Upload
rahul-deva
View
216
Download
0
Embed Size (px)
Citation preview
7/29/2019 TX242-Ch03
1/3
CHAPTER 3
Basic Design Overview (Part 2)
THIS chapter begins with the assumption that you are by
now somewhat familiar with the building plans for theproject example, and that the initial drafting (blocking out)
of the building layout is complete. Your sheet now looks
something like the example on page 140 labeledFigure A-1.
As is the typical procedure, what you have traced for areas of
exposed construction is the architects floor plan, and what
youhave traced for areas with finished construction is a close
copy of the architects reflected ceiling plan.
Once the building is blocked out in scale, it is time to draw
the sprinklers and system piping on the plan. This is the most
critical engineering portion of your work. It requires a com-
plete knowledge of theapplicable codes, mental visualization
of theproposed building, anda recall of your own knowledge
and instincts that you attained from all your past experiencein this area.
As was touched on in the last chapter, the architectural
plans mayincludea preliminarysprinkler plan,complete with
many legal disclaimers. It may be wise or unwise to use any
part of this plan as your own. The preliminary plan may be
an exact depiction of what the architect and building owner
desire, or it may simply be a quick drawing made to satisfy
some municipal requirement. Often, it has been prepared by
anengineer (hiredby thearchitect)whosereal area of special-
ization is his accompanying drawings (i.e., the mechanical,
electrical, civil, and/or plumbing plans). If the quality of the
preliminary sprinkler plan does not make this possibility ev-
ident, a phone call to this engineer is always worthwhile: for
only then will you find out if his design is diagrammatic in
nature, or if you are expected to comply with his plan with
limitedlatitudefor deviation. In many of thesecases however,
thefiner pointsin theengineers plan maybe wayoff themark
of conforming to the fire sprinkler engineering code. If so, a
good question to ask during this phone call would be about
what, if any, requirements in excess of the NFPA Pamphlet
No. 13 requirements are being asked for.
Thereareprojectsin which systemdesign hasalready been
thoroughly researched, prepared, andeven reviewed. When acommercial insurance company is very involved, as with one
of their H.P.R. clients, a pre-construction meeting is held
during the planning stages of a fire sprinkler system project
to allow for recognition of the hazard, understanding of the
project requirements, and providing bid specifications [1].
This will take care of allthe majorengineeringissues after the
local fire prevention bureau has their say, although the level
of preconstruction document review may vary substantially
depending on location [2]. Most fire prevention bureaus are
only interested in reviewing the final shop drawings which
you will prepare.
* * *For our purpose in this chapter, we are assuming that none
of the above preplanning activities have taken place. We will
now move on to the task of laying out the system after first
determining the occupancy and hazard level of the building
tenant, and whether or not any chance of pipe freezing will
exist.The answer weget isthatthis tenantis in the businessof
manufacturing thermopane glass and aluminum patio doors,
and that the facility will be heated year-round.
Since we have established that there is no reasonable
chance of future pipe rupture caused by freezing tempera-
tures, we will immediately decide to install the most reliable
system available, which is the wet-pipe automatic sprinkler
system. Speed of operation, low installation cost, and ease
of maintenance account for the fact that 75% of all sprin-
kler systems in use are of the wet-pipe type. There is no
size limitation on wet pipe systems, except that the max-
imum area protected by any one system on any one floor
of a single fire section cannot exceed 52,000 square feet
[3]. Our example building in Figure A-1 is well below this
maximum limit in size, and can be protected by a single
system.
1E\&5&3UHVV//&
http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/7/29/2019 TX242-Ch03
2/3
We are not concerned in this chapter with gridded or looped
systems, and so will utilize the only alternative left, which is
called a tree system. In this layout configuration, the water
flows from the system riser in a direction down feed-main and
cross-main piping, and finally down smaller sized branch-line
piping to the operating sprinkler. Water discharged from that
sprinkler always comes from a single direction.
In the layout phase, we first establish where we would liketo run our cross-main piping. In all phases of sprinkler design,
bear in mind this golden rule:
DO NOT MAKE A MISTAKE ON THE CROSS-MAIN!
Why? Because if branch-line (normally 12) piping can-
not be routed where you show it, an installer can correct that
without much fanfare. But rerouting the big cross-main pipe
is a different matter altogether. Not only is it expensive and
time-consuming, and not only does it affect all other down-
stream piping, but it can halt the installation completely while
the installers scratch their heads and attempt to achieve an en-
gineering solution on the job. This wastes time and time ismoney.
Again, the cross-main location and elevation is the first
thing that you lay out. The elevation must be low enough to
cross below structural beams, which usually means: lower
than the branch-lines. Naturally, the cross-main should be
hung high enough so as not to interfere with future building
operations. The system pipe elevations should be designed so
that all or most of the system can be drained when necessary
at the base of the system riser.
When steel bar-joists support the roof of the structure,
the direction of the branch-line runs are always perpendic-
ular to the joists, for ease of pipe hanging. Hence, to feed
the branch-lines, the cross-main must run parallel to the
joists.1
ALWAYS KNOW WHAT YOURE HANGING
THE PIPE TO!
Specifically, for optimum cost efficiency, the main should
be routed beneath a single joist, hung from one side of that
joist or the other.2 Look at the HVAC (Mechanical) drawings
to make absolutely certain that the joist location that you
select has the least chance of obstructional interference. And
dont select a joist (obviously) that rests directly above a
column, or the pipe will be run smack into a structural columnor I-beam. In order to avoid ductwork, it may be necessary
to offset the main once, or several times, or even change
elevation. Offsets, though, shall be minimized to reduce labor
andmaterialinstallation cost. Varying depths of I-beamsmust
be checked (on the steel drawings),3 but the highest priority
consideration must be that there is reasonable space available
for the piping to fit where it is shown. This space includes
space above the pipe as well: for example, there may be space
available to run pipe below some ductwork, but then it is
economically impractical to hang the pipe.
* * *
On concealedjobs (where all piping is concealed above
a drywall or drop-ceiling), the main piping must be hung at a
low elevation, beneath all other mechanical tradework. Many
designers routinely set cross-main elevations at 7
to 9
(pipecenterline) above the highest drop-ceiling height in these
instances. This is done because it is generally observed that
the sprinkler trade, being the last of the mechanical trades to
man a job, hang their pipe on concealed jobs below all
the ductwork, storm piping, electrical cable trays, and the
like; but also that the main must lay high enough to avoid
hindrances such as ceiling speakers and recessed lighting
fixtures. On tightjobs, where space available above ceiling
is at the bare minimum, it may be necessary to run the main
at an even lower elevation, being careful to route this pipe to
avoid hitting all the recessed lights.
* * *Before you lay out your branch-lines and fix their ele-
vation, you need to spot all the sprinkler-head locations.
The information youll need for this task is detailed more
thoroughly in Chapter 10, and requires knowledge of spac-
ing limitations. As previously mentioned, our example job
is of a glass-door manufacturer, an ordinary hazard occu-
pancy. The maximum head spacing for this tenant would be
130 sq. ft. The sprinklers must be positioned high enough
to fuse from a collection of heat, so factory and warehouse
sprinkler branch-line piping always run high, through the bar
joists. The pipe will run through either an A or V space
in these joists (Note Figure B-2 on page 151). To avoid run-
ning into joist bracing material, your safe bet is to space the
sprinkler lines an even number apart from one another (i.e.,
10, 12, or 14). The spacing between sprinklers in light and
ordinary hazard occupancies is only allowable up to a 15
maximum.6
Onceyouhave determined thedistancefrombranch-line to
branch-line, you can set the number of sprinklers on a line. In
the Figure A-2 example, the branch-lines are spaced 12apart,
andthesprinkler-headsare107 apart on-center, givingyoua
coverage per sprinkler of (12 107) 127 square feet. Your
distance from the sprinkler-head to a wall is not to exceed
one-half the distance between sprinklers in any direction (as
noted in NFPA #131999 ed.-5-5.3.2).
* * *
Noticethat we aresupplying seven sprinklers from a single
riser nipple, as opposed to six, or eight. The east half of
the building, framed by the I-beam, creates an area4 of
(23 74) 1702 sq. ft. Since our sprinkler spacing cannot
exceed130 sq. ft., and 1702 130 = 13.1, we know that we
will needat leastfourteenautomaticsprinklers to protect that
1E\&5&3UHVV//&
http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/7/29/2019 TX242-Ch03
3/3
23 74area. Twelve sprinklers would not be enough (for
any ordinary hazard occupancy). If sixteen sprinklers were to
be designed, the heads would be spaced 93apart, center-to-
center, giving you a coverage per sprinkler of (120 93)
111sq. ft.Butundernormalcircumstancesa contractor would
much prefer to install fourteen sprinklers in this area rather
than sixteen, for the same reason that one would only install
one unit heater (and not two or three) in a room if just onecould adequately do the job.
* * *
To set the elevation of the piping, we need to collect the
following facts: the building inFigure A-2 has a flat roof,5
the underside of which is 15
high. Its bar joists are all 62
apart and 20deep. The supporting I-beams all have a depth
of 24.
We have an obligation to keep our cross-main as high as
it can reasonably be situated, to maintain clearance for the
building owner. Our main piping would be safely installed at a
centerline elevation 6below the bottom of the solid I-beam.
This would translate to an elevation of (150 24 6)126. Hanging the branch-lines to run through the center of
the bar joists is also a safe bet, so we would be inclined to
have these installed at an elevation of (15 0 10) 142.
Attention must always be given to the HVAC contractor, the
no. 1 suspect in all sprinkler installation cases of conflict.
If his large airhandling equipment is to be installed on the
roof, we must be careful to avoid running sprinkler piping
below that area or areas. A basic goal of the sprinkler de-
signer is to avoid situations where field labor must cut pre-
fabricated piping because it will not fit where it is intended
to go.
Referring again to the example sketched in Figure A-2, the
fire sprinkler branch-linescould be placed116apart inorder
to reduce the overall sprinkler head spacing to (116107)
121.7 sq. ft. It may even be that this arrangement will work
well for installation, and the piping may be hung in that
fashion without field adjustment. In fact, the only field ad-
justment necessary for a branch-line obstruction, consisting
of steel bar-joist bracing in this case, would be to lengthen or
shorten the riser nipple (fed by the cross-main) to an eleva-
tion without obstruction for the line path.But our job is not to
take chances. Running the lines 116 apart would increase
thepossibility of positioning the sprinkler within 3 of a joist
web, which is a code violation as well as a sprinkler spraydischarge interference. Making use again of the information
derived from Figure B-2, I would recommend the 120spac-
ing to reduce your odds of running into structural members.
CITATIONS
1. Bruce A. Edwards, Fire Sprinkler Plan Review Process, FireProtection Contractor, Feb. 1995, p. 13.
2. Michael A. Crowley, Meeting Hospital Fire Codes: MissionImpossible? Consulting-Specifying Engineer, Feb. 1995, p. 57.
3. Sprinkler System Guide, Viking Fire Protection Associates In-corporated, Hastings, Michigan, 1981, p. 10.
ENDNOTES
1 As a general rule, 1 1/2 to 3 from the centerline of the joist is theusual spot for the pipe to hang. See Piping Methods and Details,Chapter 13.2 An installer will appreciate a note stating from which side of the
joist you intend to hang the cross-main.3 The optimum location for the main piping is to cross under theshallowest I-beam.4 Such an area created by ceiling-level beams is sometimes called atrave, or a bay.5
You will never encounter a single-story building with a perfectlyflat roof without pitch. This is strictly a hypothetical example.6 Sprinklersmay be positionedfurther apart only if specialextended-coverage sprinklers are used, in accordance with the manufacturersspecifications for installation.
1E\&5&3UHVV//&
http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/http://tx242-app-d.pdf/