m. The site

    team wanted to recheck the same

    with the tender provisions and the

    soil investigation data provided by

    the client. Finally with the reduced

    scope, the 18m pile was driven

    and tested at second bridge MDN-3D. The same also passed the

    requirements. The consultant asked

    the site team to proceed ahead

    with 18m length of pile for the

    Figure 16: Pile Load test (left) kentledge, (right) Jacks and Load cells on Pile head

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    9/10

    168 NBM&CW MARCH 2012

    Concrete Bridges

    remaining work at MDN-1A and all

    piles of MDN-3D. This iteration

    consumed lot of time.

    A typical load-settlement curve

    of pile loading test is shown in

    Fig. 17.

    When the piling work of bridge

    MDN-1A was about to get over, and

    piling work of MDN-3D was just

    started, the PMC asked contactor to

    test a 16m deep pile and test the

    same at last bridge. The 16 m

    deep pile was tested and found topass the load-settlement

    requirements. The client and PMC

    both were very happy on this cost

    saving. The PMC wanted to now

    check the 12m deep pile. Here, the

    Structural Consultant of the

    bridge had to intervene,

    asking to check the

    minimum pile length to

    resist the lateral loads, yetPMC got the approval from

    client to get the 12m pile

    checked.

    Dubais soil stratum is

    a typical example of fine

    sandy strata with week

    empty soil-pockets formed

    during soil-storms. The

    same was experienced

    while driving 12m deep pile,

    where the bore suddenly

    got collapsed inwards.

    Because of this, the clients

    instructed to stop further re-

    engineering and proceed ahead

    with the 16m deep piles.

    Unfortunately, the tendered quantity

    had got almost half. Though the

    PMC and the consultants, agreed

    with 16m depth of the pile, the

    second step of re-engineering was

    started to reduce the number of

    piles itself. But as the final pile of

    16m was just meeting the

    requirement, the number could not

    be reduced drastically. Details of

    completion of piles are shown in

    Table 2.

    The third step of re-engineering

    was in the reduction of bridge length

    in MDN-3D. Such reduction wasrequired because during the

    planning stage the minimum

    ground clearance for the bearings

    was not followed by the Planner /

    Consultants. Thus the initial few

    months time (four to five moths

    after initial mobilization period of

    two months) was critical. The

    organization could appoint a Project

    Manager from Dubai, who can

    speak the local language (Arabic),

    and could communicate with the

    clients and PMC in a better way,

    and to keep an eye on the project

    time loss. Then the organization

    decided to work on 24 x 7 basis.

    Three shifts in full swing were

    started.

    All these delays, trials, iteration

    in first five / six months gave lots of

    learning, which was used to trouble

    shoot all further hurdles / issues.

    The challenge was to maintain

    quality, without losing time, money

    and yet to give safe construction.

    Now the organization geared-up to

    do the work on time. Many otherproblems faced by the team, as

    listed below, were carefully

    addressed with sound engineering

    solutions, to meet the target.

    1) Delayed payments

    2) Alteration / reduction in scope of

    Figure 17: Details of Cyclic Pile Load Test-2

    (left) Canal cross section (right) Excavation of canal in progress

    Figure 18: Canal passing below the main bridge

  • 7/29/2019 RTA Nad Al Sheba Paper Full

    10/10

    NBM&CW MARCH 2012 169

    Concrete Bridges

    Outcome of This ProjectThe initial period of a few months was difficult for the

    contactor. Both the parties were new to each other.

    But once they understood the working style and the

    project requirements in Dubai / RTA (client), the team

    members could jointly overcome all the hurdles. Finally

    the finished quality of output (as seen in various

    photographs) was obtained. The credit also goes to

    the various vendors, suppliers and the subcontractors,

    as each one did their job the best.

    ConclusionVery limited numbers of contactors from India take a

    challenge to participate and construct international

    projects. However, such contacts give lots of

    knowledge, understanding about the International

    construction practices, legal and contractual

    provisions. Also such projects help the organization toearn lot of respect in the International construction

    industry, in addition to the financial gains. Its worth

    mentioning here that after completion of this project,

    Afcons earned a place in the list of a few preferred

    contactors to do jobs in Dubai.

    Acknowledgment & References.

    The author is thankful to the Afcons Infrastructure

    Limited and entire site team for making all the relevant

    data available for this paper. More information of this

    project may be found in the following papers:-

    1. Abhyankar V.G., Nad-al-Sheba Race Course

    Development Project: Construction of three Bridges,

    Quarterly journal of Indian Society of StructuralEngineers (ISSE), Mumbai, Vol-13/2, April-May-

    J une2011

    2. Karnik, M. D., M.R Birhade, and P.S. Bansod,

    Experiences in Construction of Bored cast-in-situ

    piles in calcareous soil Strata at Nad Al Sheba

    Race Course, Dubai to be published in Proceedings

    of Indian Geotechnical Conference, December

    15-17, 2011,RTA Dubai (Paper No. Q-199.)

    List of various Vendors / Suppliers / Sub-contactors

    involved in the project :

    Pile-driving M/s Swiss Boring

    Formwork

    o Superstructure (M/s RMD Kwikform),o Piers (M/s Anvem Steel)

    Reinforcement cutting bending, BBSM/s Ulmost,

    and partly done in house

    Prestressing system M/s Nasa Structures (sister

    co. of M/s VSL)

    Bearings, Expansion J oints M/s Alga bearings and

    Exp. J ts

    RE walls and Geo textiles M/s Freyssinet

    Concrete and other construction Chemicals :

    M/s BASF

    work under re-engineering

    3) Delay in acceptance to RFI by PMC, action taken on

    RFI

    4) Construction workers issues

    5) Idling of construction resources (machine / men) in

    absence of approval / drawings

    6) Administrative issues (pressure from other agencies /

    contactors on client)7) Relocation of utilities

    8) High magnitude of pre-stressing

    9) Incompatible values of Stressing mentioned in

    drawings, especially at cable coupler locations

    At the Nad-Al-Sheba race course, a water canal was

    planned to carry the passengers from sea shore and

    other locations to the Race course building. The main

    contractor for the construction of Water Canal was M/s

    Dutko. But the construction of part of the canal passing

    below the main bridge was the responsibility of Afcons.