ABSTRACT OF REFERENCES BIOGAS PLANT
Project: Pumpwerk III Biogas Plant Am Pumpwerk III, 38543 Hillerse
Client: Abwasserverband Braunschweig Körperschaft des öffentlichen Rechtes Neubrück, Celler Str. 22 38176 Wendeburg
Contact: Mr. Schorling Tel.: +49 / 5303 / 509-30
Consultant Dr. Born – Dr. Ermel GmbH Finienweg 7 28832 Achim b. Bremen
Contact: Mr. Lühring Tel.:+49 / 4202 / 758-244
Execution Period: January 2007 – November 2007
Contract Value:: approx. €5,055,400.00
Scope of Work: Engineering, Procurement & Construction (EPC) of a biogas plant 2,5 MWel
Civil work
Mechanical work
Electronic work
2 fermentation tanks with covering (Ø 19 m, h = 19 m / volume = 2 x 5,387 m³) 1 anaerobic fermenter (Ø 29.0 m, h = 6.0 m / volume 3,963 m³) with double
membrane gas storage) 3 storage tanks for fermentation residues (Ø 29 m, h = 6 m / volume 3 x 3,963
m³) biogas storage tank for dry gas, standing upright and cylindrically shaped, plas-
tic diaphragm accumulator 500 m³, lining with steel profiles operational building (masonry with trapezoidal roof) including cellar with pumps
for the feeding of solid matters; ground floor with pump technology (distribution) and moving floors for solid matters; top floor with pre-storage tank for corn 6 m³ from polystyrene material
outside grain silo 130 m³ from galvanized steel sheet equipping tanks and the operational building with submersible mixers and top
entry mixers heating installations in the operational building as well as in the fermenters and
anaerobic fermenters entire supply with and installation of electronic equipment and metrology for the
whole plant