Project name: BEJO VIET NAM PRODUCTION FARM
Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG
MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014
MAIN CONTRACTOR:
TAN VIET TIN CONSTRUCTION CO. LTD
CONTRACT PARTICULAR:
1. Site possession : 07March, 2014 2. Completion date : 11 October, 20143. Contract period : 219 Days ( 7.3 months )
Prepared by: TAN VIET TIN CONSTRUCTION CO. LTD
Verified by Bejo’s Supervise
Name: Le Nam Trung Name: Date: October, 2014 Date
TABLE OF CONTENT Num Page Page
1 PROJECT INTRODUCTION 0 6
2 PROJECT EXECUTIVE SUMMARY 2 8
3 PLANNING REVIEW 4 12
4 PROGRESS WORKS PROGRAMME 2 14
5 WEATHER 3 17
6 MANPOWER RECORD 2 19
7 PLANT & MACHINERY RECORD 2 21
8SUMMARY OF VO 2 23
SUBMITTALS 1 24
A. C&S - SHOPDRAWING REGISTER 1 25
B. C&S - APPROVED SAMPLE/TECHNICAL DATA REGISTER 1 26
A. M&E - SHOPDRAWING REGISTER 2 28
B. M&E - APPROVED SAMPLE/TECHNICAL DATA REGISTER 2 30
10 VARIATIONS AND CLAIMS 1 31
11 HSE REPORT 2 33
12 PROGRESS PHOTOGRAPHS 1 34
TABLE OF CONTENT
9
PROJECT BRIEF:
Project name: BEJO VIET NAM PRODUCTION FARM
Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG
Owner: BEJO VIET NAM PRODUCTION FARM 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG TEL: 0633.520.337 Project management: VIETNAM PROJECT CONSULTANTS Co. LTD
Design Consultant: THIEN NAM DESIGN CONSUTANCY JSC. 12 YERSIN P10 DA LAT – LAM DONG TEL: 0633577646 Main Contractor: Tan Viet Tin Construction Co., Ltd 456 Nguyen van Luong St, Ward 12, Dist 6, Ho Chi Minh City, Vietnam Email: tanviettin@hcm.vnn.vn Tel: +84-8.37511384 - +84-8.38756934 Fax: +84-8.37511383 Tax code: 0302227857
Project name: BEJO VIET NAM PRODUCTION FARM
Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG
Executive summary:
Commencement date: 07 March, 2014
Completion date : 11 October, 2014
Contract period : 219 days (7,3 Months)
Elapsed : 219 days ( 7,3 months)
Remaining : 0 days ( 0 months)
Project name: BEJO VIET NAM PRODUCTION FARM
Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG
Report on overall work done till 30th October 2014
Month Schedule Actual work done
Ahead/Delay
March, 2014 3% 3% 0% ( 0 day)
April, 2014 11% 10% ‐1% (2days)
May, 2014 30% 30% ‐0% (0days)
June, 2014 44% 41% ‐3% (7days)
July, 2014 65% 57% ‐8% (16days)
August, 2014 86% 72% ‐14% (28days)
September, 2014 92% 90% ‐2% (4days)
October, 2014 100% 92% ‐8% (16days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Site Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Q.A & Q.C 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Site Engineer ( C&S ) 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
6 Accountant 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
7 Foreman 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 3 3 3 3 3 3 3 3 3
8 Surveyor and Helper 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
9 Site Engineer (M&E) 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
11 Labour (C&S) 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 54 55 55 55 43 43 30 30 30
12 Labour (M&E) 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 8 8 8 8 8 8
93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 81 82 82 81 69 69 56 56 56
744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 648 656 656 648 552 552 448 448 448
TAN VIET TIN CONSTRUCTION CO., LTD.456 Nguyen Van Luong ST, Ward 12, Dist 6, HCMC
T: +84-8375-11384 Fax: +84-8375-11383
MANPOWER RECORD
Project : NTPM ( Viet Nam) Factory.
TOTAL
TOTAL HOURS
No. DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1 Welding Machine 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 32 Bar Bending Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 13 Bar Cutting Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14 Concrete Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15 Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 16 Roller Compactor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17 Heavy duty Truck 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 08 Leveling Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 19 Excavator 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 310 Theodolite 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 211 Water Pump 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 412 Vibrator 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 313 Hand compaction machine 2 2 2 2 2 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 414 Mortar mixer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 115 Sewing Machine 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4
TAN VIET TIN CONSTRUCTION CO., LTD.456 Nguyen Van Luong ST, Ward 12, Dist 6, HCMCT: +84-8375-11384 Fax: +84-8375-11383
Project : BEJO VIET NAM PRODUCTION FARM
No. DESCRIPTION
PLANT & MACHINERY RECORD
08. SUMMARY OF VO
THE QUOTATION FOR ADDITIONAL WORKS
NO NAME ITEMS SUBMITTED DATE APPROVED DATE
1 TEMPORARY TOILET FOR WORKERS 28/10/2014
2
3 CONCRETE SLAB FOR IRRIGATION ROOM 6/8/2014 7/8/2014
4 FOUNDATION OF CONDENSER UNIT 10 HP ( COOL ROOM) 7/8/2014 8/8/2014
5 ELECTRIC WORKS TO COOL ROOM 15/8/2014 19/8/2014
6 PUMP PIT AND WATER CHANNEL 11/9/2014 12/9/2014
7 LAVABO STAINLESS STEEL AND GREASE TRAP 12/9/2014 12/9/2014
8 MCCB FOR DB7 12/9/2014 12/9/2014
9 AIR CONDITION 12/9/2014 12/9/2014
10 NETWORK SYSTEM 8/10/2014 8/10/2014
11 CCTV SYSTEM 13/10/2014 18/10/2014
12 CABLE FROM ATS TO MDB 8/10/2014 15/10/2014
13 BEAMER AND SCREEN 10/10/2014 17/10/2014
14
15 SLIDING GATE ‐ AUTOMATIC SYSTEM 4/11/2014 7/11/2014
16 INSTALLATION SOCKET 3 PHASE FOR SEED PROCESSING SHED 4/11/2014 7/11/2014
17 WATER HEATER AND SMALL CABLE 4/11/2014 7/11/2014
18 EXHAUST AIR IN TOILET GREEN HOUSE SHED 5/11/2014
19 ADDITIONAL FENCING 5/11/2014 6/11/2014
20
21 HIT SOAP BOX 13/11/2014 13/11/2014
22
NO DESIGNTION DRAWING NO TITTLE1 OTHERS SD-02 EXISTING GROUND LEVEL OF CANTEEN, MAIN STORE, SEED
PROCESSING SHEDSD-04 FINISHING LEVEL OF (INTERNAL) ROAD (4m) IN FRONT OF RAM-
UP (OF GREENHOUSE SHED)SD-05 PROPOSED THE FINISHING LEVEL OF MAIN ROAD (A TO E)SD-07 GREEN HOUSE SHED, MAIN STORE, SEED PROCESSING SHED -
GROUND FLOORSD-08 WATER CHANNEL PLAN AND DETAIL ( ALONG MAIN ROAD)SD-11 FINISHING LEVEL - INTERNAL ROAD (4M) - ALL ROAD
SD-14FINISHING LEVEL - 2M ROAD (NEAR THE FENCE) - BICYCLE ROAD
SD-23 ROOF SHEET FOR GUARD HOUSE AND TOILET & STORE
SD-25 INTERNAL ROAD DETAIL
SD-26 MAIN GATE AND GUARD HOUSE DETAIL
SD-27 IRRIGATION ROOM FLOOR SLAB
SD-28 PUMP PIT
SD-35 SOIL EXCAVATION LEVEL INTERNAL ROAD 4000 mmSD-36 ALUMINUM LOUVER FOR OFFICE BUILDING, GUEST HOUSE,
CANTEENSD-42 MAIN ROAD AND ROAD 2000 mm
SD-50 CAR & MOTOBIKE PARKING
SD-51 EXISTING SOIL LEVEL AT MOTOBIKE PARKING
SD-52 100 MM CONCRETE REMAINING FOR 4 M ROADSD-56 FLAG POLE DETAILSD-59 SIGNBOARD DETAIL FOR MAIN GATE
SD-61 ADDITIONAL FENCING NEAR MAIN GATE
2 MAIN STORE SD-12 ARCHITECTURESD-29 LOUVER AND DOOR SD-30 CEILING PLAN
SD-31 MACHINCE SLAB FOR COLD ROOM
SD-48 BEHIND ENTRANCE
3 GREEN HOUSE SHED SD-03 GROUND BEAMS AND SLAB SD-06 RAM UPSD-20 ROOF SHEET AND CANOPYSD-24 BREACING BEAM ON GREEN HOUSE SHED ROOF TOP (Rejected)
SD-33 OUTSIDE STEEL STAIRCASE GL:1 GREEN HOUSE SHEDSD-36 GALVANIZED STAIR-CASE (INSIDE)
SD-37 GREEN HOUSE SHED CEILING
SD-43SPECIFICATION AND SHOP DRAWING FOR SANDWICH PANELS IN GREEN HOUSE SHED
SD-44 LIGHT GREY RESIN FOR 2nd FLOOR
SD-53 HAND WASHING SINK
4 TOILET AND STORE SD-01 FOOTING AND GROUND BEAMSD-09 ARCHITECT SD-10 GROUND FLOORSD-16 EXISTING LEVEL
C & S SHOP DRAWING
SD-21 ENTRANCE
5 SEED PROCESSING SHED SD-13 DRAIN DETAILSD-17 BRACING BEAMS
6 CANTEEN SD-15 GROUND FLOORSD-18 DRAIN DETAIL (Omitted)SD-32 ROOF EAVES DETAIL (Rejected)SD-44 ENTRANCESD-45 GAS STORAGE
7 PUMP HOUSE SD-22 ROOF SHEET
8 GUEST HOUSE SD-46 STONE ARRANGEMENTSD-54 DETAIL CEILING AT STAIR-CASESD-62 TILING WORKS FOR TOILET WALL UNDER STAIRCASE
9 OFFICE BUILDING SD-41 ALUM DOOR FOR DOOR: D2, FIXED WINDOW: VK1, VK2
NO NAME ITEMS SUPLLIER BUILDINGS COMMENTS ATTACHED WITH STATUS SUBMITTED DATE
APPROVED DATE
MSA/TVT/001
THE CATALOG FOR STEEL BAR FORM POMINA
POMINA ALL BUILDINGS PLEASE SAMPLES FOR TESTING - RANDOM SIZES 12 MM BAR & 16 MM BAR TENSILE TEST ONLY …PLEASE PROVIDE " TAGS & CERTIFICATE".
CATALOGUES APPROVED ON CONDITION, AS NOTED
27/2/2014 27/2/2014
PICS ATTACHED
MSA/TVT/002
THE CONCRETE GRADE DESIGN 10MPa, 15MPa, 20MPa, 25MPa, 30MPa
ALL BUILDINGS SPECIFICATIONS AND TEST REPORTS
APPROVED 27/2/2014 27/2/2014PICS
ATTACHED
MSA/TVT/003
BACKFILL SOIL FOR FACTORY AND ROAD
FOUNDATION, GROUND SLAB, ROAD
PLEASE GIVE COPY OF DELIVERYNOTES TO BEJO (GEOFF) THESE DELIVERY NOTE SHALL TONAGE (AMOUNT OF SOIL + DATE DELIVERY)
SAMPLES APPROVED 4/3/2014 4/3/2014
PICS ATTACHED
MSA/TVT/004
GALVANIZE STEEL TO BE USED FOR FOOTING SYSTEM
TIEN PHONG ADD BUILDINGS CATALOGUES APPROVED21/3/2014 21/3/2014
PICS ATTACHED
MSA/TVT/005
ANTI-TERMITE TREAMENT CHEMICAL
FOUNDATION & GROUND FLOOR FOR ALL BUILDINGS
TEST REPORTS APPROVED 24/3/2014 24/3/2014PICS
ATTACHED
MSA/TVT/006
ANCHOR BOLTS M16, ANCHOR BOLTS M20.
SUBCONTRACTOR - BMB
ALL BUILDINGS STEEL STRUCTURE
SAMPLES APPROVED 1/4/2014 1/4/2014PICS
ATTACHED
MSA/TVT/007
INSULLATION 1 SIDE ALU-POLYNUM (REFER TO SAMPLES)
CAT TUONG ROOFING SYSTEM FOR ALL BUILDINGS ( MAINSTORE AND SEED PROCESSING SHED)
SAMPLES + TEST REPORTS + CATALOGUES
APPROVED 1/4/2014 1/4/2014
PICS ATTACHED
MSA/TVT/008
SKYLIGHGT TO BE USED FOR ROOFING SYSTEM
NAM VIET MAIN STORE AND SEED PROCESSING SHED
COLOR OPAL CATALOGUES (COLOR CHART)
APPROVED 1/4/2014 2/4/2014PICS
ATTACHED
MSA/TVT/009
PAINTING FOR STEEL STRUCTURE
DONASA ALL BUILDINGS (MAIN STORE AND SEED PROCESSING SHED)
COLOR NO 3076 SILVER CATALOGUES APPROVED 1/4/2014 2/4/2014
PICS ATTACHED
MSA/TVT/010
COLOUR CHART TO BE USED FOR MAIN STORE AND SEED PROCESSING SHED DOOR
TNP & HD MAIN STORE AND SEED PROCESSING SHED
M9029A TO BE USED OVERHEAD DOOR SLIDING DOOR MADE OUT OF PANELSO HAVE PANEL COLOR
CATALOGUES APPROVED 20/5/2014 20/5/2014PICS
ATTACHED
MSA/TVT/011
WELDMESH TO BE USED FOR GROUND FLOOR
SONG HOP LUC
CATALOGUES + SPECIFICATION + TEST
APPROVED 28/5/2014 4/8/2014PICS
ATTACHED
MSA/TVT/012
HOLLOW AND SOILD BRICKS ALL BUILDINGS SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED
MSA/TVT/013
NATURAL STONE TO BE USED FOR WATER CHANNEL
LOCAL WATER CHANNEL
SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED
MSA/TVT/014
CONCRETE BLOCK MAIN STORE SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED
MSA/TVT/015
TILES ROOFING LAMA CANTEEN, GUEST HOUSE, OFFICE BUILDING
L104 - CHARCOAL TO BE USED CATALOGUES, SPECIFICATION, SAMPLE
APPROVED AND APPROVED ON CONDITION, AS NOTED
5/6/2014 10/6/2014PICS
ATTACHED
MSA/TVT/016
ROOF SHEET'S COLOUR CHART HOA SEN GREEN HOUSE SHED, GUARD HOUSE, TOILET, PUMP HOUSE.
BBL01 TO BE USED SAMPLES APPROVED 9/6/2014 9/6/2014PICS
ATTACHED
MSA/TVT/017
ROOF AND WALL SHEET HOA SEN MAIN STORE, SEED PROCESSING SHED.
BBL01 TO BE USED SAMPLES APPROVED 4/4/2014 4/4/2014PICS
ATTACHED
MSA/TVT/018
PVC SHEET TVT GROUND FLOOR - ALL BUILDINGS
SAMPLES APPROVED 1/6/2014 1/6/2014 PICS ATTACHED
MSA/TVT/019
DOWER BAR D16 TVT CONSTRUCTION JONT - ALL BUILDINGS
SAMPLES APPROVED 20/6/2014 20/6/2014PICS
ATTACHED
MSA/TVT/020
WALL SHEET'S COLOUR CHART HOA SEN SAME COLOR WITH FOOR SHEET BMB
SAMPLES APPROVED 9/6/2014 9/6/2014 PICS ATTACHED
MSA/TVT/021
INTERNAL AND EXTERNAL PAINTING
SONATA GUEST HOUSE, OFFICE, GREEN HOUSE SHED, CANTEEN, TOILET & STORE, GUARD HOUSE, PUMP HOUSE.
CATALOGUES, SPECIFICATION.
APPROVED 16/7/2014 4/8/2014
PICS ATTACHED
MSA/TVT/022
TILES FOR FLOOR AND WALL AMERICAN HOME VIET NAM
GREEN HOUSE SHED, CANTEEN, TOILET AND STORE
MICHIGAN 2525 FOR SHOWER AREAS + MICHIGAN 02-2540 FOR OTHERS MORE CATALOGUES/ SAMPLES REQUIRED
CATALOGUES, SPECIFICATION.
APPROVED 29/7/2014 19/8/2014PICS
ATTACHED
MSA/TVT/023
EPS SANDWICH PANEL , 50 MM THICKNESS
VIET NAM MAIN STORE CATALOGUE + SAMPLE
APPROVED 31/7/2014 1/8/2014 PICS ATTACHED
MSA/TVT/024
ALUM CEILING ALUKING OFFICE AND GUEST HOUSE'S TOILET
COLOR TO BE AK009 AS PER SPEC BY HKAP3
CATALOGUE AND SAMPLE
APPROVED 14/8/2014 19/8/2014PICS
ATTACHED
MSA/TVT/025
SINGLE FLUSH WOODEN DOOR (MDF TEAK VENEER). DOUBLE FLUSH GLASS DOOR
VIET NAM OUTSIDE GUEST HOUSE, INSIDE OFFICE AND GUEST HOUSE
SAMPLES APPROVED 18/8/2014 25/8/2014PICS
ATTACHED
MSA/TVT/026
PHENOLIC PARTITION SHED , 10 mm THICKNESS IN WC
THIEN QUY GREEN HOUSE SHED, CANTEEN, TOILET AND STORE
COLOR AS PER SAMPLE STAINLESS STEEL SERIES OT.10B
CATALOGUE AND SAMPLES
APPROVED 18/8/2014 19/8/2014PICS
ATTACHED
MSA/TVT/027
PAINTING COLOR INTERNAL AND EXTERNAL BY THIEN NAM ARCHITECTURE DESIGNER
SONATA ALL BUILDING EXCLUDED COLORS SELECTED BY HKAP3 FOR INTERNAL DESIGN. INTERNAL SI206 EDWARDIAN LACE TO BE USED
CATALOGUE APPROVED 18/8/2014 19/8/2014PICS
ATTACHED
MSA/TVT/028
COMPOUND STONE VU HIEP PHAT
OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN.
HP120 GUEST HOUSE BOTTOM PART, SEE MARKED * THIS ONE IN CATALOGUES FOR COLUMNS OFFICE
CATALOGUE + SAMPLES
APPROVED 19/8/2014 22/8/2014PICS
ATTACHED
MSA/TVT/029
SPECIFICATION AND SHOP DRAWINGS FOR THE SANDWICH PANEL IN GREEN HOUSE SHED 100 mm AND 50 mm THICKNESS
METECNO VIET NAM
LAB ROOM GREEN HOUSE SHED
FIRE RATED PANELS TO BE STEEL SHEET BOTH SIDES.
CATALOGUE + SHOP DRAWING + SPECIFICATION
APPROVED 25/8/2014 29/8/2014PICS
ATTACHED
C & S SUBMISSION
MSA/TVT/030
TEAK NATURE WOOD 23 mm THICK (STAIR-CASE). TEAK NATURE WOOD 155 mm THICK (WALL AREA INSIDE)
VIET NAM OFFICE BUILDING, GUEST HOUSE.
SAMPLES APPROVED 25/8/2014 25/8/2014PICS
ATTACHED
MSA/TVT/031
MARBLE 67 (800 × 800 × 20) mm
THICK. (GROUND FLOOR) . GRANIT 28
(600 × 300 × 20)mm THICK (BALCONY
AREA). GRANIT 95 20 mm THICK
(BOTTOM DOOR).
VIET NAM OFFICE BUILDING, GUEST HOUSE.
SAMPLES APPROVED 25/8/2014 25/8/2014
PICS ATTACHED
MSA/TVT/032
CERAMIC TILE (250 × 400) mm AT
KINCHEN WALL AREA. CERAMIC TILE
(300 × 300) mm AT WASHING FLOOR
AREA.
VIET NAM CANTEEN, GREEN HOUSE SHED
GREEN HOUSE SHED GROUND FLOOR: WASHING ROOM, TOILET, HALL, CHANGING ROOM
SAMPLES APPROVED 28/8/2014 30/8/2014PICS
ATTACHED
MSA/TVT/033
MDF TEAKWOOD FINISHING MALAYFLOOR
TRAINNING ROOM STAGE
MODEL DIAMOND CODE 788 (MALAYFLOOR)
SAMPLE APPROVED 9/9/2014 10/9/2014 PICS ATTACHED
MSA/TVT/034
PINE WOOD CANTEEN THE COLOR IS TOO LIGHT. MATERIALS CAN BE ORDERED BUT NEED ON SITE DARKER VERNIS FINISHING
SAMPLES APPROVED 24/09/2014 26/9/2014PICS
ATTACHED
MSA/TVT/035
GRANITE STONE FOR SIGNBOARD
MAIN GATE SUBMIT SAMPLE OF LETTERING ON GRANITE STONE
SAMPLE APPROVED 10/10/2014 11/10/2014 PICS ATTACHED
MSA/TVT/036
NATURAL STONE BROWN/ COPPERISCH
GUEST HOUSE COLUMNS
SAMPLE APPROVED 11/10/2014 11/10/2014 PICS ATTACHED
MSA/TVT/037
SLIDING DOOR HARDWARE D9 IN BATHROOM
GUEST HOUSE CATALOGUE APPROVED 13/10/2014 16/10/2014 PICS ATTACHED
MSA/TVT/038
DOOR HARDWARE HAFELE OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN.
CATALOGUE NOT APPROVED YET
18/10/2014PICS
ATTACHED
MSA/TVT/039
CERAMIC TILE (300 × 300) mm PORCELAIN
GUEST HOUSE TOILET FLOOR
SAMPLE APPROVED 18/10/2015 22/10/2014 PICS ATTACHED
MSA/TVT/040
VIET CERAMIC - GSB05 GUEST HOUSE KITCHEN WALL
SAMPLE APPROVED 18/10/2016 23/10/2014 PICS ATTACHED
MSA/TVT/041
WHITE-BLACK TILES/ 30Y01, 30Y06
OFFICE TOILET SIZE 100 × 100 SQUARE APPROVED ON CONDITION, AS NOTED
18/10/2017 22/10/2014PICS
ATTACHED
MSA/TVT/042
AM EXPOXICATE 403SM - RAL 7046, 7047
OFFICE, GREEN HOUSE SHED
BY PASCAL HKAP3 SAMPLE APPROVED 10/11/2014 12/11/2014 PICS ATTACHED
MSA/TVT/043
TEMPERED GLASS 10 mm THICK OFFICE, GUEST HOUSE, CANTEEN
SPECIFICATIONS AND TEST REPORTS
APPROVED 10/11/2014 12/11/2014PICS
ATTACHED
MSA/TVT/044
CEMENT BOARD CEILING, GYPROC REGULAR BOARD, MOISTURE RESISTANT, BOARD
OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN, TOILET & STORE
SAMPLES NOT APPROVED YET
18/10/2020
PICS ATTACHED
MSA/TVT/045
MDF MELAMINE FOR OFFICE & GUEST HOUSE CABINET
OFFICE AND GUEST HOUSE
SAMPLE APPROVED 22/10/2014 22/10/2014 PICS ATTACHED
MSA/TVT/046
PINE WOOD FOR CABINET GREEN HOUSE SHED
SAMPLE APPROVED 22/10/2014 22/10/2014 PICS ATTACHED
MSA/TVT/047
POLYCARBONATE EXTERNAL STAIRCASE ROOF GREEN HOUSE SHED
SAME MATERIALS TO BE USED AS EXISTING ROOF
CATALOGUE, SAMPLE
REJECTED 22/10/2014 23/10/2014PICS
ATTACHED
MSA/TVT/048
WHITE MARBLE OFFICE STAIRCASE
AS PER SIGNED SAMPLE SAMPLE APPROVED 6/11/2014 6/11/2014 PICS ATTACHED
MSA/TVT/049
STONE FOR KITCHEN COUNTER AND MELAMIN FOR CABINET
OFFICE, GUEST HOUSE
BY PASCAL HKAP3 SAMPLES APPROVED 10/11/2014 12/11/2014 PICS ATTACHED
NO DESIGNATION DRAWING NO TITLE
0MAIN DISTRIBUTION BOARD - MDB
TEST REPORT
GALVANOMETER TEST REPORTS
COMPLETE SHOP DRAWING
1 OTHERS M&E/TVT - 008 POWER SUPPLY MASTER PLAN
M&E/TVT - 027 LOCATION INSTALLATION GROUNDING FOR DISTRIBUTION BOARD
M&E/TVT - 029 WATER SUPPLY MASTER PLAN
M&E/TVT - 030 CCTV MASTER PLAN AND SINGLE LINE CCTV
M&E/TVT - 031 SINGLE LINE TEL AND DATA (OVERVIEW)
M&E/TVT - 039 LIGHTING, SOCKET, DATA IN GUARD HOUSE
M&E/TVT - 043 LIGHTNING SYSTEM FOR BUILDING FROM IRRIGATION ROOM UNTIL MAIN ROAD AND SEED PROCESSING SHED
M&E/TVT - 045 MOTOR FOR SLIDING SYSTEM( SYSTEM SLIDING GATE) MAIN GATE
2 CANTEEN M&E/TVT - 007 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN
M&E/TVT - 015 POWER SOCKET OUTLET LAYOUT PLAN
M&E/TVT - 016 DATA & TEL SOCKET OUTLET LAYOUT PLAN
M&E/TVT - 023 LIGHTING LAYOUT PLAN FOR CANTEEN
M&E/TVT - 028 WATER DRAIN FROM ROOF TO GROUND
3 MAIN STORE M&E/TVT - 018 POWER SOCKET OUTLET LAYOUT PLAN
M&E/TVT - 024 LIGHTING LAYOUT PLAN
M&E/TVT - 034 SINGLE LINE FOR MDB ( MAIN DISTRIBUTION BOARD)
M&E/TVT - 035 WATER DRAIN FROM ROOF TO GROUND
M&E/TVT - 040 WASTE WATER AND WATER SUPPLYM&E/TVT - 041 GREASE TRAP
4 GUEST HOUSE M&E/TVT - 005 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN
M&E/TVT - 020 POWER SOCKET OUTLET AND DATA & TEL SOCKET LAYOUT PLAN
M&E/TVT - 021 LIGHTING LAYOUT PLAN
M&E/TVT - 032 WATER DRAIN FROM ROOF TO GROUND
5TOILET AND STORE
M&E/TVT - 006 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN
M&E/TVT - 017 LIGHTING AND POWER SOCKET OUTLET LAYOUT PLAN
6GREEN HOUSE SHED
M&E/TVT - 003 WATER SEWAREGE AND WATER SUPPLY SYSTEM PLAN
M&E/TVT - 009 POWER SOCKET LAYOUT PLAN
M&E/TVT - 010 DATA AND TEL SOCKET LAYOUT PLAN
M&E/TVT - 019 LIGHTING AND LIGHTING POSITIONING AND SINGLE LINE LAYOUT PLAN
M&E/TVT - 037 WATER DRAIN FROM ROOF TO GROUND
M&E/TVT - 038 SINGLE LINE FOR DB7 (GREEN HOUSE)
M & E SHOP DRAWINGS
M&E/TVT - 044 EXHAUST AIR SYSTEM
7 OFFICE BUILDING M&E/TVT - 004 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN
M&E/TVT - 011 POWER SOCKET LAYOUT PLAN
M&E/TVT - 012 DATA AND TEL SOCKET LAYOUT PLAN
M&E/TVT - 022 LIGHTING LAYOUT PLAN
M&E/TVT - 033 WATER DRAIN FROM ROOF TO GROUND
M&E/TVT - 042 AIR-CONDITION
8 SEED PROCESSING SHED
M&E/TVT - 025 WATER SUPPLY PLAN
M&E/TVT - 026 LIGHTING AND SOCKET OUTLET LAYOUT PLAN
M&E/TVT - 036 WATER DRAIN FROM ROOF TO GROUND
NO NAME ITEMS SUPLLIER BUILDINGS COMMENTS ATTACHED WITH STATUS SUBMITTED DATE
APPROVED DATE
MES/TVT - 001
PVC PIPE TO BE USED FOR WATER SEWAREGE AND WATER SUPPLY SYSTEM
BINH MINH ALL BUILDINGS ENSURE AROMATIC SOLVENTS ARE NOT USED TO GLUE THE PIPEWORK
CATALOGUE + SAMPLE
APPROVED ON CONDITION, AS NOTED
24/3/2014 24/3/2014
MES/TVT - 002
PVC CONDUIT TO BE USED FOR ELECTRICAL SYSTEM
VANLOCK ALL BUILDINGS WHERE ARE THE 'CUPS' FOR FIXING CONDUITS TO WALLS
CATALOGUE + SAMPLE
APPROVED ON CONDITION, AS NOTED
24/3/2014 24/3/2014
MES/TVT - 003
SAMPLE CABLE FOR ALL BUILDINGS CADIVI ALL BUILDINGS SAMPLE APPROVED 21/4/2014 26/4/2014
MES/TVT - 004
CATALOGUE CCTV ALL BUILDINGS CAMERA SNB-5000, SLA-M 3180DN, HOUSING SHB-4200H, SURGE SUPPRESSOR, EPMP 1000 INTERGRATED RADIO.
CATALOGUES APPROVED 16/5/2014 25/7/2014
MES/TVT - 005
LIGHTING PARAGON CHANGING ROOM OF GREEN HOUSE SHED
LIGHTING PIFL228 FOR SOWING AREA, LIGHTING PCFA236 FOR CHANGING ROOM, SEED CLEANING AREA, GERMINATION ROOM, CONTROL ROOM, EXTENDTION OFFICE PHASE 1, PHYTO LAB, SAMPLING ROOM, GERMINATION LAB, POLLEN EXSTRACTION, SUPERVISER ROOM. DOWNLIGHT PRDH70E27 FOR TOILET 1-FLOOR. EXIT LAMP PEXA13SW FOR TRAINING ROOM, EMERGENCY LAMP PEMA25SW FOR CHANGING ROOM.
CATALOGUE APPROVED 9/6/2014 8/8/2014
MES/TVT - 006
CATALOGUES SANITARY EQUIPMENT
CAESAR GREEN HOUSE SHED, TOILET AND STORE, CANTEEN
WATER CLOSET CD1340 + TAP BS304, UNIRAL U0262 + TAP BF412G, LAVABO LF 5236 + TAP BF053, FLOOR DRAIN ST1010B, COAT HANGER Q8807, SOAP HOLDERS ST823V, TOILET PAPER HOLDERS Q7714V, XI PHONG BF 602, WO34-1, SHOWER BFV-28S are to be used. SHOWERHEAD TO BE RE-SUBMITTED
CATALOGUE SELECTIVITY APPROVED, AS NOTED
9/6/2014 15/7/2014
MES/TVT - 007
CATALOGUES SOCKET, SWITCH SCHNEIDER MAIN STORE, GREEN HOUSE SHED, SEED PROCESSING SHED, TOILET & STORE
SWITCH ONE WAY: F50M1-5, SWITCH TWO WAY: F50-2M1-5, COVER: FG1051, FG1052, FG1053, POWER SOCKET: F1426ESM, DATA AND TEL SOCKET: F50RJ5EM
CATALOGUES APPROVED 9/6/2014 25/7/2014
MES/TVT - 008
CABLE TRAY DONG NAM A GREEN HOUSE SHED, SEED PROCESSING SHED
FOR MAINSTORE AND SEED PROCESSIING SHED CABLE TRAYDUCT TYPE TO BE USED 100×50 AND NO COVER.. DIMENSION ACCORDING SHOP DRAWING.
CATALOGUE AND SAMPLE
APPROVED 19/6/2014 23/7/2014
MES/TVT - 009
SOLAR POWER SINGAPORE CAMERA. OUTDOOR
CATALOGUES APPROVED 8/7/2014 29/8/2014
MES/TVT - 010
WATER HEATER ARISTON GUEST HOUSE ARISTON VERO IM-4522EP (BẠC) TO BE USED CATALOGUE APPROVED 10/9/2014 11/9/2014
MES/TVT - 011
NETWORK ALL BUILDINGS CAT 6A TO BE USED. AP-SWITCH - MODULES TO BE LEFT OUT.
CATALOGUE APPROVED 11/8/2014 9/9/2014
M & E SUBMISSION
MES/TVT - 012
TRUNKING SOCKET L&S GREEN HOUSE SHED
FA 100/40 100 mm × 40mm × 2 mm. FA
100/60 100 mm × 60 mm × 2 mm.
CATALOGUE APPROVED 4/9/2014 4/9/2014
MES/TVT - 013
ROAD LAMP POLE LU GIA IN SITE 73-F1-010 + KATO 0516010250 CATALOGUE APPROVED 16/8/2014 19/8/2014
MES/TVT - 014
BRASS FITTING VIET NAM ALL BUILDINGS SAMPLE APPROVED 23/8/2014 23/8/2014
MES/TVT - 015
WALL DECORATIVE LIGHTING CHINA GUEST HOUSE CATALOGUE NOT APPROVED YET
26/8/2014 REJECTED. BEJO WILL SUPPLY
MES/TVT - 016
DOWNLIGHT FOR BATHROOM PHILIP GUEST HOUSE CATALOGUE APPROVED 26/8/2014 1/9/2014
MES/TVT - 017
POLE FOR CAMERA LU GIA IN SITE 8 METER POLE TO BE USED CATALOGUE APPROVED 29/8/2014 12/9/2014
MES/TVT - 018
LAVOBO CAESAR MAINSTORE CATALOGUE APPROVED 1/9/2014 1/9/2014
MES/TVT - 019
LAVABO STAINLESS STEEL HA TIEN LAB ROOM AT GREEN HOUSE SHED
CATALOHUE APPROVED 1/9/2014 1/9/2014
MES/TVT - 020
MACHINE AIR CONDITION DAIKIN OFFICE BUILDING
TO BE SURE ALL COMPONENT SUCH AS DUCTS + UNITS FIT IN CEILING AND SPACE
CATALOGUE APPROVED 16/9/2014 18/9/2014
MES/TVT - 021
FAN AIR EXHAUST PANASONIC GUEST HOUSE FV-20AUG TO BE USED CATALOGUE APPROVED 16/9/2014 16/9/2014
MES/TVT - 022
LIGHTNING EQUIPMENT GREEN HOUSE SHED
CATALOGUE APPROVED 22/10/2014 5/11/2014
MES/TVT - 023
SOCKET 3 PHASE SEED PROCESSING SHED
CATALOGUE APPROVED 22/10/2014 23/10/2014
MES/TVT - 024
MOTOR FOR SLIDING SYSTEM MAIN GATE CATALOGUE APPROVED 22/10/2014 3/11/2014
MES/TVT - 025
TV K+ GUEST HOUSE CATALOGUE APPROVED 25/10/2014 25/10/2014
10. VARIATIONS AND CLAIMS
11. HSE REPORT
No Description As for this month Accumulated
1 Total Exposure Hour 20680 18100M/H
2 Reported Safety Cases 0
A. Fatalities 0 0
B. Lost Workday Cases 0 0
C. Medical Treatment 0 0
D. Restricted Word Cases 0 0
E. First Aid Cases 0 0
F. Motor Fleet Accidents (Light/ Heavy) 0 0
G. Near Miss Incidents 0 0
H. Fires 0 0
I. Major Property Damage 0 0
3 Total Lost Time Injuries (A + B) 0 0
4 Total Reportable Cases (A + B + C + D) 0 0
5 Total No Lost Time 20680 18100M/H
HSE REPORT
The Safety supervisor of TVT, We compliance with safety policy by the Government. Contractor is implementing all possible safety procedures and tight control of subcontractor's workers to maintain high safety standard at Site. Workers trained in basic safety by monitoring building safety.
Recommended