42
ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I

Atec 2340 lecture7

Embed Size (px)

Citation preview

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

ATEC 2340 Project Management for Arts & Technology - I

Agenda• Project Time

Management

• Project Cost Management

• Mid Term

ATEC 2340 Project Management for Arts & Technology - I

Project Management Body of Knowledge (PMBOK)

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Time Management

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Before we begin…

Project Time Management = Project Scheduling

Because, 95 % of the time when people think about project management, they think about schedule.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Importance of Project Schedules…

• Managers often cite delivering projects on time as one of their biggest challenges.

• Schedule issues are the main reason for conflicts on projects, especially during the second half of projects.

• Time has the least amount of flexibility; it passes no matter what happens on a project.

*The Standish Group, “Latest Standish Group CHAOS Report Shows Project Success Rates Have Improved by 50%,” (www.standishgroup.com) (March 25, 2003

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Time Management: The Big Picture

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Time Management Processes

• Activity definition: Identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.

• Activity sequencing: Identifying and documenting the relationships between project activities.

• Activity resource estimating: Estimating how many resources a project team should use to perform project activities.

• Activity duration estimating: Estimating the number of work periods that are needed to complete individual activities.

• Schedule development: Analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule.

• Schedule control: Controlling and managing changes to the project schedule.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Activity Definition• Activity List:

– An activity list is a tabulation of activities to be included on a project schedule.– All activities necessary and sufficient to produce the product deliverables– Defined in sufficient detail to promote understanding by project team

• Activity Attributes:Activity attributes provide more information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.

– Activity identifier and code– Activity description– Assumption and constraints– Predecessor and Successor Activities– Resource Requirements– Team Member Responsible for Performing the Work

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Milestones

• A milestone is a significant event that normally has no duration.

• It often takes several activities and a lot of work to complete a milestone.

• Milestones are useful tools for setting schedule goals and monitoring progress.

• Examples include completion and customer sign-off on key documents and completion of specific products.

ATEC 2340 Project Management for Arts & Technology - I

Project Time Management: The Big Picture

ATEC 2340 Project Management for Arts & Technology - I

Activity Sequencing• Identifies the dependencies among the schedule activities and orders the

activities accordingly – A task has a dependency if it involves an activity, resource or work

product which is subsequently required by another task

• Tasks may have dependencies because they require the same resource

A BActivity A is a predecessor

of activity BActivity B is a successor of

activity A

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Precedence Relationships• Finish to Start

– Initiation of the successor activity depends upon completion of the predecessor activity

• Finish to Finish– The completion of the successor activity depends upon the completion of

the predecessor activity• Start to start

– The initiation of the successor activity depends upon the initiation of the predecessor activity

• Start to finish– The completion of the successor activity depends upon the initiation of

the predecessor activity

ATEC 2340 Project Management for Arts & Technology - I

Precedence Relationships

ATEC 2340.001.F16 Sagar Wadhwani http://www.stellman-greene.com

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Three types of Dependencies

• Mandatory Dependencies– Inherent to the schedule activities (e.g. software must be developed

before it can be tested)• Discretionary Dependencies

– Dependencies at the discretion of the project team (e.g. acceptance test with marketing before accounting)

• External Dependencies– Involves a relationship between a project activity and a non-project

activity (e.g. Windows Vista Delivered)

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Network Diagram

• Network diagrams are the preferred technique for showing activity sequencing.

• A network diagram is a schematic display of the logical relationships among, or sequencing of, project activities.

• Two main formats are the arrow and precedence diagramming methods.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

A Sample Network Diagram

ATEC 2340 Project Management for Arts & Technology - I

Project Time Management: The Big Picture

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Activity Resource Estimating

• Before estimating activity durations, you must have a good idea of the quantity and type of resources that will be assigned to each activity.

• Consider important issues in estimating resources:– How difficult will it be to complete specific activities on this project?– What is the organization’s history in doing similar activities?– Are the required resources available?

ATEC 2340 Project Management for Arts & Technology - I

Project Time Management: The Big Picture

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Activity Duration Estimating

• Duration includes the actual amount of time worked on an activity plus the elapsed time.

• Effort is the number of workdays or work hours required to complete a task.

• Effort does not normally equal duration.

• People doing the work should help create estimates, and an expert should review them.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Developing the Schedule

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Schedule Development

• Uses results of the other time management processes to determine the start and end dates of the project.

• Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.

• Important tools and techniques include Gantt charts, critical path analysis, critical chain scheduling, and PERT analysis.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Gantt Charts

Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

A Sample Gantt Chart

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Adding Milestones to Gantt Charts

• Many people like to focus on meeting milestones, especially for large projects.

• Milestones emphasize important events or accomplishments in projects.

• You typically create milestone by entering tasks that have a zero duration, or you can mark any task as a milestone.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Schedule Control

• Perform reality checks on schedules.

• Allow for contingencies.

• Don’t plan for everyone to work at 100 percent capacity all the time.

• Hold progress meetings with stakeholders and be clear and honest in communicating schedule issues.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Reality Checks on Scheduling

• Review the draft schedule or estimated completion date in the project charter.

• Prepare a more detailed schedule with the project team.

• Make sure the schedule is realistic and followed.

• Alert top management well in advance if there are schedule problems.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Using Software to assist in Time Management

• Software for facilitating communication helps people exchange schedule-related information.

• Decision support models help analyze trade-offs that can be made.

• Project management software can help in various time management areas.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Cost Management

ATEC 2340 Project Management for Arts & Technology - I

Project Management Body of Knowledge (PMBOK)

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Cost Management

• Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange

– Costs are usually measured in monetary units like dollars

• Project cost management includes the processes required to ensure that the project is completed within an approved budget

– Project managers must make sure their projects are well defined, have accurate time and cost estimates and have a realistic budget that they were involved in approving

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Cost Management Process

1. Plan Cost Management

• Establish the policies and procedures for planning and managing project costs.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Cost Management Process

1. Plan Cost Management2. Estimate Costs

• Develop an estimate or approximation of the monetary resources needed to complete project activities.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Cost Management Process

1. Plan Cost Management2. Estimate Costs3. Determine Budget

• Combining the total estimated costs of individual activities – plus contingency – to develop a cost baseline, also known as approved budget.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Project Cost Management Process

1. Plan Cost Management2. Estimate Costs3. Determine Budget4. Control Costs

• Monitor and manage costs, as based on status of activities.

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Plan Cost Management

Inputs:• Project Management Documents to date• Enterprise & Environmental Factors• Organizational Process & Policies

Tools and Techniques:• Expert Judgement • Financial Strategies such as Purchasing, renting, leasing, Internal or

external funding or investments

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Estimate CostsInputs:• Cost Management Plan• Scope baseline• Project schedule

Tools and Techniques:• Expert judgement• Analogous estimating - Similar project• Bottom-up or Rolled-up - Estimate individual activities and roll up• Three point estimating - Most likely, Optimistic, Pessimistic/worst case

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Determine Budget

Inputs:• Cost management plan• Scope• Schedule• Activity cost estimates• Resource calendars• Agreements• Organizational rules and tools

ATECARTS & TECHNOLOGY

ATEC 2340 Project Management for Arts & Technology - I

Determine Budget

Tools and Techniques:

• Expert Judgement• Cost Aggregation – take details and roll up• Reserve analysis – estimates of contingency• Analogous estimates – similar projects• Funding limits and estimated costs