ShaftSinkingPracticesfor Mining

  • Upload
    td1985

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    1/22

    ShaftSinkingPracticesfor Mining

    Chairmen: J.S. Redpath

    C. Heever

    ].S. Redpath Ltd. North Bay Ont. Canada

    Cyril Heever Partners Inc. Carletonville South Africa

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    2/22

    Chapter

    SHAFT SINKING AT NOSE ROCK

    by

    Mr. James O. Greenslade

    PhillipsUranium Corporation

    Vice Presidentof Mining & Milling

    Crownpoint,New Mexico

    Mr. Cherie Tilley

    PhillipsUranium Corporation

    DevelopmentManager

    Crownpoint,New Mexico

    Mr. Gerald G. Griswold

    HarrisonWestern Corporation

    Vice Presidentof EngineeringServices

    Denver, Colorado

    Mr. Richard Reseigh

    HarrisonWestern Corporation

    Manager of Engineering& Administration

    Crownpoint,New Mexico

    INTRODUCTION

    The HarrisonWestern Corporation,a leadingDenver based mine

    contractingand engineeringconcern,is presentlyengaged in

    sinking two 1,006 m (3,300 ft) shafts for the PhillipsUranium

    Corporationat their Nose Rock Project,approximately13 miles

    northeastof the small communityof Crownpointin McKinleyCounty,

    New Mexico. The Nose Rock Project is the first attempt by the

    PhillipsUranium Corporationto tap the deep uranium reservesin

    what has become known as the Grants Mineral Belt. (See Figure 1)

    ProjectDescription

    PhillipsUranium Corporations plan for the large 2700 metric

    ton per day (2950 tons/day)mining facilitycalls for a series of

    deep access and ventilationshafts ranging from 4.27 m (14 ft) to

    5.49

    m

    (18

    ft) in diameterto approximatedepths of 1,006m (3,300

    ft). The initialpair of shafts consistsof one productionshaft and

    one ventilationshaft separatedby a distanceof

    91 m (300

    ft).

    The

    interbedded layers of sedimentary sandstones and shales to be

    penetrated by the shafts contain several major water producing

    aquifers, the deepest being the mineralized zone called the Westwater

    Canyon Member of the Morrison Formation.

    955

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    3/22

    956

    1981 RETC PROCEEDINGSVOLUME 2

    FIGURE 1.

    PROJECT SITE

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    4/22

    SHAFT SINKING AT NOSE ROCK

    957

    A series of temporaryand permanentwater pumping stationsis

    planned. Generally,the temporarystationsare located above

    major aquifers to facilitatewater removalwhile sinking through

    the aquiferand the permanentstationsconstitutewhat, in the

    final mode, will be the mine dewateringsystem. In addition,

    PhillipsUranium Corporationhas installedand is maintaininga

    system of depressurizationwells that temporarilypump the major aqui-

    fers and considerablyreduce the water inflows durinq shaft construc-

    tion,

    The major aquifers are alao chemicallygroutedprior to sinking.

    Site work for the project was initiatedin the fall of 1976. Full

    scale shaft sinking commencedin November of 1977 on the 4.88 m (I6

    ft) diameterventilationshaft and on the 5.49 m (18 ft) production.

    shaft by another contractor.

    HarrisonWestern Corporationbegan work

    on the project on November 4,

    1979 with the productionshaft at a

    depth of 633 m (2,076 ft) and the ventilationshaft at a depth of 474

    m (1,554 ft).

    This paper will address only the portion of shaft

    sinking completedby HarrisonWestern.

    Geology and Hydrology

    The Nose Rock Project is located on the Chaco Slope in the

    southernextreme of the San Juan Basin in northwestNew Mexico.

    The southernSan Juan Basin is generallybound by the Defiance

    Uplift to the west, the Zuni Uplift to the south and the

    NacimientoUplift to the east.

    The Grants MineralBelt occupies

    most of the southernportion of the San Juan Basin and this pro-

    ject is located on the northernextreme of the Grants Mineral

    Belt. The San Juan Basin is comprised of sedimentary rock of

    continental, marginal-marine and marine origin, that dip northward

    from the Zuni Uplift and Chaco Slope into the interiorof the San

    Juan Basin.

    (SeeFigure 2)

    Major Formations The major geologic formationsto be penetrated

    range from mudstoneand shales to ailtstonesand sandstones.

    The

    sandstonesare highly productiveaquiferswhich, under static

    conditions,would flow artesian.

    Water temperaturesin the aqui-

    fers are high and thereforeare a force to be dealt with. Temper-

    atures range from 18C (65F)in the upper aquifersto 48C

    (118F)in the lower. The mudstonesare generallybentonitic.

    (SeeFigure 2)

    GALLUP SANDSTONE: The Gallup Sandstoneis the first major

    regressivewedge in the San Juan Basin of the Cretaceus era and

    at this project is about 35 m

    (115

    ft) thick.

    It is medium

    grainedand prior to depressuriation carrieda hydrostaticwater

    3

    pressureof over 72.5 kg per cm (1,031psi) whi~h is artesian.

    Compressivestr ngthranges from 334.7 kg per cm (4,760psi) to

    421.8 kg per cm (6,OOOpsi).

    Water temperatureis approximately

    30c (860F).

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    5/22

    958

    1981

    RETC PROCEEDINGSVOLUME 2

    C.EOLCC,C ~.w.. o. COLUMN

    T-

    *

    M, N, F.,

    MLLATO TONG.,

    OF . . .

    MA.cos

    MC,t.lcos

    812

    26s

    w, ,W.R w...

    w..,.

    ,

    ,6 )

    WCI),.OUJCTION SHAFT No,, v,r4T,.AT,ON SHAFT

    ,_L_EPT.

    .m. . .

    = :

    ..s.O ,

    .....

    .

    m,,

    , ,...,,

    i

    FIGURE 2. SHAFTSVERTICAL CROSS SECTION

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    6/22

    SHAFT SINKING AT NOSE ROCK

    MANCOS SHALE:

    The Mancos Shale comprisesthe bulk of marine

    depositsin the San Juan Basin and representsdepositionin

    deeper, quieter water in offshoreareas where energy levelswere

    lower and finer elasticscould settle out. At Nose Rock, the

    Mancos Shale is roughly 207 m (680 f~) thick. Compressive

    st engths range from 188.4 kg per cm

    5

    (2,680 psi) to 400.7 kg per

    cm (5,700psi).

    It is not water bearing.

    DAKOTA SANDSTONE: The Dakota Sandstoneand its corresponding

    Twowellsmember is approximately98 m (322 ft) thick at Nose

    Rock. The main body of the Dakota Sandstoneis a fine grained

    sandstonewith the so calledTwowells sandstonetongue actually

    being a siltstone. Prior to depressurization,wate~ ;: ;;yI)) ta

    was under a hydrostaticpressure of 108.1kg per cm ,

    also artesian.

    2

    Compressivest engthsrange from 386.okg per cm

    (5,490psi) to 562.4 kg per cm (8,OOOPsi). Water temperatureis

    approximately43C (109F).

    BRUSHY BASIN SHALE: The Brushy Basin Member is the upper-most

    member of the MorrisonFormationwhich marks the approximate

    boundry between the Cretaceus and Jurassic eras. Locally, it is

    composedof a sequenceof fine grained sandstones,siltstonesand

    mudstoneswhich grade into one another,althoughdisconformities

    are sometimesdistinguishable.

    The mudstonesand siltstones

    constitutethe greater part of the section. Overall, it is Q4 m

    (143 ft) thick and some of the sandstonesare wa er bearing.

    3

    Compressivestr ngths range from 456.3 kg per cm (6,49o psi) to

    5

    954.8 kgpercm (13,580Psi).

    WESTWATER CANYON MEMBER: The WestwaterCanyon Member of the

    MorrisonFormationwas depositedin a continentalenvironment

    during the Jurassic era and is the ore bearing sandstonefor the

    Nose Rock Project. It is actually comprisedof three submembers

    called Upper, Middle and Lower.

    The WestwaterCanyon Member is a

    classic example of an artesianaquiferwith water being recharged

    from topographicallyhigher outcropson both the Zuni and Defiance

    uplifts. Prior2todepressurization,the hydrostaticpressurewas

    120.2 kg per cm (1,710psi). Grain sizes range from mediu~ to

    coarse,and compressivestreng~hsrange from 94.9 kg Per cm

    (1,350psi) to 348.7 kg per cm (4,96opsi). Note that the lower

    range for compressivestrength is lower than the originalhydro-

    static pressure,indicatinga possiblerunning sand conditionif

    sinkingshould be attemptedin the absence of de ressurizationor

    8

    grouting. Water temperatureis approximately48 C (118F).

    959

    Depressurization Wells The Phillips Uranium Corporation has put

    into operationand maintaineda series of depressurizationwells

    in the area of the shafts to reduce the hydrostaticpressure in

    the major aquifersin order to facilitateshaft sinking.

    Six

    wells were drilled through the Gallup Sandstone,four wells in the

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    7/22

    980 1981 RETC PROCEEDINGSVOLUME 2

    Dakota Sandstone and six wells in the Westwater Canyon Member.

    The casing was slotted throughout the total length of each aquifer

    and the pump settings were generally just above each aquifer.

    Number Months

    lni.tial Residual

    Formation

    Wells Pumped Yield

    Pressure Pressure Effect

    Gallup

    6 17

    1080 gpm

    1038

    psi

    135 pai 82

    Dakota

    4 14

    1120 gpm 1537 psi

    350 psi

    77

    Westwater

    4- 6

    6 1760 gpm 1711 psi 238

    pSi

    86

    Table 1. Summary of Results of DepressurizationWells

    As can be seen from the results summarizedin Table 1, the program

    has been highly effective. More perspectiveconcerningresidual

    formationpressurescan be gained by the followingestimates,

    preparedby PhillipsUranium Corporationgeologists,of potential

    inflows to both shaftswith and without the repressurization

    wells.

    With Without

    Formation Wells Wells

    Gallup 1,080 gpm

    2, 307 gpm

    Dakota

    1, 120 gpm 2,562 gpm

    Westwater 2,212 gpm

    5,020 gpm

    Table 2. PotentialInflowEstimates

    Althoughthese potentialyields with the benefitof the wells

    would by no means prohibitshaft sinking,the water inflow from

    the upper

    aquifers was further reduced by chemical grouting of the

    formations prior to sinking.

    Grouting

    Carrying large volumes of water on the shaft bottom during

    sinking probablypossessesthe greatestsingle detrimentto high

    shaft sinking productivity.

    For the most part, the system of

    depressurizationwells had the effect of reducingpotentialin-

    flows from the upper aquifersduring sinking to around 4,I6o

    liters per minute (1,100gpm). As mentionedabove, these inflows

    would not necessarilyprohibitsinking,although carryingthese

    volumes of water would have the dual effect of increasingcapital

    expenditurescaused by slower shaft sinking rates and increasing

    future operatingexpensescaused by pumping larger quantitiesof

    water over a significantportion of the mine life.

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    8/22

    SHAFT SINKING AT NOSE ROCK

    961

    From the above, it was apparent that further reduction of

    potential inflows from the major aquifers would be beneficial if

    the reductions could be obtained at a reasonable cost.

    Owing

    largely to the success of Harrison Westernts chemical grouting

    program at the Gulf Mineral Resources Companys M.. Taylor Pro-

    ject, it was decided to instigate a similar program at the Nose

    Rock Project for the upper aquifers.

    No grouting is planned for

    the mineralized Westwater Canyon Member since any potential in-

    flows will be fully realized during mine development.

    I t should be recognizedthat the groutingprocess itself is

    expensiveas it is not uncommon to spend one to two months treat-

    ing 30 m (100 ft) of shaft.

    In addition,initialapplicationsare

    highly beneficialbut time spent attemptingto obtain a Iperfect

    curtainis subjectto the law of diminishingreturns.

    Theoret-

    ically, the right amount could be determinedby adding the cost of

    groutingto the incrementalsavingsof shaft sinkingcosts due to

    grouting,and comparingthe totals to the after tax discounted

    cash flow savings of incrementalmine life pumping expense.

    Supposedly,if this comparisonyielded a positivenet present

    value, further groutingwould be warranted.

    The extreme diffi-

    culty of estimatingaccuratevalues for the above parametersis

    obvious and therefore,the outcome of any attempt must be viewed

    with suspicion.

    Grout Materials The grouting agents used at Nose Rock were

    selectedprimarilyon the basis of successfuluse on other similar

    projectsin the Grants Mineral Belt.

    CEMENT: All of the sandstoneaquifersrequiringgrout treat-

    ment were of fine enough porosityto preclude the use of suspen-

    sion type groutingagents.

    Cement grout was used primarilyto

    stabilizethe rock mass around the concretegroutingpad and to

    seal leaks where the pad joined the shaft lining.

    Pumped cement grout was mixed with water in water to cement

    ratios that varied from 12:1 to 1:1 by weight.

    CHEMICALRESIN GROUT: A water soluble resin prepolymerwas the

    primarygrouting agent used at Nose Rock. The resin is supplied

    as a fine powder which readily dissolvesin water, and in the

    presenceof catalystsand accelerators,forms an irreversible,

    impermeablegel.

    The mixture normallyhas a viscosityclose to

    that of water and can thereforebe injectedinto formationsof low

    porosity.

    The set time or gel time is the time elapsed to form a stiff

    gel after the chemicalsare mixed.

    For the most part, gel times

    can be predictedand controlledby varying the concentrationof

    the solutionandlor the addition of a sodium silicate

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    9/22

    962

    1981 RETCPROCEEDINGS VOLUME 2

    accelerator.

    Gel times are also a functionof temperaturewith

    the relationshipbeing inverse.

    Two

    variations of chemical grouting agents were

    used at the

    Nose Rock Project.

    The first type was characterizedby the resin

    and caustic soda catalystbeing packagedseparately.

    The second

    type is packagedtogetherwith other modifications. Care in

    transportationand storageof the second type must be exercisedto

    preventthe reactionfrom taking place in the bags prematurely.

    GroutingEquipment The equipmentselectedwas based on successful

    experienceon similar projectselsewhere.

    PUMPS AND MIXING TANKS: A double-actng recirculationtype

    pu~p capable

    3

    of pumping at

    345

    kg per cm (4,900psi) at 8 kg per

    cm (100 psi) air pressurewas used.

    The pump is modeled after

    the South African type grout pump.

    Two mixing tanks were equipped

    with air poweredmixing and agitationpaddles with one tank

    elevatedabove the other.

    The tanks were sized to mix the con-

    tents of one 23 kg (50 lb) bag in the most dilutedmix of 129 1

    (34

    gal). One bag was mixed in the upper tank while a solution

    was being pumped from the lower tank.

    JUMBO AND DRILLS: The grout jumbos consistedof two drill

    buggies which circled the shaft on a single track from a pivot in

    the center of the shaft.

    High speed,air powered, chain fed

    rotary drills with 1.5 m (5 ft) feed were used with EX diameter

    drill rod.

    MISCELLANEOUSEQUIPMENT: Schedule 80 pipe of 5 cm (2 in)

    diameterwas used for stand pipes.

    These were coupledwith drill

    through ball valves of similar diameter. Blow-outpreventers

    capable of closing an EX drill rod were also used for added

    safety.

    GroutingProcedure Normally,one or more probe holes were drilled

    into each aquifer from a safe distanceabove. The probe hole

    served the dual purpose of determiningthe exact locationof the

    aquiferand finding suitablestrata to pour the groutingpad.

    Normally the pad was located from 6 m (20 ft) to 9 m (30 ft) above

    the aquifer.

    GROUT PAD: When the predetermineddepth was reached, the

    excavationwas done for the grout pad. The curb or lower ring

    of the shaft form was removedand the pad poured, forminga solid

    concreteplug poured tight againstand keyed under the shaft

    lining. The plug was designedto withstand the anticipated

    grouting pressure. While the pad was curing, the jumbo was set up

    and the standpipesinstalled.

    Before grouting commenced,every

    standpipewas tested to full groutingpressure.

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    10/22

    SHAFT SINKING AT NOSE ROCK

    Upon completionof the above, the holes were drilled 3 m

    ft) to 6 m (20 ft) and the rock mass between the pad and the

    aquifer was injectedwith cement to consolidatethe mass and

    leaks between the pad and the shaft lining.

    963

    10

    seal

    GROUTING:

    Due to widely varying porositiesand local fractur-

    ing conditions,experiencehas shown that precalculatedgrout

    quantitiesfor a given aquifer are unreliable. As a result, holes

    were pumped to refusal at a predeterminedpressureinstead of a

    predeterminedquantity.

    The groutingpressurewas determinedby

    the amount of residual formationpressureto be overcomeand the

    acceptabilityof the formationdue to grain size, porosity,

    fracturesand other characteristics. Normally, this pressurewas

    approximatelytwice the hydrostaticpressurecalculatedfrom the

    surface,and many times the residualhydrostaticpressure due to

    the effect of the depressurizationwells. A curtain length of

    30

    m (100 ft) was

    the

    approxi mate

    maximum depth that could be grouted

    from one pad.

    The hole pattern was designedto interceptas many fracturesas

    possiblewith the distancebetween holes at the base of the cur-

    tain not exceeding 1.4 m (4.5 ft). The aquiferwas grouted from

    the top down in stages of 3 m (10 ft) and all holes in the pattern

    were grouted to refusalbefore deepeningthe holes to advance the

    cover.

    (SeeFigure 3)

    Generally,75 -

    90% of the potentialinflowswere sealed off

    by the grout curtains.

    SHAFT SINKING

    For the most part, the shaft sinkingmethods used at the Nose

    Rock Project can be classifiedas conventional. Methods and

    techniquesemployedon any project depend, to a large extent, on

    safetyand health regulationspromulgatedby appropriateregula-

    tory agencies at both state and federal levels. At the federal

    level, the project falls under the Federal Mine Safety and Health

    Act of 1977 (PublicLaw 95-164) and is administeredby the newly

    createdMine Safety and Health Administration of the Department of

    Labor.

    subsequent to enactment of the ~977 Act, the New Mexico

    Mine Safety Code has adopted the federal standardsas their own.

    In addition,the state of New Mexico periodicallydevelops

    stricterstandards,mostly as a result of previousserious acci-

    dents. The most importantof these to the shaft sinker is a

    requirementlimitingunsupportedground in verticalshafts to 3 m

    lo f ).

    The two shafts are generallyscheduledto be sunk together.

    The resultingplan representsthe earliestpossiblecompletion

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    11/22

    964

    1981 RETC PROCEEDINGSVOLUME 2

    VERTICMSCME

    FMMATION

    mri

    LUG

    WTER BEMINC

    SANDS

    I

    1

    I

    \__ ..51,00

    VERTICALCROSS SECTION

    OFDRILLOLE

    PLAN TYPICALDAKOTA GROUT COVER

    FIGURE 3. PLAN-TYPICALDAKOTA GROUT COVER

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    12/22

    SHAFT SINKING AT NOSE ROCK

    965

    date and allows the fresh air base to be lowered when connecting

    stations are reached in order to counteract the high temperatures

    caused by hot water emanating from various aqui-fers.

    Sinking Equipment

    The permanentproductionhoist and headframeare used for

    sinking the 5.5 m (I8 ft) diameterproductionshaft. The hoist is

    a 1,119kw (1,500hp) double drum, double clutch unit, capable of

    610 meters per minute (2,000 fpm) line speed. A temporaryhoist

    and headframeare used for sinking the 4.9 m 16 ft) ventilation

    shaft. The hoist is a 1,007kw (1,350hp) double drum, single

    clutch unit capable of 579 meters per minute (1,900 fpm) line

    speed. Hoist ropes are 38.1 mm (1.5 in) diameterand are of 18 x

    7 non-rotating right lang lay construction.

    Compressed alr is supplied to both shafts by seven electrically

    powered rotary compressors located on the surface. A portable

    concrete batching plant is used to supply concrete into transit

    trucks that mix and deliver it to t e respe tive shafts. Concrete

    9?

    is transported underground in 2.7 m 95 ft ) buckets.

    Galloway stages are suspended by four 25.4 mm 1 in) locked

    coil ropes and are

    used in each shaft as work platforms.

    Each

    Galloway consistsof four decks and weighs approximately31,070kg

    (65,000lb).

    The locked coil ropes serve as crossheadguides for

    the counterbalancedbuckets.

    The Galloway stagesare raised and

    loweredby four winches that are electricallywired to operate

    together,although any winch can be clutchedout by hand in order

    to periodicallybalance tensionbetween the ropes. The rope speed

    of the Gallowaywinches is about 2.4 meters per minute (8 fpm).

    The Crydermanshaft mucker anchoredto the liningwith brackets

    is used for mucking (excavationof blastedmaterial). Invented

    and developedin Canada, the mucker is essentiallyan air powered

    clamshellmounted on a telescopingboom.

    Positioningcylinders

    and the telescopingfeaturesof the boom itself allow positive

    crowd at any locationon the muck pile.

    The machine is controlled

    by levers actuatingtwo four-wayvalves, with the left hand con-

    trollingboom positionand the right hand controllingthe

    clamshelland the telescopingfeatureof the boom.

    Two units are

    used in the larger productionshaft and a single unit in the

    ventilationshaft.

    In all cases, the units are suspendedon cable

    winches located on the surfacewith the rail and bracketanchoring

    39

    ystemsal owing v rtical movement only. Muck bucket izes ran e

    Y l

    from 2.7 m

    95 ft ) in the ventilation shaft to 3.5 m 123 ft )

    in the production shaft.

    Drilling is done with 28 kg 62 lb) hand-held. sinkers with a

    piston diameter of 67 mm 2-5/8 in). Drills are lowered in a

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    13/22

    966

    1981 RETCPROCEEDINGSVOLUME 2

    speciallydesignedbasket containingall materialsrequired for

    the operation.

    The concreteforms are of all steel construction of the appro-

    priate diameter with a length of 3 m 10 ft). The forms are

    constructed of four vertical sections of .75 m 2.5 ft) length to

    enable any multiple of .75 m 2.5 ft) pour to be made if ground

    conditions are poor.

    The curb ring is of blast proof construction

    and contains the ring blockoutnecessaryto enable pouring the

    subsequentpour below.

    The top Pmatcherting laps the previous

    pour and containsthe guillotinedoors that are closed after the

    form is filled with concrete. The form itself is suspendedfrom

    the previouspour by six hanging rods.

    TypicalSinking Cycle

    Due in most part to the wet conditions,the benchingmethod of

    excavationis used. This techniqueprovidesa lower area for an

    electricsubmersiblepump to be placed after each blast.

    More-

    over, the blowovernprocess of cleaningthe bench in preparation

    for drillingallows a thoroughexaminationfor misfires and the

    rock mass thrown by the blast is directed at the shaft walls

    instead of the Galloway, thus minimizing damage.

    The cycle describedbelow may vary in duration from as little

    as 14 hours to as much as 34 hours, dependingon conditions.

    Sinking rates for both shafts are comparable. The larger produc-

    tion shaft has an advantagewith the additionalCrydermanmucker,

    but this seems to be offset by the lesser volume of muck and a

    somewhatfaster concretecycle in the ventilationshaft.

    Drill and Blast This segment of the cycle begins with a thorough

    blow over of loose muck into the sump created by the preceding

    bench. Forty to fifty 2.4 m (8 ft) holes are drilled and charged

    with a semigelatindynamite.

    The dynamiteselected is a reason-

    able compromisebetween the desired characteristicsof adequate

    strength,low fumes, good water resistanceand cost. A non-

    electricdelay blastingcap systemhas been used for detonating

    explosiveswith reasonablesuccess. The crews remain on the

    surface for a few minutes while the smoke clears.

    (SeeFigure 4)

    Mucking,

    The Cryderman mucker s) are lowered and mucking begins.

    Normally, the bucket chains remain attached to the hoist hook and

    swivel during loading.

    Since the boom llft (not in or out) opera-

    tion is the most time consuming,Crydermanoperatorssoon learn to

    excavatea hole for the next bucket which tends to save time.

    While the loaded bucket is hoisted and dumped, the Cryderman

    operator(s)can move muck from hard to reach to convenientplaces

    which also conservestime. Buckets are dumped with a lazy chain

    controlledby a toplanderfrom the crowqsnestn in the

    headframe.

    (See Figure 5)

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    14/22

    SHAFT SINKING AT NOSE ROCK

    967

    FIGURE 4. DRILLINGTHE BENCH

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    15/22

    9 8

    98 RET PRO EEDINGS VOLUME 2

    FIGURE 5 MUCKING

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    16/22

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    17/22

    970

    1981

    RETC PROCEEDINGSVOLUME 2

    FIGURE 6. SETTING CONCRETEFORMS

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    18/22

    SHAFT SINKING AT NOSE ROCK

    971

    that attaches the weep pipe to the form. After the curb ring is

    lowered, the pipes are attached to the form with a fastening

    device that threads into the couplingand allows the water to come

    throughthe form.

    The curb ring is then filled with concrete

    forming a tight seal for the bottom of the pour. After the

    remainingform is loweredand poured, the water flows freely

    through the weep pipes.

    These are later connectedto a 10.2 mm

    (4) drain line which carries the water into a pump station or a

    super water ring discussedfurtherbelow.

    Super Water Rings The in-shaft pumping system consisted of 43 kw

    58 hp) submersible pumps on the bottom and staged up the shaft

    wall in distancesnot exceeding

    61 m (200

    ft). The electric

    submersiblepumps of this type require frequentmaintenanceand

    normally this must be done on the surface.

    To facilitatepump

    changeoutand providea sump for staged pumps, HarrisonWestern

    engineersdevelopedthe fsuperwater ring.

    Essentially,the

    super water ring is the enlargementof a 3 m (10 ft) vertical

    section of the shaft by .6 m (2 ft) in radiuswith a .6 m (2 ft)

    steel dam installedflush with the shaft lining.

    Submersible

    pumps in these rings eventuallytransferwater to temporaryor

    permanentpumping stations.

    FiberglassWater Rings The purpose of the fiberglasswater ring

    is to collect water running on the inside of the shaft lining.

    The rings are installedabove pump stations,super water rings or

    periodicallywhen needed,and are connectedwith hose or piping to

    the drain line, super water ring or station. They are fabricated

    to attach to the concreteform and are easily installed.

    Bonus and Incentives

    In

    recent years, industrial managers have gravitated towards

    the theories of motivation espoused by such management theorists

    as Fredrick Herzburg et al.

    These theories stress job

    enrichment or other such enlargementof an individualstask or

    area of responsibilityas a motivatingforce in order to otherwise

    offset the boredom and dissatisfactionthat often accompaniesthe

    modern industrialwork setting.

    For the most part, these theorists would deny that additional

    remuneration is a motivating factor per se, although admitting

    that substandard pay scales can be a source of considerabledis-

    satisfactionamoung a work force.

    Undergroundconstructionand

    mining in the Rocky Mountainsand in a large portion of Canada are

    some of the last bastionsof the piece work system still existing

    in North America, albeit in modified form.

    Seeminglyin defianceof modern managementtheory, the Nose

    Rock Projecthas successfullyapplied two forms of bonus

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    19/22

    972

    1981 RETC PROCEEDINGSVOLUME 2

    incentivesaffectingall contractorpersonnelon the project. The

    first is a direct bonus which is paid only to those working below

    the shaft collar.

    This bonus is basicallya piece rate system

    applied to the crew as a whole with a guaranteedminimum base rate

    for each man.

    The second form of bonus is paid to all others not

    receivingthe first and is based on a review of the overall pro-

    ject status comparedwith the originalproject schedule. This

    bonus is paid (if earned) every calendarquarter as a percentage

    of the base wage rate.

    Sinking Rates Attained

    Shaft sinking rates of 3 meters per day (10 ft per day) were

    regularlyattained,even throughmost major aquifers,and rates of

    30 meters per week (100 ft per week) were regularlyattained

    throughmuch of the Mancos shale.

    The productionshaft crew

    achievedan area record of 36.3 meters (119 ft) of completedshaft

    in one week of seven days.

    The ventilationshaft crew achieveda

    one month productionof 132.6meters (435 ft) of completedshaft,

    also believed to be an area record.

    PUMPING SYSTEM - TEMPORARYAND PERMANENT

    Dependablepumping systemsare an absolutenecessityto the

    constructionand operationof a mine such as this one with the

    shafts penetratingfive major aquifersand the ore itselfhaving

    been depositedin the matrix of the fifth, the Westwater Canyon

    Member.

    Extensiveplanningwas requiredby both the Phillips

    Uranium Corporationand HarrisonWestern Corporationto insure

    that the systemwas reliable for sinking,mine developmentand

    later for ore extraction.

    The two permanentpump stationsrepre-

    sent the system requirementfor mine developmentand ore extrac-

    tion. Unfortunately,this system is not entirelyadequate for

    sinking the shafts and as a result, the permanentsystem was

    augmentedby a series of temporarypumping stationsfor sinking.

    Of prime considerationwhen locatingpumping stationsis the

    capabilityof the equipmentitself and the selectionof suitable

    strata in which to locate the station.

    The sandstonesto be mined

    can be expectedto yield a certain amount of sand particulateto

    the dischargewater and even with the benefit of a desanding

    facility,the pumps must be able to pump water containingsand

    particulate.

    For this reason and the fact that desandingequip-

    ment is not availablefor sinking,less efficientslurry type

    centrifugalpumps were selected.

    These pumps enjoy wide popu-

    larity at other mines in the Grants Mineral Belt, mainly for their

    ability to pump water containingabrasivesolids over long periods

    of time with low maintenancecosts.

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    20/22

    Permanent Pump Stations

    SHAFT SINKING AT NOSE ROCK

    973

    The two permanent pump stations at the Nose Rook Project were

    des@ned for a sustained pumping capability of Z2,700 liters per

    minute, 6OOO gpm) with an additional11,350liters per minute

    (3,000

    gpm

    backup.

    These stationsconsist of three banks of five

    pumps per bank with each bank being capable of pumping 11,350

    liters per minute (3,000 gpm). Provisionswere made in each

    station to install a fourth bank of equal capacitysometime in the

    future,should conditionsdictate.

    The primary pumps of each bank are 313 kw (500 hp) electrically

    powered,direct driven centrifugalslurry pumps, each capable of

    11,350

    liters per minute (3,000gpm) at a total dischargehead of

    137 meters (450 ft]. These pumps are connectedin series to

    attain the desired system head and in all cases are force fed with

    high volume, low head feed pumps, to minimize the effects of

    cavitation. The last pump of each bank is equippedwith a fluid

    couplingwhich, in conjunctionwith electricmetering and feed

    back of sump water levels, can automaticallyregulateoutput to

    allow continuousoperationat levelsas low as 6,o5o liters per

    minute (1,600gpm).

    The upper permanentpump station is located 457 meters (1,500

    ft) below the surface.

    Each bank of pumps on this station con-

    sists of three main pumps connectedin series and force fed by two

    feed pumps, also connectedin series. The lower permanentpump

    station is located at 957 meters (3,140 ft) below the surface and

    when completedwill dischargeinto sumps on the upper station.

    The typical bank on the lower station consistsof four main pumps

    in series force fed by a verticalcentrifugalpump which will be

    located in a sump on the haulage level 23 meters (75 ft) below.

    TemporaryPump Stations

    Temporarypump stationsare normallylocated above major

    aquifersin order to minimize the less reliablein-shaftsuper

    water ring system describedearlier.

    These stationsare equipped

    with either the primarypumps describedearlier or a smaller

    version capable of 7,570 liters per minute (2,000 gpm) at a total

    dischargehead of 98 meters (320 ft). The maximum lift for a

    temporarystationwas 305 meters (1000 ft).

    Five temporarypump stationswere used for shaft sinkingat the

    Nose Rock Project. These stationseither dischargedinto higher

    temporarystationsor permanentstations. As permanentstations

    were completedand became available,they were incorporatedinto

    the system.

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    21/22

    974

    1981 RETCPROCEEDINGSVOLUME 2

    CONCLUSION

    The Nose Rock Project is currentlyrunning approximatelythree

    months ahead of schedule. Althoughno methods or techniqueshave

    been used that could be classifiedas unconventional,through a

    combinationof experiencedmanagement,proven water control

    techniques,well structuredbonus incentiveplans, and a positive

    overall relationshipbetween owner and contractor,record sinking

    rates have been attained.

    When completed,the Nose Rock Project will unlock for public

    use a considerableamount of uraniumore from deep underground.

    Combinedmanagmentand technicalachievementsof both Phillips

    Uranium Corporationand HarrisonWestern Corporationare

    responsiblefor this success.

  • 8/9/2019 ShaftSinkingPracticesfor Mining

    22/22

    SHAFT SINKING AT NOSE ROCK

    975

    REFERENCES

    chenowith, W.L. , 1977,

    tUraniumin the San Juan Basin - An

    Overview,WNew Mexico GeologicalSociety Guidebook,28th Field

    Conference,San Juan Basin III, pp. 257-262.

    Greenslade, W.M., Sprouls, E.P., 1977, Geotechnical and

    Hydrologic Investigation, Production Shaft, Mining Unit 1,

    Nose Rock Project, Dames and Moore, Phoenix, Arizona.

    Griswold,G.G.,

    White, L.G., 1980,tWaterControlDuring Shaft

    Sinking UtilizingDepressuringWells and Resin Grouting

    Techniques,nHarrisonWestern Corporation,Denver, Colorado.

    Kelly, T.E.,

    1977,

    W3eohydrology of the WeStWaterCanYon Member~

    MorrisonFormation,of the SouthernSan Juan Basin, New

    Mexico,nNew Mexico GeologicalSociety Guidebook,28th Field

    Conference,San Juan Basin III, pp. 285-290.

    Molenaar, C.M., Y3tratigraphy and Depositional History of Upper

    Cretaceus Rocks of the San Juan Basin Area New Mexico and

    Colorado, with a Note on Economic Resources,n New Mexico

    Geoloj@cal Society Guidebook, 28th Field Conference, San Juan

    Basin IIILPP 159-166.

    Vanderwoude, M.D., 1980,

    Mine Geologist,PhillipsUranium

    Corporation,Private Communication.