yanshuwang-17

Embed Size (px)

Citation preview

  • 8/9/2019 yanshuwang-17

    1/7

    Use of the explosive method in the soil improvement work of

    a highway project

    S. W. Yan and J. Chu

    A highway was constructed in Jiangxi Province, China,

    through a mountainous area. Some sections of the

    highway went through valleys where a soft clay layer

    6 8.5 m deep was encountered. A new explosive method

    was developed and adopted for this project. The method

    uses the energy of the explosion to remove the soft clay

    and replace it with crushed stones. Explosive charges are

    placed in the soil to be improved according to a specific

    pattern. Crushed stones are piled up next to the area

    where the charges are installed. The explosion creates

    cavities in the soil and causes the pile of crushed stones

    to slide into the exploded area. The detail of the method

    and its application to the highway project are described.

    The effectiveness of the method is evaluated using

    borehole exploration, plate load tests and ground-

    probing radar tests.

    1. INTRODUCTION

    Explosive compaction has been a method used in past decades

    for the compaction of loose granular soil. The method usesenergy from confined detonations of explosive charges placed

    within the soil mass to densify loose, saturated sand or gravel.

    Various theoretical and case studies have been published in the

    past.18

    However, most of the studies are limited to

    applications in granular soils. The use of explosive compaction

    or similar methods in other types of soil, such as soft clay, is

    rare. Recently a new explosive method has been developed in

    China for removing and replacing seabed mud with rocks for

    offshore dike construction.9

    Encouraged by this development, a

    new method to replace soft clay with crushed stones by

    blasting has been tested in conjunction with a highway

    construction in Jiangxi Province, China. After some

    experiments, a workable method has been established and

    adopted in the soil improvement work for this highway project.

    This new method is called the explosive replacement method.

    The detail of the method and its application in this highway

    project are presented in this paper.

    2. BACKGROUND TO THE PROJECT

    To cater for the rapid economic development, a highway

    connecting Ganzhou and Dingnan in Jiangxi Province (see Fig.

    1) was constructed from January 2002 to January 2004. The

    highway is 127 km long and 26.5 m wide. A few sections of

    highway run through valley zones. The valleys were 2050 m

    wide, with the water table typically at the ground surface. A

    typical soil profile is shown in Fig. 2. The soils were alluvial in

    nature. The first layer was silty clay 68.5 m thick with a

    vegetation layer 0.5 0.6 m thick on top. The second layer was

    silty gravel 1.32 m thick overlying weathered sandstone. The

    top 12 m of the sandstone was highly decomposed. Typical

    soil properties of the soft clay are shown in Fig. 3. The water

    content of the soil was generally higher than the liquid limit

    (Fig. 3(b)). The undrained shear strength of the silty clay was

    only about 20 kPa (Fig. 3(c)). How to improve the soft clay

    layer rapidly for highway construction becameoneof the

    challenges to this project. Some of the commonly adopted soil

    improvement methodscould not be applied, as these methods

    could not offer an expedient solution to meet the project

    schedule. For example, surcharge or vacuum preloading

    together with vertical drains10

    are normally used for similar

    projects. However, the time required for consolidation was too

    long for this project. Deep cement mixing is also used

    sometimes for highway construction in China.11

    However, this

    method was considered too expensive to be used over a longsection. Furthermore, the use of this method might not meet

    the construction schedule either. The explosive replacement

    Article number = 13713

    Fig. 1. Location map

    Geotechnical Engineering 152 Issue GE1 Yan Chu 1Use of explosive method in soil improvement

    _________________________________________________________________________________________http://www.paper.edu.cn

  • 8/9/2019 yanshuwang-17

    2/7

    method was considered feasible for this project for the

    following three reasons:

    (a) The construction was in a remote mountainous area, so

    blasting was permitted.

    (b) Plenty of rocks were generated from the tunnelling work

    for the same project.(c) The soft clay layer to be replaced was only about 6 8.5 m

    thick.

    After some experiments, a workable method was established

    and adopted for this highway project.

    3. ANALYSIS

    The use of the explosive replacement method depends on the

    selection of design parameters such as the positioning of the

    charges, the charge messes, and the detonation sequence. Some

    relationships between these parameters have been used for

    explosive compaction:

    Hopkinsons number:12

    HNW1=3

    R1

    Normalised weight:8

    NW

    W=Lc 1=2

    R2

    Energy input attenuation:5

    E1 X Wi

    R2vi

    3

    whereWis the charge weight (kg), R is the effective radius in

    plan (m),Lc is the charge length (m), Wi is the weight of

    individual charges around a point in the soil mass (g), and Rviis the minimum vector distance from a charge to a point in the

    soil mass (m). HN, NWand E1 are constants. Unfortunately, for

    a given value ofHN,NWorE1, the above relationships may

    provide infinite combinations of charge weight with radius.

    Furthermore, it is difficult to select suitable valuesofHN,NW

    orE1 in practice. Based on blasting mechanics,13

    anew set of

    equations is derived as follows.

    As the explosion takes place very rapidly, it can be assumed to

    be aninsulated process. Based on the LondauStanyukowich

    theory,13

    we have

    ForPvp > Pk:

    Gravel 1

    8

    05

    Soft clay

    Vegetation

    8m

    Weathered sandstone bedrock

    Fig. 2. Typical soil profile in the valley

    0

    2

    4

    6

    8

    10

    12

    Void ratio

    Depth:m

    (a)

    0

    2

    4

    6

    8

    10

    12

    WC, LL and PL: %

    Depth:m

    WC

    LL

    PL

    (b)

    0

    2

    4

    6

    8

    10

    12

    cu: kPa

    Depth:m

    (c)

    0 1 2 30 25 50 75 100 0 20 40 60

    Fig. 3. Typical soil properties: (a) void ratio; (b) water content (WC), liquid limit (LL) and plastic limit (PL); (c) undrained shearstrength,cu

    Geotechnical Engineering 152 Issue GE1 Yan Chu Use of explosive method in soil improvement

    ________________________________________________________________________________________http://www.paper.edu.cn

  • 8/9/2019 yanshuwang-17

    3/7

    Pvp

    Pe

    Ve

    Vvp

    k4

    ForPvp , Pk:

    Pvp

    Pk

    Vk

    Vvp r

    5

    wherePkand Vkare the pressure and volume at the conjugate

    point, which is specified as the point where k 3 and r 4/3;

    Pvp is the pressure in the cavity (Pa); Vvp is the volume of the

    cavity (m3);Ve is the volume of explosive; and Pe is the

    explosive pressure (Pa), which can be calculated from:13

    Pe re D

    2

    2 k 1 6

    where re is the density of the explosive (kg/m3), and D is thevelocity of the explosive (m/s).

    For a spherical explosive, Ve 4r30=3 and Vvp 4R

    3v p=3,

    wherer0 is the radius of the explosive and Rvp is the radius of

    the cavity. Therefore:

    ForPvp > Pk:

    Pvp

    Pe

    Ve

    Vvp

    k

    r0

    Rvp

    97

    Thus, forPvp > Pk:

    Pvp re D

    2

    8

    r0

    Rvp

    98

    At the conjugate point Pvp PkandRvp Rk. Then, from

    equation(8),we have:

    Rk re D

    2

    8Pk

    1=9

    r09

    When the cavity expands furtherthat is, whenPvp , Pkwe

    have

    Pvp PkVk

    Vvp

    4=3 Pk

    Rk

    Rvp

    410

    When the cavity due to explosion ceases expansion,Pvp P0,

    whereP0 is the atmospheric pressure, Pa, plus the verticaloverburden pressure,

    Pni1i hc i, wherehc is the thickness of

    the soft clay above a cavity. Therefore the final radius of cavity

    due to explosion can be calculated as

    Rvd Pk

    P0

    1=4re D

    2

    8Pk

    1=9r0

    0:794P5=36k r

    1=9e D

    2=9 Pa Xni1

    i(hc)i

    " #1=4r0

    11

    As the mass of the explosive,Q, can be calculated as

    Q 3rer30=4Q 3rer0

    3=4, equation(11)can also be written

    as

    Rvd 0:4926P5=36k

    D

    re

    2=9Pa

    Xni1

    i hc i

    " #1=4Q1=312

    4. OUTLINE OF THE METHOD

    The explosivereplacement method is illustrated in Fig. 4. As

    shown in Fig.4(a), explosive charges are first installed in the

    soil layer, and then crushed stones are piled up next to it on

    the side of the road that has been improved. When the chargesare detonated, the soft soil is blown out and cavities are

    formed. At the same time, the crushed stones collapse into the

    cavities. In this way, the soft soil is replaced with crushed

    stones in a rapid manner. The soil that is blown into the air

    will form a liquid and flow away after it falls to the surface.

    The crushed stones after collapsing form a slope of 1V: 3Hor

    1V: 5H, as shown in Fig. 4(b). The impact of the explosion also

    causes an instantaneous reduction in the shear strength of the

    soil below the level of explosion14

    so that the crushed stones

    can sink into the soft clay layer. The stones help the soil at the

    bottom to consolidate, and the clay itselfwill also regain part

    of its original strength after explosion.14

    The explosion also

    has a densification effect on the gravel layer below the clay

    layer. More crushed stones are backfilled to form a levelled

    ground and a steeper slope, as shown in Fig. 4(c). The above

    process is then repeated to remove and to replace the soil in

    another section.

    5. APPLICATION

    A typical cross-section of the highway is shown in Fig.5. The

    road surface is elevated to up to 6 m above the ground to

    counter flooding. The width of the soft soil layer to be

    improved is required to be 5 m wider than thetoe of the

    embankment on each side, as shown in Fig.5.

    5.1. Placement of charges

    A TNT type of explosive was used for the project. The design

    parameters for the explosive were: density, re 1100 kg/m3;

    velocity,D 6200 m/s;Pk 3.0 3 108 Pa. The unit weight of

    the soil was 18 000 N/m3. Substituting all the parameters into

    equation(12),we have:

    Rvd 10:4Q1=3

    98000 18000hc 1=413

    As the purpose of blasting is to remove the soft clay, the

    thickness of the soft clay above a cavity should be controlled

    to be small. Usinghc 0 in equation(13),we have:

    Geotechnical Engineering 152 Issue GE1 Yan Chu 3Use of explosive method in soil improvement

    ________________________________________________________________________________________http://www.paper.edu.cn

  • 8/9/2019 yanshuwang-17

    4/7

    Rvd 0:59Q1=314

    equation(13)is equivalent to equation(1) when NH 0.59.

    ForQ 1020 kg, we getRvd 1.271.6 m from equation

    (14).The distance between charges, L, can be estimated as

    L Rvd15

    where 1.5 2.0. When 2,L the diameter of the

    cavity. To allow some overlapping, , 2 should be used.

    Based on the above analysis, a constant value ofL 2 m was

    used for this project. The weight of each charge can then be

    calculated using equation(13),and the values are tabulated in

    Table 1 for different depths of soft clay. As the charges used

    were cylindrical rather than spherical, the cavity would be a

    teardrop shape, with its vertical dimension much larger than

    the calculatedRvd.13

    For this reason, the actual depth of the

    clay above the cavity was small. A factor of 1.3 1.5 was also

    applied to the weight of charge to ensure a complete collapse

    of the cavities formed. The real weight of each charge with

    respect to different depths of soft clay is given in Table 1.

    The charges were installed at a horizontal spacing of 2 m in

    one row. The embedded depth of the charge was determined

    based on the depth of the clay layer as calculated in Table 1.

    Thecharges were installed using a 16 t excavator, as shown in

    Fig.6. A pipe 21.3 cm in diameter and 12 m long was driven

    into the soft clay using a 11 kW vibrator. Once the pipe

    reached the required depth, a cylindrical charge 19 cm in

    diameter was placed. For a charge weight of 1624 kg, the

    length of the charge would be 5080 cm. Water was filled intothe pipe as an overburden pressure to the charge before the

    pipe was pulled out. Sequential detonation was used to reduce

    the impact of the explosion. A picture taken at the moment of

    explosion is shown in Fig. 7.

    5.2. Placement of crushed stones

    The source of the crushed stones was the sandstone rock

    excavated from tunnelling construction for the same highway

    Section that has been

    replaced by crushed

    stones

    Pile of crushed stones

    56

    1

    1V

    08H

    46

    Charge685m

    Soft clay

    (a)

    (b)

    (c)

    Profile before explosion

    Profile after explosion

    1V

    (35)H

    Soft clay

    Soft clay

    Backfill

    1

    Fig. 4. Explosive displacement procedure: (a) before explosion;(b) after explosion; (c) after backfill

    Gravel

    Replaced crushed stones

    Embankment

    265 m

    5 m 445 m 5 m

    85m

    1

    8m

    6m

    15

    1

    Fig. 5. Typical cross-section of the road

    Geotechnical Engineering 152 Issue GE1 Yan Chu Use of explosive method in soil improvement

    ________________________________________________________________________________________http://www.paper.edu.cn

  • 8/9/2019 yanshuwang-17

    5/7

    PROOFS

    project. The particle size of the stones ranged from 10 to

    70 cm. The pile of crushed stones was typically 12 m high

    and 56 m wide (see Fig. 4(a)). After the explosion, the stonesfell into the cavities and formed a slope of 1V: 3Hto 1V: 5H.

    More stones were backfilled to form a levelled ground and a

    boundary slope of 1V: 0.8H. With every round of explosion,

    the improvement section could be advanced for 6 8 m.

    5.3. Construction of

    embankment

    An embankment typically

    6 m high (see Fig.5) was

    constructed after the soil

    improvement work. The fill

    used for the embankment wasmainly a clayey sand with

    basic properties as given in

    Table 2. The maximum dry

    density and the optimum

    water content as obtained

    from standard Proctor

    compaction tests were

    1.8 Mg/m3 and 14.5%

    respectively. Roller

    compaction with 0.3 0.5 m

    for each lift was used. The

    relative compaction values

    specified were 95% for the

    top 0.8 m, 93% for the fill

    between 0.8 and 2.3 m, and

    90% for the fill below 2.3 m. The pavement cover consisted of

    a 600 mm thick concrete layer and a 160 mm thick bitumen

    concrete layer on top.

    6. VERIFICATION

    6.1. Borehole exploration

    Boreholes were drilled to examine the depth of the crushed

    stones after soil improvement. One of the borehole logs is

    shown in Fig.8. The stones were found to be present up to 9 m,

    in which the top 56 m was densely packed whereas the

    remaining 45 m was embedded in clay. Below the crushed

    stone layer were the silty gravel layer and the weathered

    sandstone layer.

    6.2. Plate load tests

    Plate load tests were conducted using a square plate 1.0 m 3

    1.0 m. The load was applied via a hydraulic jack reacted

    against a steel beam, which was counterbalanced by dead

    weight. The plate was placed on the ground surface before the

    6 m of embankment was built. The results of a typical plate

    load test are shown in Fig.9. The results indicate that the

    improved ground had adequate bearing capacity. Using the

    loadsettlement curve shown in Fig.9, the modulus of

    subgrade reaction, ks, which is used for pavement design,15

    can be determined as the secant modulus for a specified point

    on the curve.16

    The modulus of subgrade reaction determined

    from the initial linear portion of the curve was 120 MPa (see

    Fig.9). It should be pointed out that the plate load test results

    reflected only the condition of the upper layer of 1 .52 m

    depth in the compacted stone layer. The critical area for

    settlement would be the deeper zone where the stone was

    mixed with soft clay, which was not significantly stressed by

    the plate load tests. Therefore the plate load test results gave anoptimistic picture of the loadsettlement behaviour. The

    settlement of the improved foundation soil measured 3 months

    after the opening of thehighway was more than the maximum

    settlement shown in Fig. 9, but less than 30 mm. The total

    settlement of the highway measured at the same time was less

    than 100 mm. The total allowable settlement as specified by the

    Depth of soil, h: m 5 6 7 8

    Distance betweencharges, L: m 2 2 2 2 in equation(15) 1.7 1.6 1.5 1.5Radius of cavity, R vd: m 1.18 1.25 1.33 1.33Thickness of soft clay above cavity, hc: m 2.65 3.50 4.33 5.34Embedded depth for charges, hc + R vd: m) 3.83 4.75 5.66 6.67Weight of each charge, Q: kg 10.9 14.0 18.0 19.3Weight of each charge used, Qu: kg 16 20 24 24

    Table 1 Calculation of the weight of each charge

    Fig. 6. Installation of charges

    Fig. 7. During explosion

    Soil type Liquidlimit

    Plasticlimit

    Plasticityindex

    Fines content(less than 75 m)

    Organiccontent

    Clayey sand (SC)* 25.3% 12.3% 13% 18% 2.7%

    *According to the Unified Soil Classification System.

    Table 2 Basic properties of the fill used for embankment

    Geotechnical Engineering 152 Issue GE1 Yan Chu 5Use of explosive method in soil improvement

    ________________________________________________________________________________________http://www.paper.edu.cn

  • 8/9/2019 yanshuwang-17

    6/7

    PROOFS

    Ministry of Transport for the design of expressways in China

    was 300 mm.

    6.3. Ground-probing radar

    (GPR) tests

    GPR was used to detect the

    distribution of the crushed

    stones in the soft clay. The

    radar system transmits

    repetitive, short-pulse

    electromagnetic waves into

    the ground from a broad-

    bandwidth antenna. Some of

    the waves are reflected when

    they hit discontinuities in the

    subsurface, and some are

    absorbed or refracted by thematerials that they come into

    contact with. The reflected

    waves are picked up by a

    receiver, and the elapsed time between wave transmission and

    reception is automatically recorded. More explanation of the

    method can be found in reference17.

    The GPR system used in this project adopted a frequency of

    100 MHz. This frequency was chosen to suit the depth of the

    crushed stone layer. GPR tests were conducted along six lines

    of a total length of 417 m. Of these, two lines were along the

    longitudinal direction and four were along the transverse

    direction of the highway. One scanned profile is shown in Fig.

    10.The crushed stones in the top 5 m of the soil profile were

    detected. Soft clay pockets within this layer could also be

    identified from the image, as indicated by arrows in Fig. 10.

    However, the stones in the deeper layer could not be identified

    clearly from the image. This could be because the radar wave

    became much less effective when it penetrated the layer of

    stones embedded in clay.

    7. SUMMARY

    A new explosive replacement method was developed and

    adopted for the soil improvement work of a highway project in

    Jiangxi, China. The method uses the energy of explosion toremove and replace soft clay with crushed stones. Explosive

    charges were placed in the soil to be improved according to a

    specific pattern. Crushed stones were piled up next to the area

    where the charges were installed. The explosion created

    cavities in the soil and caused the pile of crushed stones t o

    slide into the exploded area. Based on blasting mechanics,13

    a

    set of equations regarding the weight of the charge and the

    radius of the explosive cavity were derived to calculate the

    weight of the charges and the spacing between the charges. The

    design of the charges was made using the equations and the

    results were found to be satisfactory. A method to install

    charges was also developed and used in this project. Borehole

    exploration after the soil improvement revealed that the

    crushed stones were densely packed in the top 56 m, but were

    embedded in clay in the bottom 34 m. The results of plate load

    tests indicated that the top layer of the improved ground had

    sufficient bearing capacity and a high modulus of subgrade

    reaction. The ground-probing radar adopted was effective in

    detecting the layer of the densely packed crushed stones.

    0

    56 m

    89 m

    9105 m

    Crushed stones, densely

    packed

    Crushed stone embedded inclay

    Siltygravel

    Sandstone with top 12 m

    heavily weathered

    Siltygravel

    Fig. 8. Borehole log of the replaced soil layer

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    Load: kPa

    S

    ettlement:mm

    ks120 MPa

    0 200 400 600 800

    Fig. 9. Results of plate load test

    Fig. 10. An image from ground-probing radar

    Geotechnical Engineering 152 Issue GE1 Yan Chu Use of explosive method in soil improvement

    ________________________________________________________________________________________http://www.paper.edu.cn

  • 8/9/2019 yanshuwang-17

    7/7

    PROOFS

    REFERENCES

    1. HALLC. E. Compacting a dam foundation by blasting.

    Journal of Soil Mechanics and Foundation Division, ASCE,

    1962, 88, No. 3, 3351.

    2. CHADWICKP., COXA. D. and HOPKINSH. G. Mechanics of

    deep underground explosions. Proceedings of the Royal

    Society, London, 1964, A256, No. 1070, 235300.

    3. CHARLIE W. A., JACOBSP. J. and DOEHRING D. O.

    Blasting-induced liquefaction of an alluvial sand deposit.

    Geotechnical Testing Journal, ASTM, 1992, 15, No. 1,

    1423.

    4. NARIN VANCOURTW. A. and MITCHELLJ. K. New insights

    into compaction of loose, saturated, cohesionless soils. In

    Soil Improvement for Earthquake Hazard Mitigation, ASCE

    Geotechnical Special Publication No. 49, 1995, pp. 5165.

    5. NARIN VANCOURTW. A. and MITCHELLJ. K. Investigation of

    predictive methodologies for explosive compactions.

    Proceedings of the ASCE Specialty Conference on

    Geotechnical Earthquake Engineering and Soil Dynamics,

    Seattle, WA, ASCE Geotechnical Special Publication No.

    75, 1998, pp. 639653.

    6. GANDHIS. R., DEYA. K. and SELVAM S. Densification ofpond ash by blasting. Journal of Geotechnical and

    Geoenvironmental Engineering, ASCE, 1998, 125, No. 10,

    889899.

    7. GOHLW. B., JEFFERIES M. G., HOWIEJ. A. and DIGGLE D.

    Explosive compaction: design, implementation and

    effectiveness.Geotechnique, 2000, 50, No. 6, 657665.

    8. DEMBICKIE., IMIOLEKR. and KISIELOWAN. Soil compaction

    with blasting method. In Geomechanics and Water

    Engineering in Environmental Management(CHOWDHURYR.

    N. (ed.)). Balkema, Rotterdam, 1992, pp. 599622.

    9. JINL. and SHIF. Blasting techniques for underwater soft

    clay improvement.China Harbour Engineering, 1999, No.

    2, 10 17; No. 3, 1627.

    10. YANS. W. and CHUJ. Soil improvement for a road using

    the vacuum preloading method. Ground Improvement,

    2003,7, No. 4, 165172.

    11. LINK. Q. and WONGI. H. Use of deep cement mixing to

    reduce settlements at bridge approaches. Journal of

    Geotechnical and Geoenvironmental Engineering, ASCE,

    1999,125, No. 4, 309320.

    12. IVANOVP. L. Compaction of Noncohesive Soil by Explosions.

    US Department of Commerce, Springfield, VA, 1967,

    National Technical Information Service Report No.

    TT70-57221.

    13. HENRYCHJ. The Dynamics of Explosion and Its Use.

    Elsevier, Amsterdam, 1979.

    14. OSIPOVV. I., NIKOLAEVAS. K. and SOKOLOVV. N.

    Microstructural changes associated with thixotropic

    phenomena in clay soils. Geotechnique, 1984, 34, No. 2,

    293303.15. AASHTO Guide for Design of Pavement Structures.

    American Association of State Highway and Transportation

    Officials, Washington, DC, 1993.

    16. BOWLES J. E.Foundation Analysis and Design.

    McGraw-Hill, New York, 1996.

    17. KOERNER R. M. Construction and Geotechnical Methods

    in Foundation Engineering. McGraw-Hill, New York,

    1984.

    Please email, fax or post your discussion contributions to the secretary: email: [email protected]; fax: 44 (0)20 665 2294;

    or post to Mary Henderson, Journals Department, Institution of Civil Engineers, 17 Great George Street, London SW1P 3AA.

    Geotechnical Engineering 152 Issue GE1 Yan Chu 7Use of explosive method in soil improvement

    ________________________________________________________________________________________http://www.paper.edu.cn