Da Nang June, 26th 2014
1
The Urban Nexus Da Nang/Vietnam June, 26th 2014
Dipl.-Ing. (FH) Martin Schaub WEHRLE Umwelt GmbH
www.wehrle-umwelt.com
Licence Partner ofMYT Business Unit
WEHRLE’s history in MBT Technology
2002
1980
1927–2005
1920
End 19. Cty
1860
Transfer of the Environmental Branchof WEHRLE-WERK AG into thesubsidiary company WEHRLE UmweltGmbH (WUG), Foundation of WEHRLEChina
Begin of business in the field of Environmental Protection Technologies (Waste Water Treatment, Sludge Treatment) in a WEHRLE-WERK AG branch
Expanding business of WEHRLE-WERK AG with various products: Boilers, Combined Heat-and-power stations, Thermal treatment of household refuse and toxic waste, Energy recovery from biomass
Transformation into a stock corporation“WEHRLE-WERK AG”
Begin of manufacturing of low pressureboilers
Foundation of the locksmith’s trade"Wilhelm Wehrle"
Milestones in the history of the WEHRLE-WERK AG and
WEHRLE Umwelt GmbH
2Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
WEHRLE Umwelt GmbH today:
more 25 years of experience in the waste water business
100% subsidiary company of WEHRLE-WERK AG
60 employees
waste water treatment for the industry and leachate from landfills
plants for mechanical- biological treatment of solid waste and organic matter (AD technology)
potable water processing plants
More than 200 references world-wide
Turn over 13-18 Mil. €
3Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
Environmental Technologies of WEHRLE Umwelt GmbH
Membrane bioreactor (BIOMEMBRAT®)
EGSB reactor (BIODIGAT® SB)
WEHRLE Loop Reaktor (WLR)
Mechanical biological treatment of mixed solid waste (MYT)
Sequencing-Batch-Reactor (SBR)
Activated Carbon plant
Ammoniak stripping plants
Mechanical biological treatment of mixed solid waste (Dry
Digestion)Mechanical biological treatment of
high organic waste (Wet Digestion)
Membrane units (Ultra-, Nanofiltration, Reverse Osmosis)
Aerobic waste water treatment
Anaerobic waste water treatment Digestion of solid waste
Physical–chemical watertreatment
Anaerobic Filter (BIODIGAT® AF)
Anaerobic (BIODIGAT® AS)4
Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
Municipal Solid Waste KahlenbergZAK-Concept
Biologcical decomposition
Anaerobic digestionAerobic waste
water treatment
Mechanical separation
Electric current
Biological drying
Off-gas treatment
Inerts Solid recovered fuel
Metalseparation
Mechanicalpretreatment
Paper, packaging
Heat
Co-generation
MixedMSW
5Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
February 1997 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for the world’s first pilot plant for “Percolation”(Commissioning and Operation 1997-1999)
July 1999 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 20,000 tons/year MSW)(Commissioning and Operation 2000-2002)
July 2002 Commissioning of the Biological Drying Pilot Plant
July 2004 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 100,000 tons/year MSW)(Commissioning 2006)
Feb 2010 - Aug 2010 Commissioning and Operation of the BIODAMP Plant in Thailand
July 2012 Order of an important International Pharmaceutical Company for a technical Wet Digestion Plant (Throughput: 70,000 tons/year)
January 2013 Order for Engineering Services for the MYT Plant Symevad(Northern France)
June 2013 - Oct 2013 Commissioning and Operation of the BIODAMP Pilot Plant in China
WEHRLE‘s history in MBT Technology
6Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
Percolation Pilot Plant
Company: ZAK, Ringsheim
Location: Kahlenberg, Germany
Input: 1 ton/dayMunicipal Solid Waste (MSW)
Year: 1997
WEHRLE‘s history in MBT Technology
7Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
February 1997 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for the world’s first pilot plant for “Percolation”(Commissioning and Operation 1997-1999)
July 1999 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 20,000 tons/year MSW)(Commissioning and Operation 2000-2002)
July 2002 Commissioning of the Biological Drying Pilot Plant
July 2004 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 100,000 tons/year MSW)(Commissioning 2006)
Feb 2010 - Aug 2010 Commissioning and Operation of the BIODAMP Plant in Thailand
July 2012 Order of an important International Pharmaceutical Company for a technical Wet Digestion Plant (Throughput: 70,000 tons/year)
January 2013 Order for Engineering Services for the MYT Plant Symevad(Northern France)
June 2013 - Oct 2013 Commissioning and Operation of the BIODAMP Pilot Plant in China
WEHRLE‘s history in MBT Technology
8Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
Percolation Demonstration Plant
Company: ZAK, Ringsheim
Location: Kahlenberg, Germany
Input: 20,000 tons/yearMunicipal Solid Waste (MSW)
Year: 2000
WEHRLE‘s history in MBT Technology
9Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
February 1997 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for the world’s first pilot plant for “Percolation”(Commissioning and Operation 1997-1999)
July 1999 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 20,000 tons/year MSW)(Commissioning and Operation 2000-2002)
July 2002 Commissioning of the Biological Drying Pilot Plant
July 2004 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 100,000 tons/year MSW)(Commissioning 2006)
Feb 2010 - Aug 2010 Commissioning and Operation of the BIODAMP Plant in Thailand
July 2012 Order of an important International Pharmaceutical Company for a technical Wet Digestion Plant (Throughput: 70,000 tons/year)
January 2013 Order for Engineering Services for the MYT Plant Symevad(Northern France)
June 2013 - Oct 2013 Commissioning and Operation of the BIODAMP Pilot Plant in China
WEHRLE‘s history in MBT Technology
10Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
Biological Drying Pilot Plant
Company: ZAK, Ringsheim
Location: Kahlenberg, Germany
Input: 10,000 tons/yearMunicipal Solid Waste (MSW)
Year: 2002
WEHRLE‘s history in MBT Technology
11Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
February 1997 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for the world’s first pilot plant for “Percolation”(Commissioning and Operation 1997-1999)
July 1999 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 20,000 tons/year MSW)(Commissioning and Operation 2000-2002)
July 2002 Commissioning of the Biological Drying Pilot Plant
July 2004 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 100,000 tons/year MSW)(Commissioning 2006)
Feb 2010 - Aug 2010 Commissioning and Operation of the BIODAMP Plant in Thailand
July 2012 Order of an important International Pharmaceutical Company for a technical Wet Digestion Plant (Throughput: 70,000 tons/year)
January 2013 Order for Engineering Services for the MYT Plant Symevad(Northern France)
June 2013 - Oct 2013 Commissioning and Operation of the BIODAMP Pilot Plant in China
WEHRLE‘s history in MBT Technology
12Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
MYT® Plant „MBT Kahlenberg“
Company: ZAK, Ringsheim
Location: Kahlenberg, Germany
Input: 100,000 tons/yearMunicipal Solid Waste (MSW)
Year: 2006
WEHRLE‘s history in MBT Technology
13Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
February 1997 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for the world’s first pilot plant for “Percolation”(Commissioning and Operation 1997-1999)
July 1999 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 20,000 tons/year MSW)(Commissioning and Operation 2000-2002)
July 2002 Commissioning of the Biological Drying Pilot Plant
July 2004 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 100,000 tons/year MSW)(Commissioning 2006)
Feb 2010 - Aug 2010 Commissioning and Operation of the BIODAMP Plant in Thailand
July 2012 Order of an important International Pharmaceutical Company for a technical Wet Digestion Plant (Throughput: 70,000 tons/year)
January 2013 Order for Engineering Services for the MYT Plant Symevad(Northern France)
June 2013 - Oct 2013 Commissioning and Operation of the BIODAMP Pilot Plant in China
WEHRLE‘s history in MBT Technology
14Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
BIODAMP Pilot Plant Thailand
Company: WEHRLE Umwelt GmbH
Location: Petchaburi, Thailand
Input: 3 tons/dayMunicipal Solid Waste (MSW)
Year: 2010
WEHRLE‘s history in MBT Technology
15Da Nang June, 26th 2014
WEHRLE’s history in MBT Technology
February 1997 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for the world’s first pilot plant for “Percolation”(Commissioning and Operation 1997-1999)
July 1999 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 20,000 tons/year MSW)(Commissioning and Operation 2000-2002)
July 2002 Commissioning of the Biological Drying Pilot Plant
July 2004 Order of Zweckverband Abfallbehandlung Kahlenberg (ZAK)for a technical Percolation plant (Throughput: 100,000 tons/year MSW)(Commissioning 2006)
Feb 2010 - Aug 2010 Commissioning and Operation of the BIODAMP Plant in Thailand
July 2012 Order of an important International Pharmaceutical Company for a technical Wet Digestion Plant (Throughput: 70,000 tons/year)
January 2013 Order for Engineering Services for the MYT Plant Symevad(Northern France)
June 2013 - Oct 2013 Commissioning and Operation of the BIODAMP Pilot Plant in China
WEHRLE‘s history in MBT Technology
16Da Nang June, 26th 2014
Da Nang June, 26th 2014
17
Da Nang June, 26th 2014
18The grounds of the Zweckverband Abfallbehandlung Kahlenberg
Da Nang June, 26th 2014
19Landfill from 1973 - 2005: Disposal of about 6 Mio. tons of waste
Da Nang June, 26th 2014
20The landfill after renaturation: Habitat for many rare animals and plants
Da Nang June, 26th 2014
21Conservation area and goal for family outings
Merops Apiaster
Da Nang June, 26th 2014
22
Zweckverband Abfallbehandlung Kahlenberg (ZAK)
• ZAK is a special purpose association formed in a legal communalcooperation between the counties Emmendingen(EM) andOrtenaukreis (OG)
• ZAK is based in Ringsheim (Germany)
• ZAK serves 570,000 residents -> producing about 100,000 tons ofhousehold waste per year
• ZAK‘s function: Waste management of the delivered waste viarecycling, maximum yield extraction of biogas & RDF and disposal
Da Nang June, 26th 2014
23Location of the ZAK in Germany
ZAK
State of Baden-Württemberg
Da Nang June, 26th 2014
24
Household Waste Bio-Waste Packaging Paper Glass
About 20 drop-off points (excavated ground, construction rubble, used tires,
electronic waste, matured wood, lop, bulky waste)
Two extra pick-ups per year (bulky waste, lop, special waste)
Commercial waste (third party private)
Waste management in the ZAK linked districts
Da Nang June, 26th 2014
25
Mechanical – Biological Waste Treatment Trials
• 1996 - Fermentation trials on a semi-technical scale(No appropriate technology available, extreme amount of procedural deficiencies)
• Parallel development of the ZAK-Process(MBT treatment of household waste including household bio-waste)
– Material utilisation and landfilling (e.g. inert material and metals)
– Energy utilisation (RDF, Biogas)
– Operational efficiency (reduction of mass, minimalisation of non-treated residue and bio-waste, energy self-sufficient MBT)
– Ecology (encapsulation, air and water treatment, saving fossil fuels)
• 2000 - 2003 - Large Pilot/Demonstration-Plant
Da Nang June, 26th 2014
26View of the Demonstration-Plant
Da Nang June, 26th 2014
27Waste breakdown
Biogas
MBT
RDF
Metals
Minerals
Water
Rest
Losses
Ben
efit
/ Val
ue fo
r use
constituents
Household Waste
Da Nang June, 26th 2014
28
Mechanical – Biological Waste TreatmentMBT – Kahlenberg
Da Nang June, 26th 2014
29
Process steps of the MBT Kahlenberg: Mechanical Preparation
Da Nang June, 26th 2014
30
Building 1: Waste acceptance bunker - approx. 100,000 tons household waste per year from 570,000 residents
Da Nang June, 26th 2014
31Building 2: View of the mechanical preparation step
Da Nang June, 26th 2014
32Heavy mineral fraction sorted out
Da Nang June, 26th 2014
33„Can scrap“
Da Nang June, 26th 2014
34
Process steps of the MBT Kahlenberg: Biological Conversion
Da Nang June, 26th 2014
35
Solids
Press water
Process waterWaste
Agitator
Screw Press
DAMP® - Defined Aerobic Mixing Process
Da Nang June, 26th 2014
36Aggregates of the Biological Conversion step: DAMP-Reactor
DAMP-Reactor Design Figures:
• 6 concrete DAMP-Reactors
• Filling Volume 250 m³ (each)
• Retention Time in DAMP 2-3 days
Da Nang June, 26th 2014
37Aggregates of the Biological Conversion step: Agitator
Fundamental and conceptional further developments (Percolation / DAMP):• Goal: Determine and set RDF and Bio-Gas output rates
• Grade size reduction / homogenisation (Slurry-Mix)
• Reduction of toxic substances
• Aerobic pre-treatment – ideal for Biological Drying
• Remaining material includes useful organics for theBiological Drying step
elements:
- percolator / DAMP / mixer
- biogas fermenter
- waste water cleaning system
- presses
Da Nang June, 26th 2014
38Aggregates of the Biological Conversion step: Planetary Gearbox
Da Nang June, 26th 2014
39
Discharge from the biological conversion step, reduced in size, washed and homogenized
Da Nang June, 26th 2014
40Aggregates of the Biological Conversion step: Dewatering Press
Da Nang June, 26th 2014
41Mechnical-physical water treatment
Da Nang June, 26th 2014
42Aggregates of the biological conversion step: Biogas fermenters
CHP Plant
Da Nang June, 26th 2014
43
Process steps of the MBT Kahlenberg: Biological Drying
Da Nang June, 26th 2014
44Aggregates of the Biological Drying step: Drying tunnel
Demands on the input material:
• loose, homogeneous, air-flow-friendly material
• defined consistant moisture content(approx. 55% - 60% dry substance)
• aerobic pre-treated material
• microbiological useful organic content
• controlled air, solids and energy management
Da Nang June, 26th 2014
45Biological Drying tunnel (equipped with moving-floor)
Da Nang June, 26th 2014
46Aggregates of the Biological Drying step: Discharge Machine
Da Nang June, 26th 2014
47Aggregates of the Biological Drying step: Conveyors und dischargemachine, completely enclosed and evacuated
Da Nang June, 26th 2014
48Output of the Biological Drying step
Da Nang June, 26th 2014
49
Process steps of the MBT Kahlenberg:Air Treatment
Da Nang June, 26th 2014
50
Air Treatment Basics
• Preferably tight encapsulation of all machines and controlled and monitored air extraction
• Preferably airtight building construction
• Multiple use of extracted air volume
• Differentiated, flexible air treatment processes
• Consequential cleanliness and maintenance of all equipment
• Minimise emission exposure to personnel
Da Nang June, 26th 2014
51
facility buildings (machine halls)
collected exhaust air (point sources and buildings)
drying tunnels
supply airventilation
DAMP / MZR
alkaline air scrubbing
acid air scrubbing air moistening
clean air
biofilter
fresh air
excess air
regenerative thermal oxidizer
Air flow concept of the MBT Kahlenberg
enclosures of machinery (point sources)
Da Nang June, 26th 2014
52Aggregates of the Air Treatment step: Humidifier, waschers
Da Nang June, 26th 2014
53Aggregates of the Air Treatment step: Bio filters
Da Nang June, 26th 2014
54Aggregates of the Air Treatment step: RTO
Regenerative Thermal Oxidation (RTO)
Da Nang June, 26th 2014
55
Process steps of the MBT Kahlenberg: Mechanical Material Separation
Da Nang June, 26th 2014
56View of the Mechanical Material Separation step
Goals:
• specified, homogeneous RDF
• defined inert material
• scrap metal
Demands on the input material:
• loose, homogeneous and free-flowingmaterial
• specified consistant moisture content(>85 % dry)
• absolute dustproof encapsulation
• trouble free „just in time“ logistics
Da Nang June, 26th 2014
57Controlling of the separation quality
Da Nang June, 26th 2014
58
MYT® Maximum Yield Technology
Da Nang June, 26th 2014
59
MBT KahlenbergThe important products generated from the treatment
of about 100,000 tons/a of household waste
Plant operating time: 5 days/week, 2 shifts
Da Nang June, 26th 2014
60
Products of the Mechanical Separation step:EBS (Refuse Derived Fuel) mid caloric range (~13,000 MJ/ton)
Da Nang June, 26th 2014
61
Products of the Mechanical Separation step:EBS (Refuse Derived Fuel) mid caloric range (~14,000 MJ/ton)
Da Nang June, 26th 2014
62
Products of the Mechanical Separation step:EBS (Refuse Derived Fuel) high caloric range (~16,000 MJ/ton)
Da Nang June, 26th 2014
63
• Fuel or mineral optimized produktion• Landfilling according legal Landfill Directives• Separation accurancy adjustable „at the touch of a button“
Products of the Mechanical Separation step:Mineralstoffe (Mineral fraction)
Da Nang June, 26th 2014
64
Da Nang June, 26th 2014
65
BiogasRDF CHP Plant
Power Plants
Cement Plants
Electricity
Heating
Power Grid
Heating Network
BT
Gas Network
BT
Vehicles
Further development of the energy concept
MYT®
Obtain max. Energy potential
Efficient use
of Energy
Energy – and Environmental Management
Da Nang June, 26th 2014
66
Example MBT Kahlenberg Energy potential out of approx. 120,000 tons household waste
Hu about 7,000 MJ/ton, Hu about 235,000 MWh/year
MYT® works on its own energy and covers its energy needscompletely through the use of regenerative energy sources
25,00030,00040,000
165,000
235,000
0,000
50,000
100,000
150,000
200,000
250,000
Energy potentialtotal
Energy carrierRDF
Energy carrierBiogas
Losses House load MYT®
Ener
gy p
oten
tial /
Hea
ting
valu
e (M
Wh/
a)
Da Nang June, 26th 2014
67
Example MBT Kahlenberg Annual CO2 - savings from about 120,000 tons household waste
- Electricity from Biogas (pp) – RDF instead of coal
Climate friendly electricity and heat is obtained from the energy carriers biogas and high-biomass content RDF
62,000
20,000
0,000
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
Tons
per
Yea
r
RDF instead of coal Electricity from Biogas (pp)
Da Nang June, 26th 2014
68
Waste fees Baden-Württemberg
Comparison of the waste fees for a
4 person model household in 2013
in Baden-Württemberg
The Ortenaukreis has a simple and clear
waste management concept and tariff system
The waste fees are low!
Da Nang June, 26th 2014
69
Simple waste management concepts – low efforts needed for logistic and sorting systems reduced costs helps keep waste collection fees low.
Short waste treatments times – keeps machine size to a minimum = lower investment costs.
Well thought out design and tried and proven technology.High operational reliability means long term operational success.
Complete and flexible use of the energy potential. Energy carriers adapted to the needs of the energy user.
Modular concept – using tried and proven machines.Small and large sized plants economically viable.
Experienced specialized companies guaranteean easy and secure new project implementation.
Flexible site location – in the center of the waste collection area within direct vacinity to the energy users – economic logistic concepts.
Ecologically sound low-emission technology – site acceptance evenin direct vicinity to populated areas.
Operators profit from the training and consultation of ZAK.New plants can be operated with own personnel and in an exemplary manner.
Da Nang June, 26th 2014
70