TAV FIRINI/ANNEALING FURNACE
KULLANMA KLAVUZU / USER'S GUIDE
GTİP/HS Code: 8454.10.00.00.00
Çelik Kuyumculuk Kalıp Makine San. Ve Tic.
Ltd. Şti.
Adres: Atatürk Mahallesi Marmara Sanayi Sitesi R Blok No:
455 İkitelli/Küçükçekmece İstanbul
Telefon: +90 212 494 44 60
Fax: +90 212 494 44 61
Web: www.steelkalip.com
E-mail adresi: [email protected]
İÇİNDEKİLER:
. Teknik Özellikler
. Genel Açıklamalar
. Makine Montaj Şeması
. Parça Listesi
. Makinenin Kullanıma Hazırlanması
. Dikkat Edilmesi Gereken Hususlar
. Makine Bakım ve Onarımı
Teknik Özellikler:
En, Boy, Yükseklik : *126 *215 *231
Net Ağırlık : 650 Kg
Kullanılan Elektrik : 380 V - 50Hz
Elektrik Gücü : 15 Kw
Kullanılan Hava Basıncı : 6 Bar
Fırın Gücü : 12 Kw
Fırın Cehennemlik Hacmi : 160/300 mm
Amonyak Ayrıştırıcı : 3 Kw
Fırın Sıcaklığı : 950 °C
Amonyak Sıcaklığı : 850 °C
Genel Açıklamalar:
- Zaman ayarı sayesinde içine koyulan madeni tam ve homojen şekilde
tavlama yapar.
- Asansörü sayesinde kolay maden alırsınız.
Makine Montaj Şeması:
Parça Listesi:
1- Boşaltma Asansörü
2- Cehennem Arka Kapak Piton
3. Cehennemlik ve Soğutma bağlantı yeri
4- Cehennemlik
5- Cehennemlik Ön Kapağı
6- Baca
7- Brülör
8- Amonyak Ayrıştırıcısı
9- Amonyak Ayrıştırıcı Rezistansı
10- Su Tankı
Makinenin Kullanıma Hazırlanması:
-Elektrik fişi prize takılır.
-Su deposu su ile doldurulur.
-Amonyak gaz bağlantıları yapılır.
-Likid gaz bağlantısı yapılır.
-Makine su terazisi ile teraziye alınır ve düz olmasına dikkat edilir.
-Fırın ve amonyak şalteri açılır.
-Fırın sıcaklığı 950 °C ‘ ye ayarlanır(Maximum).
-Amonyak sıcaklığı 850 °C ‘ ye ayarlanır(Maximum).
-İstenilen ısıya geldiğinde makine çalışmaya hazır duruma gelmiştir.
Dikkat Edilmesi Gereken Hususlar:
-Amonyak tüpünde kaçak kontrol edilmelidir.
-Amonyak saati yeteri kadar açılmalıdır. Az açılırsa çıkan ürünler kararmış
şekilde çıkar, çok açılır ise amonyak kokar.
- Malzeme cehennemlikte iken cehennemlik kapağının kapalı olmasına ve
hava almamasına dikkat edilmelidir.
-Makine kapandığında Likid gaz vanası kapalı olduğundan emin olunuz.
-Makine içerisine ürün koyarken ve çıkartırken maşa kullanınız.
Makine Bakım ve Onarımı:
-Makinenin su haznesindeki suyun, kirlenmesi ve eksilmesi durumlarında ilave
edilmesi gerekir.
CONTENTS:
. Technical Specifications
. General Descriptions
. Mounting Sketch
. Parts List
. Use The Preparation of The Machine
. Issues to Be Considered
. Machinery Maintenance and Repair
Technical Specifications:
Width, Size, Height : *126 *215 *231
Net Weight : 650 Kg
Electric Used : 380 V - 50Hz
Electric Power : 15 Kw
Used air pressure Pressure : 6 Bar
Oven Power : 12 Kw
Oven Volume Hell : 160/300 mm
Ammonia Parser : 3 Kw
Oven Temperature : 950 °C
Ammonia Temperature : 850 °C
General Descriptions:
- Placed into the mine through the time setting makes a complate
and homogeneous annealling. Lift easy to get mine.
Mounting Sketch:
Parts List:
1- Discharge Elevator
2- Hell Back Cover Piston
3. Hell and Cooler Connection Location
4- Hell
5- Hell Front Cover
6- Flue
7- Burner
8- Ammonia Separator
9- Ammonia Separator Resistance
10- Water Tank
Use The Preparation of The Machine:
-Electrical outlet plug
-Water tank is filled with water
- Ammonia gas connections are made
- Gas connections are made
- Flat ground with spirit level
- Switch opens the oven and ammonia
- Oven temperature is set to 950 ° C (Max.)
- Ammonia temperature is set to 850 ° C (Max.)
- When the desired temperature, the machine is ready for use
Issues to Be Considered:
- Gas leakage should be checked
- Ammonia valve must be opened far enough. Valve is opened much
the air smells of ammonia but valve is opened insufficient products
goes darker
- While the material in hell, the closed doors of hell and the air should
not be there.
- After the machine is turned off, make sure that the gas valve closed
- Use tongs when placing and removing material inside the machine.
Machinery Maintenance and Repair:
-in case of water absence or pollution water, must be added or
changed.
Steel Mould and Machine
Address: Atatürk District Marmara Industrial Site
R Blok No:455 İkitelli - Küçükçekmece - İstanbul
Tel: +90 212 494 44 60
Fax: +90 212 494 44 61
Web: http://www.steelkalip.com/
E-mail: [email protected]
Address: Urom Persia Gold Address: Ltd. 13,Tsurupa str. MOSCOW &Jewelery PR.Co. Tel/Fax: (495) 718 41 01
Fahkt Atayi Bldy No:4 Atayi www.jeweller-partner.ru
Ave - Uromieh IRAN E-Mail: [email protected]
Phone: +98 441 223 52 98
Fax : +98 441 224 38 08
Cell: +98 914 346 37 62
Cell: +90 530 602 30 16
Cell: +90 530 602 30 15
www.urompersia.ir
E-Mail : peyman@urompersia