Manajemen Proyek Tugas 1 Andri

Preview:

DESCRIPTION

Project Management Task

Citation preview

Muhammad Andri Alkautsar R.1106070073Metalurgi dan Material

TUGAS MANAJEMEN PROYEK

1. Gantt Chart dari tabel pekerjaan Task Start Time

(Weeks)Duration (Weeks) End Date

A 0 5 5B 6 3 9C 7 4 11D 7 9 16E 8 2 10F 9 8 17G 12 7 19

Tabel Gantt Chart

A

B

C

D

E

F

G

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Tugas terakhir (task g) akan selesai pada minggu ke 19.

2. Rencana pengeluaranWeek Task Weekly Direct Expense Cumulative Expense1 A 10 102 A 10 203 A 10 304 A 10 405 A 10 506 0 507 B 15 658 B,C,D 75 1409 B,C,D,E,F 105 24510 C,D,E,F 90 33511 C,D,F 80 41512 D,F 55 47013 D,F,G 65 535

Muhammad Andri Alkautsar R.1106070073Metalurgi dan Material

14 D,F,G 65 60015 D,F,G 65 66516 D,F,G 65 73017 F,G 55 78518 G 10 79519 G 10 805

Grafik cumulative expense

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 190

100

200

300

400

500

600

700

800

900Cumulative

Expense; 805

Cumulative Expense

Cum

ulat

ive

Expe

nse

$100

0

Grafik weekly expense

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 190

20

40

60

80

100

120

Chart Title

Series1

Week

Wee

kly

exp

ense