6/23/2016
Information system planning & Project Management
INFO – 461 – 001 Project Charter
Mohamed Abbas
2
Table of Contents
Team Charter …………………………………...……………………………………………………3 Project Description & Summary…………………………………………………………………..7
Document the Team Learning Record & Action Plan…………………………………………8
Measurable Organizational Value (MOV….……………………………………………………...9
Comparison of Alternatives:……………………………………………………………………..10
Total of Benefits /Cost of Ownership (TCO/TBO):……………………………………………12
Recommendation:……………………………………………………………………………………………13
Resources Requirements…………………………………………………………………………………..13
Stakeholder Analysis………………………………………………………………………………………..14
Resources Cost Table:………………………………………………………………………………………15
Deliverable Structure Chart (DSC):……………………………………………………………...17
3
Use Case Diagram………………………………………………………………………………….18
Work Breakdown Structure………………………………………………………………………19
Scope Change Request Form:…………………………………………………………………...20
Scope Change Request Log:……………………………………………………………………..21
Project plan……………………………………………………………………………………………………22
Questions to be answered …………………………………………………………………………………25
A Project Summary Report (original project plan, schedule & budget)……………………………26
A Project Summary Report (revised project plan)……………………………………………………..28
A Project risk analysis and plan Report—understanding the sources and impact of risks to projects………………………………………………………………………………………………………..29
Earned Value Analysis ……………………………………………………………………………31
Analysis of BugBuster’s work……………………………………………………………………36
Quality Management Plan…………………………………………………………………………37
MS Project Tutorial I………………………………………………………………………………..38
MS Project Tutorial II……………………………………………………………………………….40
MS Project Tutorial III………………………………………………………………………………48
Team Leader:
Mohamed Abbas *Leadership position will rotate throughout the semester*
Purpose and Statement of Team Charter:
The team has been formed in order to cooperate together in order to complete a set of
assignments, which is compiled into a group project. Our overall objectives are to integrate our own
research and become proficient in the materials taught in class in order to come to a conclusion with
4
our own individual presentations to create a unified project. We are confident in each other’s abilities to
bring out the best of the team, and to also work effectively, with commitment to each other to create a
learning experience.
Team Members:
1. Mohamed Abbas- abbasm@vcu.edu, 202-763-2778
2. Omar Alshareef- alshareefof@vcu.edu, 757-773-9633
3. Fahib Keita- keitaft@vcu.edu , 202-802-8459
4. Cain Haney haneyce@vcu.edu, 757-679-4806
Roles and Responsibilities-
Mohamed Abbas- Mohamed’s role as the leader is to motivate the group and ensure objectives are met
and the steps to a successful team are underway.
Fahib Keita- is to accumulate all team collaborative information, data, and research and organize it in
a presentable fashion.
Cain Haney- role in team is to make sure all work is presented correctly with the needed information
and details. Having the role of the enforcer, I’m also responsible for making sure all members are
showing up, participating, and work completing their assigned work.
Omar Alshareef- the roles of Omar are to motivate the group and ensure objectives are with the leader
and accumulate all team collaborative information, data, and research and organize it in a presentable
fashion with the manager. And make sure all work is presented correctly with the needed information
and details with the group members, also determining the right types of research and information which
will need to be presented in a professionally.
Team Strengths and Weaknesses:
By analyzing each team member’s strength and weakness, we can work towards a productive and
improve ourselves in the criteria that we lack, even by motivating each other. As we identified our skills
and experiences, we can dictate where we are strong and where we lack in ability.
Strengths
1. Interpersonal skills: All of the group members seem quite inept in this category, as they come
from a background of communicating and have leadership building experience.
5
2. Background: Each member has had experience with team-based settings dealing with problems
that require more than one solution. Whether it’s volunteering in an organization or job based
work, each member understands the definition of collaborative projects.
3. Skills & Knowledge: As one member is able to juggle being in different organizations and
holding a job, this will provide a balance and a strong source of motivation to each group
member, and the group as a whole.
Weaknesses
Fahib Keita: tends to overthink problems or solutions that need to be carried, which can
consume more time.
Cain Haney: Can sometimes be bullheaded and doesn’t like when conversations about work
become derailed and want to steer it back without letting it naturally flowing back. Communication can
also be difficult with a poor group, but through this team charter and working with the committed
individuals in team Diverse, these problems should be non-existent.
Mohamed Abbas: Mohamed’s lack of focus sometimes would be problematic, as he tends to
zone out and thinks of irrelevant things. By adhering to the objective of the group and focusing on the
outcome, this weakness can be overturned.
Omar Alshareef: Tends to stress over the little details, which leads to consuming time on things
that don't matter. By focusing and using time management
Members’ Biographies:
Mohamed Abbas- As a student studying Information systems at Virginia Commonwealth University,
Mohamed is looking to gain the knowledge of Information Systems to better understand what makes a
business prosper in the age of technology. Having been at VCU for 1 year has taught Mohamed the
meaning of being independent and self sufficiency, which is an experience in its own right. Mohamed
hails from Arlington, Virginia and looks forward to an outstanding college experience.
Fahib Keita- I am a Senior here at Virginia Commonwealth University, I was born on February 21 1993
in Fairfax, VA. I study Information Systems here and when I graduate looking to get a job in the network
security field of IT and I am looking to head to the Air Force to become an officer and work IT there.
Also plan on getting my Masters in information systems.
6
Cain Haney- I was born June 22, 1994. Raised in Virginia with a couple of moves along the way. I
currently attend VCU as an Information Systems major with a minor in German. I graduated from
James Monroe High School. As of now I work at the Stoplight Gelato café, a new upstart in Richmond
that we hope to open up in the next few weeks. It is my intention to graduate next fall semester and then
pursue a career in IS.
Omar Alshareef- I’m a senior student year at VCU, also I’m in Information Systems major. I will
graduate in fall 2016.from anther hand, I have engineering degree in communication and more than 6
years of experience as section head in IT department.
Team Expectations and Rules:
Each member will be responsible for completing their assigned task as an individual and be able to
present the material efficiently. Last each member is responsible for showing up to group meetings on
time and one should notify the whole group if they will not be present or late. If a member misses three
meetings without notifying any team member, that member will be obligated to hold a mandatory
meeting with the supervisor about their issues and whether they can or cannot attend group meetings for
the time being. Each member is expected to present their pure, honest work and should equally divide
the work equally within the team to ensure positive results.
Meeting Times:
In each meeting, every member will discuss their ideas and thoughts and we will begin by
brainstorming. We will discuss our objective for the day and what will be expected from each member.
Each member will have the opportunity and time to express their thoughts and ideas. Each member is
responsible for showing up at the proper time for each designated meeting, if a member is unable to
make it to a meeting, he or she will have to address the group or leader ahead of time so adjustments
will be made. Everyone is expected to contribute equally so the group will function properly and
efficiently. Participation is critical to a successful project. Outside of meetings, the group will have
other resources to stay in touch with one another including emails, text messaging, video chat, and
Google Docs.
Code of Ethics:
7
Diverse is strives on mutual respect. Each member will respect one another, and if a conflict arises, we
will discuss the matter in a professional manner. No slandering one’s work or ideas, or use of profanity,
as this is a professional setting. Plagiarism or stealing another’s work and passing it off as their own
will not be tolerated. Each member will be responsible for following the same practices of the VCU
Code of Conduct when working together as a team and individuals.
Project Description & Summary:
Husky Air is a fixed base operator (FOB) that was established in January of
2008, and is located in DeKalb, Illinois at the DeKalb Taylor Municipal Airport (DKB).
They also house a charitable service called Pilot Angels dedicated to transferring stable
patients and organs to the needed location. The call for this project was provoked by
Husky Air’s need for a more effective and efficient system to manage the operations of
their Pilot Angel program. Husky Air has asked for a computer-based program capable
of tracking and handling Pilot Angel volunteer data, the pertinent data on the aircraft
being used, and correct passenger data. They also have communicated a need for
better customer data and list of all Pilot Angel flights to better recognize volunteers. Pilot
Angels matches volunteer privet pilots who are willing to donate their time and personal
8
aircraft with needy people whose health problems require them to travel to receive
diagnostic or treatment services. Pilot Angels will also charter flights for the delivery of
organs to patients across the nation. All flights are free of charge. Flight costs are often
paid by the volunteer pilots who are using their own aircraft. Travel companions, such
as a relative, friend, or nurse, are common and encouraged if room is available.
Upon request of the Pilot Angels service, Husky Air gathers information such as the
name of the traveler, the destination, dates/times, and the number of travel companions.
The weights of the passengers and their luggage are also needed because of the
weight restrictions in small aircraft.
Currently, Husky Air manually stores all data with pen and paper. Record-keeping is
becoming an issue with growing demands for the service. Employees often contact
many pilots until they find one available that also meets the weight-carrying
requirements. This is an inefficient use
of time. Husky Air has requested a computerized system to help with this. The system
will keep track of information such as volunteer names, addresses, contact information,
availability, and their aircraft specifications and whereabouts.
This system will also maintain basic information about patients, hospitals, clinics,
organ banks, and other customers who request the Pilot Angels service in order to more
efficiently meet requests. Finally, this system will also keep track of every Pilot Angel
flight and include information such as the pilot, number of passengers on board and/or
type of organ, the aircraft that was used, the total time of the flight, the distance traveled
and destination of the flight in order to recognize specific volunteers for their
contributions.
Document the Team Learning Record & Action Plan:
Our action plan will be first to determine the measurable organizational value through
analyzing the most relevant areas of impact and determine the appropriate metric. Our team
will evaluate the alternatives and make our recommendation to our client.
Start Date Completion Date
Actions Responsibility Recourses
May 26 May 26 Determine the measurable organizational value
Project Manager and team Members.
All group members.
May 24 May 29
Analyzing the most relevant areas of impact Determine the appropriate metric
Project Manager and team Members.
All group members.
May 24 May 31
Evaluate the alternatives and
make recommendation to client.
Project Manager and team Members.
All group members.
9
Measurable Organizational Value (MOV)
A: Desired Areas of Impact:
Husky Air would like to improve its collection of data and interface with that data. This
new system has the potential to help many facets of their business including their pilots,
customers, and technicians. The specific areas of impact can be broken into customer,
finance, strategic, finance and social. These areas are addressed below according to their
preferences.
Desired Area of Impact Improvement Preference(Rating)
1. Operational Operational status among the areas of impact is a result of the planned system’s ability to significantly reduce the amount of time it takes for data retrieval. It would make what used to be a long arduous processes take but a few keystrokes. · Fastest way of evaluation of individual i.e. Tests
schedules, registration, payment system, reports and initialing. · Less time in business process will reduce student
time, instructor time and staff time · Data such as flight time and cargo of a specific plane can easily be looked up and displayed on screen without the need to physically sort the large amount of relevant data. · No longer need large filing system in work place freeing up space for other uses
1st
2. Customer The most important area of impact is the customer. Key sections within this identified area that are desired to be improved are: · Improve customer relations between not just individuals, but larger entities, such as hospitals, that seek to use Husky Air’s Pilot Angels services. · Data retrieval time, data accuracy and no loss of data
for customer interactions
· Increased consumer basis with the streamlining of services
2nd
3. Finance · Providing a good mobile based app and web based
application will reduce costs and result in an increase in revenue · Desktop application and mobile app are easy mean
for marketing and hence increase the market and revenue. ·The proposed system would allow for those in the finance department of Husky Air too better access data related to Pilot Angels. This drastically reduces lookup time and will cut operational costs in this area as well. All expenses and relevant charitable tax break information will be at their fingertips instead of in a drawer.
3rd
10
4. Strategic · Increase Market share and marking. · With enhanced development organization will
normally expand.
4th
5. Social · Educate the public and potential organizations about
system · Improve the charitable side of their business increasing goodwill and awareness of their company
5th
B: Desired Value of IT Project:
The desired value of the proposed IT project is mainly operational, but the result will bleed out
into all other facets of the organization. It is possible with a successful implementation that
Husky Air’s Pilot angels section would be able to decrease processing time by 60%, decrease
instructor time by 25%, decrease wait-time by 40% for all stakeholders as well as decrease the
time schedule time. This project strives to optimize data retrieval and addition. Having a faster
means of processing and storing data will mean Husky Air can better allocate the resources
that were once devoted to their complex and lengthy physical file management system. Husky
Air with this new system will also be given better mobility; data can be updated in the field from
cellular devices and be updated in real time. The information recovery and correspondence
between organization focuses and client will turn out to be quick and thus bring about a
productive venture framework.
C: Develop an Appropriate Metric The implementation of the proposed IT project for Husky Air’s Pilot Angels program will reduce handling and processing of data by at least 60%. This in turn will increase other processes regarding to Pilot Angels such as being able to devote once locked up resources that were used for data retrieval and entry to other important tasks and allow for quicker communication to business partners. D: Set a Time Frame for Achieving the MOV
Goals Set Time Frame
for Achieving the MOV
11
Planning and formulation of IT project 2 weeks
Implementation of IT project 3 weeks
Training 1 week
Achievement of MOV desired value 1 week
Review of project (what went right & what can be improved upon)
1 weeks
E: Summarize the MOV - Areas of impact:
Implementation of automated system increases the productivity and efficiency within the Pilot
Angels program. Benefits will result throughout program through an increase of roughly 60% on the data entry and lookup side of business. Automated and computerized systems are necessary for an organization that wishes to be quick and agile, this will translate to a better experience for employees and customers as well. This project will succeed if properly implemented and adopted by employees and customers as well.
Comparison of Alternatives:
By the research done by Diverse team, using cost benefit analysis we have come up to 3 alternatives that can be used.
1. Maintain the status quo:
Maintaining the status quo has lower upfront costs, since the system is now in place and
all of the customers are qualified to use it. Ongoing support and maintenance cost would
stay the same, but that’s moderately low due to the cost of paper and employment lost to
such an operational efficiencies system. Indirect costs would be the biggest factor, bearing
in mind the cost of discovery and fixing reduced turnaround times, reduced operational
redundancy, acknowledged assurance claims, encryption and miscalculations initiated by a
operational system and all of the employment phase lost.
2. Purchase software package accompanying your requirements:
Your second preference is to purchase a software package called Win Air. This
integrated system will offer benefits over the status quo, shifting to a Scratch system that
can be easily restructured and altered. This system is more beneficial and reliable than
using paper-based, decreasing employment time verdict and fixing slip-ups in material data.
This is particularly significant bearing in mind that success of the company is at stakes and
must rely precise data and productivity of this functional structure. The organization
integrated maintenance system is easier to use and constructs conclusions about what
patients should be engaged with which pilots, storing all the database in one place. It has
adequate upfront cost, mainly from hardware, since you will need to purchase multiple
12
interacted workplaces for the system. This is web-based service and you will require Internet
service. The client server would cost around $135 per month and Internet service costing
$69.95 per month. You need support service for the hardware and software installations.
3. Build a custom system around your needs:
The final option is to construct a custom information system that will deliver the
most value to the corporation. You have to purchase the same hardware and software
infrastructure system as mentioned in the software package option. This includes: Internet
fees and client server fees, but also the comparable fee of the actual software development
whether in-house or outsourced. Training will be a significant investment especially with a
drastic change from paper to electronic use. These costs are leveraged by their benefits.
With a custom built system Husky Air is allowed to tailor a brand new system to their needs
and not compromise like they may have to with an off-the-shelf package. Extra tools such as
bar coding, real time labor management and reliability will be greatly improved. This
system creation has the distinct possibility to save huge amounts time and work. One
possibility for an outsourcing partner would be SITA. SITA is a leading specialist in air
transport communications and information technology, and has worked with many other
FOBs. SITA should be well equipped to handle the actual construction of the Husky Air Pilot
Angel system once given the proper deliverables by team Diverse and Husky Air.
Total of Benefits /Cost of Ownership (TCO/TBO):
13
Recommendation:
Total benefitsTotal costs
Net Present Value Net BenefitsNet Present Value of Total Costs
$(8,000,000,000)
$(6,000,000,000)
$(4,000,000,000)
$(2,000,000,000)
$-
$2,000,000,000
$4,000,000,000
$6,000,000,000
$8,000,000,000
1 2 3 4 5 6 7
Break Even Point
Total benefits
Total costs
Net Present Value Net Benefits
Net Present Value of Total Costs
$-
$1,000,000,000
$2,000,000,000
$3,000,000,000
$4,000,000,000
$5,000,000,000
$6,000,000,000
$7,000,000,000
$8,000,000,000
$9,000,000,000
$10,000,000,000
1 2 3 4 5 6 7
Break Even Point
Total costs Total benefits
14
Husky Air’s business needs for this system while complex do not present an overly
unique problem. The nature of the system allows for a few potential options, these include
build in-house, commercial off the shelf, or custom development. Based on review of the
requirements presented by Husky Air this team would recommend an off-the-shelf purchase.
This team would suggest Win Air as they specialize in FoB software and their products should
be capable of handling the data necessary of the Pilot Angels section of Husky Air.
Resources Requirements
1. People
a. Programmer – $54,392; $4,532/month
b. Database analyst/designer – $55,538; $4,628/month
c. Project manager – $73,589; $6,132/month
d. System analyst/designer – $51,245; $4,270/month
e. Technical Trainer – $60,542; $5,045/month
2. Technology
a. 2 desktops/all-in-ones [Dell Vostro 260s w/ 20 inch monitor] – $468/desktop
b. Small server [Dell PowerEdge t410] – $599
c. Custom software
d. Network cable and drops - $69.99 for 1000ft/ $1.99 for 10 drops, $0.99 for each
faceplate
e. High-speed internet access - $54.99/month
f. Will use customer desktops for development
g. Laptops for mobile work and presentations [vostro v131] - $599x2
h. Cell phones for all personnel - $200/month + $30 per phone
i. High-speed internet for office - $54.99/month
3. Facilities
a. Office space near Husky Air with room for all equipment for project, and
workspaces for each person -$ 950/month [loopnet.com]
4. Other
a. Gas - $3.99/gallon
Stakeholder Analysis
Stakeholder Interest Influence Potential Conflicts Role Objective Strategy
15
L. T. Scully +1 5 Other stakeholders will not agree with his decisions
President and CEO of Husky
Air
Authorizes payments. Provide needed resources and approvals
Maintain communication so that everything is clear so project can be successful
Alma Coleman
-1 3 Alma is not considering learning a new system if it’s hard. She is used to her old system of maintenance
Scheduler and
Coordinator of flights
Schedules flights, maintains all files and folders
Providing reports and financial stipends.
Pat 0 3 Conflict can arise between the 3 IT specials and how they correspond with one another
Network
Specialist
Technical skills. Provide expertise to complete the project work
Support project team with adequate resources while minimizing overload of work.
Yan 0 3 Resources not available for use by IT specialist will be problematic for the progress of the project
Systems Analyst
Database and Programming skills. Provide expertise to complete the project work
Support project team with adequate resources while minimizing overload of work.
Sitaramin 0 3 Resources not available for use by IT specialist will be problematic for the progress of the project
Systems Analyst
Database and Programming skills. Provide expertise to complete the project work
Support project team with adequate resources while minimizing overload of work.
Volunteer Pilots
+1 4 Unavailable resources will make it hard for these pilots to do their required objectives if materials are not at their disposal
Pilots Provide transportation of patients, organs and/or medical personnel
Provide expertise flight skills and save travels to passengers
Passengers 0 4 Passengers will want the best service and accommodations and these are provided by the other holders
Passengers
Profit Currency and Profits
Tim Williams
+1 5 As a co-owner and project manager of GTS Tim has to work and compromise with other stakeholders especially Scully in order for this project to progress and be successful
Project Manager
Lead and manage the project so that it achieves
Work closely with project stakeholders and project team to provide a smooth and successful operation
Resources Cost Table:
16
1. Contract Payment Method
The nature of this project would lead this team to recommend a fixed price or lump sum contract. This recommendation stems from the fact that scope has been clearly defined and unless otherwise expected by those at Husky Air management it should not change greatly. The contract could be implemented so that incentives are provided for meeting certain performance objectives and also include penalties for objectives that are not met.
2. Learning Cycle
1. Understand & Frame the Problem
The assignment was thoroughly read through in both the text and online directions. Once this was done discussion occurred via email and cellular messaging to ensure all members understood the requirements and framework of the task at hand.
2. Plan
Through online messaging we coordinated tasks to various team members. Omar and Mohamed took on the role of creating resource requirements and a resource cost table. Cain was given the responsibility to create the contract payment method and learning cycle iteration. Lastly Fahib made and revised the project description and MOV, as well as taking on the responsibility to organize all parts into one succinct project infrastructure report.
3. Action
Team members each sought to fulfill their duties in a timely manner. Communication happened throughout to ensure help was found when needed and all were working harmoniously together.
4. Reflect and Learn
Team members are working sufficiently and all are coordinating efforts to get work done in time for the stringent deadlines. Having such short time periods to complete sizeable tasks come with a certain amount of hardship. Coordinating tasks to members who cannot physically meet was somewhat difficult, but the hardworking nature within each group member made it possible.
18
Deliverable Structure Chart (DSC):
Before making a deliverable structural chart, we need to define the
deliverables or tasks needed for project completion. The integration and
completion of the system depends on the type of system life cycle you follow.
The diverse Team Infrastructure follows rapid development life cycle. As soon
as the requirements are compiled, the designing and implementation starts
on the basis of requirements. The system is flexible enough to integrate the
additional requirements in the system.
Tasks or Deliverables: (The Improved Husky Air System)
Business case, Project charter & project plan, Technology & organizational
assessment, requirements definition, user interface, physical & technical
design, application system, testing plan, change management and
implementation plan, project evaluations, final project report & lessons
learned.
19
Use Case Diagram
Work Breakdown Structure
System
Update Flight Schedule
Access Pilot Files
Access Patient Files
Access Flight Schedule
Update Pilot Files
Update Patient Files
Pilot
Patient
Organ Donor Bank
Hospital
Airport
Boss
20
Scope Change Request Form:
THE IMPROVED Husky Air SYSTEM
21
Scope Change Request Form Project Name: _______________________ Project Location: ______________________ Requestor Name: _____________________ Request Date: ________________________ Request Title: ________________________ Request Number: _____________________ Request Source: ______________________ Requestor Signature: __________________ Request System Description (please indicate design change or non-compliance change): Justification (Priority): Possible Alternatives:
Impacts Alternative 1 Alternative 2 Alternative 3 Recommendation
Scope
Schedule
Resources required
Cost
Recommendations: Authorized by Date
______________________________________________
Scope Change Request Log:
Diverse Company - Project (THE IMPROVED Husky Air SYSTEM)
22
Scope Change Request Log
Notes:
Project plan
A. Part I (WBS) Request Number
Request Name
Initial Description
Date of Request
Requestor Name
Priority Approve by
Expected Response Date
Approval Status (Y/N)
Progress Percentage (%)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
23
24
B. Part 2 (Time line and dependencies):
25
26
27
Questions to be answered:
a. What are beginning (dates) and end dates for your project? How many days will it take to complete the project?
The project start date is Wednesday June 1,2016 and the end date is Wednesday July 13,2016. It will take almost 31 days to complete the project.
b. Does your project have a single critical path or multiple critical paths? What is the importance of the critical path?
This project has one critical path. The critical path allows us to see the crucial parts of the project that done in order take the longest time to complete. This gives an idea of the shortest possible time to complete the project. It is also an important tool for the project manager because any change in duration of a task or activity on the critical path will have a direct impact on the project’s schedule.
c. What is the total project cost of the project?
The total cost of the project is $165,200.00.
d. Does your project have any over allocated resources? If so, be sure to level your resources
No, the project my team made does not have any over allocated resources
28
A Project Summary Report (original project plan, schedule &
budget).
29
30
A Project Summary Report (revised project plan).
31
A Project risk analysis and plan Report—understanding the sources
and impact of risks to projects.
Ranked Risk Owners Risks Strategy
1 Husky Air Management & Project Team
False Expectations There can be no ambiguity in the needs for a proposed system. If owners expect one thing and are given another, this can have huge repercussions to the organization. The creation and follow through of a project can be a costly and arduous process, it must seek as best it can to meet the expectations of the owners. Husky Air has mitigated this risk by clearly defining what the project hopes and expectations are.
2 Project Team Roles Not Clearly Defined
At the beginning of a project a team charter needs to be completed by all team members and signed into action so that if a member is not sure of their role or place in the group they can always reference the charter. Husky Air has mitigated this risk by employing a skilled team that practices the steps of a project lifecycle and SDLC methodologies.
32
3 Project Team & Husky Air Management
Scope Creep A risk that can develop during the main phase of the project is scope creep. When a team sets goals for what they want to be completed within the timeframe and budget it is important that they stick to these goals and do not end up trying to do more than what they can. Adding extra functionality and roles to the system may sound good in theory, but these additions have the possibility to lead to the downfall of a project.
4 Technology & Management
Lack of System Testing
When major goals are reached in building a system a snapshot or developed module of the project users should be able to get their hands on it and provide feedback. Without this system feedback it is possible to loose track of what users actually want and need from the new system. It also allows for the adjustment and remedy of technical issues that may not have been detected before.
5 User Basis Lack of Adoption by Users
After a successful rollout of a project that many users seem to be happy with it is
33
important to take into consideration all of the views that users have. Some users may be slow or even opposed to the adoption of a new system. If there are certain groups who oppose the new system, it is imperative to address their concerns and try to reach a solution.
Earned Value Analysis
Initial WBS #1
34
35
Updated #2
36
Reports #4
37
Earned Value Analysis
38
Analysis of BugBuster’s work.
An analysis of the WBS for BugBuster’s product testing of Husky Air’s Pilot Angel’s new system show many key tasks took longer than expected. This increase throughout some of the tasks performed causes the price to pay resources to also increase. This increase means a significant rise in the actual costs over the expected costs for the project. While it is unfortunate that estimates were not made, analysis of percentage of work completed does show us that the project is nearing completion. Many organizations often overlook testing in favor of putting out a buggy system; it is strongly recommended that BugBusters be allowed to complete their testing. The new system to be implemented at Pilot Angel’s houses key data required for the majority of the personnel at the organization. If a system is delivered without proper testing poor performance could lead to malfunctions and incorrect data. This data if wrong could possibly lead to disasters in a worst case scenario. If a plan’s data were to indicate that repairs were done when they had not been and an accident was to occur Husky Air would be directly responsible for any damages or loss of life. With the importance of the system it is strongly recommended that BugBusters be allowed to finish the testing of the system.
39
Quality Management Plan
a. Team Objective:
My Team focuses on customer satisfaction that makes sure we provide the highest quality of products to them. Testing this system continuously will help understand and demolish all bugs or errors present. My Team is responsible for the perfection of this system. This project is promised to be a 100% satisfaction guaranteed.
b. Quality Based Metrics
Process Availability- a measure of how long it will take to receive the equipment
Human Defect – a measure for lost time due to human error
Product Life Defect – Time allocated before the system needs an update
Usability measure- the amount of people that found the training useful.
Project Schedule Defect- how much time over schedule the project is.
Cost Defect – amount of money over cost the project is.
c. Verification Activities
Technical reviews are essential to make sure that the system meets all requirements of Husky Air.
The business review will be conducted to ensure proper functionality of the
project scope. Deliverables will be considered to ensure they are complete and
provide information that refer to the methodology of the project.
Project will then go through a managerial review. This is when the projects
progress will be compared against the project plan.
d. Validation Activities
There will be tests done to ensure the quality of the project
A unit test will help make sure the functions of the system
It will then go through an integration test
Finally, it will have to pass an acceptance test which will ensure to see if it satisfies our customer. It will have to perform all the tasks expected of the
customer.
40
MS Project Tutorial I
41
42
MS Project Tutorial II
43
44
45
46
47
48
49
50
MS Project Tutorial III
51
52
53
54
55
56
57
58