Upload
vivek-g-abhyankar
View
222
Download
0
Embed Size (px)
Citation preview
7/29/2019 RTA Nad Al Sheba Paper Full
1/10
GeneralDubai, one of the seven emirates
was just a small fishermen colony,
about fifty years ago (Fig.1a). But in
the past 35 years, i.e. after theformation of United Arab Emirates
(UAE), Dubai has developed by
leaps and bounds. Dubai has
become a hub for foreign Investors.
Dubai is known for its modern
structures, rapidly growing
civilization, foreign-tourism and
trade. It is one of the seven
emirates of the UAE where
maximum investment and
developments have taken place.
Ambitious projects like Burj-Arab
tower (Burj-Khallifa), Burj-Dubai,
Palm-Island, World-Island and
several other upcoming projects
(See Fig.1b) challenged the entire
engineering community. The local
government authorities are coming
up with projects that continuously
challenge the engineer and
modernize the habitat in Dubai.
But since 2007, Dubai is
experiencing very challenging
situation because of the global
slow-down.
Prestressed Concrete Bridges for Nad-al-
Sheba Race Course Development Project,Dubai- Lessons Learnt
AFCONS infrastructure Limited (which is the Infrastructure wing of
M/s Shapoorji & Pallonji Group) recently executed its first bridge
project in Dubai. It consisted of three prestressed concrete bridges
at Nad-al-Sheba (horse and camel) Race Course, for Roads and
Transport Authority (RTA) Dubai. During the execution, the team
members faced various problems and creative solutions were devised.
However, the project was completed in record time, fetching
appreciation from the client. Various techniques adopted and other
technical details of the project are presented in this paper.
Vivek G. Abhyankar,Sr. Manger (Design),
AFCONS Infrastructure limited, Mumbai
Figure 1a: A scene of old Dubai
160 NBM&CW MARCH 2012
Concrete Bridges
7/29/2019 RTA Nad Al Sheba Paper Full
2/10
NBM&CW MARCH 2012 161
Concrete Bridges
Afcons, being one of the
pioneering construction companiesof marine structures in India and
getting diversified in other sectors
of construction like Infrastructure,
Nuclear and Industrial etc., was
keen to participate in the
international bid floated by RTA, for
the development of Nad-Al-Sheba
race course. As the tender was on
International level, construction
companies all over the world had
participated in it. But finally RTA
shortlisted Afcons, as the technical
and financial bids were most
competitive. Though it was not anew experience for the company to
work on foreign soils, the
responsibility to fulfill the
expectations of RTA was a
challenge before the project team.
(Afcons already had a considerable
experience in International projects
at locations such as Mauritius,
Madagascar (Africa), Ruwais (Abhu-
Dabhi), Iraq etc., but mostly in the
marine sector.) As RTA was
considered as a strict client to work
with, Afcons was alert during eachphase of construction.
RTA, formerly known as Dubai
Municipal Corporation had stringent
norms of construction. The entire
project was monitored by experts
from various parts of the world
under the shed of M/s Africon and
Al-Burj. Invariably the projects with
RTA are not given the Time and
Cost extension. The contractor
delaying on the projects may even
get black-listed, and will not beallowed to perform any project in
future in UAE. Officers from Britain,
Switzerland, Sudan, Pakistan, Iraq,
Sri Lanka were appointed by the
company to execute the work. The
client also had a team of competent
engineers with focused scope.
The overall project of Nad-al-
Sheba race course development
had four parts (packages) namely
construction of roads and bridges,
construction of water canal from sea
till the race course (for navigation
of visitors from other emirates), andconstruction of Main structures /
stadium, and development of
adjoining areas. Amongst these the
first package of construction of
roads and bridges was executed
by Afcons. The overall work gave
lots of learning to the organization
and entire site team. The author of
this paper is one of these teammembers. Hence the lively
experience shared by him &
presented in the paper would be of
interest to all.
Briefs About the
ProjectNad-al-sheba race course (See
Fig.1c) is located to the south of
world famous Al-Burj-tower. Sea
shore is also very close from the
race course. The areas like Camel
market, falcon house are very closefrom the project site.
The scope of work for Afcons
included construction of three
approach Bridges (namely MDN-1A,
MND-3D and the Main Bridge) to
the race course and construction of
main roads within the enter area
(See Fig.19, showing entire
alignment, scope of work),
construction of canal, partly below
the main bridge.
The fourth bridge, approaching
to the Race course building, called
VIP bridge (No. 2c in Fig. 19) was
a separate package in this tender.
The tendering of VIP Bridge was
done after processing first package.
The VIP was constructed by M/s
Figure 1b: A few modern structures (existing / coming up) in Dubai
Figure 1c: Nad-Al-Sheba Race course - birds eye view
7/29/2019 RTA Nad Al Sheba Paper Full
3/10
162 NBM&CW MARCH 2012
Concrete Bridges
Balfour Beatty (See Fig.2). Another
package was to construct the
approach water canal. The
construction of canal was done by
M/s Dutco. The construction ofStadium building was executed by
M/s Mydan. For the roads and
bridges in the scope of Afcons, the
structural design was provided by
M/s Al-Burg and the Project
management consultant. For the VIP
bridge the design was provided by
a team consisting of M/s DNEC,
together with Africon UAE, Dutco
Balfour Beatty LLC, and Petrofab
Intl. FZC.
In the present paper, the works
executed by Afcons only are
described in detail. The key detailsof all the three Bridges are
described below.
Link-1A, Link-1B were completely
reduced from the current works
because of financial crises. Later
the South wing also reduced
partially.
Concrete grade used:
Super structure M40
Substructure M40
Reinforcement Grade used: Fe500
Project Duration: 19 months
Project cost: 498 M Dirham (after
Revision of scope)
PilingThe piles were driven using
Casagrande pile driving rigs. The
freshly driven bores were stabilized
using polymer solution instead of
conventional bentonite slurry. This
helped in maintaining a clean site.
A steel liner was used to stabilize
the top 10m of the freshly driven
bore. The designed capacity of each
pile below pier cap was 450 MT
and 600 MT below the Abutments.
As welding of rebars was not
allowed, couplers were used for
reinforcements in the piles, after
approval from PMC, Client and
testing lab. (Figs 3-15 show the
project at various stages of
construction). Table 1 shows
quantities involved and the time
cycle for construction of 18 m long
piles in this project.
Figure 2: The VIP bridge (recently completed by Ms/ Dutco Balfour Beatty LLC)
(a) Night View on VIP Bridge(b) Fish bone shape Steel frames
used in the VIP bridge
Project Technical Details
7/29/2019 RTA Nad Al Sheba Paper Full
4/10
NBM&CW MARCH 2012 163
Concrete Bridges
Figure 3a: (Left) Rebar cage for piles getting ready, (right) final rebar cage for typical pile
Figure 3b: (Left) Pile Driving in progress, (Right) Pile-cap formwork by M/s RMD Kwikform
(i) Pile cutting device, to obtain desiredpile-cutoff level
(ii) Freshly cut pile before finishing (iii) Cut pile just after finishing
Figure 3c: Pile cutting
7/29/2019 RTA Nad Al Sheba Paper Full
5/10
164 NBM&CW MARCH 2012
Concrete Bridges
Figure 3d: Reinforcements of the Piers are fitted by dedicated Rebar team and View of Pier immediately after de-shuttering
Figure 3e: Typical View of Pier Formwork supplied by M/s Anvem
7/29/2019 RTA Nad Al Sheba Paper Full
6/10
NBM&CW MARCH 2012 165
Concrete Bridges
Figure 4, 5: RMDK formwork / staging for the bridge deck and Densely reinforced Prestressed concrete section
Figure 6. 7: Workers engaged in placing the Reinforcements and cable ducts at place and Typical View of Inner Bridge Formwork(M/s RMD Kwikform type)
Figure 8, 9: Bridge Expansion J oints and Bearings
7/29/2019 RTA Nad Al Sheba Paper Full
7/10
166 NBM&CW MARCH 2012
Concrete Bridges
Figure 10, 11: Concreting of the bridge structure and Bitumen Road in progress
Figure 12: MDN-1A- view of portion of completed bridge(note the white epoxy coating)
Figure 13: Large width deck slab (
7/29/2019 RTA Nad Al Sheba Paper Full
8/10
NBM&CW MARCH 2012 167
Concrete Bridges
Construction HurdlesWhen Afcons received a work order
for this project in August 2009, it
was a very pleasant moment.
Immediately the organization started
initial mobilization of resources
(man, material and machinery),
considering the importance of this
work. Here it is worth mentioning
that all the major works associated
with Infrastructure growth in UAE
are directly monitored by the
Ministry. Soon after acquiring the
site, the site team noticed the
clouds of Recession in all the
trades in Dubai, including the
construction projects. The team
noticed that most of the Mega-projects were on the verge of
getting Hold tag. The big projects
like Lagoons were already closed.
This created an unstable feeling
within the project team members.
After two months of initial
mobilization, the Project team
started working at site (Oct-Nov
2008). In UAE the Project offices
usually open at 6:30am / 7:00am
and close down the work at around
4:00pm, due to extreme heat. This
was a time of rainy season in UAE.
The rains imposed constraints in
the road construction and
underground works. This time was
utilized by the technical team
members, to minutely study the
Construction drawings, prepare
action plans, study the methods
followed in close by projects by
other International construction
companies, etc. During this study,the team noticed various missing
information / errors at a few places.
The same was discussed with
PMC, and queries were raised in
the form of RFI. The clients were
soon got flooded with many RFIs.
Hence consultant had to appoint
dedicated engineer to sort all the
RFI. Considering the fast tack nature
of project, Afcons team raised query
/ request to client (RTA) to pay
attention to this matter. On this RTA
instructed the contractor and
consultant both to solve the matter
at the earliest without affecting the
time and cost estimate. Soon the
consultant informed the contractor
that there are certain changes
expected to take place in the
engineering details, under re-
engineering.
In Dubai it is mandatory for any
party executing the works to have
Approval with Dubai municipal
Corp. To avoid any further delays
in approval (leading to wastage of
time) the organization decided toappoint an approved agency for
construction of piling activity. Various
approved companies were
scrutinized and M/s Swiss Bore was
finalized to start the work. As per
original contract, the bored cast-in-
situ pile of 1000 mm diameter and
32 m depth were to be constructed.
Immediately after constructing thefirst pile, the same was asked to
be load tested (using the Kentledge
method) by the PMC (see Fig.16).
The 32m pile showed very high
capacity during the test hence PMC
and client asked to perform one
more of 24m deep pile (the 24m
depth was estimated by
interpolation, though it was not an
exact approach, it was fairly logical
for friction piles in uniform strata
as exists in places like Dubai).
Soon the 24m pile was driven
and tested. The 24m also passed
the required load and settlement
criteria. The site team was asked
to proceed ahead with the piling of
bridge MDN-1A with 24m depth.
Soon the PMC started pressurizing
the contractor to further reduce the
length of the pile to 18m. The site
team wanted to recheck the same
with the tender provisions and the
soil investigation data provided by
the client. Finally with the reduced
scope, the 18m pile was driven
and tested at second bridge MDN-3D. The same also passed the
requirements. The consultant asked
the site team to proceed ahead
with 18m length of pile for the
Figure 16: Pile Load test (left) kentledge, (right) Jacks and Load cells on Pile head
7/29/2019 RTA Nad Al Sheba Paper Full
9/10
168 NBM&CW MARCH 2012
Concrete Bridges
remaining work at MDN-1A and all
piles of MDN-3D. This iteration
consumed lot of time.
A typical load-settlement curve
of pile loading test is shown in
Fig. 17.
When the piling work of bridge
MDN-1A was about to get over, and
piling work of MDN-3D was just
started, the PMC asked contactor to
test a 16m deep pile and test the
same at last bridge. The 16 m
deep pile was tested and found topass the load-settlement
requirements. The client and PMC
both were very happy on this cost
saving. The PMC wanted to now
check the 12m deep pile. Here, the
Structural Consultant of the
bridge had to intervene,
asking to check the
minimum pile length to
resist the lateral loads, yetPMC got the approval from
client to get the 12m pile
checked.
Dubais soil stratum is
a typical example of fine
sandy strata with week
empty soil-pockets formed
during soil-storms. The
same was experienced
while driving 12m deep pile,
where the bore suddenly
got collapsed inwards.
Because of this, the clients
instructed to stop further re-
engineering and proceed ahead
with the 16m deep piles.
Unfortunately, the tendered quantity
had got almost half. Though the
PMC and the consultants, agreed
with 16m depth of the pile, the
second step of re-engineering was
started to reduce the number of
piles itself. But as the final pile of
16m was just meeting the
requirement, the number could not
be reduced drastically. Details of
completion of piles are shown in
Table 2.
The third step of re-engineering
was in the reduction of bridge length
in MDN-3D. Such reduction wasrequired because during the
planning stage the minimum
ground clearance for the bearings
was not followed by the Planner /
Consultants. Thus the initial few
months time (four to five moths
after initial mobilization period of
two months) was critical. The
organization could appoint a Project
Manager from Dubai, who can
speak the local language (Arabic),
and could communicate with the
clients and PMC in a better way,
and to keep an eye on the project
time loss. Then the organization
decided to work on 24 x 7 basis.
Three shifts in full swing were
started.
All these delays, trials, iteration
in first five / six months gave lots of
learning, which was used to trouble
shoot all further hurdles / issues.
The challenge was to maintain
quality, without losing time, money
and yet to give safe construction.
Now the organization geared-up to
do the work on time. Many otherproblems faced by the team, as
listed below, were carefully
addressed with sound engineering
solutions, to meet the target.
1) Delayed payments
2) Alteration / reduction in scope of
Figure 17: Details of Cyclic Pile Load Test-2
(left) Canal cross section (right) Excavation of canal in progress
Figure 18: Canal passing below the main bridge
7/29/2019 RTA Nad Al Sheba Paper Full
10/10
NBM&CW MARCH 2012 169
Concrete Bridges
Outcome of This ProjectThe initial period of a few months was difficult for the
contactor. Both the parties were new to each other.
But once they understood the working style and the
project requirements in Dubai / RTA (client), the team
members could jointly overcome all the hurdles. Finally
the finished quality of output (as seen in various
photographs) was obtained. The credit also goes to
the various vendors, suppliers and the subcontractors,
as each one did their job the best.
ConclusionVery limited numbers of contactors from India take a
challenge to participate and construct international
projects. However, such contacts give lots of
knowledge, understanding about the International
construction practices, legal and contractual
provisions. Also such projects help the organization toearn lot of respect in the International construction
industry, in addition to the financial gains. Its worth
mentioning here that after completion of this project,
Afcons earned a place in the list of a few preferred
contactors to do jobs in Dubai.
Acknowledgment & References.
The author is thankful to the Afcons Infrastructure
Limited and entire site team for making all the relevant
data available for this paper. More information of this
project may be found in the following papers:-
1. Abhyankar V.G., Nad-al-Sheba Race Course
Development Project: Construction of three Bridges,
Quarterly journal of Indian Society of StructuralEngineers (ISSE), Mumbai, Vol-13/2, April-May-
J une2011
2. Karnik, M. D., M.R Birhade, and P.S. Bansod,
Experiences in Construction of Bored cast-in-situ
piles in calcareous soil Strata at Nad Al Sheba
Race Course, Dubai to be published in Proceedings
of Indian Geotechnical Conference, December
15-17, 2011,RTA Dubai (Paper No. Q-199.)
List of various Vendors / Suppliers / Sub-contactors
involved in the project :
Pile-driving M/s Swiss Boring
Formwork
o Superstructure (M/s RMD Kwikform),o Piers (M/s Anvem Steel)
Reinforcement cutting bending, BBSM/s Ulmost,
and partly done in house
Prestressing system M/s Nasa Structures (sister
co. of M/s VSL)
Bearings, Expansion J oints M/s Alga bearings and
Exp. J ts
RE walls and Geo textiles M/s Freyssinet
Concrete and other construction Chemicals :
M/s BASF
work under re-engineering
3) Delay in acceptance to RFI by PMC, action taken on
RFI
4) Construction workers issues
5) Idling of construction resources (machine / men) in
absence of approval / drawings
6) Administrative issues (pressure from other agencies /
contactors on client)7) Relocation of utilities
8) High magnitude of pre-stressing
9) Incompatible values of Stressing mentioned in
drawings, especially at cable coupler locations
At the Nad-Al-Sheba race course, a water canal was
planned to carry the passengers from sea shore and
other locations to the Race course building. The main
contractor for the construction of Water Canal was M/s
Dutko. But the construction of part of the canal passing
below the main bridge was the responsibility of Afcons.