16
Hybrid Solar PV systems for SCI Beirut Country Office & Field Offices in Beirut, Zahle & Tripoli

SCI Lebanon - Solar PV Systems

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

 

 

Hybrid Solar PV systems for SCI Beirut Country Office & Field Offices in Beirut, Zahle & Tripoli 

   

  

 

 

 

 

  

                                       

         

     

    

TableofContent  

1.     Executive summary    

2.     Design and sizing   

2.1.      Design Considerations    

2.2.      Design methodology    

2.3.       Sizing    

3.     Scope of supply    

3.1.       PV power plant   

3.1.1.        Photovoltaic panels   

3.1.2.        Hybrid Inverters    

3.1.3.        Battery Bank    

3.2.       Safety Measures   

3.2.1.       Grounding System   

3.2.2.        Protection against Electrical Shock    

3.2.3.        Protection against Over Current    

3.2.4.        Protection against Over‐Voltage   

3.3.       Commissioning    

3.4.      Operation Manual and training     

4.     Maintenance    

4.1.       Thermal imaging of PV panels    

4.2.       Power performance test    

5.     Project Time Line    

5.1.       Project Timeline    

6.     Warranty    

7.     Country of Origin   8.     Annexes 

   

 

1.Executivesummary

This is a request for Solar hybrid PV systems required for SCI offices in accordance with the following details:  ‐ 12.0 Kw Peak for Beirut Country Office located in Pikasso Building – Thawita – Furn El Chebbak (TYPE‐A) 

To be Connected to Three Phase Power Supply Network ‐ 6.0 Kw Peak for Beirut Field Office located in Pikasso Building – Thawita – Furn El Chebbak (TYPE‐B) 

To be Connected to Three Phase Power Supply Network ‐ 12.0 Kw Peak for Zahle Field Office located in Zahle (TYPE‐C) 

To be Connected to Single Phase Power Supply Network ‐ 12.0 Kw Peak for North Field Office located in Koura (TYPE‐C) 

To be Connected to Single Phase Power Supply Network     

2.Designandsizing

2.1.DesignConsiderations

The offered PV system is designed based on the following parameters 

 ‐ The system size was selected based on critical loads of 18A for an autonomy of 10 hours for  

Type‐A & C & 9A for an autonomy of 10 hours for Type‐B  

‐ The electrical distribution to Offices Electrical Panel Boards shall be performed by the PV 

Supplier  including any modification  to  feed all  critical  loads  from one single point  in the 

main electrical panel 

‐ Elevated  Steel  Structure with  an  average height of  2.5 M  shall  be provided  for  Zahle  Field 

Office as the Panels will be installed in the Parking. The structure shall be able to handle the 

Snow & Wind Load  

‐ All needed trenching to lay the cables between the parking, batteries room and main 

electrical room shall be included in this offer 

‐ The Batteries &  Inverter  in  ZFO will  be  located  in  the Ground  Floor  near  the  Solar 

Panels  

‐ The PV Panels in North Field Office will be installed on the Red Roofing. The batteries 

& Inverter will be installed at Roof directly under the Solar Panels   

‐ The  PV  Panels  in  County  &  Beirut  Field  Office  will  be  installed  on  the  Flat  Roof. 

Galvanized Structure shall be provided by the PV Supplier. Installation shall be done  

‐  

 

on concrete pads to avoid damaging the existing water proofing system  

‐ The Batteries & Inverter in Country & Beirut Field Office will be installed at Roof near 

the Solar Panels 

‐ The offer must include Surge Protection Devices on DC and AC sides, Lightning Protection 

& Grounding Systems for the PV Solar System  

  

2.2.Designmethodology

The system will be grid  interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, or to the grid with Net Metering System (Where applicable) the batteries can be charged from Grid if PV output is not enough for loads and batteries.  

Hybrid Solar PV System is considered with Dual Mode Inverters with Internal Automatic Transfer Switch  

2.3.Sizing

The PV system and batteries are sized based on the following:  

     TYPE A 

‐      18 A critical load (12,000 BTU/HR AC Unit for Server Room, Server, Charging Sockets 12 Laptops & 12  Mobile Phone, 30 Led Lights) 

 

‐      10 hours’ autonomy  

‐      60% Depth of discharge  

      

 TYPE B 

‐      9 A critical load (Charging Sockets 12 Laptops & 12 Mobile Phone, 30 Led Lights)  

‐      10 hours’ autonomy  

‐      60% Depth of discharge   

TYPE C ‐      18 A critical load (12,000 BTU/HR AC Unit for Server Room, Server, Charging Sockets 12 Laptops & 12  

Mobile Phone, 30 Led Lights)  

‐      10 hours’ autonomy  

‐      60% Depth of discharge         

  

3.Scopeofsupply

The scope of supply shall cover the supply, installation, connection to electrical panel boards, testing, 

commissioning, handing over, training & one‐year preventive and corrective maintenance 

 The Contractor shall perform a detailed engineering site survey to acquire all necessary information for preparation of final design documentation and discuss technical issues with SCI representatives  

 Contractor  shall  submit  shop  drawings  for  all  architectural,  civil,  electrical  and  a  complete 

photovoltaic solar system works, including a single line diagram showing all the components of the PV 

system, DC and AC distribution boards,  PV Arrays  lay  out  and battery backup  systems  connections 

and cables, wires cross section for all the system to be approved by the Engineer before executing the 

work. 

 

Contractor  shall  submit  a  detailed  material  submittal  of  each  component  showing  the  requested 

specifications stated at the bill of quantity. 

 

The  contractor  shall  submit  the  Manufacture  testing  certificate,  country  of  origin,  certified 

characteristics,  test  performance  curves,  spare  parts  regular  (as  recommended  by  manufacturer  , 

maintenance manuals and manufacturer’s warranty for each components of the system. 

As‐built drawings and writing setting parameters shall be submitted after handing over the work. 

 

The  price  includes  all  builders’  &  Civil  works,  making  good  and  reinstatement  including  necessary 

materials and workmanship as well as removal of unwanted materials to dump sites approved by the 

engineer to complete the job successfully. 

 

TYPE A 

  12.0 kWp Hybrid PV power plant. This PV plant is composed of: 

3 Single Phase Hybrid Inverters of 5 KVA rated AC Power each (4000 W Continuous Output  

        Power at 25 Deg. C). The three Inverters shall be configured for Three Phase Output  

28 PV panels of 430 Wp (Higher Capacity Panels are acceptable; the number will be reduced accordingly)  

Solar Batteries bank consisted of 48 batteries SOPZS 860 Ah (673 Ah C12)  

Electrical components for installation & protection 

Electrical components for connection to the Office Panel Board & Critical Loads Arrangement  

 

 

 

 

TYPE B 

  6.00 kWp Hybrid PV power plant. This PV plant is composed of: 

3 Single Phase Hybrid Inverters of 3 KVA rated AC Power each (2400 W Continuous Output  

        Power at 25 Deg. C). The three Inverters shall be configured for Three Phase Output  

14 PV panels of 430 Wp (Higher Capacity Panels are acceptable; the number will be reduced accordingly)  

Solar Batteries bank consisted of 24 batteries SOPZS 860 Ah (673 Ah C12)  

Electrical components for installation & protection 

Electrical components for connection to the Office Panel Board & Critical Loads Arrangement  

 

 

TYPE C 

  12.0 kWp Hybrid PV power plant. This PV plant is composed of: 

2 Single Phase Hybrid Inverters of 8 KVA rated AC Power each (6400 W Continuous Output  

        Power at 25 Deg. C) . The two inverter shall work in parallel to achieve a 16 KVA Power Output   

28 PV panels of 430 Wp (Higher Capacity Panels are acceptable; the number will be reduced accordingly)  

Solar Batteries bank consisted of 48 batteries SOPZS 860 Ah (673 Ah C12)  

Electrical components for installation & protection 

Electrical components for connection to the Office Panel Board & Critical Loads Arrangement  

3.1.PVpowerplant

3.1.1.Photovoltaicpanels

The PV modules shall be of high efficiency MONO / POLY crystalline PV module with minimum 

capacity of 430 Wp. The module efficiency shall be of 20% and has a positive 0 to +3% power 

tolerance  

 The  panel  shall  be  equipped  with  two  4mm2  stranded,  sunlight  resistant  output  cables  that  are 

terminated with PV  connectors  ready  for most  installations,  and a  junction box  containing bypass 

diodes wired in parallel with the PV cell strings. In the case of partial shading, the diodes bypass the 

current generated by the non‐shaded cells, thereby limiting module heating and performance losses.  

 

 

 

The module shall be certified to withstand 2400PA wind load and 5400PA snow load. 

  

The  panels  shall  have  an  expected  life  of more  than  25  years,  and  they must  be  supplied with  a 

limited  power  warranty  of  90.0%  after  12  years  and  80.7%  at  25  years,  resulting  in  a  panel 

degradation factor of less than 1%. 

 All  PV  panels  shall  be  grounded  with  appropriate  earth  cables  and  connected  to  the  main 

earthing system. 

    

3.1.2.HybridInverters

DC/AC Hybrid type 1‐phase inverter configured to supply three phase Network where needed, Rated DC Voltage:  48V, Grid  Input Voltage: 220VAC  / 380VAC,  Input  frequency: 50HZ, Output Voltage:  220VAC / 380VAC,  Output  Frequency:  50Hz,  Pure  Sine  Wav.  with  data  communication  unit  with  Ethernet connection,  (monitoring  and  controlling  unit).  The  inverter  must  be  suited  to  any  PV  module configuration, and depending on the system design and installation proposed and for the future extended also.  The  DC  max  power  input  rating  should  be  equal  or  more  than  of  the  PV  modules  capacity  at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.  Protections: reverse polarity, short‐circuit, overvoltage, under voltage, over‐discharge, ant hunter. Include  (MPPT Charge controller), Remote Control Unit  (RC Unit) compatible with  inverter  rated power with  all  necessary  (automatic  transfer  control  box),  interface modules  and  connections  for masters  & slaves , electrical cables and data communication unit with Ethernet connection, connectable in parallel and modularly extendable. The Battery Inverter must include the following concepts such as (Ac and DC coupling,  High  efficiency,  intelligent  battery  management  for  maximum  battery  life,  charge  level calculation,  extreme  overload  capability,  and  battery  temperature  sensing  and  battery  current measurements).  And  connect  all  DC  cables  appropriately  sized  in  accordance  with  the  installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable  terminations  end  which  shall  be  DC  plug  and  socket  connectors  to  have  a  complete  job,  the allowable voltage drop for DC cables between inverters and PV system shall be less than 2% while only 1% is accepted at the AC side of the system for a total of 3% in voltage drop for the entire system.  The  Inverter  must  be  equipped  with  external  current  sensor  for  load  management  to  optimize  self‐consumption and, if required, to prevent grid feed. In case of a power outage, the Inverter will continue to supply the critical loads  The  correct  grid  code  shall  be  set  through  the  data  logger  allowing  the  inverter  to  comply  with  the tolerance parameters of Over Voltage, Under Voltage, Over Frequency and Under Frequency       

 

3.1.3.BatteryBank

  SOPZS  Batteries  as  per  BOQ  details,  the  batteries  must  provide  high‐quality  and  achieving  superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, with maximum compatibility – design according to DIN 40736‐1 The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with  all  bus  bars,  conduits,  clamps,  stainless  steel  bolts,  washers  and  cable  end  terminations  and  all needed materials  to  complete  the  job.  All DC  cables must  be  sized  in  accordance with  the  installation requirements  applicable  on  site,  the  allowable  voltage  drop must  be  less  than  2%.  Battery  Banks  rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the  job. the rack must be enough to carry all the weight of the required batteries for the system.  

    

3.2.SafetyMeasures

3.2.1.GroundingSystem

All PV modules, inverters, cable trays, support structure and cabinets shall be bonded and connected to 

the grounding system. 

Along the cable tray, earth bars shall be installed where the ground wires coming from the PV chassis, 

structure and cable trays, shall be connected. 

From these earth bars, ground wires shall be pulled back into the inverter room where they are 

connected to the main earth busbar. 

  

Special  grounding  accessories  shall  be  used  between  the  structure,  the  PV  chassis  and  the 

copper  earth  wires  to  avoid  any  risk  of  electrolyte  torque  when  fitting  metallic  masses  for 

equipotential bonding. 

 The offer must include a new earthing system in Zahle & North & connection to the existing 

earthing system in Beirut  

 

 3.2.2.ProtectionagainstElectricalShock

The  supplier  shall  ensure  to  provide  the  best  practices  according  to  the  international  standards 

regarding protection against electrical shock at the DC side with systems classified as Class II. 

 

For  the AC  side  the  protection  shall  be  done  by  double  insulation  for  any  live  conductor  and  any 

earthed or exposed conductive. 

 

 3.2.3.ProtectionagainstOverCurrent

The selected inverters shall be supplied with overcurrent protection on the DC side, while on the AC 

side  the  supplier  shall  install  an  AC  circuit  breaker  at  the  output  of  each  inverter  and  one  at  the 

tapping point for the protection of all the cables and inverters. 

 

 

 3.2.4.ProtectionagainstOver‐Voltage

The supplier shall ensure that the protection level of the PV Plant electrical installations, PV Plant 

and PV Plant equipment respect the below important factors: 

  Electrical isolation material from the equipment 

 

Overvoltage protection devices characteristics  

  

3.3.Commissioning

In order to ensure a quality commissioned system, the supplier shall follow the below procedure:     

Step 1: Following mechanical and electrical  installation, conduct a short circuit current, 

open circuit voltage and insulation resistance tests prior to power up in order to validate 

the electrical installation 

Step 2: When Step 1 is successfully completed, the supplier shall move to Power up and PV 

plant controller commissioning 

Step  3:  Impp  and  Vmpp  tests  shall  be  performed  to  guarantee  the  performance  of  the 

installed system 

Step  4: When  all  the  system  is  tested  and  ready,  the  supplier  shall  proceed with  the 

handover and employee training 

        

 

 3.4.OperationManualandtraining

Upon system delivery, the supplier shall submit an operation manual including:   

General description of the installed PV system  

Description of the installed monitoring system explaining how the customer can use it to 

collect data 

Description of the Online Monitoring platform  

Maintenance procedures  

Commissioning Test Reports  

As built mechanical PV layout  

As built string layouts  

As built single line diagram  

As built wiring diagram  

As built main cabinet layout  

As built AC combiner  

As build bill of materials  

Datasheets of all installed components for customer reference.   

The supplier shall conduct as well a detailed training on various plant functions to help the 

customer manage the PV plant, thus reducing downtime due to bad management 

 

4.Maintenance

As part of the system warranty, the supplier shall provide in addition to the scope mentioned above a  

1 year of operation and maintenance (Preventive & Corrective) package excluding cleaning of the panels.   The package shall include 2 scheduled visits during the first year from the supplier Engineer to  perform the below tests: 

   

4.1.ThermalimagingofPVpanels

The objective of the test is to detect the existence of hotspots on PV panels.   

An  infrared  camera  is  used  to  take  temperature  range  pictures  of  the  solar  PV  system  which  is 

illustrated in a range of colors that represent different values of temperature. This test shows clearly 

if certain parts or cells of the module are producing more heat dissipation than other regions. This 

could be caused by faulty connections, or malfunctioned cells inside the module. A faulty cell will act 

as a resistor in the module and actually consume power instead of producing it. The heat produced 

is a byproduct of this malfunction and can be captured by a sensitive infrared camera     

4.2.Powerperformancetest

The objective of this test is to check the power performance of the system.   

The supplier shall be able to perform the following tests: 

  Lead resistance null test 

 

Protective earth/ground resistance  

Auto Test (VOC, ISC & Insulation resistance)  

AC & DC Current Measurement  

DC Power Measurement  

Temperature for ambient and local  

Irradiation values  

Tilt and orientation   

In the following test, the ISC, VOC, and irradiation values for each string collection will be recorded 

during mid noon of a sunny clear day. 

 

 

5.ProjectTimeLine

5.1.ProjectTimeline

The supplier shall complete & hand over the Solar PV Systems within  10 Weeks upon receipt of 

the official Purchase Order  

     

     

  

6.Warranty

The Supplier shall provide a warranty period of:   

10‐year limited product warranty for the panels   

Limited power warranty for the panels 10 years at 91.2% of the minimal rated power output,  

25 years at 80.7% of the minimal rated power output  

5 years warranty on the inverter & batteries

 

7.CountryofOriginSolar Panels: European or Chinese (Prime Brands) are approvedInverter & MPPT solar charge controller: Only European Brands are approved  Batteries: Only European Brands are approved   Note: All Products shall be certified according to International standards and norms  

8.AnnexesAnnex‐1: Beirut Country Office ‐ BOQ Annex‐2: Beirut Field Office ‐ BOQ Annex‐3: North Field Office ‐ BOQ Annex‐4: Zahle Field Office ‐ BOQ 

 

Item Description Unit QuantityUnit Rate

USDTotal USD

Remarks

A

Supply, Installation, Testing & Commissioning of Hybrid Solar PV System and facilitate the comprehensive maintenance of the system for the period of One Year form the date of commissioning. Price shall include the supply & installation of all components with all necessary accessories to insure proper operation & performance of the system. Served Area: Beirut Country Office

1Supply of Roof Top Mounting PV Module Mono / Poly Crystalline, 430Wp EachPV Array capacity is 12kWp equivalent to 54 A.

Set 28

2

Supply of Hybrid (EDL/GEN. - SOLAR) Solar Inverter with MPPT Charge Controller. The Inverter Shall be supplied with External Current Sensor, Online Monitoring & remote ControllerInverter Capacity is 5 KVA. The three Inverters shall be configured for Three Phase Output

Set 3

3

SOPZS Batteries 2 V 860 Ah (673 Ah C12)Autonomy of the battery bank at 60% DOD is 10 hours at 18 Amp LoadN.B. Price must Include Battery Rack

Ea 48

4Cable, Cable connector, Earthing kit, Array Junction Box, DC Wiring between panels to control unit, AC Wiring between Inverter & Combiner Box

LS 1.00

5Solar Modules Mounting Structures made from Galvanized Steel Elements including casting of Concrete Curbs / Pads on Roof & Waterproofing Repair; if needed

LS 1.00

6Electrical Connections from/to Beirut Country Office Electrical Panel Board and Connection to Earthing System

LS 1.00

TOTAL AMOUNT EXCLUDING VAT (USD)

VAT (11%)

TOTAL AMOUNT T.T.C (USD)

Save The Children

Project: BCO HYBRID SOLAR PV SYSTEM

ANNEX-1

Item Description Unit QuantityUnit Rate

USDTotal USD

Remarks

A

Supply, Installation, Testing & Commissioning of Hybrid Solar PV System and facilitate the comprehensive maintenance of the system for the period of One Year form the date of commissioning. Price shall include the supply & installation of all components with all necessary accessories to insure proper operation & performance of the system. Served Area: Beirut Field Office

1Supply of Roof Top Mounting PV Module Mono / Poly Crystalline, 430Wp EachPV Array capacity is 6kWp equivalent to 27 A.

Set 14

2

Supply of Hybrid (EDL/GEN. - SOLAR) Solar Inverter with MPPT Charge Controller. The Inverter Shall be supplied with External Current Sensor, Online Monitoring & remote ControllerInverter Capacity is 3 KVA. The three Inverters shall be configured for Three Phase Output

Set 3

3

SOPZS Batteries 2 V 860 Ah (673 Ah C12)Autonomy of the battery bank at 60% DOD is 10 hours at 9 Amp LoadN.B. Price must Include Battery Rack

Ea 24

4Cable, Cable connector, Earthing kit, Array Junction Box, DC Wiring between panels to control unit, AC Wiring between Inverter & Combiner Box

LS 1.00

5Solar Modules Mounting Structures made from Galvanized Steel Elements including casting of Concrete Curbs / Pads on Roof & Waterproofing Repair; if needed

LS 1.00

6Electrical Connections from/to Beirut Field Office Electrical Panel Board and connection to Earthing System

LS 1.00

TOTAL AMOUNT EXCLUDING VAT (USD)

VAT (11%)

TOTAL AMOUNT T.T.C (USD)

Save The Children

Project: BFO HYBRID SOLAR PV SYSTEM

ANNEX-2

Item Description Unit QuantityUnit Rate

USDTotal USD

Remarks

A

Supply, Installation, Testing & Commissioning of Hybrid Solar PV System and facilitate the comprehensive maintenance of the system for the period of One Year form the date of commissioning. Price shall include the supply & installation of all components with all necessary accessories to insure proper operation & performance of the system. Served Area: North Field Office

1Supply of Roof Top Mounting PV Module Mono / Poly Crystalline, 430Wp EachPV Array capacity is 12kWp equivalent to 54 A.

Set 28

2

Supply of Hybrid (EDL/GEN. - SOLAR) Solar Inverter with MPPT Charge Controller. The Inverter Shall be supplied with External Current Sensor, Online Monitoring & remote ControllerInverter Capacity is 8 KVA. The two inverter shall work in parallel to achieve a 16 KVA Power Output

Set 2

3

SOPZS Batteries 2 V 860 Ah (673 Ah C12)Autonomy of the battery bank at 60% DOD is 10 hours at 18 Amp LoadN.B. Price must Include Battery Rack

Ea 48

4Cable, Cable connector, Earthing kit, Array Junction Box, DC Wiring between panels to control unit, AC Wiring between Inverter & Combiner Box

LS 1.00

5Solar Modules Mounting Structures made from Galvanized Steel Elements on Red Roofing including proper Waterproofing for all penetration

LS 1.00

6Electrical Connections from/to North Field Office Electrical Panel Board

LS 1.00

7

Earthing & Lightning Protection Systems for the Solar PV System including all necessary civil worksEarthing for PV StructureIndependent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance.the item includes (all required copper electrodes 15mm2 driven into ground to achive the resistance low than 2 ohm, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system

LS 1.00

TOTAL AMOUNT EXCLUDING VAT (USD)

VAT (11%)

TOTAL AMOUNT T.T.C (USD)

Save The Children

Project: NFO HYBRID SOLAR PV SYSTEM

ANNEX-3

Item Description Unit QuantityUnit Rate

USDTotal USD

Remarks

A

Supply, Installation, Testing & Commissioning of Hybrid Solar PV System and facilitate the comprehensive maintenance of the system for the period of One Year form the date of commissioning. Price shall include the supply & installation of all components with all necessary accessories to insure proper operation & performance of the system. Served Area: Zahle Field Office

1Supply of Roof Top Mounting PV Module Mono / Poly Crystalline, 430Wp EachPV Array capacity is 12kWp equivalent to 54 A.

Set 28

2

Supply of Hybrid (EDL/GEN. - SOLAR) Solar Inverter with MPPT Charge Controller. The Inverter Shall be supplied with External Current Sensor, Online Monitoring & remote ControllerInverter Capacity is 8 KVA. The two inverter shall work in parallel to achieve a 16 KVA Power Output

Set 2

3

SOPZS Batteries 2 V 860 Ah (673 Ah C12)Autonomy of the battery bank at 60% DOD is 10 hours at 18 Amp LoadN.B. Price must Include Battery Rack

Ea 48

4Cable, Cable connector, Earthing kit, Array Junction Box, DC Wiring between panels to control unit, AC Wiring between Inverter & Combiner Box

LS 1.00

5

Solar Modules Mounting Structures made from Galvanized Steel Elements & Scondary Steel Structure made of Black Steel Elements Coated with Epoxy Primer, Intermediate & Top Coat. The Structure shall withstand the Snow & Wind Load. The rate shall include Concrete Pads under Steel Columns

LS 1.00

6Electrical Connections from/to Zahle Field Office Electrical Panel Board

LS 1.00

7

Earthing & Lightning Protection Systems for the Solar PV System including all necessary civil worksEarthing for PV StructureIndependent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance.the item includes (all required copper electrodes 15mm2 driven into ground to achive the resistance low than 2 ohm, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system

LS 1.00

TOTAL AMOUNT EXCLUDING VAT (USD)

VAT (11%)

TOTAL AMOUNT T.T.C (USD)

Save The Children

Project: ZFO HYBRID SOLAR PV SYSTEM

ANNEX-4