HOJA 1 DE 2 Obra / Project: "PARAISO AKUMAL RESORT" Ubicación / Location: AKUMAL Q. ROO. Fecha / Date: 11 DE FEBRERO DE 2015 Plano Ref/ Construction Plan: "EDIFICIO H" CLAVE CONCEPTO UNIDAD CANTIDAD ANTERIOR CANTIDAD ESTA SEM. 07 ACUMULADO 2014 CANTIDAD TOPE CANTIDAD RESTANTE % DE AVANCE P.U. IMPORTE SEMANA 07 IMPORTE ACUMULADO 2014 OBSERVACIONES ULTIMA ESTIMACION 001 CIMENTACION (EDIFICIO H) 5VACONCLCM CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS Y MUROS M3 301.00 -301.00 0.00 301.00 301.00 0% $100.00 30,100.00 -$ - $ DEDUCTIVA 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 301.00 301.00 301.00 0.00 100% $120.00 36,120.00 $ 36,120.00 $ ADITIVA 001.01 PLANTA BAJA (EDIFICIO H) N. P. T. +3.30 5VACONDPC CONCRETO EN DALAS , PRETILES Y CASTILLOS M3 32.30 32.30 32.30 0.00 100% $87.00 - $ 2,810.10 $ 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 0.00 301.00 301.00 0% $120.00 - $ - $ 5VACONCLCM CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS Y MUROS M3 77.00 -77.00 0.00 77.00 77.00 0% $100.00 7,700.00 -$ - $ DEDUCTIVA 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 77.00 77.00 301.00 224.00 26% $120.00 9,240.00 $ 9,240.00 $ ADITIVA 001.02 PRIMER NIVEL (EDIFICIO H) N. P. T. +6.55 5VACONDPC CONCRETO EN DALAS , PRETILES Y CASTILLOS M3 25.60 25.60 25.60 0.00 100% $87.00 - $ 2,227.20 $ 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 0.00 301.00 301.00 0% $120.00 - $ - $ 5VACONCLCM CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS Y MUROS M3 70.00 -70.00 0.00 81.00 81.00 0% $100.00 7,000.00 -$ - $ DEDUCTIVA 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 70.00 70.00 301.00 231.00 23% $120.00 8,400.00 $ 8,400.00 $ ADITIVA 002.03 SEG. NIVEL (EDIFICIO H) N. P. T. +9.80 5VACONDPC CONCRETO EN DALAS , PRETILES Y CASTILLOS M3 32.00 32.00 50.00 18.00 64% $87.00 - $ 2,784.00 $ 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 0.00 301.00 301.00 0% $120.00 - $ - $ 002.04 TERCER NIV. (EDIFICIO H) N. P. T. +13.05 5VACONDPC CONCRETO EN DALAS , PRETILES Y CASTILLOS M3 25.60 25.60 25.60 0.00 100% $87.00 - $ 2,227.20 $ 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 0.00 301.00 301.00 0% $120.00 - $ - $ 5VACONCLCM CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS Y MUROS M3 77.00 -77.00 0.00 81.00 81.00 0% $100.00 7,700.00 -$ - $ DEDUCTIVA 5VACONC120 CONCRETO EN CIMENTACIÓN, LOSAS, COLUMNAS, MUROS Y CASTILLOS M3 0.00 77.00 77.00 301.00 224.00 26% $120.00 9,240.00 $ 9,240.00 $ ADITIVA PERIODO DEL 06/02/2015 AL 10/02/2015 ESTIMACION DE OBRA ESTIMACIÓN No. 34 DE SEMANA 07 (DEDUCTIVAS Y ADITIVAS POR PRECIOS DE CONCRETO Y CIMBRA) CONTRUCCION DEL HOTEL PARAISO AKUMAL RESORT PERIODO DEL 06 DE FEBRERO DE 2015 AL 10 DE FEBRERO DE 2015 DE FECHA 11 DE FEBRERO DE 2015 HOJA 1 DE 2

02.- Est.H Salinas 02

Embed Size (px)

Citation preview

Page 1: 02.- Est.H Salinas 02

HOJA 1 DE 2

Obra / Project: "PARAISO AKUMAL RESORT"

Ubicación / Location: AKUMAL Q. ROO. Fecha / Date: 11 DE FEBRERO DE 2015

Plano Ref/ Construction Plan: "EDIFICIO H"

CLAVE CONCEPTO UNIDADCANTIDAD

ANTERIOR

CANTIDAD ESTA

SEM. 07ACUMULADO 2014 CANTIDAD TOPE

CANTIDAD

RESTANTE

% DE

AVANCEP.U.

IMPORTE SEMANA

07IMPORTE ACUMULADO 2014

OBSERVACIONES ULTIMA

ESTIMACION

001 CIMENTACION (EDIFICIO H)

5VACONCLCMCONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS Y MUROSM3 301.00 -301.00 0.00 301.00 301.00 0% $100.00 30,100.00-$ -$ DEDUCTIVA

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 301.00 301.00 301.00 0.00 100% $120.00 36,120.00$ 36,120.00$ ADITIVA

001.01 PLANTA BAJA (EDIFICIO H) N. P. T. +3.30

5VACONDPCCONCRETO EN DALAS , PRETILES Y

CASTILLOSM3 32.30 32.30 32.30 0.00 100% $87.00 -$ 2,810.10$

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 0.00 301.00 301.00 0% $120.00 -$ -$

5VACONCLCMCONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS Y MUROSM3 77.00 -77.00 0.00 77.00 77.00 0% $100.00 7,700.00-$ -$ DEDUCTIVA

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 77.00 77.00 301.00 224.00 26% $120.00 9,240.00$ 9,240.00$ ADITIVA

001.02 PRIMER NIVEL (EDIFICIO H) N. P. T. +6.55

5VACONDPCCONCRETO EN DALAS , PRETILES Y

CASTILLOSM3 25.60 25.60 25.60 0.00 100% $87.00 -$ 2,227.20$

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 0.00 301.00 301.00 0% $120.00 -$ -$

5VACONCLCMCONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS Y MUROSM3 70.00 -70.00 0.00 81.00 81.00 0% $100.00 7,000.00-$ -$ DEDUCTIVA

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 70.00 70.00 301.00 231.00 23% $120.00 8,400.00$ 8,400.00$ ADITIVA

002.03 SEG. NIVEL (EDIFICIO H) N. P. T. +9.80

5VACONDPCCONCRETO EN DALAS , PRETILES Y

CASTILLOSM3 32.00 32.00 50.00 18.00 64% $87.00 -$ 2,784.00$

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 0.00 301.00 301.00 0% $120.00 -$ -$

002.04 TERCER NIV. (EDIFICIO H) N. P. T. +13.05

5VACONDPCCONCRETO EN DALAS , PRETILES Y

CASTILLOSM3 25.60 25.60 25.60 0.00 100% $87.00 -$ 2,227.20$

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 0.00 301.00 301.00 0% $120.00 -$ -$

5VACONCLCMCONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS Y MUROSM3 77.00 -77.00 0.00 81.00 81.00 0% $100.00 7,700.00-$ -$ DEDUCTIVA

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 77.00 77.00 301.00 224.00 26% $120.00 9,240.00$ 9,240.00$ ADITIVA

PERIODO DEL 06/02/2015 AL 10/02/2015

ESTIMACION DE OBRAESTIMACIÓN No. 34 DE SEMANA 07 (DEDUCTIVAS Y ADITIVAS POR PRECIOS DE CONCRETO Y CIMBRA)

CONTRUCCION DEL HOTEL PARAISO AKUMAL RESORT PERIODO DEL 06 DE FEBRERO DE 2015 AL 10 DE FEBRERO DE 2015 DE FECHA 11 DE FEBRERO DE 2015

HOJA 1 DE 2

Page 2: 02.- Est.H Salinas 02

HOJA 2 DE 2

Obra / Project: "PARAISO AKUMAL RESORT"

Ubicación / Location: AKUMAL Q. ROO. Fecha / Date: 11 DE FEBRERO DE 2015

Plano Ref/ Construction Plan: "EDIFICIO H"

CLAVE CONCEPTO UNIDADCANTIDAD

ANTERIOR

CANTIDAD ESTA

SEM. 07ACUMULADO 2014 CANTIDAD TOPE

CANTIDAD

RESTANTE

% DE

AVANCEP.U.

IMPORTE SEMANA

07IMPORTE ACUMULADO 2014

OBSERVACIONES ULTIMA

ESTIMACION

PERIODO DEL 06/02/2015 AL 10/02/2015

ESTIMACION DE OBRAESTIMACIÓN No. 34 DE SEMANA 07 (DEDUCTIVAS Y ADITIVAS POR PRECIOS DE CONCRETO Y CIMBRA)

CONTRUCCION DEL HOTEL PARAISO AKUMAL RESORT PERIODO DEL 06 DE FEBRERO DE 2015 AL 10 DE FEBRERO DE 2015 DE FECHA 11 DE FEBRERO DE 2015

002.05 CUARTO NIV. (EDIFICIO H) N. P. T. +16.30

5VACONDPCCONCRETO EN DALAS , PRETILES Y

CASTILLOSM3 24.11 24.11 24.11 0.00 100% $87.00 -$ 2,097.57$

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 0.00 301.00 301.00 0% $120.00 -$ -$

5VACONCLCMCONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS Y MUROSM3 77.00 -77.00 0.00 81.00 81.00 0% $100.00 7,700.00-$ -$

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 77.00 77.00 301.00 224.00 26% $120.00 9,240.00$ 9,240.00$

002.06 AZOTEA. (EDIFICIO H) N. P. T. +19.55

5VACONCLCMCONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS Y MUROSM3 74.84 -74.84 0.00 81.00 81.00 0% $100.00 7,484.00-$ -$ DEDUCTIVA

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 74.84 74.84 301.00 226.16 25% $120.00 8,980.80$ 8,980.80$ ADITIVA

002.08 ALBERCA H-G

5FORCAR01 CIMBRA CIRCULAR EN ALBERCA M2 364.63 -364.63 0.00 364.63 364.63 0% $180.00 65,633.40-$ -$ DEDUCTIVA

5CIMBCUR210 CIMBRA CIRCULAR EN ALBERCA M2 0.00 364.63 364.63 364.63 0.00 100% $210.00 76,572.30$ 76,572.30$ ADITIVA

5VACONCLCMCONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS Y MUROSM3 185.00 -185.00 0.00 185.00 185.00 0% $100.00 18,500.00-$ -$ DEDUCTIVA

5VACONC120CONCRETO EN CIMENTACIÓN, LOSAS,

COLUMNAS, MUROS Y CASTILLOSM3 0.00 185.00 185.00 185.00 0.00 100% $120.00 22,200.00$ 22,200.00$ ADITIVA

Subtotal estimación 28,175.70$ Presupuesto inicial $ -

Deductiva -$ Anticipo $ -

Subtotal 1 28,175.70$ % Anticipo 0.00%

I. V, A. 16 % 4,508.11$ Total acumulado $ 3,093,386.04

Total factura 32,683.81$ % Pagado presupuesto 0%

SALCON GSCH S. A. DE C. V. CONSTRUCTORA KARO S. A. DE C. V. CONSTRUCTORA KARO S. A. DE C. V. DIRECTOR DEL PROYECTO

Cantidad con letra: (Son: Treinta y dos mil seiscientos ochenta y tres pesos 81/100 M. N.)

Elaboró: Ing. Enrique Yam Tun Revisó: Ing. Arturo Alvarado Revisó: Ing. Jose Mendez Aprobó: Ing. Carlos Ortega Zuñiga

HOJA 2 DE 2