Strategy adopted for indigenous manufactureExpected date of award 01.01.2011
Establish Commissioning date Done
Contractual Deliveries Worked out
Float Considered
Transportation time Considered
Experience of Similar organizations Considered
Work out Ex Factory Delivery Worked out
7/27/2019 Presentation 211010.ppt
2/13
Strategy adopted for indigenous manufacture
Time schedule for factory built up 10/2012
Factory operational 12/2012
Time & sequence of operations Indicated
Machine schedule Prepared
Assembly schedule Prepared
Critical activities Identified
Mitigation plan Prepared
7/27/2019 Presentation 211010.ppt
3/13
Time required for
synchronization after receipt ofGen 10 Months
LPT 18 Months
IPT 14 Months
HPT 12 Months
Zero Date Assumed 1.1.2011
Synchronization time 44 Months
Synchronization time indicated by Experts, from
the receipt of major Assemblies
7/27/2019 Presentation 211010.ppt
4/13
7/27/2019 Presentation 211010.ppt
5/13
Set No. 1st 2nd 3rd 4th 5th
Project NBN1 SP1 NBN2 SP2 NBN3
Commissioning date Dec-14 Feb-15 Jun-15 Aug-15 Dec-15
Box up Nov-13 Jan-14 May-14 Jul-14 Nov-14
Supply at site Jul-13 Sep-13 Jan-14 Mar-14 Jul-14
Considering float of 3mths. Apr-13 Jun-13 Oct-13 Dec-13 Apr-14
Turbine -Transportation 2 mths
Turbine -Ex Factory Feb-13 Apr-13 Aug-13 Oct-13 Feb-14
HP (Dates indicated by Kamlesh) SEP 13 Nov 13 Mar 14
IP (Dates indicated by Kamlesh) SEP 13 Nov 13 Mar 14
LP (Dates indicated by Kamlesh) AUG 13 Oct 13 Feb 14
Valves
Pedestal
Generator -Transportation 4 mths
Generator -Ex Factory 12-Dec Feb-13 Jun-13 Aug-13 Dec-13
Stator (Dates indicated by Kamlesh) SEP 13
Rotor
Ex Factory deliveries (Date wise) to meet Contractual
requirements (Assuming NTP as 01.01.2011)
7/27/2019 Presentation 211010.ppt
6/13
Set No. 1st 2nd 3rd 4th 5th
Months
from
NTPProject NBN1 SP1 NBN2 SP2 NBN3
commissioning/
Synchronization
Aug-14 Oct-14 Feb-15 May-15 Aug-15 44
Box up
Supply at site
Considering float of 3months,
Turbine -Transportation 2mths.
HP Aug-13 Oct-13 Feb-14 Apr-14 Aug-14
IP Jun-13 Aug-13 Dec-13 Feb-14 Jun-14
LP Feb-13 Apr-13 Aug-13 Oct-13 Dec-13
Ex works HP Jun-13 Aug-13 Dec-14 Feb-14 Jun-14 30
Ex works IP Apr-13 Jun-13 Oct-13 Dec-13 Apr-14 28
Ex works LP Dec-10 Feb-13 Jun-13 Aug-13 Oct-13 24Generator -Transportation 4
mths.
Stator Oct-13 Dec-13 Apr-14 Jun-14 Oct-14
Rotor Oct-13 Dec-13 Apr-14 Jun-14 Oct-14
Ex Works Jun-13 Aug-13 Dec-13 Feb-14 Jun-14 30
Delivery Schedule suggested by Experts
7/27/2019 Presentation 211010.ppt
7/13
OUTER CASING
Get fully machined & hydraulically tested casings. Approved venders
are available This has also been considered while planning facilities.
INNER CASING
Machine Inner casing in JV or Partially machined casing except final
machining of blade plan Blades may be procured from machine supplier if required. Blading & post blading machining in JV
ROTOR
Procure forgings/welded Rotor from Birr
Blades to be manufactured in JV/ procured from machine supplier, if
required Blading & post blading machining in JV. Balancing Pit to be expedited /Balancing in Baroda Tunnel/ OR
Import from BIRR
ACTION PLAN FOR HP TURBINE
7/27/2019 Presentation 211010.ppt
8/13
OUTER CASING
Get fully machined & hydraulically tested casings. Approved vendors
are available
This has also been considered while planning facilities.INNER CASING
MACHINE CASTINGS IN JV or procure Partially machined casing
(except final machining of blade plan) Blades to be manufactured in JV or may be procured from machine
supplier in case capacity is not sufficient Blading & post blading machining in JV
ROTOR
Procure forgings/welded Rotor from Birr
Blades may be manufactured /procured from machine supplier, if
required Blading & post blading machining in JV Balance in Balancing Pit to be expedited/ or utilize the facility at
Baroda/ OR IMOPRT FROM BIRR
ACTION PLAN FOR IP TURBINE
7/27/2019 Presentation 211010.ppt
9/13
OUTER CASING
Fabrication in JVB. In case required, suitable & qualified fabricatorsavailable in India. These can be suitably validated and trained.
INNER CASINGCASTING from approved sourcesMachining in JVLast stage blades from Alstom. Other blades can be manufactured in
JVBlading & post blading machining in JV
ROTOR
Welded Rotor from BirrFully machined in JVBalancing Pit to be expedited to meet the time lines for 3rd set
ORFully machined & bladed & balanced rotor from Alstom
ACTION PLAN FOR LP TURBINE
7/27/2019 Presentation 211010.ppt
10/13
STATOR
Wound Stator to be manufactured in India for 3rd set
Other components such as end shields, terminal box etc. to be
manufactured in JV or can be sourced from India
Assembly & Testing in India
Testing facilities to be expedited to meet the time lines for 3rd set
ROTOR
Forgings to be imported
Facilities available for Turning & slot milling
Rotor Coils from Birr Balancing pit to be expedited to meet the time lines for 3rd set
OR
In the mean time Import Complete Rotor duly balanced from
Alstom Birr
ACTION PLAN FOR GENERATOR
7/27/2019 Presentation 211010.ppt
11/13
Civil works to be expedited
Ordering of machine tools to be expedited
Expedite factory build up
Immediate decision for Balancing Tunnel
LP Rotor & Generator Rotor from Alstom tillfacility for balancing is not visible.
Finalization of design for Generator test stand
CRITICAL ACTIVITIES
7/27/2019 Presentation 211010.ppt
12/13
3rd , 4th and 5th set can be manufactured with
following constraints:
For HP Turbine and IP Turbine, balancing of Rotors is constraint
in view of uncertainty of Balancing Tunnel. This can either be
balanced in Baroda Pit or fully bladed and balanced Rotor may be
imported from Alstom network.
LP Rotor not possible to be manufactured in JV due to invisibility
of Balancing Pit. It may be have to be sourced from Alstom
Generator Rotor not possible to be manufactured in JV due toinvisibility of Balancing Pit. It may be have to be sourced from
Alstom
Finalization of design for Generator test stand. This is critical
CONCLUSION
7/27/2019 Presentation 211010.ppt
13/13
Mr. Swamy proposed to import 3rd and 4th
Turbine from Alstom network :
To keep provision of slots for expected orders from IPPs
Alstom today is considering to provide slots for JV which may not
be provided later
Bharat Forge expressed that as order from IPP is not certain, lets
not worry about the slots today and allocate the capacity to NTPC.
Shall see how to manage when order from IPPs becomes visible.
Mr Swamy had his own views and conveyed that management
shall take suitable decision.
CONCLUSION
Recommended