45
Stream crossings What permits are required for gaining temporary access, permanent access and installing utility lines across a stream, or wetland. By Chris Droste , CESCO Senior Erosion Control Specialist Westmoreland Conservation District

Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

  • Upload
    vankien

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Stream crossingsWhat permits are required for gaining temporary access, permanent access and installing utility lines across a stream, or wetland.

By Chris Droste, CESCO

Senior Erosion Control Specialist

Westmoreland Conservation District

Page 2: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Types of permits requiredGeneral permits: GP-7, GP-8, GP-5

Page 3: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

General Permit 7- Minor Road Crossings– Used for permanent access to a property– Can be used when there is < 1 sq. mile or less watershed

draining to crossing.– Can also be used to remove an existing bridge or culvert.– Cannot be used in EV ( exceptional value waters)– Cannot be used for stream enclosures– Can be used to cross wetlands with the following conditions:

– Length of crossing is less than 100 feet– Total wetland area is less than .1 acre

Page 4: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Conditions of the GP-7– must be completed within 3 years of permit issuance

– No additional fill should be placed in the floodway which includes the approaches to the crossing. Approaches should be constructed at original grade.

– Bridge and culverts should have an opening to adequately pass a “bank full flow” of the stream.

– Headwalls and endwalls should be installed to prevent an instable situation.

– Bridge abutments shale be set well into the banks of stream as to prevent

obstructions.

Page 5: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Conditions of GP-7

– Culverts shale be installed with an invert 6” below the natural stream bed.

– Spacing of culverts and bedding requirements shale be in accordance with manufacturer’s specification of the pipe.

– Depth of fill over the pipe should “not exceed” the minimum required by the manufacturer.

Page 6: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Common culvert and bridge projects that require GP-7

Page 7: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

GP-8 Temporary road Crossings

pipe and timber mat bridge use

Page 8: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

GP-8 conditions

Crossings can be installed and left in place for 1 full year. ( can be extended by DEP or Conservation district.

Not to be installed during Stocked trout streams from March 1 through June 15.

Cross at right angle to stream.

Culvert must provide sufficient flow for normal conditions

Culvert must be installed to allow for overtopping within the confines of the stream channel. (a dip with minimal fill over pipe to allow for flood flows.

Culvert should be as large as possible as to minimize fill placement.

Multiple pipes can also be used if 1 large pipe cannot be used.

Page 9: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

FIGURE 26 – Temporary Stream Crossing Details

An 8” thick layer of AASHTO #1 stone shall be maintained for a minimum distance of 50’ from top of bank on both sides of stream channel.

Page 10: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Problems with crossings

1. Fill over pipes is too high (4-5 feet)2. Fill is not Clean Rock3. Pipes are directing flow into stream bank causing erosion4. Crossing is not depressed as to allow overflow of water

Page 11: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Keep 1-1.5 feet of clean rock fill over pipes

Multiple pipes are used to carry normal flow

Page 12: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Timber mats are used for wetland crossingsTemporary bridge use, and crossing soft areas

Page 13: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Stream crossing methods with utility lines GP-5

Page 14: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Crossing Guidelines

Utility lines should be 3 ft under bed of stream

Completed in low flow when possible

Should be at Right angle to bank

Supervisor for foreman must notify Fish commission 10 days Prior to start.

Page 15: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Pipes must be 3’ under the bed of stream.If solid rock is encountered, pipe can be installedon top, but cannot protrude above bottom of streamBottom.

Page 16: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Construction Methods

By-pass Pump around

Pipe Fluming of stream

Coffer Dam

Page 17: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

By-pass PumpAround detail

Filter bag

pump

Page 18: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Installing a pump bypass system to do bridge and culvert work

Page 19: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

First is to install the pump in the location, set up hoses in the intakeAnd outfall locations

Intake side near sandbag dam

Page 20: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

3. Sandbags are placed above work areas

2. The intake hoses are placed in stream

Page 21: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Intake hose location

Sandbag coffer dam

Work area

Page 22: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Work area is fairly dry. Sandbags are also wrapped in plasticFor a uniform seal.

Page 23: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Discharge hose needs to be placed in a stable rock area or plastic sheeting

Page 24: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Pumping the dirty water

Page 25: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Dirty water must be pumped into a geotextile Filter bag with a separate pump

Page 26: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet
Page 27: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Make sure hose is Connected well

Bags must be installed in thickVegetation or on a bed of StoneThat drains to a stable area

Page 28: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

The filter bag can be set near the stream bankAs long as there is a strip of fabric under bag and Over stream bank to stream.

Page 29: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Please do not lay filter bag in a flowingStream!

This is an obstruction and If bag rips open, a major sedimentPollution problem!

Page 30: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Clean water hose

Filter BagOn vegetatedarea

Geotextile placed to prevent washout fromPump water

Pump By-pass method for pipe installation

Page 31: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

This would not be a good alternative for a filter bag!

Page 32: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Pumpng water into a pit is not acceptable means to filter sediment!

What not to do:

Page 33: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Flume installation

Page 34: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Bridge re-construction projectUsing flumes to by-pass stream

Page 35: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Bridge replacement with majorStream to bypass

Page 36: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet
Page 37: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Make sure that the sandbags direct the water into the flume.

Page 38: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Coffer Dam installation

Page 39: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Coffer Dam standard DEP details

Page 40: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Jersey barriers must be wrapped in plastic and sandbags used to seal offSections.

Page 41: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Stabilizing the stream banks after installation

Page 42: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Blankets can be used in lieu of Riprapnear HQ/EV

Page 43: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Straw blankets can be used with riprap placed at the toe Of the bank.

riprap

Page 44: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

Using R-3 rock is too small, It washes away easily.R-4 is a minimum, but engineer should size properly

Page 45: Temporary road Crossings using pipe - Westmoreland ...wcdpa.com/wp-content/uploads/stream-crossings.pdf · Crossing is not depressed as to allow overflow of water. Keep 1-1.5 feet

There is a little too much rock placed on the bottomwhich could obstruct the stream flow