Upload
doanduong
View
219
Download
4
Embed Size (px)
Citation preview
Turkish Power System 2
Basic facts
Area:814.578 km²
Population:77.695.904 (2014)
Consumer: 35.714.380 (2013)
1 TSO
21 DSOs
Peak load: 41.003 MW
(14.08.2014 14:30)
2
Turkish Power System 3
Global map of the gridand of its interconnections
3
Interconnectorswith: Greece
Bulgaria
Georgia
Armenia
Azerbaijan
Iran
Iraq
Syria
TURKEY
400 kV Existing400 kV Underconstruction220 kV Existing154 kV Existing
Turkish Power System 4
Grid facts and characteristics
4
TRANSMISSION LINES (2014)
400 kV : 17.747 km
154 kV : 35.384 km
220 kV : 85 km
66 kV : 509 km
Total : 53.725 km
SUBSTATIONS (2014)
400 kV : 93
220 kV : 1
154 kV : 575
66 kV : 14
Total : 693 Subs. with 127.705 MVA capacity
The electricity grid in Turkey is sub-divided intotransmission grids (more than 66 kV) anddistribution grids.
Turkish Power System 5
Structure of Turkish power system
5
TEK
1994 2001
TEDAŞ
TEAŞ TETAŞ
TEİAŞ
EÜAŞ
TEDAŞ
Distribution
VerticallyIntegrated
Generation,Transmission &
Trade
Trade
Transmission&Marketing
Generation
Distribution
1970 1994 2001
TEİAŞ
2015
Transmission
EPİAŞ
Marketing
Turkish Power System 7
Information on TSO
Sole owner of Turkish transmission system is Turkish Electricity Transmission Co. (TEIAS)
Network length:53.725 km
Serving: 814.578 km²
www.teias.gov.tr
7
Turkish Power System 8
Transmission structure of the Turkey
8
Operation and maintenance works of transmissionassets are conducted by 22 regional offices.
Turkish Power System 9
Transmission structure of the Turkey
9
Turkish Electricity Grid is managed by one National Control Center (NCC)located in Ankara and nine Regional Control Center (RCC).
Turkish Power System 10
Installed capacity withreference to primary resources
Installed capacities (GW), year Biomass Coal Gas Hydro power Lignite Nuclear Oil Solar powerWind power Others
10
Total: 69.516,4 MW
Generation
Type
Installed
Capacity
(MW)
Percentage
Natural Gas 25550,1 36,75%
Coal 15303,7 22,01%
Liquid Fuel 658,8 0,95%
Hydro 23640,9 34,01%
Wind 3629,7 5,22%
Geothermal 404,9 0,58%
Solar 40,2 0,06%
Other 288,1 0,41%
Total 69516,4 100,00%
Turkish Power System 12
Increase of Comsuption12
-4,0
-2,0
0,0
2,0
4,0
6,0
8,0
10,0
12,0
0,0
50,0
100,0
150,0
200,0
250,0
300,0
19
98
19
99
20
00
20
01
20
02
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
20
14
Consumption (TWh) Increase (%)
Turkish Power System 14
Location of renewable energy sources
14
Distribution of Wind Power Plants in Turkey as of 2014
* Red: In Operation Blue: Planned
PLANNED + INSTALLED: ~12.000 MW
Turkish Power System 15
Location of renewable energy sources
Turkish Solar potential
15
According to Strategy Paper of Energy Ministry, Turkey’saim in solar energy is to have 3.000 MW solar power plantintegration by 2023.
Turkish Power System 17
Development of photovoltaic power
Installed Capacity (MW):
Year Amount(MW)
2014 40,2
First half of 2015 74,8
TOTAL 115,0
17
Turkish Power System 19
Electricity market organisation19
• Electricity Market Law numbered 4628 was published.2001
• Market Financial Settlement Center (PMUM) at TEIAS started to operate the balancing mechanism.
• Imbalances started to be settled as night, day and peak time period.2006
• Balancing and Settlement Regulation was published on 1st December of 2009.
• Day Ahead Planning was being used for day ahead trading and balancing activities.
• Balancing Power Market is being used for real-time balancing. Imbalances started to be settled hourly.
2009
• Day Ahead Market came in to force on 1st December of 2011
• Daily advance payments, collateral mechanism and renewable energy resources support mechanism started to be implemented.
2011
• Electricity Market Law numbered 6446 was published. Law numbered 4628 was renamed as “Law on the organization and duities of Energy Market Regulatory Authority”
2013
• In accordance with the Electricity Market Law, a new liberal company called EPİAŞ (Electricity Markets Operating Incorporate Company) which will operate day ahead market, intraday market and settlement of these markets, was established.
• EPİAŞ started to operations in 1st of September 2015. After this date TEIAS is responsible only balancing of power market.
2015
Milestones on the formation of the Turkish electricity market
Turkish Power System 20
Power balance in 2014
Generation (TWh): 251.962, 8
Consuption (TWh): 257.220,1
Imports (TWh): 7.953.3
Exports (TWh): 2.696.0
Losses (TWh): %2,4
20