View
220
Download
0
Category
Preview:
Citation preview
7/28/2019 Mihai 1
1/10
Metoda P.E.R.T. (Program Evaluation and Review Technique).
Programul de Evaluare i Examinare Tehnic (PERT) este un model de tip reea care permite randomizarea
n programarea timpului de ndeplinire a sarcinilor unui proiect. Prin PERT se poate reduce att t impul, ct icosturile unui proiect.
Etape n procesul de planificare PERT:1. Identificarea activitilor specifice i a obiectivelor intermediare:
Este de ajutor sa se alcatuiasc o lista de activiti care, n etape ulterioare, s poata fi extins cu ajutorul
informaiilor avute la dispoziie;2. Determinarea etapizrii activitilor:
Aceast etap presupune o analiz a fiecrei activiti n parte pentru a determina relaiile acestora una cu
cealalta i ordinea n care trebuie finalizate;3. Construirea diagramei de reea:
Construirea diagramei se poate face cu ajutorul unui software specializat sau manual. n ambele cazuri, este
bine s se foloseasc simboluri uzuale ca de exemplu: activitile vor fi reprezentate de sgei, n timp ce
obiectivele intermediare sunt simbolizate prin cercuri.4. Estimarea timpului necesar pentru realizarea fiecrei activiti:
Pentru a determina timpul de realizare a unei activiti, n mod normal se determina trei timpi:timpul
optimistic, "timpul cel mai probabil, "timpul pesimistic.Timpul de realizare a unei activiti se
calculeaz apoi astfel:
Tra=(Topt+4*Tprob+Tpes)/6
5. Determinarea cii critice:
Calea critic se determin prin adugarea timpilor activitilor pentru fiecare secven i determinnd cea
mai lung cale a proiectului.6. Updatarea PERT pe msura ce proiectul progreseaz:Pe masura ce proiectul progreseaz, se pot face modificri. Timpii programai pot fi modificai cu ceirealizai. Daca apar ntarzieri, se vor aloca resurse adiionale pentru recuperarea acestuia i diagrama
PERT va fi modificat pentru a reflecta acest lucru.
7/28/2019 Mihai 1
2/10
Model PERT - etapizare simpla
Avantaje ale metodei PERT:
Diagrama PERT este mai folositoare dect alte metode utilizate n prezent deoarece ne pune la dispoziie
unele informaii precum: Timpul prognozat de realizare a proiectului;
Probabilitatea de realizare naintea datei specificate;
Activitaile ci critice care au impact direct asupra datei de finalizare a proiectului;
Activitaile care au timp suplimentar la dispoziie care poate fi pus la dispozitia activitatilor ci
critice; Data de ncepere i ncheiere a proiectului.
Dezavantaje ale PERT:
Printre limitarile PERT, se pot aminti urmatoarele: Estimrile timpilor activitilor sunt oarecum subiective i depind de judecata uneia sau mai multor
persoane pe baza unor informaii (complete sau incomplete) avute la dispoziie n momentul realizrii
estimrilor; Chiar dac timpii activitilor sunt bine estimai, PERT accept o beta distribuie a acestor
estimri n cadrul ntregului proiect, n timp ce distribuia real poate fi real.
Chiar daca PERT realizeaz o beta-distribuie similar cu cea real, exist posibilitatea apariiei unor
ntrzieri deoarece timpul asociat de catre PERT cii critice va fi ntotdeauna mai mare dect n mod real.
Program Evaluation & Review Technique(PERT)
PERT Activity TimesoThree time estimates are required
Optimistic time (a) if everything goes according toplan
Mostlikely time (m) most realistic estimate Pessimistic time (b) assuming very unfavorable
conditions
7/28/2019 Mihai 1
3/10
o Follow beta distributiono Expected time: t = (a + 4m + b)/6o Variance of times: v = [(b a)/6]2
Project Timeso Conduct CPM method using expected activity timeso Expected project time (T)
Sum of critical path activity times (t)
o Project Variance
Sum of critical path activity variances (v)
Probability of Project Completiono Project variance is computed by summing the variances of
critical activitieso 2 = Project variance
= (variances of activities on critical path)
o PERT makes two more assumptions:Total project completion times follow a normal
probability distribution
Activity times are statistically independento What is the probability this project can be completed on or
before the 16 week deadline?
Z =(due date expected date of completion)/p
7/28/2019 Mihai 1
4/10
Where Z is the number of standard deviations the duedate lies from the mean
Variability of Completion Time for Noncritical Pathso Variability of times for activities on noncritical paths must
be considered when finding the probability of finishing in aspecified time
o Variation in noncritical activity may cause change in criticalpath
Critical Path Method (CPM)
Critical Path Method (CPM) Analysis
oA single time estimate for each activity
o Provides activity information Earliest Start (ES) & Earliest Finish (EF)
7/28/2019 Mihai 1
5/10
Latest Start (LS) & Latest Finish (LF)
Slack(S): Allowable Delay
o Identifies Critical Path Longest path through the network Shortest time in which the project can be completed Any delay in critical path activities delays the project Critical path activities have 0 slack time
Forward Passo Begin at starting event and work forwardo Earliest Start Time Rule:
If an activity has only one immediate predecessor, itsES equals the EF of the predecessor
If an activity has multiple immediate predecessors, itsES is the maximum of all the EF values of itspredecessors
ES = Max (EF of all immediate predecessors)o Earliest Finish Time Rule:
The earliest finish time (EF) of an activity is the sum ofits earliest start time (ES) and its activity time
EF = ES + Activity time
7/28/2019 Mihai 1
6/10
Backward Passo Begin with the last event and work backwardso Latest Finish Time Rule:
If an activity is an immediate predecessor for just asingle activity, its LF equals the LS of the activity thatimmediately follows it
If an activity is an immediate predecessor to morethan one activity, its LF is the minimum of all LSvalues of all activities that immediately follow it
LF = Min (LS of all immediate following activities)o Latest Start Time Rule:
7/28/2019 Mihai 1
7/10
The latest start time (LS) of an activity is thedifference of its latest finish time (LF) and its activitytime
LS = LF Activity time
7/28/2019 Mihai 1
8/10
The CPM Methodo Create a network diagramo Indentify all possible paths from start to finish through the
networko Determine length (or duration) of each path by adding task
times for all tasks on patho
Longestpath is critical path
Critical path corresponds to longest path in thenetwork for a project completion
All activities (or tasks) on critical path are calledcritical activities
Advantages & Limitations of PERT/CPM
Advantages of PERT/CPM1. Especially useful when scheduling and controlling large
projects2. Straightforward concept and not mathematically complex
7/28/2019 Mihai 1
9/10
3. Graphical networks help to perceive relationships amongproject activities
4. Critical path and slack time analyses help pinpointactivities that need to be closely watched
5. Project documentation and graphics point out who isresponsible for various activities6. Applicable to a wide variety of projects
7. Useful in monitoring not only schedules but costs as well
Limitations of PERT/CPM1. Project activities have to be clearly defined, independent,
and stable in their relationships2. Precedence relationships must be specified and networked
together3. Time estimates tend to be subjective and are subject to
fudging by managers
4. There is an inherent danger of too much emphasis beingplaced on the longest or critical path
Phase 2: Scheduling - relates people,money, & supplies to specific activities &activities to each other
Project activities Start & end times Network
Phase 2: Project Scheduling
7/28/2019 Mihai 1
10/10
o Identifying precedence relationshipso Sequencing activitieso Determining activity times & costso Estimating material and worker requirementso Determining critical activities
Recommended