LAPORAN STATISTIKSTATISTIC REPORT
2015
LAPORAN STATISTIKSTATISTIC REPORT
2015
2 LAPORAN STATISTIKSTATISTIC REPORT2015
DAFTAR ISI
Table of Contents
2
DAFTAR TABELTable List
3
DAFTAR GRAFIKGraphic List
4
PENGANTARForeword
5
PROFIL PERUSAHAAN Company Profile
Identitas Perusahaan Corporate Identity
7
Sejarah Singkat Brief History
8
IKHTISAR Summary
10
DAFTAR ISITABLE OF CONTENTS
SISTEM JAWA BALIJava Bali System
Penyediaan Tenaga ListrikElectricity Supply
16
Pengiriman EnergiEnergy Transfer
20
DAYA TERPASANGInstalled Capacity
24
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRIProduction, Sales and Self Consumption
28
Produksi Per Unit Production Per Unit
29
Penjualan Per UnitSales Per Unit
33
Pemakaian Sendiri Per UnitSelf Consumption Per Unit
36
Produksi Per Jenis PembangkitProduction Per Power Plant Type
38
Penjualan Per Jenis PembangkitSales Per Power Plant Type
41
Pemakaian Sendiri Per Jenis PembangkitSelf Consumption Per Power Plant Type
45
PEMAKAIAN BAHAN BAKARFuel Consumption
48
Pemakaian Bahan Bakar Per UnitFuel Consumption Per Unit
50
Pemakaian Bahan Bakar Per Jenis PembangkitFuel Consumption Per Power Plant Type
53
KINERJA OPERASIONALOperational Performance
KinerjaPerformance
56
Kinerja Per UnitPerformance Per Unit
57
KEUANGANFinancial
66
KEPEGAWAIAN
Human Resources
70
PENJELASAN
Glossary of Terms
75
DAFTAR SINGKATAN
List of Abbreviation
76
3LAPORAN STATISTIKSTATISTIC REPORT 2015
DAFTAR TABELTABLE LIST
01
Penyediaan Tenaga Listrik Sistem Jawa Bali Tahun 2011-2015Electricity Supply of Java Bali System in 2011-2015
16
02
Penyediaan Tenaga Listrik PT PJB (MW) Tahun 2015Electricity Supply of PT PJB (MW) in 2015
18
03
Penyediaan Tenaga Listrik Tanjung Jati B dan UPJB Tahun 2015Electricity Supply of Tanjung Jati B and UPJB in 2015
19
04Penyediaan Tenaga Listrik IPP Tahun 2015Electricity Supply of IPP in 2015
19
05
Pengiriman Energi ke Sistem Jawa Bali Tahun 2011-2015Energy Transferred to Java Bali System in 2011-2015
20
06
Realisasi Pengiriman Energi ke Sistem Jawa Bali Tahun 2014-2015 dan Rencana Tahun 2016Realization of Energy Transferred to Java Bali System in 2014-2015 and Plan of 2016
22
07
Daya Terpasang Pembangkit yang dimiliki Perusahaan Tahun 2011-2015Installed Capacity of Units Owned by the Company in 2011-2015
24
08
Daya Terpasang Pembangkit yang Dikelola Perusahaan Tahun 2011-2015Installed Capacity of Units Managed by the Company in 2011-2015
25
09Daya Terpasang Pembangkit Tahun 2015Installed Capacity of Units in 2015
26
10
Daya Terpasang Pembangkit dari Pembelian Tenaga Listrik Tahun 2011-2015Installed Capacity of Units Owned by the Purchase of Electricity in 2011-2015
26
11
Pertumbuhan Produksi, Penjualan dan Pemakaian Sendiri Tahun 2011-2015Production, Sales and Self Consumption Growth in 2011-2015
28
12
Realisasi Produksi Tahun 2014-2015 dan Rencana Tahun 2016Production Realization in 2014-2015 and Plan of 2016
29
13Produksi Per Unit Tahun 2015Production Per Unit in 2015
31
14
Realisasi Penjualan Tahun 2014-2015 dan Rencana Tahun 2016Sales Realization in 2014-2015 and Plan of 2016
33
15Penjualan Per Unit Tahun 2015Sales Per Unit in 2015
34
16
Realisasi Pemakaian Sendiri Tahun 2014-2015 dan Rencana Tahun 2016Self Consumption Realization in 2014-2015 and Plan of 2016
36
17Pemakaian Sendiri Per Unit Tahun 2015Self Consumption Per Unit in 2015
37
18
Realisasi Produksi Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016Production Realization Per Power Plant Type in 2014-2015 and Plan of 2016
38
19
Produksi Per Jenis Pembangkit Tahun 2015Production Per Power Plant Type in 2015
40
20
Realisasi Penjualan Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016Sales Realization Per Power Plant Type in 2014-2015 and Plan of 2016
41
21Penjualan Per Jenis Pembangkit Tahun 2015Sales Per Power Plant Type in 2015
42
22
Realisasi Pemakaian Sendiri Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016Self Consumption Realization Per Power Plant Type in 2014-2015 and Plan of 2016
44
23
Pemakaian Sendiri Per Jenis Pembangkit Tahun 2015Self Consumption Per Power Plant Type in 2015
46
24Pemakaian Bahan Bakar Tahun 2011-2015Fuel Consumption in 2011-2015
48
25
Realisasi Pemakaian Bahan Bakar Per Unit Tahun 2014-2015 dan Rencana Tahun 2016Fuel Consumption Realization Per Unit in 2014-2015 and Plan of 2016
50
26Pemakaian Bahan Bakar Per Unit Tahun 2015Fuel Consumption Per Unit in 2015
51
27
Realisasi Pemakaian Bahan Bakar Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016Fuel Consumption Realization Per Power Plant Type in 2014-2015 and Plan of 2016
53
28
Pemakaian Bahan Bakar Per Jenis Pembangkit Tahun 2015Fuel Consumption Per Power Plant Type in 2015
54
29
Kinerja Unit Indonesia Power Tahun 2011-2015Indonesia Power Unit Performance in 2011-2015
56
30
Realisasi EAF Tahun 2014-2015 dan Rencana Tahun 2016EAF Realization in 2014-2015 and Plan of 2016
57
31
Realisasi CF Tahun 2014-2015 dan Rencana Tahun 2016CF Realization in 2014-2015 and Plan of 2016
57
32
Kinerja Unit Pembangkitan Suralaya Tahun 2015Suralaya Generating Unit Performance in 2015
58
33
Kinerja Unit Pembangkitan dan Jasa Pembangkitan Priok Tahun 2015Priok Generating and Generating Services Unit Performance in 2015
58
34
Kinerja Unit Pembangkitan Saguling Tahun 2015Saguling Generating Unit Performance in 2015
59
35
Kinerja Unit Pembangkitan dan Jasa Pembangkitan Kamojang Tahun 2015Kamojang Generating and Generating Services Unit Performance in 2015
60
36
Kinerja Unit Pembangkitan Mrica Tahun 2015Mrica Generating Unit Performance in 2015
61
37
Kinerja Unit Pembangkitan Semarang Tahun 2015Semarang Generating Unit Performance in 2015
62
38
Kinerja Unit Pembangkitan Perak Grati Tahun 2015Perak Grati Generating Unit Performance in 2015
63
39
Kinerja Unit Pembangkitan dan Jasa Pembangkitan Bali Tahun 2015Bali Generating and Generating Services Unit Performance in 2015
64
40
Pertumbuhan Jumlah Aktiva, Laba Tahun Berjalan, Pendapatan Usaha dan Pendapatan Penjualan Energi Listrik Tahun 2011-2015Growth of Total Asset, Income of the Year, Revenue and Electricity Sales Revenue in 2011-2015
66
41
Pendapatan Penjualan Energi Listrik Per Unit Tahun 2015 (dalam juta)Electricity Sales Revenue Per Unit in 2015 (in million)
67
42
Pendapatan Penjualan Energi Listrik Per Jenis Pembangkit Tahun 2015 (dalam juta)Electricity Sales Revenue Per Power Plant Type in 2015 (in million)
68
43Laba Rugi Tahun 2014-2015 (dalam juta)Profit/Loss Statement in 2014-2015 (in million)
68
44Jumlah Pegawai Aktif Tahun 2011-2015Total of Active Employees in 2011-2015
70
45Jumlah Pegawai Berdasarkan Usia Tahun 2015Total Employees Based on Age in 2015
71
46
Jumlah Pegawai Berdasarkan Jenjang Jabatan Tahun 2015Total Employees Based on Position Level in 2015
72
47Jumlah Pegawai Berdasarkan Jenis Kelamin Tahun 2015Total Employees Based on Gender in 2015
73
48
Jumlah Pegawai Berdasarkan Pendidikan Tahun 2015Total Employees Based on Education in 2015
74
4 LAPORAN STATISTIKSTATISTIC REPORT2015
DAFTAR GRAFIKGRAPHIC LIST
01
Penyediaan Tenaga Listrik Sistem Jawa Bali Tahun 2011-2015 (MW)Electricity Supply of Java Bali System in 2011-2015 (MW)
16
02
Pengiriman Energi ke Sistem Jawa Bali Tahun 2011-2015 (GWh)Energy Transferred to Java Bali System in 2011-2015 (GWh)
20
03
Realisasi Pengiriman Energi ke Sistem Jawa Bali Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Realization of Energy Transferred to Java Bali System in 2014-2015 and Plan of 2016 (GWh)
22
04
Daya Terpasang Pembangkit yang dimiliki Perusahaan Tahun 2011-2015Installed Capacity of Units Owned by the Company in 2011-2015
24
05
Daya Terpasang Pembangkit yang Dikelola Perusahaan Tahun 2011-2015 (MW)Installed Capacity of Units Managed by the Company in 2011-2015 (MW)
25
06Produksi dan Penjualan Tahun 2011-2015 (GWh)Production and Sales in 2011-2015 (GWh)
28
07
Pertumbuhan Produksi dan Penjualan Tahun 2011-2015 (%)Growth of Production and Sales in 2011-2015 (%)
28
08
Realisasi Produksi Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Production Realization in 2014-2015 and Plan of 2016 (GWh)
30
09Pertumbuhan Produksi Tahun 2014 dan Tahun 2015 (%)Production Growth in 2014 and 2015 (%)
30
10Produksi per Unit Tahun 2015 (GWh)Production based on Unit in 2015 (GWh)
32
11
Realisasi Penjualan Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Sales Realization in 2014-2015 and Plan of 2016 (GWh)
33
12Pertumbuhan Penjualan Tahun 2014 dan Tahun 2015 (%)Sales Growth in 2014 and 2015 (%)
34
13Penjualan Per Unit Tahun 2015 (GWh)Sales Per Unit in 2015 (GWh)
35
14
Realisasi Pemakaian Sendiri Tahun 2014-2015 dan Rencana Tahun 2016 (%)Self Consumption Realization in 2014-2015 and Plan of 2016 (%)
36
15Pemakaian Sendiri Per Unit Tahun 2015 (%)Self Consumption Per Unit in 2015 (%)
37
16
Realisasi Produksi Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Production Realization Per Power Plant Type in 2014-2015 and Plan of 2016 (GWh)
39
17
Pertumbuhan Produksi Per Jenis Pembangkit Tahun 2014 dan Tahun 2015 (%)Production Growth Per Power Plant Type in 2014 and 2015 (%)
39
18
Produksi Per Jenis Pembangkit Tahun 2015 (GWh)Production Per Power Plant Type in 2015 (GWh)
40
19
Realisasi Penjualan Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Sales Realization Per Power Plant Type in 2014-2015 and Plan of 2016 (GWh)
41
20
Pertumbuhan Penjualan Per jenis Pembangkit Tahun 2014-2015 (%)Sales Growth Per Power Plant Type in 2014 and 2015 (%)
42
21
Penjualan Per Jenis Pembangkit Tahun 2015 (GWh)Sales Per Power Plant Type in 2015 (GWh)
43
22
Realisasi Pemakaian Sendiri Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 (%)Self Consumption Realization Per Power Plant Type in 2014-2015 and Plan of 2016 (%)
45
23
Pemakaian Sendiri Per Jenis Pembangkit Tahun 2015 (%)Self Consumption Per Power Plant Type in 2015 (%)
46
24
Pemakaian Bahan Bakar HSD dan MFO Tahun 2011-2015 (kiloliter)HSD and MFO Fuel Consumption in 2011-2015 (kiloliter)
48
25
Pertumbuhan Pemakaian Bahan Bakar HSD dan MFO Tahun 2011-2015 (%)HSD and MFO Consumption Growth in 2011-2015 (%)
49
26
Pemakaian Bahan Bakar Gas (mmbtu) dan Batubara (ton) Tahun 2011-2015Gas (mmbtu) and Coal (ton) Consumption in 2011-2015
49
27
Pertumbuhan Pemakaian Bahan Bakar Gas dan Batubara Tahun 2011-2015 (%)Gas Consumption and Coal Consumption Growth in 2011-2015 (%)
49
28
Realisasi Pemakaian Bahan Bakar HSD dan MFO per Unit Tahun 2014-2015 dan Rencana Tahun 2016 (kiloliter)HSD and MFO Consumption Realization Based on Unit in 2014-2015 and Plan of 2016 (kiloliter)
50
29
Realisasi Pemakaian Bahan Bakar Gas (mmbtu) dan Batubara (ton) 2014-2015 dan Rencana Tahun 2016Gas (mmbtu) and Coal (ton) Consumption Realization in 2014-2015 and Plan of 2016
51
30
Pemakaian Bahan Bakar HSD dan MFO Tahun 2015 (kiloliter)HSD and MFO Fuel Consumption in 2015 (kiloliter)
52
31
Pemakaian Bahan Bakar Gas (mmbtu) dan Batubara (ton) Tahun 2015Gas (mmbtu) and Coal (ton) Consumption in 2015
52
32
Kinerja Unit Indonesia Power Tahun 2011-2015 (%)Indonesia Power Unit Performance in 2011-2015 (%)
56
33
Kinerja Unit Pembangkitan Suralaya Tahun 2015 (%)Suralaya Generating Unit Performance in 2015 (%)
58
34
Kinerja Unit Pembangkitan dan Jasa Pembangkitan Priok Tahun 2015 (%)Priok Generating and Generating Services Unit Performance in 2015 (%)
59
35
Kinerja Unit Pembangkitan Saguling Tahun 2015 (%)Saguling Generating Unit Performance in 2015 (%)
59
36
Kinerja Unit Pembangkitan dan Jasa Pembangkitan Kamojang Tahun 2015 (%)Kamojang Generating and Generating Services Unit Performance in 2015 (%)
60
37
Kinerja Unit Pembangkitan Mrica Tahun 2015 (%)Mrica Generating Unit Performance in 2015 (%)
61
38
Kinerja Unit Pembangkitan Semarang Tahun 2015 (%)Semarang Generating Unit Performance in 2015 (%)
62
39
Kinerja Unit Pembangkitan Perak Grati Tahun 2015 (%)Perak Grati Generating Unit Performance in 2015 (%)
63
40
Kinerja Unit Pembangkitan dan Jasa Pembangkitan Bali Tahun 2015 (%)Bali Generating and Generating Services Unit Performance in 2015 (%)
64
41
Jumlah Aktiva, Laba Tahun Berjalan dan Pendapatan Usaha Tahun 2011-2015 (dalam Rp miliar)Total Asset, Income for the Year, and Revenue in 2011-2015 (in billion Rp)
66
42
Pertumbuhan Jumlah Aktiva, Laba Tahun Berjalan dan Pendapatan Usaha Tahun 2011-2015 (%)Total Asset, Income for the Year, and Revenue in 2011-2015 (%)
67
43Jumlah Pegawai Aktif Tahun 2011-2015Total of Active Employees in 2011-2015
70
44Jumlah Pegawai Berdasarkan Usia Tahun 2015Total Employees Based on Age in 2015
71
45
Jumlah Pegawai Berdasarkan Jenjang Jabatan Tahun 2015Total Employees Based on Position Level in 2015
72
46Jumlah Pegawai Berdasarkan Jenis Kelamin Tahun 2015Total Employees Based on Gender in 2015
73
47
Jumlah Pegawai Berdasarkan Pendidikan Tahun 2015Total Employees Based on Education in 2015
74
5LAPORAN STATISTIKSTATISTIC REPORT 2015
PT Indonesia Power selanjutnya disebut “Indonesia Power” atau “Perusahaan” tahun ini menerbitkan Buku Statistik Indonesia Power Tahun 2015 yang merupakan penerbitan lanjutan dari buku statistik tahun sebelumnya. Data pada buku ini disusun berdasarkan hasil data laporan Unit, konsolidasi laporan Kantor Pusat Indonesia Power dan PT PLN (Persero) dan Pusat Pengatur Beban (P2B). Buku ini dimaksudkan untuk memberikan informasi mengenai hasil kerja Perusahaan di bidang Pengusahaan Pembangkit, Niaga, Keuangan, dan SDM tahun 2015 dan perkembangannya selama 5 tahun terakhir. Sebagai sebuah perusahaan yang maju, di samping harus memiliki program-program ke depan, juga banyak meluangkan perhatian untuk melakukan analisa-analisa data perusahaan. Data statistik perusahaan yang disusun dalam buku ini, pada dasarnya adalah satu upaya dari Perusahaan untuk menampilkan data-data statistik untuk menjadi sebuah informasi yang sangat berguna bagi Perusahaan. Informasi-informasi yang diperoleh dari data analisa yang kuantitatif dan cermat akan menjadi “feedback” yang baik bagi Perusahaan. Data atau informasi dari data statistik Perusahaan akan makin memberikan “value” jika disertai data-data pembanding atau informasi “best practice” dari perusahaan sejenis.
Analisa data/informasi perusahaan bisa dijadikan “tool” bagi Perusahaan untuk pengambilan keputusan ke depan untuk menghindarkan terjadinya risiko yang sama di masa mendatang dan menjaga hal-hal positif di masa lalu untuk tetap dijaga dan diperbaiki di masa mendatang.
Akhir kata atas nama Direksi, kami berterimakasih kepada tim yang sudah menyusun buku ini semoga bermanfaat bagi Perusahaan ke depan. Tidak ada gading yang tidak retak, upaya perbaikan ke depan dalam penyusunan buku yang sama di masa mendatang sangat diharapkan dari Pembaca/Penyusun buku ini.
Sripeni Inten Cahyani PLT Direktur Utama | President Director (Acting)
PT Indonesia Power hereinafter called as “Indonesia Power” or “the Company” publishes the 2015 Statistic Book, which is continuous edition from the previous year. Data is classified based on Unit Report, Consolidated Report of Indonesia Power and PT PLN (Persero) and Load Control Center (P2B). Statistic Book provides information about Indonesia Power’s performance in several areas, i.e. plant utilization, Sales, Finance and Human Resource in 2015 and its development during the last 5 year. As a developed company, in addition to have future programs, it is also required to pay attention on company’s data analysis. Company’s statistic data compiled in this book is basically one of Company’s efforts to show statistical data as useful information for the Company. The information obtained from quantitative and accurate analytical data will be a good feedback for the Company. Data or information from Company’s statistical data will give added values if it is followed by comparative data or best practice information from similar company.
Company’s information or analytical data can be used as a tool for the Company to make decision in the future and to avoid the occurrence of similar risks in the future as well as to maintain the positive things in the past and improve them in the future.
Finally, on behalf of the Board of Directors, we thank the team who has compiled this book and hope it will be useful for the Company in the future. There is no ivory that is not cracked, hence, inputs from the readers/authors for further improvement of this book are still expected.
PENGANTARFOREWORD
6 LAPORAN STATISTIKSTATISTIC REPORT2015
7LAPORAN STATISTIKSTATISTIC REPORT 2015
IDENTITAS PERUSAHAANCORPORATE IDENTITY
NAMA PERUSAHAANPT Indonesia Power
BIDANG USAHAPenyediaan tenaga listrik dan penyediaan jasa Operation & Maintenance (O&M).
KOMPOSISI PEMEGANG SAHAMa. PT PLN (Persero) sebanyak 1 lembar saham seri 1 dan
5.215.647.598 lembar saham seri 2b. Yayasan Pendidikan dan Kesejahteraan PT PLN (Persero)
sebanyak 1 lembar saham seri 2
TANGGAL PENDIRIAN3 Oktober 1995
DASAR HUKUM PENDIRIANa. Akte Pendirian PT PLN Pembangkitan Tenaga Listrik Jawa-Bali
I (PT PLN PJB I) tanggal 3 Oktober 1995b. Akte Perubahan Nama dari PT PLN PJB I menjadi PT Indonesia
Power tanggal 8 Agustus 2000
MODAL DASARRp10.000.000.000.000 (sepuluh triliun rupiah)
MODAL DITEMPATKAN DAN TELAH DISETOR PENUHRp2.607.823.800.000 (dua triliun enam ratus tujuh miliar delapan ratus dua puluh tiga juta delapan ratus ribu rupiah)
KRONOLOGIS PENCATATAN SAHAMIndonesia Power belum pernah mencatatkan saham di Bursa Efek Indonesia
KRONOLOGIS PENCATATAN EFEK LAINNYAIndonesia Power belum mencatatkan kepemilikan efek dan surat berbagai lainnya di Bursa Efek Indonesia
KANTOR PUSATJl. Jenderal Gatot Subroto Kav. 18 Jakarta Selatan 12950Phone : (62-21) 526 7666 (Hunting)Faximile : (62-21) 525 1923, 525 2623E-mail : [email protected] : www.indonesiapower.co.id
Jaringan Kantor:5 Unit Pembangkitan (UP), 3 Unit Pembangkitan dan Jasa Pembangkitan (UPJP), 1 Unit Jasa Pemeliharaan (UJH) serta 6 Unit Jasa Pembangkitan (UJP)
Entitas Anak dan Entitas Afiliasi:5 Anak Perusahaan, 1 Perusahaan Patungan dan 1 Perusahaan Asosiasi.
CORPORATION NAMEPT Indonesia Power
CORE BUSINESSElectricity power supply and Operation & Maintenance service supply.
COMPOSITION OF SHAREHOLDERSa. PT PLN (Persero) owns 1 share series 1 and 5,215,647,598
shares series 2b. Yayasan Pendidikan dan Kesejahteraan PT PLN (Persero) owns
1 shares series 2
DATE OF ESTABLISHMENTOctober 3rd, 1995
ESTABLISHMENT LEGAL BASISa. PT PLN Pembangkitan Tenaga Listrik Jawa-Bali I (PT PLN PJB
I) deed of establishment dated on October 3rd, 1995b. Change of name deed from PT PLN PJB I into PT Indonesia
Power dated on August 8th, 2000
AUTHORIZED CAPITALRp10,000,000,000,000 (ten trillion rupiah)
CAPITAL ISSUED AND FULLY PAIDRp2,607,823,800,000 (two trillion, six hundred and seven billion eight hundred twenty three million eight hundred thousand rupiah)
CHRONOLOGICAL LISTING SHARESIndonesia Power has never been listed its shares on the Indonesia Stock Exchange
CHRONOLOGICAL LISTING OF OTHER STOCKIndonesia Power has never listed the ownership of stocks and other securities in Indonesia Stock Exchange
HEAD OFFICEJl. Jenderal Gatot Subroto Kav.18 Jakarta Selatan 12950Phone : (62-21) 526 7666 (Hunting)Faximile : (62-21) 525 1923, 525 2623E-mail : [email protected] : www.indonesiapower.co.id
Office Network:5 Generating Unit (GU), 3 Generating and Generating Services Unit (GGSU), 1 Maintenance Services Unit (MSU) and 6 Generating Services Unit (GSU)
Subsidiaries and Affliates:5 Subsidiaries, 1 Joint Venture Company and 1 Affiliated Company
Keterangan:1. Unit Pembangkitan (UP) sebagai penyedia fungsi operasional penyediaan
tenaga listrik.2. Unit Pembangkitan dan Jasa Pembangkitan (UPJP) sebagai penyedia
fungsi operasional penyediaan tenaga listrik serta fungsi jasa pengelolaan O&M.
3. Unit Jasa Pembangkitan (UJP) sebagai penyedia fungsi jasa pengelolaan O&M.
4. Unit Jasa Pemeliharaan (UJH) sebagai penyedia fungsi kegiatan pemeliharaan.
Notice:1. Generating Unit (GU) as the provider of electricity supply’s operational
function.2. Generating and Generating Services Unit (GGSU) as the provider of
electricity supply’s operational function as well as O&M management services function.
3. Generating Services Unit (GSU) as the provider of O&M management services function.
4. Maintenance Services Unit (MSU) as the provider of maintenance function.
8 LAPORAN STATISTIKSTATISTIC REPORT2015
SEJARAH SINGKATBRIEF HISTORY
Indonesia Power is one of the subsidiaries of PT PLN (Persero) which was established in October 3rd, 1995 and formerly known as PT PLN Pembangkitan Tenaga Listrik Jawa-Bali I (PT PLN PJB I) as stipulated on the Minister of Justice of the Republic of Indonesia’s Decree No. C2-12496-HT.01.01. Th.1995.
In October 3rd, 2000 PT PLN PJB I officially changed its name to PT Indonesia Power to assert the Company’s goal, being an independent power company with purely business-oriented. The current main business activity of the Company’s is to focus as a provider of electrical power through power generation with total capacity installed reached to 9,111 MW and as an operation and maintenance of power plants’ service provider with total capacity installed reached to 5,233 MW that operates power plants across Indonesia. In addition to managing the generating unit, Indonesia Power has 5 Subsidiaries, 1 Joint Venture Company and 1 Affiliated Company to support the Business strategies and processes of the Company.
“To be a trusted energy company with sustainable growth” is the main objective of Indonesia Power, which can be observed from the Company’s vision. In an effort to realize this vision, the Company has established the mission of Indonesia Power, namely “Conducting the business of power generation and related services that are friendly to the environment”. In the next phase, the Company establishes the core competencies of Indonesia Power, namely “Operation and Maintenance of Plant as well as Plant Development” as an effort to increase competitiveness and accomplishing the mission of the Company. To support the achievement of the Vision and Mission, the Company established the principles that form the basis for directing the behavior of individuals and policies within the Company. Those principles are called the Corporate Culture that is reflected in “Indonesia Power Way” with the corporate values of “IP AkSi (Integrity, Professional, Proactive, Synergy)”
Improvement of a more effective and efficient business processes is carried through the integration of the company’s management systems with the implementation of Indonesia Power Integrated Management System (InPower IMS) that integrates ISO 14001 (Environmental Management System), ISO 9001 (Quality Management System), ISO 31000 (Risk Management System), OHSAS 18001, ISO 28001 (Security Management System for Supply Chain), Malcolm Baldrige, SMP (Security Management System), and SMK3 (HSE Management System), ISO 26000 (Standard Corporate Social Responsibility), ISO 55001 (Assets Management Standards).
Indonesia Power merupakan salah satu anak perusahaan PT PLN (Persero) yang didirikan pada tanggal 3 Oktober 1995 dengan nama PT PLN Pembangkitan Tenaga Listrik Jawa-Bali I (PT PLN PJB I) melalui Surat Keputusan Menteri Kehakiman Republik Indonesia No. C2-12496-HT.01.01. Th.1995.
Pada tanggal 3 Oktober 2000 PT PLN PJB I secara resmi berganti nama menjadi PT Indonesia Power sebagai penegasan atas tujuan perusahaan yang menjadi perusahaan pembangkit tenaga listrik independen yang berorientasi bisnis murni. Kegiatan utama bisnis Perusahaan saat ini yakni fokus sebagai penyedia tenaga listrik melalui pembangkitan tenaga listrik dengan total kapasitas terpasang sebesar 9.111 MW dan sebagai penyedia jasa operasi dan pemeliharaan pembangkit listrik dengan kapasitas terpasang sebesar 5.233 MW yang mengoperasikan pembangkit yang tersebar di Indonesia. Selain mengelola unit pembangkit, Indonesia Power memiliki 5 Anak Perusahaan, 1 Perusahaan Patungan dan 1 Perusahaan Asosiasi untuk mendukung strategi dan proses Bisnis Perusahaan.
“Menjadi Perusahaan energi tepercaya yang tumbuh berkelanjutan” merupakan sasaran utama Indonesia Power, sebagaimana dapat dilihat dari visi Perusahaan. Dalam upaya mewujudkan visi tersebut, Perusahaan telah menetapkan misi Indonesia Power yaitu “Menyelenggarakan bisnis pembangkitan tenaga listrik dan jasa terkait yang bersahabat dengan lingkungan”. Pada tahap selanjutnya, Perusahaan menetapkan kompetensi inti Indonesia Power yakni “Operasi dan Pemeliharaan Pembangkit serta Pengembangan Pembangkit” sebagai upaya untuk meningkatkan daya saing dan menjalankan misi Perusahaan. Guna mendukung pencapaian Visi dan Misi, Perusahaan menetapkan prinsip yang menjadi landasan dalam mengarahkan perilaku individu dan kebijakan dalam Perusahaan. Prinsip-prinsip tersebut disebut Budaya Perusahaan yang tercermin dalam “Indonesia Power Way” dengan tata nilai perusahaan yaitu “IP AkSi (Integritas, Profesional, Proaktif, Sinergi)”. Penyempurnaan proses bisnis yang lebih efektif dan efisien dilakukan melalui integrasi sistem-sistem manajemen perusahaan dengan implementasi Indonesia Power Integrated Management System (InPower IMS) yang mengintegrasikan ISO 14001 (Sistem Manajemen Lingkungan), ISO 9001 (Sistem Manajemen Mutu), ISO 31000 (Sistem Manajemen Risiko), OHSAS 18001, ISO 28001 (Sistem Manajemen Keamanan Rantai Pasokan), Malcom Baldrige, SMP (Sistem Manajemen Pengamanan), dan SMK3 (Sistem Manajemen K3), ISO 26000 (Standar Tanggung Jawab Sosial Perusahaan), ISO 55001 (Standar Manajemen Aset).
9LAPORAN STATISTIKSTATISTIC REPORT 2015
10 LAPORAN STATISTIKSTATISTIC REPORT2015
IKHTISARSUMMARY
SISTEM JAWA BALI
PENYEDIAAN TENAGA LISTRIKPada Tahun 2015, total penyediaan tenaga listrik (daya mampu netto) untuk Sistem Jawa Bali mencapai 31.663,58 MW, dengan perincian: Indonesia Power sebesar 25,99% (8.230,08 MW), UPJB sebesar 25,77% (8.161,00 MW), PT PJB sebesar 20,13% (6.374,85 MW), UB Tanjung Jati B sebesar 8,35% (2.643,80 MW) dan IPP sebesar 19,75% (6.253,85 MW).
PENGIRIMAN ENERGISelama tahun 2015, jumlah energi listrik yang dikirim ke Sistem Jawa Bali sebesar 165.993 GWh meningkat 1,11% dibandingkan tahun sebelumnya yang sebesar 164.167 GWh. Dari jumlah tersebut, 26,25% (43.575 GWh) dikirim oleh UPJB, 22,97% (38.129 GWh) dikirim oleh Indonesia Power, 15,35% (25.485 GWh) dikirim oleh PT PJB, 10,55% (17.507 GWh) dikirim oleh UB Tanjung Jati B, 0,01% (22 GWh) dikirim oleh Project dan 24,87% (41.275 GWh) dikirim oleh IPP.
INDONESIA POWER
DAYA TERPASANG PEMBANGKITJumlah daya terpasang pembangkit yang dimiliki dan dikelola oleh Indonesia Power melalui 5 Unit Pembangkitan (UP) dan 3 Unit Pembangkitan dan Jasa Pembangkitan (UPJP) di tahun 2015 untuk Sistem Jawa Bali Grid & Embedded sebesar 9.029,72 MW meningkat dari tahun sebelumnya yang sebesar 8.901,50 MW. Kenaikan kapasitas daya terpasang dikontribusi masuknya PLTDG Pesanggaran 200 MW Bali dengan status operasi secara penuh sejak bulan Mei 2015. Selain Perusahaan memiliki dan mengelola pembangkit di Jawa Bali, Perusahaan juga memiliki 3 unit pembangkit di Sumatera yang dikelola oleh Anak Perusahaan yaitu Cogindo DayaBersama (CDB) sebesar 81 MW sama dengan tahun sebelumnya. Sehingga total kapasitas terpasang pembangkit yang dimiliki Perusahaan tahun 2015 sebesar 9.110,72 MW meningkat dari tahun sebelumnya sebesar 8.982,50 MW.
JAVA BALI SYSTEM
ELECTRICITY SUPPLYIn 2015, the total of Java Bali System Electricity Supply (net maximum capacity) reached 31,663.58 MW, with details as follows: Indonesia Power by 25.99% (8,230.08 MW), UPJB by 25.77% (8,161.00 MW), PT PJB by 20.13% (6,374.85 MW), UB Tanjung Jati B by 8.35% (2,643.80 MW) and IPP by 19.75% (6,253.85 MW).
ENERGY TRANSFERREDDuring 2015, total electricity transferred to Java Bali System reached 165,993 GWh, an increase of 1.11% compared to the previous year which was 164,167 GWh. From that number, 26.25% (43,575 Gwh) was transferred by UPJB, 22.97% (38,129 GWh) was transferred by Indonesia Power, 15.35% (25,485 GWh) was transferred by PT PJB, 10.55% (17,507 GWh) was transferred by UB Tanjung Jati B, 0.01% (22 GWh) was transferred by Project and 24.87% (41,275 GWh) was transferred by IPP.
INDONESIA POWER
GENERATOR INSTALLED CAPACITYTotal installed capacity owned and managed by Indonesia Power through its 5 Generating Units (GU) and 3 Generating and Generating Services Unit (GGSU) in 2015 for the Grid & Embedded Java Bali System reached 9,029.72 MW, an increase from previous year which reached 8,901.50 MW. The increase of installed capacity was contributed by the entrance of Pesanggaran GTDPP 200 MW Bali with the operational status was fully since May 2015. Besides owning and managing power plants in Java Bali, the Company also has 3 power plant units in Sumatra which managed by its subsidiary, Cogindo DayaBersama (CDB) reached up to 81 MW in which same as last year. Therefore, total installed capacity owned by the Company in 2015 was reached 9,110.72 MW, an increase from last year which was 8,982.50 MW.
11LAPORAN STATISTIKSTATISTIC REPORT 2015
Kapasitas terpasang pembangkit terbesar milik Indonesia Power adalah UP Suralaya dengan kapasitas terpasang 3.400 MW (37,32%), kemudian UP Semarang sebesar 1.408,93 MW (15,46%), UPJP Priok sebesar 1.348,08 MW (14,80%), UP Perak Grati sebesar 864,08 MW (9,48%), UP Saguling sebesar 797,37 MW (8,75%), UPJP Bali sebesar 556,51 MW (6,11%), UPJP Kamojang sebesar 345 MW (3,79%), dan UP Mrica sebesar 309,74 MW (3,40%), PLTG Indralaya sebesar 45 MW (0,49%) serta PLTG Keramasan dan PLTG Jambi masing-masing sebesar 18 MW (0,20%).
Dalam kegiatan usaha pengelolaan jasa Operation & Maintenance pembangkit, Perusahaan mengelola pembangkit milik PLN dengan total kapasitas terpasang pembangkit sebesar 5.233 MW di tahun 2015. Kapasitas terpasang pembangkit terbesar yang dikelola oleh Perusahaan adalah UJP Pelabuhan Ratu sebesar 1.050 MW, kemudian UJP Lontar sebesar 945 MW, PLTGU Priok Blok 3 sebesar 740 MW, UJP Adipala sebesar 660 MW, UJP Suralaya sebesar 625 MW, UJP Labuhan sebesar 600 MW, UJP Pangkalan Susu sebesar 400 MW, PLTU Barru sebesar 100 MW, PLTU Jeranjang sebesar 75 MW, PLTU Sanggau sebesar 14 MW dan PLTP Ulumbu sebesar 10 MW.
Sebagai fungsi pendukung, Indonesia Power juga melakukan pembelian listrik di sebagian Area Bali dengan total kapasitas terpasang sebesar 220,90 MW menurun dari tahun sebelumnya sebesar 399,29 MW. Penurunan daya kapasitas terpasang terjadi karena berakhirnya kontrak pembelian tenaga listrik PLTD Pemaron pada bulan Juli 2014.
PRODUKSI Selama tahun 2015 melalui 5 UP dan 3 UPJP di sistem Jawa Bali Grid & Embedded, Indonesia Power telah memproduksi energi listrik sebanyak 39.126,74 GWh meningkat 4,45% dari tahun sebelumnya yang sebesar 37.461,12 GWh. Peningkatan produksi listrik Jawa Bali Grid & Embedded di kotribusi oleh beroperasi PLTGU Tambaklorok dengan berbahan bakar gas.
The biggest installed capacity of Indonesia Power was Suralaya GU by 3,400 MW (37.32%), followed by Semarang GU by 1,408.93 MW (15.46%), Priok GGSU by 1,348.08 MW (14.80%), Perak Grati GU by 864.08 MW (9.48%), Saguling GU by 797.37 MW (8.75%), Bali GGSU by 556.51 MW (6.11%), Kamojang GGSU by 345 MW (3.79%), Mrica GU by 309.74 MW (3.40%). Indralaya GTPP by 45 MW (0.49%) and also Keramasan GTPP and Jambi GTPP by 18 MW (0.20%) each.
In managing the Operation & Maintenance service of power plant, the Company managed PLN’s power plants with total installed capacity reached 5,233 MW in 2015. The biggest installed capacity managed by the Company was Pelabuhan Ratu GSU by 1,050 MW, then Lontar GSU by 945 MW, Priok Block 3 CPP by 740 MW, Adipala GSU by 660 MW, Suralaya GSU by 625 MW, Labuhan GSU by 600 MW, Pangkalan Susu GSU by 400 MW, Barru SPP by 100 MW, Jeranjang SPP by 75 MW, Sanggau SPP by 14 MW and Ulumbu GPP by 10 MW.
As a support function, Indonesia Power also purchased electricity in several areas of Bali with total installed capacity was 220.90 MW, a decrease compared to previous year which was 399.29 MW. The decreasing in installed capacity was due to contract termination of electricity purchase of Pemaron DPP in July 2014.
PRODUCTIONIn 2015, through its 5 GU and 3 GGSU in Grid & Embedded Java Bali System, Indonesia Power has produced electricity by 39,126.74 GWh, an increase of 4.45% compared to previous year of 37,461.12 GWh. The increase in electricity production of Java Bali Grid & Embedded was contributed by the operation of Tambaklorok CPP with gas fuel.
12 LAPORAN STATISTIKSTATISTIC REPORT2015
Sedangkan realisasi produksi listrik dari hasil Pembelian listrik di sebagian Area Bali sebesar 603,37 GWh menurun 75,02% dari tahun sebelumnya sebesar 2.415,03 GWh. Penurunan produksi dari hasil Pembelian listrik di Area Bali terjadi karena berakhirnya kontrak pembelian tenaga listrik PLTD A, C, D Pesanggaran.Sehingga total produksi listrik yang dihasilkan Indonesia Power tahun 2015 sebesar 39.730,12 GWh menurun 0,37% dari tahun sebelumnya sebesar 39.876,15 GWh.
Dari total produksi energi listrik yang dihasilkan pada tahun 2015, produksi listrik terbesar dihasilkan oleh UP Suralaya sebesar 23.528,45 GWh, kemudian UPJP Priok sebesar 3.434,65 GWh, UPJP Kamojang sebesar 2.892,87 GWh, UP Semarang sebesar 2.562,61 GWh, UP Saguling sebesar 2.497,13 GWh, UP Perak Grati sebesar 2.452,32 GWh, UP Mrica sebesar 897,87 GWh, UPJP Bali sebesar 860,85 GWh dan pembelian listrik Area Bali sebesar 603,37 MW.
Berdasarkan jenis pembangkit, PLTU mencapai produksi tertinggi sebesar 23.528,45 GWh, kemudian PLTGU sebesar 8.271,98 GWh, PLTA sebesar 3.395 GWh, PLTP sebesar 2.892,87 GWh, PLTG sebesar 615,73 GWh, PLTD sebesar 603,40 GWh dan PLTDG sebesar 422,69 GWh.
PENJUALANEnergi listrik yang telah disalurkan Indonesia Power ke Sistem Jawa Bali Grid & Embedded selama tahun 2015 sebanyak 37.408,37 GWh, meningkat 4,22% dari tahun sebelumnya sebesar 35.892,42 GWh. Kenaikan penjualan energi listrik Jawa Bali Grid & Embedded tahun 2015 dibandingkan 2014, seperti disampaikan pada penjelasan penurunan produksi energi listrik.
Sedangkan realisasi penjualan listrik dari hasil Pembelian listrik di sebagian Area Bali sebesar 602,74 GWh menurun 74,97% dari tahun sebelumnya sebesar 2.407,60 GWh. Penjelasan penurunan produksi dari hasil Pembelian listrik di Area Bali seperti disampaikan pada penjelasan penurunan produksi energi listrik.
Meanwhile, the actual electricity production from the purchase of electricity in several areas of Bali which was 603.37 GWh experienced a decrease of 75.02% from the previous year which was 2,415.03 GWh. The decline in production from electricity purchase in Bali area occurred due to the purchase contract termination in Pesanggaran A, C, D DPP. So that the total production of electricity generated by Indonesia Power in 2015 amounted to 39,730.12 GWh, a decrease of 0.37% from the previous year at 39,876.15 GWh.
From the total production of electrical energy produced in 2015, the biggest electricity production was produced by Suralaya GU by 23,528.45 GWh, followed by Priok GGSU by 3,434.65 GWh, Kamojang GGSU by 2,892.87 GWh, Semarang GU by 2,562.61 GWh, Saguling GU by 2,497.13 GWh, Perak Grati GU by 2,452.32 GWh, Mrica GU by 897.87 GWh, Bali GGSU by 860.85 GWh and electricity purchase in Bali area was 603.37 MW.
Based on power plant type, SPP has attained the biggest production by 23,528.45 GWh, followed by CPP by 8,271.98 GWh, HPP by 3,395 GWh, GPP by 2,892.87 GWh, GTPP by 615.73 GWh, DPP by 603.40 GWh and GTDPP by 422.69 GWh.
SALESThe electricity distributed by Indonesia Power to Grid & Embedded Java Bali System in 2015 was 37,408.37 GWh, an increase of 4.22% from previous year of 35,892.42 GWh. The increase in sales of electrical energy and Java Bali Grid & Embedded in 2015 compared to 2014, was as stated in the explanation of the decline in production of electrical energy.
Meanwhile, the actual electricity sales from the purchase of electricity in several areas of Bali which was 602.74 GWh experienced a decrease of 74.97% from the previous year which was 2,407.60 GWh. The explanation of the decline in production from the purchase of electricity in Bali area was referred to the explanation of the decline in production of electric energy.
13LAPORAN STATISTIKSTATISTIC REPORT 2015
So that the total sales of electricity generated by Indonesia Power in 2015 amounted to 38,011.11 GWh, a decrease by 0.75% from the previous year which was 38,300.02 GWh.
From the total electrical energy distributed in 2015, Suralaya GU has distributed the largest electricity by 22,206.08 GWh, followed by Priok GGSU by 3,366.03 GWh, Saguling GU by 3,150.71 GWh, Kamojang GGSU by 2,759.19 GWh, Saguling GU by 2,490.67 GWh, Semarang GU by 2,477.34 GWh, Perak Grati GU by 2,382.01 GWh, Mrica GU by 883.11 GWh, Bali GGSU by 843.94 GWh and the electricity purchase in Bali area by 602.74 MW.
Based on power plant type, SPP has attained the biggest sales by 22,201.18 GWh, followed by CPP by 8,054.36 GWh, HPP by 3,373.79 GWh, GPP by 2,759.19 GWh, GTPP by 606.35 GWh, and DPP 602.75 GWh and GTDPP by 413.40 GWh.
SELF CONSUMPTIONThe self-consumption of Java Bali Grid & Embedded of Indonesia Power in 2015 reached 4.39% it was not better than the previous year which was 4.19%. The realization of PS in 2015 was not better than in 2014, mainly from the derating in Suralaya SPP. From the total self-consumption in 2015, Suralaya GU was the largest self-consumption of the electricity which was 5.62%, followed by Kamojang GGSU by 4.62%, Semarang GU by 3.33%, Perak Grati GU by 2.87%, Priok GGSU by 2%, Bali GGSU by 1.96%, Mrica GU by 1.64% and Saguling GU by 0.26%.
Based on the types, steam power plants consume the most electricity for own use amounted to 5.64%, DPP by 4.62%, CPP by 2.63%, GTDPP by 2.20%, GTPP by 1.52% and HPP by 0.62%.
FUEL CONSUMPTIONFuel consumption calculated was the usage fuel to generate electrical energy. During 2015, there was an increase in fuel
Sehingga total penjualan listrik yang dihasilkan Indonesia Power tahun 2015 sebesar 38.011,11 GWh menurun 0,75% dari tahun sebelumnya sebesar 38.300,02 GWh.
Dari total energi listrik yang disalurkan pada tahun 2015, UP Suralaya menyalurkan energi terbesar sebanyak 22.206,08 GWh, kemudian UPJP Priok sebesar 3.366,03 GWh, UPJP Kamojang sebesar 2.759,19 GWh, UP Saguling sebesar 2.490,67 GWh, UP Semarang sebesar 2.477,34 GWh, UP Perak Grati sebesar 2.382,01 GWh, UP Mrica sebesar 883,11 GWh, UPJP Bali sebesar 843,94 GWh dan pembelian listrik Area Bali sebesar 602,74 MW.
Berdasarkan jenis pembangkit, PLTU mencapai penjualan tertinggi sebesar 22.201,18 GWh, kemudian PLTGU sebesar 8.054,36 GWh, PLTA sebesar 3.373,79 GWh, PLTP sebesar 2.759,19 GWh, PLTG sebesar 606,35 GWh, PLTD sebesar 602,75 GWh dan PLTDG sebesar 413,40 GWh.
PEMAKAIAN SENDIRIUntuk jumlah pemakaian sendiri Jawa Bali Grid & Embedded Indonesia Power di tahun 2015 sebesar 4,39% tidak lebih baik dari tahun sebelumnya sebesar 4,19%. Realisasi PS tahun 2015 tidak lebih baik dibandingkan dengan tahun 2014 terutama dari derating di PLTU suralaya. Dari total pemakaian sendiri tahun 2015, UP Suralaya adalah unit yang paling banyak mengkonsumsi energi listrik untuk pemakaian sendiri yaitu sebesar 5,62%, kemudian UPJP Kamojang sebesar 4,62%, UP Semarang sebesar 3,33%, UP Perak Grati sebesar 2,87%, UPJP Priok sebesar 2%, UPJP Bali sebesar 1,96%, UP Mrica sebesar 1,64% dan UP Saguling sebesar 0,26%.
Berdasarkan jenis pembangkit di sistem PLTU yang paling banyak mengkonsumsi energi listrik untuk pemakaian sendiri sebesar 5,64%, PLTP sebesar 4,62%, PLTGU sebesar 2,63%, PLTDG sebesar 2,20%, PLTG sebesar 1,52% dan PLTA sebesar 0,62%.
PEMAKAIAN BAHAN BAKARPemakaian bahan bakar yang dihitung merupakan pemakaian bahan bakar untuk menghasilkan energi listrik. Selama tahun
14 LAPORAN STATISTIKSTATISTIC REPORT2015
2015, terjadi kenaikan pemakaian bahan bakar batubara dan gas sedangkan penurunan pemakaian bahan bakar terjadi pada BBM (HSD dan MFO) dibandingkan tahun sebelumnya. Untuk pemakaian batubara mencapai 12.168.482 ton atau meningkat 5,24% dari tahun sebelumnya sebesar 11.562.704 dan, pemakaian gas mencapai 76.851.477 MMBTU atau meningkat 22,30% dari tahun sebelumnya sebesar 62.838.572 MMBTU. Peningkatan pemakaian batubara dan gas sejalan dengan program perusahaan dalam pengembangan pembangkit Non BBM dan kebijakan pemerintah terkait penghematan BBM. Sedangkan pemakaian HSD sebesar 326.944 kiloliter atau menurun 57,98% dari tahun sebelumnya sebesar 778.070 kiloliter dan pemakaian jenis MFO sebesar 100.804 kiloliter atau menurun 16,98% dari tahun sebelumnya sebesar 121.422 kiloliter.
KINERJA OPERASIONALFaktor keandalan pembangkit Indonesia Power yang tercermin pada Equivalent Availability Factor (EAF) di tahun 2015 sebesar 90,85% atau meningkat 1,08% dari tahun sebelumnya yang sebesar 89,88%. Ketercapaian kinerja EAF disebabkan oleh keberhasilan unit-unit pembangkit, seperti UPJP Priok, UP Perak Grati dan UP Suralaya dalam menjaga keandalan pembangkit dan penerapan asset management. Faktor efisiensi pembangkit Capacity Factor (CF) selama tahun 2015 sebesar 51,89% atau meningkat 3,43% dari tahun sebelumnya sebesar 50,17%.
KEUANGANPada tahun 2015, jumlah aktiva Indonesia Power mengalami peningkatan sebesar 325,34% menjadi Rp226,49 triliun dibandingkan tahun sebelumnya sebesar Rp53,25 triliun. Peningkatan aktiva perusahaan sebagai dampak dilakukannya revaluasi aset di tahun 2015. Untuk jumlah laba tahun berjalan yang dibukukan Perusahaan tahun 2015 mengalami peningkatan 184,08% menjadi Rp4,68 triliun dari tahun sebelumnya sebesar Rp1,65 triliun. Peningkatan jumlah laba tahun berjalan disebabkan oleh adanya dampak revaluasi aset, dimana revaluasi aset diakui di tahun yang sama baik dari komersial maupun fiskal sehingga menambah pendapatan pajak tangguhan. Di sisi pendapatan usaha Perusahaan tahun 2015 mencapai Rp32,00 triliun yang sebagian besar dikontribusi dari pendapatan penjualan energi listrik yang mencapai Rp30,68 triliun. Pencapaian pendapatan usaha di tahun 2015 menurun 10,37% dari tahun sebelumnya yang sebesar Rp35,72 triliun. Penurunan pendapatan usaha selaras dengan penurunan produksi dan penjualan listrik.
KEPEGAWAIANJumlah pegawai aktif Indonesia Power di tahun 2015 mencapai 3.639 pegawai, meningkat 2,42% dibandingkan tahun sebelumnya yang sebesar 3.553 pegawai. Komposisi pegawai terbanyak berada di UP Suralaya dengan prosentase 19,84% dari total pegawai, 22,51% pegawai berusia dibawah 26 tahun, 46,72% pegawai berjenjang pelaksana, 89,83% pegawai berjenis kelamin pria dan 43,45% pegawai berpendidikan SMK.
consumption of coal and gas while a decrease occurred in fuel consumption (HSD and MFO) compared to the previous year. For coal consumption reached 12,168,482 tons or increased by 5.24% from the previous year of 11,562,704 and, the use of gas reached 76,851,477 MMBTU, an increase of 22.30% from the previous year of 62,838,572 MMBTU. The increasing usage of coal and gas was in line with the Company’s program in the development of non-fuel plants and government policy related to fuel savings. While HSD usage was amounted to 326,944 kiloliters, a decrease of 57.98% from the previous year of 778,070 kiloliters and MFO usage was amounted to 100,804 kiloliters, a decrease of 16.98% from previous year of 121,422 kiloliters.
OPERATIONAL PERFORMANCEThe reliability factor of Indonesia Power which reflected by Equivalent Availability Factor (EAF) 90.85% in 2015, increase 1.08% compared to the previous year which was 89.88%. The accomplishment of EAF was supported by the achievement of power plant units, as Priok GGSU, Perak Grati GU and Suralaya GU in maintaining plant reliability and improving asset management. The power plant efficiency of Capacity Factor (CF) in 2015 by 51.89% or increased 3.43% compared to previous year of 50.17%.
REVENUETotal assets of Indonesia Power in 2015 an increase 325.34% to Rp226.49 trillion compared to previous year of Rp53.25 trillion. The increasing of Company’s asset was due to asset revaluation in 2015. Total income for the year booked in 2015 increased 184.08% by Rp4.68 trillion compared to previous year of Rp1.65 trillion. The increment of total income for the year was due to the asset revaluation impact, where asset revaluation of the year was approved, both from commercial and fiscal, which in return increase the income from deferred tax. The Company’s revenue in 2015 was Rp32.00 trillion, which mainly contributed by income from electricity sales of Rp30.68 trillion. Revenue in 2015 decreased by 10.37% compared to previous year of Rp35.72 trillion. The decrement of the revenue was in line with the decrease of electricity production and sales.
HUMAN RESOURCESThe total number of Indonesia Power’s employees in 2015 reached 3,639 employees, an increase of 2.42% compared to previous year of 3,553 employees. Main composition of the employee was in Suralaya GU with the percentage of 19.84% of the total employees in which 22.51% were below 26 years old, 46.72% were in managerial level, 89.83% were men and 43.45% were High School graduate.
SistemJawa BaliJava Bali
System
SISTEM JAWA BALI JAVA BALI SYSTEM16 LAPORAN STATISTIK
STATISTIC REPORT2015
2011 2012 2013 2014 2015
PT Indonesia Power PT PJB Muara Tawar UB Tanjung Jati UB Cilegon UB Lontar UB Indramayu IPP UPJB Sistem Jawa Bali/Java Bali System
8.19
2,67
7.98
1,62
8.0
47,6
2
8.16
7,27
8.2
30,0
8
6.32
4,00
6.32
4,00
6.32
3,85
6.38
4,00
6.3
74,8
5
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1.98
3,00
2.64
4,00
2.64
3,80
2.64
3,80
2.64
3,80
1.80
9,00
560,
00
615,
00
883,
00
870,
004.
191,
00 5.66
7,05
5.78
4,95
5.84
0,85
6.25
3,85
5.72
4,00
23.9
29,6
7
28.9
55,6
7
30.0
22,2
2
31.1
96,9
2
31.
663,
58
6.3
39,0
0
8.16
1,00
8.16
1,00
PENYEDIAAN TENAGA LISTRIKELECTRICITY SUPPLY
Tabel Table
01Penyediaan Tenaga Listrik Sistem Jawa Bali Tahun 2011-2015Electricity Supply of Java Bali System in 2011-2015
PerusahaanCompany
Tahun | Year2011 2012 2013 2014 2015
MW (%) MW (%) MW (%) MW (%) MW (%)
PT Indonesia Power 8.192,67 34,24 7.981,62 27,56 8.047,62 26,81 8.167,27 26,18 8.230,08 25,99 PT PJB 6.324,00 26,43 6.324,00 21,84 6.323,85 21,06 6.384,00 20,46 6.374,85 20,13 UB Tanjung Jati B 1.983,00 8,29 2.644,00 9,13 2.643,80 8,81 2.643,80 8,47 2.643,80 8,35 UB Cilegon * 1.809,00 7,56 - - - - - - - UB Lontar ** 560,00 2,34 615,00 2,12 883,00 2,94 - - - - UB Indramayu * 870,00 3,64 - - - - - - - - IPP *** 4.191,00 17,51 5.667,05 19,57 5.784.95 19,27 5.840,85 18,72 6.253,85 19,75 UPJB - - 5.724,00 19,77 6.339,00 21,11 8.161,00 26,16 8.161,00 25,77
Sistem Jawa BaliJava Bali System 23.929,67 100 28.955,67 100 30.022,22 100 31.196,92 100 31.663,58 100
Keterangan * UB Indramayu dan UB Cilegon masuk ke UPJB pada tahun 2012 ** Pada tahun 2013, UB Lontar meliputi PLTU Pacitan, Pelabuhan ratu, dan Tanjung
Awar-awar dan di tahun 2014 UB Lontar masuk ke dalam UPJB *** Tahun 2015 telah masuk PLTP Kamojang 5 dan PLTU Celukan Bawang (IPP)
Notes * UB Indramayu and UB Cilegon were operated by UPJB in 2012** In 2013, UB Lontar which including Pacitan SPP, Pelabuhan ratu SPP, and Tanjung
Awar-awar SPP and also in 2014 UB Lontar were operated by UPJB*** In 2015, Kamojang 5 GPP and Celukan Bawang SPP were being operated
Grafik Graph
01Penyediaan Tenaga Listrik Sistem Jawa Bali Tahun 2011-2015 (MW)Electricity Supply of Java Bali System in 2011-2015 (MW)
SISTEM JAWA BALI JAVA BALI SYSTEM 17LAPORAN STATISTIK
STATISTIC REPORT 2015
SISTEM JAWA BALI JAVA BALI SYSTEM18 LAPORAN STATISTIK
STATISTIC REPORT2015
Unit Pembangkit Generating Unit
Mesin Pembangkit | Power Plant Jumlah Unit
Total of Unit
Jumlah Kapasitas Total of Capacity
1 2 3 4 5 6 7 8 9 10 11
Kapasitas (MW) | Capacity (MW)
UP Muara Karang 718,00 Muara Karang PLTU-M
SPP-F 162,00 162,00 2 324,00
PLTU-GSPP-G
PLTGU-MCPP-F
90,00 90,00 90,00 124,00 4 394,00
PLTGU-GCPP-G
UP Muara Tawar 12 1.740 1.729,00 Muara Tawar Blok 1 PLTGU-M
CPP-F137,00 137,00 137,00 204,00 4 615,00
PLTGU-GCPP-G
Muara Tawar Blok 2 PLTGU-MCPP-F
137,00 137,00 2 274,00
PLTGU-G CPP-G
Muara Tawar Blok 3&4 PLTGU-MCPP-F
140,00 140,00 140,00 140,00 140,00 140,00 6 840,00
PLTGU-G CPP-G
UP Gresik 18 3.200 1.971,00
Gresik PLTG-MGTPP-F
15,50 15,50 2 31,00
PLTU-MSPP-F
80,00 80,00 170,00 170,00 4 500,00
PLTU-GSPP-G
GRBRU G PLTGUCPP
100,00 100,00 100,00 100,00 100,00 100,00 100,00 100,00 100,00 9 900,00
GRBRU S PLTGUCPP
180,00 180,00 180,00 3 540,00
GLTMR PLTGGTPP
Sutami 102,99
Sutami PLTAHPP
34,33 34,33 34,33 3 102,99
UP Brantas 25 232 157,87
Wlingi PLTAHPP
26,81 26,81 2 53,62
Lodoyo PLTAHPP
4,46 1 4,46
Selorejo PLTAHPP
4,71 1 4,71
Sengguruh PLTAHPP
14,23 14,23 2 28,46
Tulungagung PLTAHPP
17,86 17,86 2 35,72
Mendalan PLTAHPP
4,20 5,50 5,50 5,50 4 20,70
Siman PLTAHPP
3,40 3,40 3,40 3 10,20
Area IV 7,99 Giringan PLTA | HPP 0,88 0,88 1,40 3 3,16
Golang PLTA | HPP 0,89 0,89 0,89 3 2,67
Ngebel PLTA | HPP 2,16 1 2,16
UP Cirata 948,00
Cirata PLTA | HPP 118,50 118,50 118,50 118,50 118,50 118,50 118,50 118,50 8 948,00
UP Paiton 740,00 Paiton PLTU-B
SPP-C370,00 370,00 2 740,00
PLTU-M SPP-F
Jumlah | Total 1.344,93 1.334,90 981,02 1,024,00 657,50 495,50 218,50 218,50 100,00 - - 6.374,85
Tabel Table
02Penyediaan Tenaga Listrik PT PJB (MW) Tahun 2015Electricity Supply of PT PJB (MW) in 2015
SISTEM JAWA BALI JAVA BALI SYSTEM 19LAPORAN STATISTIK
STATISTIC REPORT 2015
Unit Pembangkit Generating Unit
Mesin Pembangkit | Power PlantJumlah UnitTotal of Unit
Jumlah Kapasitas Total of Capacity
1 2 3 4 5 6 7 8 9 10 11 12
Kapasitas (MW) | Capacity (MW)Perum Jasa Tirta II 180,00 Jatiluhur PLTA | HPP 30,00 30,00 30,00 30,00 30,00 30,00 6 180,00
PT Geo Dipa Energy 100,00 Dieng PLTP | GPP 45,00 1 45,00
Patuha PLTP | GPP 55,00 1 55,00
PT Dayabumi Salak Pratama Ltd 183,00 Salak PLTP | GPP 61,00 61,00 61,00 3 183,00PT Magma Nusantara Listrindo 225,16 Wayangwindu PLTP | GPP 112,06 113,10 2 225,16Chevron Texaco Energy Indonesia Ltd 196,04 Drajat II PLTP | GPP 90,24 1 90,24 Drajat III PLTP | GPP 105,80 1 105,80PT Paiton Energy (PEC) 2.035,00 Paiton 7,8 PLTU-B | SPP-C 815,00 610,00 610,00 3 2.035,00
PT Jawa Power 1.220,00 Paiton 5,6 PLTU-B | SPP-C 610,00 610,00 2 1.220,00 PT Cikarang Listrindo Power Company 300,00 Cikarang PLTG-G I GTPP - G 300,00 1 300,00PT Krakatau Daya Listrik Krakatau PLTU-B | SPP-C PT Sumberenergi Sakti Prima 562,00 Cilacap PLTU-B | SPP-C 281,00 281,00 2 562,00PT Pertamina 93,85 Kamojang IV PLTP | GPP 60,85 33,00 2 93,85
CEP 660,00Cirebon PLTU-B | SPP-C 660,00 1 660,00
Bekasi Power 118,80Bekasi Power PLTGU | CPP 118,80 1 118,80
PT General Energy Bali 380,00Celukan Bawang PLTGU | CPP 125,00 12,005 130,00 1 380,00
Jumlah | Total 1601,86 514,34 950,80 151,85 734,00 701,00 610,00 610,00 - - - - 6.253,85
Tabel Table
03Penyediaan Tenaga Listrik Tanjung Jati B dan UPJB Tahun 2015Electricity Supply of Tanjung Jati B and UPJB in 2015
Tabel Table
04Penyediaan Tenaga Listrik IPP Tahun 2015 Electricity Supply of IPP in 2015
Unit Pembangkit Generating Unit
Mesin Pembangkit | Power PlantJumlah UnitTotal of Unit
Jumlah Kapasitas Total of Capacity
1 2 3 4 5 6 7 8 9 10 11
Kapasitas (MW) | Capacity (MW)
Tanjung Jati B PLTU-B | SPP-C 660,80 660,80 661,10 661,10 4 2.643,80 UPJB 8.161,00
Pelabuhan Ratu PLTU-B | SPP-C 323,00 323,00 323,00 3 969,00 Pacitan PLTU-B | SPP-C 280,00 280,00 2 560,00 Tanjung Awar-awar PLTU-B | SPP-C 323,00 1 323,00 Suralaya 8 PLTU-B | SPP-C 590,00 1 590,00 Labuan PLTU-B | SPP-C 280,00 280,00 2 560,00 Rembang PLTU-B | SPP-C 280,00 280,00 2 560,00 Lontar PLTU-B | SPP-C 280,00 280,00 280,00 3 840,00 Priok Blok 3 PLTGU-G | CPP-G 235,00 235,00 250,00 3 720,00 Cilegon PLTGU-G | CPP-G 212,00 212,00 236,00 3 660,00 Indramayu PLTU | SPP 290,00 290,00 290,00 3 870,00 Muara Karang Repowering PLTGU | CPP 235,00 235,00 70,00 70,00 70,00 5 680,00
Muara Tawar Blok 5 PLTGU | CPP 143,00 71,00 2 214,00 Paiton 9 PLTU-B | SPP-C 615,00 1 615,00
Jumlah | Total 2.881,00 2.486,00 1.449,00 70,00 70,00 - - 590,00 615,00 - - 10.804,80 Keterangan: * Pada tahun 2014, UB Lontar yang meliputi PLTU Pacitan, Palabuhan Ratu, dan Tanjung Awar-
awar masuk ke dalam UPJB
Notes:* In 2014, UB Lontar which including Pacitan SPP, Pelabuhan Ratu SPP, and Tanjung Awar-awar SPP were operated by UPJB
SISTEM JAWA BALI JAVA BALI SYSTEM20 LAPORAN STATISTIK
STATISTIC REPORT2015
PENGIRIMAN ENERGIENERGY TRANSFER
2011 2012 2013 2014 2015
PT Indonesia Power PT PJB UB Tanjung Jati UB Cilegon UB Lontar UB Indramayu IPP UPJB Sistem Jawa Bali | Java Bali System Project
43.2
27
37.
936
40.
608
37.9
28
38.1
29
31.
940
0 0 00 0 00 00 0 00 0 0 220
26.6
72
27.
549
29.7
42
25.4
85
12.5
94 17.
011
18.5
49
18.1
32
17.5
07
9.90
54.
341
2.03
6
2.95
7
3.22
9 2
9.22
5
134
.461 14
5.91
0
156
.398
164.
167
165
.993
36.
655
38.4
61
39.
563
41.2
75
25.
600
28.2
74
38.8
01
43.5
75
PerusahaanCompany
Tahun | Year2011 2012 2013 2014 2015
GWh (%) GWh (%) GWh (%) GWh (%) GWh (%)PT Indonesia Power 43.227 32,15 37.936 26,00 40.608 25,96 37.928 23,10 38.129 22,97 PT PJB 31.940 23,75 26.672 18,28 27.549 17,61 29.742 18,12 25.485 15,35 UB Tanjung Jati B 12.594 9,37 17.011 11,66 18.549 11,86 18.132 11,04 17.507 10,55 UB Cilegon * 9.905 7,37 - - - - - - - - UB Lontar ** 4.341 3,23 2.036 1,40 2.957 1,89 - - - - UB Indramayu * 3.229 2,40 - - - - - - - - IPP 29.225 21,73 36.655 25,12 38.461 24,59 39.563 24,10 41.275 24,87 UPJB - - 25.600 17,55 28.274 18,08 38.801 23,64 43.575 26,25 Project *** - - - - - - - - 22 0,01 Sistem Jawa Bali Java Bali System
134.461 100 145.910 100 156.398 100 164.167 100 165.993 100
Keterangan: * UB Indramayu dan UB Cilegon masuk ke UPJB pada tahun 2012 ** Pada tahun 2013, UB Lontar meliputi PLTU Pacitan, Pelabuhan Ratu, dan Tanjung Awar-awar dan di tahun 2014 UB Lontar masuk ke dalam UPJB *** Penerimaan Tanjung Awar-awar unit 2 pada saat masih project
Note: * UB Indramayu and UB Cilegon was operated by UPJB in 2012 ** In 2013, UB Lontar including Pacitan SPP, Pelabuhan Ratu SPP and Tanjung Awar-awar SPP and also UB Lontar in 2014 were operated by UPJB *** The acceptance of Tanjung Awar-awar unit 2 while in project period
Grafik Graph
02Pengiriman Energi ke Sistem Jawa Bali Tahun 2011-2015 (GWh)Energy Transferred to Java Bali System in 2011-2015 (GWh)
Tabel Table
05Pengiriman Energi ke Sistem Jawa Bali Tahun 2011-2015Energy Transferred to Java Bali System in 2011-2015
SISTEM JAWA BALI JAVA BALI SYSTEM 21LAPORAN STATISTIK
STATISTIC REPORT 2015
SISTEM JAWA BALI JAVA BALI SYSTEM22 LAPORAN STATISTIK
STATISTIC REPORT2015
Realisasi | Realization2014
Realisasi | Realization2015
Rencana | Plan2016
PT Indonesia Power PT PJB UB Tanjung Jati IPP UPJB Sistem Jawa Bali | Java Bali System Project
37.
928
29.7
42
18.1
3239
.563
3
8.80
1
164
.167
38.1
29
25.4
85
17.5
0741
.275
43
.575
165.
993
175.
692
51.
460
45.3
4419
.20823.4
62 36.
215
00 22
PerusahaanCompany
Realisasi Realization
(GWh)
RencanaPlan
(GWh)
Realisasi Realization
(GWh)
PencapaianAchievement
(%)
Rencana**Plan
(GWh)
Pertumbuhan(%)
Growth
2014 2015 2016 2014 2015
PT Indonesia Power 37.928 39.701 38.129 104,12 36.215 (6,60) 0,53
PT PJB 29.742 28.638 25.485 112,37 23.462 7,96 (14,31)
UB Tanjung Jati B 18.132 19.477 17.507 111,25 19.208 (2,25) (3,45)
IPP 39.563 43.260 41.275 104,81 45.344 2,87 4,33
UPJB 38.801 46.541 43.575 106,81 51.460 37,23 12,30
Project* - - 22 - - - -
Sistem Jawa Bali | Java Bali System 164.167 177.617 165.993 107,00 175.692 4,97 1,11
Keterangan: * Penerimaan Tanjung Awar-awar unit 2 pada saat masih project** Data Rencana menggunakan Rencana Operasi Tahunan (ROT)
Note: * The acceptance of Tanjung Awar-awar unit 2 while in project period** Data Plan based on Annual Operating Plan
Grafik Graph
03Realisasi Pengiriman Energi ke Sistem Jawa Bali Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Realization of Energy Transferred to Java Bali System in 2014-2015 and Plan of 2016 (GWh)
Tabel Table
06Realisasi Pengiriman Energi ke Sistem Jawa Bali Tahun 2014-2015 dan Rencana Tahun 2016Realization of Energy Transferred to Java Bali System in 2014-2015 and Plan of 2016
Daya Terpasang
Installed Capacity
DAYA TERPASANGINSTALLED CAPACITY24 LAPORAN STATISTIK
STATISTIC REPORT2015
DAYA TERPASANGINSTALLED CAPACITY
Tabel Table
07Daya Terpasang Pembangkit yang dimiliki Perusahaan Tahun 2011-2015Installed Capacity of Units Owned by the Company in 2011-2015
Grafik Graph
04Daya Terpasang Pembangkit yang dimiliki Perusahaan Tahun 2011-2015Installed Capacity of Units Owned by the Company in 2011-2015
PLTD | DPP PONTIANAK
PLTG | GTPPINDRALAYA 1
PLTG | GTPP JAMBI
PLTG | GTPP KERAMASAN
UPJP | GGSU BALI
UP | GU PERAK GRATI
UP | GU SEMARANG
UP | GU MRICA
UPJP | GGSU KAMOJANG
UP | GU SAGULING
UPJP | GGSU PRIOK
UP | GUSURALAYA
3.40
0,00
3.
400,
00
3.40
0,00
3.
400,
00
3.40
0,00
1.34
8,08
1.34
8,08
1.34
8,08
1.34
8,08
1.34
8,08
797,
36
797,
36
797,
36
797,
36
797,
37
375,
0037
5,00
375,
0037
5,00
345,
00
309,
7530
9,74
309,
7430
9,74
309,
75
864,
0886
4,08
864,
0886
4,08
864,
08
20,1
0 20
,10
18,0
018
,00
18,0
0
20,1
020
,10
18,0
0 18
,00
18,0
0
48,8
048
,80
45,0
045
,00
45,0
0
13,0
013
,00
0 0 0
432,
6743
2,67
432,
6739
8,31 5
56,5
1
1.46
9,16
1.40
8,93
1.40
8,93
1.40
8,93
1.40
8,93
2011 2012 2013 2014 2015
Unit PembangkitGenerating Unit
2011 2012 2013 2014 2015 MW % MW % MW % MW % MW %
UP | GU SURALAYA *) 3.400,00 37,37 3.400,00 37,62 3.400,00 37,71 3.400,00 37,85 3.400,00 37,32 UPJP | GGSU PRIOK *) 1.348,08 14,82 1.348,08 14,92 1.348,08 14,95 1.348,08 15,01 1.348,08 14,80 UP | GU SAGULING *) 797,36 8,76 797,36 8,82 797,36 8,84 797,36 8,88 797,37 8,75 UPJP | GGSU KAMOJANG *) 375,00 4,12 375,00 4,15 375,00 4,16 375,00 4,17 345,00 3,79 UP | GU MRICA *) 309,75 3,40 309,74 3,43 309,74 3,44 309,74 3,45 309,75 3,40 UP | GU SEMARANG *) 1.469,16 16,15 1.408,93 15,59 1.408,93 15,63 1.408,93 15,69 1.408,93 15,46 UP | GU PERAK GRATI *) 864,08 9,50 864,08 9,56 864,08 9,58 864,08 9,62 864,08 9,48 UPJP | GGSU BALI *) 432,67 4,76 432,67 4,79 432.67 4,80 398.31 4,43 556,51 6,11 PLTG | GTPP KERAMASAN **) 20,10 0,22 20,10 0,22 18,00 0,20 18,00 0,20 18,00 0,20 PLTG | GTPP JAMBI **) 20,10 0,22 20,10 0,22 18,00 0,20 18,00 0,20 18,00 0,20 PLTG | GTPP INDRALAYA 1 **) 48,80 0,54 48,80 0,54 45,00 0,50 45,00 0,50 45,00 0,49 PLTD | DPP PONTIANAK 13,00 0,14 13,00 0,14 - - - - - - TOTAL 9.098,10 100,00 9.037,86 100,00 9.016,86 100,00 8.982,50 100,00 9.110,72 100,00 *) Indonesia Power bertindak sebagai pemilik aset (asset owner) dan pengelola aset (asset manager dan
asset operator) pembangkit tersebut**) Indonesia Power bertindak sebagai pemilik aset (asset owner) pembangkit tersebut sedangkan
pengelola aset (asset manager dan asset operator) pembangkit dilakukan oleh Anak Perusahaan yaitu PT Cogindo DayaBersama
*) Indonesia Power acted as the asset owner, asset manager and asset operator of the power plant
**) Indonesia Power acted as the asset owner of the power plant while asset manager and asset operator of the power plant were conducted by subsidiaries namely PT Cogindo DayaBersama
DAYA TERPASANGINSTALLED CAPACITY 25LAPORAN STATISTIK
STATISTIC REPORT 2015
Tabel Table
08Daya Terpasang Pembangkit yang Dikelola Perusahaan Tahun 2011-2015Installed Capacity of Units Managed by the Company in 2011-2015
Grafik Graph
05Daya Terpasang Pembangkit yang Dikelola Perusahaan Tahun 2011-2015 (MW)Installed Capacity of Units Managed by the Company in 2011-2015 (MW)
2011 2012 2013 2014 2015
PLTP | GPP ULUMBU
PLTU J | SPP JERANJANG
PLTU | SPP BARRU
PLTU | SPP SANGGAU
UJP PLTU | SPP GSU PANGKALAN SUSU
PLTGU | CPPPRIOK BLOK 3
UJP PLTU | SPP GSU JAWA TENGAH 2 CENTRAL JAVA 2
ADIPALA
UJP PLTU | SPP GSU JAWA BARAT 2 | WEST JAVA 2
PELABUHAN RATU
UJP PLTU | SPP GSU BANTEN 3 LONTAR
UJP PLTU | SPP GSU BANTEN 2 LABUHAN
UJP PLTU | SPP GSU BANTEN 1 SURALAYA
625,
00
625,
00
625,
00
625,
00
625,
00
600
,00
600
,00
600
,00
600
,00
945,
0094
5,00
945,
0094
5,00
945,
00
1.05
0,00
1.05
0,00
1.05
0,00
1.05
0,00
1.05
0,00
660,
0066
0,00
660,
0066
0,00
660,
00
740,
0074
0,00
740,
0074
0,00
740,
00
400,
00
14,0
0 14
,00
14,0
0
100,
00
10,0
010
,00
5,00
100,
0010
0,00
25,0
0 75,0
075
,00
400,
0040
0,00
00 00 00 00 00
600
,00
Unit PembangkitGenerating Unit
2011 2012 2013 2014 2015
MW % MW % MW % MW % MW % UJP PLTU | SPP GSU BANTEN 1 SURALAYA 625,00 13,53 625,00 13,53 625,00 12,07 625,00 11,94 625,00 11,94 UJP PLTU | SPP GSU BANTEN 2 LABUHAN 600,00 12,99 600,00 12,99 600,00 11,59 600,00 11,47 600,00 11,47 UJP PLTU | SPP GSU BANTEN 3 LONTAR 945,00 20,45 945,00 20,45 945,00 18,25 945,00 18,06 945,00 18,06 UJP PLTU | SPP GSU JAWA BARAT 2 PELABUHAN RATU 1.050,00 22,73 1.050,00 22,73 1.050,00 20,28 1.050,00 20,06 1.050,00 20,06 UJP PLTU | SPP GSU JAWA TENGAH 2 ADIPALA 660,00 14,29 660,00 14,29 660,00 12,75 660,00 12,61 660,00 12,61 PLTGU | CPP PRIOK BLOK 3 740,00 16,02 740,00 16,02 740,00 14,29 740,00 14,14 740,00 14,14 UJP PLTU | SPP GSU PANGKALAN SUSU - - - - 400,00 7,72 400,00 7,64 400,00 7,64 PLTU | SPP SANGGAU - - - - 14,00 0,27 14,00 0,27 14,00 0,27 PLTU | SPP BARRU - - - - 100,00 1,93 100,00 1,91 100,00 1,91 PLTU | SPP JERANJANG - - - - 25,00 0,48 75,00 1,43 75,00 1,43 PLTP | GPP ULUMBU - - - - 5,00 0,10 10,00 0,19 10,00 0,19 TOTAL 4.620,00 100,00 4.620,00 100,00 5.178,00 100,00 5.233,00 100,00 5.233,00 100,00
Indonesia Power bertindak sebagai pengelola aset (asset manager dan asset operator) pembangkit dimana pemilik aset (asset owner) pembangkit adalah PLN
Indonesia Power acted as the asset manager and asset operator of the power plant while the asset owner of the power plant was PLN
DAYA TERPASANGINSTALLED CAPACITY26 LAPORAN STATISTIK
STATISTIC REPORT2015
Unit PembangkitGenerating Unit
2011 2012 2013 2014 2015
MW % MW % MW % MW % MW %
PESANGGARAN 80,00 64,00 80,00 39,02 205,10 60,70 266,49 66,74 220,90 100,00
PEMARON 45,00 36,00 125,00 60,98 132,80 39,30 132,80 33,26 - -
TOTAL 125,00 100,00 205,00 100,00 337,90 100,00 399,29 100,00 220,90 100,00
Unit PembangkitGenerating Unit
Mesin Pembangkit | Power Plant Jumlah | Total
1 2 3 4 5 6 7 8 9 10 11 12 MesinPower
Daya Terpasang Installed Capacity Kapasitas (MW) | Capacity (MW)
Suralaya 7 3.400,00PLTU-B | SPP-C Suralaya 1 -4 400,00 400,00 400,00 400,00 4 1.600,00PLTU-B | SPP-C Suralaya 5 -7 600,00 600,00 600,00 3 1.800,00
Priok 18 1.348,08PLTD-M | DPP-F Kebayoran 2,52 3,00 2,52 2,52 2,52 3,00 6 16,08PLTG-M | GTPP-F Priok 26,00 26,00 2 52,00PLTGU-G | CPP-G Priok 130,00 130,00 130,00 200,00 130,00 130,00 130,00 200,00 8 1.180,00PLTU-M | SPP-F Priok 50,00 50,00 2 100,00
Saguling 29 797,37PLTA | HPP Saguling 175,18 175,18 175,18 175,18 4 700,72PLTA | HPP Bengkok 1,05 1,05 1,05 0,70 4 3,85PLTA | HPP Plengan 1,08 1,08 1,08 2,02 1,61 5 6,87PLTA | HPP Lamajan 6,52 6,52 6,52 3 19,56PLTA | HPP Cikalong 6,40 6,40 6,40 3 19,20PLTA | HPP Ubrug 5,94 5,94 6,48 3 18,36PLTA | HPP Kracak 6,30 6,30 6,30 3 18,90PLTA | HPP Parakan Kondang 2,49 2,49 2,46 2,46 4 9,90
Kamojang 6 345,00PLTP | GPP Kamojang 55,00 55,00 2 110,00PLTP | GPP Gunung Salak 60,00 60,00 60,00 3 180,00PLTP | GPP Darajad 55,00 1 55,00
Mrica 28 309,75PLTA | HPP PB. Sudirman 60,30 60,30 60,30 3 180,90PLTA | HPP Jelok 5,12 5,12 5,12 5,12 4 20,49PLTA | HPP Timo 4,00 4,00 4,00 3 12,00PLTA | HPP Wonogiri 6,20 6,20 2 12,40PLTA | HPP Garung 13,20 13,20 2 26,40PLTA | HPP Sempor 1,00 1 1,00PLTA | HPP Ketenger 3,52 3,52 1,00 0,50 4 8,54PLTA | HPP Wadaslintang 9,00 9,00 2 18,00PLTA | HPP Kedungombo 22,50 1 22,50PLTA | HPP Kelambu 1,17 1 1,17PLTA | HPP Pejengkolan 1,40 1 1,40PLTA | HPP Sidorejo 1,40 1 1,40PLTA | HPP Tapen 0,75 1 0,75PLTA | HPP Siteki 1,20 1 1,20PLTA | HPP Plumbungan 1,60 1 1,60
Semarang 14 1.408,93PLTGU-M | CPP-F Tambaklorok 109,65 109,65 109,65 188,00 4 516,95PLTGU-G | CPP-G Tambaklorok 109,65 109,65 109,65 188,00 4 516,95PLTU-M | SPP-F Tambaklorok 50,00 50,00 200,00 3 300,00PLTG-M | GTPP-F Cilacap 29,00 26,00 2 55,00PLTG-G | GTPP-G Sunyaragi 20,03 1 20,03
Perak Grati 9 864,08PLTGU-G | CPP-G Grati 100,75 100,75 100,75 159,58 4 461,83PLTG-G | GTPP-G Grati 100,75 100,75 100,75 3 302,25PLTU-M | SPP-F Perak 50,00 50,00 2 100,00
Bali 19 556,51PLTDG | GTDPP Pesanggaran 16,64 16,64 16,64 16,64 16,64 16,64 16,64 16,64 16,64 16,64 16,64 16,64 12 199,66PLTG-M | GTPP-F Pesanggaran 21,35 20,10 42,00 42,00 4 125,45PLTG-M | GTPP-F Gilimanuk 133,80 1 133,80PLTG-M | GTPP-F Pemaron 48,80 48,80 2 97,60
JAWA BALI GRID & EMBEDDED 130 9.029,72
Tabel Table
09Daya Terpasang Pembangkit Tahun 2015Installed Capacity of Units in 2015
Tabel Table
10Daya Terpasang Pembangkit dari Pembelian Tenaga Listrik Tahun 2011–2015Installed Capacity of Units Owned by the Purchase of Electricity in 2011–2015
DAYA TERPASANGINSTALLED CAPACITY 27LAPORAN STATISTIK
STATISTIC REPORT 2015
Produksi, Penjualan dan
Pemakaian SendiriProduction,
Sales and Self Consumption
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION28 LAPORAN STATISTIK
STATISTIC REPORT2015
Pertumbuhan Penjualan | Sales GrowthPertumbuhan Produksi | Production Growth
2011 2012 2013 2014 2015-15
-12
-9
-6
-3
3
0
6
9
2011 2012 2013 2014 2015Produksi/Production Penjualan/Sales
45.
446,
57 4
3.55
3,96
39.9
54,7
6 38
.314
,55 42.
624,
17
40.
917,
38
39.
876,
15
38.3
00,0
2
39.7
30,1
2 3
8.01
1,11
Tabel Table
11Pertumbuhan Produksi, Penjualan dan Pemakaian Sendiri Tahun 2011-2015Production, Sales and Self Consumption Growth in 2011-2015
Grafik Graph
06Produksi dan Penjualan Tahun 2011-2015 (GWh)Production and Sales in 2011-2015 (GWh)
Grafik Graph
07Pertumbuhan Produksi dan Penjualan Tahun 2011-2015 (%)Growth of Production and Sales in 2011-2015 (%)
Uraian | DescriptionRealisasi | Realization
2011 2012 2013 2014 2015
Produksi | Production (GWh) 45.446,57 39.954,76 42.624,17 39.876,15 39.730,12
Pertumbuhan Produksi | Production Growth (%) (4,07) (12,08) 6,68 (6,45) (0,37)
Penjualan | Sales (GWh) 43.553,96 38.314,55 40.917,38 38.300,02 38.011,11
Pertumbuhan Penjualan | Sales Growth (%) (4,14) (12,03) 6,79 (6,40) (0,75)
Pemakaian Sendiri | Self Consumption (GWh) 1.892,61 1.632,21 1.698,97 1.568,70 1.718,37
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRIPRODUCTION, SALES AND SELF CONSUMPTION
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 29LAPORAN STATISTIK
STATISTIC REPORT 2015
Tabel Table
12Realisasi Produksi Tahun 2014-2015 dan Rencana Tahun 2016Production Realization in 2014-2015 and Plan of 2016
Unit
Realisasi Realization
(GWh)
Rencana Plan
(GWh)
Realisasi Realization
(GWh)
Pencapaian Achievement
(%)
Rencana Plan
(GWh)
Pertumbuhan Growth
(%)
2014 2015 2016 2014 2015
A. JAWA BALI GRID & EMBEDDED 37.461,12 42.530,16 39.126,74 92,00 42.862,52 (1,70) 4,45
Suralaya 22.596,76 23.208,00 23.528,45 101,38 22.336,07 1,08 4,12
Priok 3.819,14 4.346,59 3.434,65 79,02 3.528,81 (15,61) (10,07)
Saguling 3.157,96 3.277,17 2.497,13 76,20 2.646,77 28,30 (20,93)
Kamojang 2.842,56 2.576,03 2.892,87 112,30 2.686,63 (2,64) 1,77
Semarang 346,71 3.340,30 2.562,61 76,72 5.553,68 14,37 639,12
Mrica 882,42 1.069,85 897,87 83,92 1.011,46 (8,37) 1,75
Perak Grati 2.953,00 3.565,27 2.452,32 68,78 3.779,04 (14,08) (16,96)
Bali 862,56 1.146,96 860,85 75,05 1.320,07 (24,65) (0,20)
B. PEMBELIAN LISTRIK PURCHASE OF ELECTRICITY
2.415,03 435,76 603,37 138,47 459,97 30,94 (75,02)
Pesanggaran 1.549,38 429,24 580,46 135,23 424,45 171,16 (62,54)
Pemaron 363,15 - - - - (52,69) (100,00)
Nusa Penida - - 22,91 - 28,11 (100,00) -
Keramasan 130,94 - - - - 14,35 (100,00)
Jambi 115,88 - - - - (7,83) (100,00)
Indralaya 1 255,68 - - - - 3,32 (100,00)
Karimunjawa - 6,52 - - 7,42 - -
INDONESIA POWER 39.876,15 42.965,92 39.730,12 92,47 43.322,50 (0,20) (0,37)
PRODUKSI PER UNIT PRODUCTION PER UNIT
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION30 LAPORAN STATISTIK
STATISTIC REPORT2015
INDONESIA POWER
KarimunjawaIndralaya 1JambiKeramasanNusa PenidaPemaronPesanggaranBaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya
22.5
96,7
6
Realisasi | Realization 2014
23.5
28,4
5 22
.336
,07
3.8
19,1
43.
434,
653.
528,
81
3.15
7,96
2.
497,
13
2.6
46,7
7
2.84
2,56
2.68
6,63
2.56
2,61
34
6,71
5.55
3,68
39.8
76,1
5
39.
730,
12
43.3
22,5
0
882,
42
897,
87
1.01
1,46
2.95
3,00
2.
452,
32
3.7
79,0
4
862
,56
860,
85
1.32
0,07
1.54
9,38
580
,46
424,
45
363,
150 0 22
,91
0 28,
11
0130,
94
0 0115,
88
0 0255,
68
0 00 7,42
2.89
2,87
JAWA BALI GRID & EMBEDDED PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY
Realisasi | Realization 2015 Rencana| Plan 2016
Pertumbuhan Produksi 2015 | Production Growth 2015Pertumbuhan Produksi 2014 | Production Growth 2014
PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY JAWA BALI GRID & EMBEDDED
INDONESIAPOWER
KarimunjawaIndralaya 1JambiKeramasanNusa PenidaPemaronPesanggaranBaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya-100
0
100
200
300
400
500
600
700
800
Grafik Graph
08Realisasi Produksi Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Production Realization in 2014-2015 and Plan of 2016 (GWh)
Grafik Graph
09Pertumbuhan Produksi Tahun 2014 dan Tahun 2015 (%)Production Growth in 2014 and 2015 (%)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 31LAPORAN STATISTIK
STATISTIC REPORT 2015
Unit
Triwulan | Quarterly
2015 TW I TW II TW III TW IV
Produksi (GWh) | Production (GWh)
A. JAWA BALI GRID & EMBEDDED 9.035,99 9.943,04 9.608,69 10.539,02 39.126,74
Suralaya 5.057,38 5.967,31 6.247,05 6.256,71 23.528,45
Priok 883,13 936,04 705,14 910,35 3.434,65
Saguling 936,78 703,57 347,06 509,71 2.497,13
Kamojang 737,12 713,95 759,55 682,25 2.892,87
Semarang 300,26 281,23 677,25 1.303,87 2.562,61
Mrica 351,71 306,97 83,77 155,42 897,87
Perak Grati 521,11 647,56 662,85 620,80 2.452,32
Bali 248,51 386,41 126,02 99,91 860,85
B. PEMBELIAN LISTRIK | ELECTRICITY PURCHASE 308,34 202,79 73,07 19,18 603,37
Pesanggaran 308,34 192,19 67,16 12,78 580,46
Nusa Penida - 10,60 5,91 6,40 22,91
Karimunjawa - - - - -
INDONESIA POWER 9.344,33 10.145,83 9.681,76 10.558,20 39.730,12
Tabel Table
13Produksi Per Unit Tahun 2015Production Per Unit in 2015
2,29%Mrica
6,27%Perak Grati
6,55%Semarang
2,20%Bali
60,13%Suralaya
8,78%Priok
6,38%Saguling
7,39%Kamojang
Produksi Per Unit Tahun 2015 Production Per Unit in 2015
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION32 LAPORAN STATISTIK
STATISTIC REPORT2015
TW I TW II TW III TW IV
INDONESIA POWER
KarimunjawaNusa PenidaPesanggaranBaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya
5.05
7,38 5.
967,
316.
247,
056.
256,
71
883
,13
936,
04
705,
1491
0,35
936,
7870
3,57
34
7,06
509,
71
737,
12
713,
95
759
,55
682,
25
0 10,6
05,
916,
40
0 0 0 0
1.30
3,87
6
77,2
528
1,23
300,
26
351
,71
306,
97 8
3,77
1
55,4
2
521,
11
647
,56
662,
8562
0,80
248,
51
386
,41
126,
0299
,91
308,
34
9.34
4,33 10
.145
,83
9.6
81,7
610
.558
,20
192,
19 6
7,16
12
,78
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY
JAWA BALI GRID & EMBEDDED
Grafik Graph
10Produksi Per Unit Tahun 2015 (GWh)Production Per Unit in 2015 (GWh)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 33LAPORAN STATISTIK
STATISTIC REPORT 2015
Unit
Realisasi Realization
(GWh)
Rencana Plan (GWh)
Realisasi Realization
(GWh)
Pencapaian Achievement
(%)
Rencana Plan
(GWh)
Pertumbuhan Growth
(%)
2014 2015 2016 2014 2015
A. JAWA BALI GRID & EMBEDDED 35.892,42 40.668,55 37.408,37 91,98 40.944,38 (1,61) 4,22 Suralaya 21.374,64 21.916,78 22.206,08 101,32 21.076,25 1,20 3,89 Priok 3.743,78 4.242,24 3.366,03 79,35 3.450,38 (15,49) (10,09)Saguling 3.150,71 3.265,70 2.490,67 76,27 2.637,34 28,34 (20,95)Kamojang 2.709,00 2.451,54 2.759,19 112,55 2.556,18 (2,84) 1,85 Semarang 323,03 3.188,06 2.477,34 77,71 5.303,15 21,29 666,91 Mrica 868,66 1.052,59 883,11 83,90 993,63 (8,29) 1,66 Perak Grati 2.872,48 3.462,70 2.382,01 68,79 3.667,45 (14,18) (17,07)Bali 850,11 1,088,95 843,94 77,50 1.260,00 (24,37) (0,73)
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY 2.407,60 435,76 602,74 138,32 459,97 31,10 (74,97)Pesanggaran 1.549,38 429,24 579,83 135,08 424,45 171,16 (62,58)Pemaron 363,15 - - - - (52,69) (100,00)Nusa Penida - - 22,91 - 28,11 - - Keramasan 129,73 - - - - 14,52 (100,00)Jambi 113,66 - - - - (7,89) (100,00)Indralaya 1 251,69 - - - - 3,56 (100,00)Karimunjawa - 6,52 - - 7,42 - -
INDONESIA POWER 38.300,02 41.104,31 38.011,11 92,47 41.404,35 (0,04) (0,75)
PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY JAWA BALI GRID & EMBEDDED
21.37
4,64
22.20
6,08
21.07
6,25
INDONESIAPOWER
KarimunjawaIndralaya 1JambiKeramasanNusa PenidaPemaronPesanggaranBaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya
Realisasi | Realization 2014 Realisasi | Realization 2015 Rencana | Plan 2016
3.743
,783.3
66,03
3.450
,38
3.150
,71
2.490
,672.6
37,34
2.709
,00 2.
759,1
92.5
56,18
323,0
3 2.477
,34 5.303
,15
868,6
6 88
3,11
993,6
3 2.872
,482.3
82,01
3.66
7,45
850,1
1 84
3,94
1.260
,00
1.549
,38
38.30
0,02
38.01
1,11 41.40
4,35
579,8
342
4,45
363,1
5 0 0 0 22
,91 28
,11
129,7
30 0 11
3,66
0 0 251,6
9 0 0 0 0 7,4
2
PENJUALAN PER UNITSALES PER UNIT
Tabel Table
14Realisasi Penjualan Tahun 2014-2015 dan Rencana Tahun 2016Sales Realization in 2014-2015 and Plan of 2016
Grafik Graph
11Realisasi Penjualan Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Sales Realization in 2014-2015 and Plan of 2016 (GWh)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION34 LAPORAN STATISTIK
STATISTIC REPORT2015
Grafik Graph
12Pertumbuhan Penjualan Tahun 2014 dan Tahun 2015 (%)Sales Growth in 2014 and 2015 (%)
Tabel Table
15Penjualan Per Unit Tahun 2015 Sales Per Unit in 2015
Unit
Triwulan | Quarterly
2015 TW I TW II TW III TW IV
Penjualan (GWh) | Sales (GWh)
A. JAWA BALI GRID & EMBEDDED 8.637,90 9.507,65 9.172,43 10.090,39 37.408,37
Suralaya 4.747,35 5.624,54 5.908,27 5.925,92 22.206,08
Priok 865,90 917,49 688,74 893,91 3.366,03
Saguling 934,83 701,89 345,76 508,19 2.490,67
Kamojang 702,90 681,13 724,84 650,32 2.759,19
Semarang 291,67 271,55 658,13 1.255,99 2.477,34
Mrica 346,06 302,07 82,09 152,90 883,11
Perak Grati 502,94 628,25 643,74 607,08 2.382,01
Bali 246,26 380,73 120,86 96,09 843,94
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY 308,33 213,38 68,15 12,88 602,74
Pesanggaran 308,33 202,78 62,24 6,48 579,83
Nusa Penida - 10,60 5,91 6,40 22,91
INDONESIA POWER 8.946,23 9.721,03 9.240,58 10.103,27 38.011,11
Pertumbuhan Produksi 2015 | Production Growth 2015Pertumbuhan Produksi 2014 | Production Growth 2014
PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY JAWA BALI GRID & EMBEDDED
INDONESIA POWER
KarimunjawaIndralaya 1JambiKeramasanNusa PenidaPemaronPesanggaranBaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya
-100
0
100
200
300
400
500
600
700
800
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 35LAPORAN STATISTIK
STATISTIC REPORT 2015
Grafik Graph
13Penjualan Per Unit Tahun 2015 (GWh)Sales Per Unit in 2015 (GWh)
4.74
7,35
5.6
24,5
4 5
.908
,27
5.92
5,92
865,
90
917,
49
688,
74 8
93,9
1
934
,83
701,
89
345,
76 508,
19
702,
9068
1,13
724,
8465
0,32
291,
67
271,
55
658
,13
1.25
5,99
346
,06
82,
09
152,
90
502,
94
628,
25 6
43,7
4 6
07,0
8
246,
2638
0,73
12
0,86
96
,09
308,
33
8.9
46,2
3 9
.721
,03
9.2
40,5
8 1
0.10
3,27
202,
7862
,24
6,48
0 10,6
0 5,
916,
40302,
07
INDONESIAPOWER
Nusa PenidaPesanggaranBaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya
TW IIITW IITW I TW IV
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY
JAWA BALI GRID & EMBEDDED
2,26%Bali
2,36%Mrica
59,36%Suralaya
6,37%Perak Grati
6,62%Semarang
9,00%Priok
6,66%Saguling
7,38%Kamojang
Penjualan Per Unit Tahun 2015 Sales Based on Unit in 2015
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION36 LAPORAN STATISTIK
STATISTIC REPORT2015
Unit
Realisasi Realization
Rencana Plan
Realisasi Realization
Pencapaian Achievement
Rencana Plan
(GWh) (%) (GWh) (%) (GWh) (%) (%) (GWh) (%)
2014 2015 2016
JAWA BALI GRID & EMBEDDED 1.568,70 4,19 1.861,61 4,38 1.718,37 4,39 92,31 1.918,15 4,53
Suralaya 1.222,12 5,41 1.291,22 5,56 1.322,37 5,62 102,41 1.259,83 5,64
Priok 75,36 1,97 104,35 2,40 68,62 2,00 65,76 78,43 2,22
Saguling 7,24 0,23 11,47 0,35 6,46 0,26 56,32 9,42 0,36
Kamojang 133,57 4,70 124,49 4,83 133,68 4,62 107,39 130,44 4,86
Semarang 23,69 6,83 152,24 4,56 85,27 3,33 56,01 250,53 4,51
Mrica 13,76 1,56 17,26 1,61 14,75 1,64 85,50 17,83 1,76
Perak Grati 80,52 2,73 102,58 2,88 70,31 2,87 68,54 111,59 2,95
Bali 12,45 1,44 58,01 5,06 16,91 1,96 29,14 60,08 4,55
INDONESIA POWER 1.568,70 4,19 1.861,61 4,38 1.718,37 4,39 92,31 1.918,15 4,53
Realisasi | Realization 2014 Realisasi Realization 2015 Rencana | Plan 2016
5,4
1 5,6
2
5,6
4
1,9
7
2,0
0
2,2
2
0,23
0,26
0,3
6
4,7
0
6,8
3
3,3
3
2,73
2,
87
2,95
4,5
1 4,62
4,86
1,5
6
1,6
4
1,44
1,9
6
4,5
5
4,19
4,3
9
4,5
3
1,7
6
INDONESIA POWER
BaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya
PEMAKAIAN SENDIRI PER UNITSELF CONSUMPTION PER UNIT
Tabel Table
16Realisasi Pemakaian Sendiri Tahun 2014-2015 dan Rencana Tahun 2016 Self Consumption Realization in 2014-2015 and Plan of 2016
Grafik Graph
14Realisasi Pemakaian Sendiri Tahun 2014-2015 dan Rencana Tahun 2016 (%)Self Consumption Realization in 2014-2015 and Plan of 2016 (%)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 37LAPORAN STATISTIK
STATISTIC REPORT 2015
Unit
Triwulan | Quarterly2015
TW I TW II TW III TW IV
(GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%)
JAWA BALI GRID & EMBEDED 398,09 4,41 435,39 4,38 436,26 4,54 448,63 4,26 1.718,37 4,39
Suralaya 310,03 6,13 342,77 5,74 338,78 5,42 330,79 5,29 1.322,37 5,62
Priok 17,23 1,95 18,55 1,98 16,39 2,32 16,44 1,81 68,62 2,00
Saguling 1,96 0,21 1,68 0,24 1,30 0,37 1,52 0,30 6,46 0,26
Kamojang 34,22 4,64 32,81 4,60 34,71 4,57 31,93 4,68 133,68 4,62
Semarang 8,59 2,86 9,68 3,44 19,12 2,82 47,88 3,67 85,27 3,33
Mrica 5,65 1,61 4,90 1,60 1,68 2,01 2,52 1,62 14,75 1,64
Perak Grati 18,17 3,49 19,31 2,98 19,11 2,88 13,72 2,21 70,31 2,87
Bali 2,24 0,90 5,68 1,47 5,16 4,09 3,82 3,82 16,91 1,96
INDONESIA POWER 398,09 4,41 435,39 4,38 436,26 4,54 448,63 4,26 1.718,37 4,39
TW IIITW IITW I TW IV
INDONESIA POWER
BaliPerak GratiMricaSemarangKamojangSagulingPriokSuralaya
5,29
1,95
1,9
8 2,32
1,8
1
0,2
1 0
,24
0,37
0,
30
6,13
5,74
5,
42
4,6
4
4,60
4,
574,
68
2,8
6 3,44
2
,82
3,67
1,61
1,
60 2,0
1
1,62
3,49
2,
98
2,8
8 2,
21
0,9
0
1,47
4
,09
3,8
2
4,4
1 4
,38
4,5
4 4
,26
0,98%Bali
0,38%Saguling
76,96%Suralaya
3,99%Priok
7,78%Kamojang
0,86%Mrica
4,96%Semarang
4,09%Perak Grati
Tabel Table
17Pemakaian Sendiri Per Unit Tahun 2015Self Consumption Per Unit in 2015
Grafik Graph
15Pemakaian Sendiri Per Unit Tahun 2015 (%)Self Consumption Per Unit in 2015 (%)
Pemakaian Sendiri Per Unit Tahun 2015 Self Consumption Per Unit in 2015
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION38 LAPORAN STATISTIK
STATISTIC REPORT2015
Jenis PembangkitanPower Plant Type
Realisasi Realization
(GWh)
Rencana Plan (GWh)
Realisasi Realization
(GWh)
Pencapaian Achievement
(%)
Rencana Plan
(GWh)
Pertumbuhan Growth
(%)
2014 2015 2016 2014 2015
A. JAWA BALI GRID & EMBEDDED 37.461,12 42.530,16 39.126,74 92,00 42.862,52 (1,70) 4,45 PLTU | SPP 22.596,76 23.816,86 23.528,45 98,79 22.948,75 0,56 4,12
PLTU (batu bara) | Coal-fired SPP 22.596,76 23.208,00 23.528,45 101,38 22.336,07 1,08 4,12 PLTU (Gas) | Gas SPP - 205,24 - - 612,67 - - PLTU (MFO) | MFO SPP - 403,62 - - - (100,00) -
PLTG | GTPP 1.085,79 717,51 615,73 85,81 405,35 (7,41) (43,29)PLTG (Gas) | Gas GTPP 222,74 373,58 172,05 46,05 383,04 70,11 (22,76)PLTG (HSD) | HSD GTPP 863,06 343,93 443,68 129,00 22,31 (17,15) (48,59)
PLTGU | CPP 6.887,14 10.251,80 8.271,98 80,69 11.862,48 (13,93) 20,11 PLTGU (Gas) | Gas CPP 6.605,99 9.270,04 8.242,04 88,91 11.815,11 3,11 24,77 PLTGU (HSD) | HSD CPP 281,15 981,76 29,94 3,05 47,37 (82,37) (89,35)
PLTD | DPP 8,48 - 0,02 - - (92,99) (99,74)PLTP | GPP 2.842,56 2.576,03 2.892,87 112,30 2.686,63 (2,64) 1,77 PLTA | HPP 4.040,38 4.347,02 3.395,00 78,10 3.658,23 17,98 (15,97)PLTDG | GTDPP - 820,95 422,69 51,49 1.301,10 (100,00) -
PLTDG (Gas) | Gas GTDPP - - - - 1.258,34 - - PLTDG (MFO) | MFO GTDPP - 820,95 120,13 14,63 - (100,00) - PLTDG (HSD) | HSD GTDPP - - 302,55 - 42,75 - -
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY 2.415,03 435,76 603,37 138,47 459,97 30,94 (75,02)PLTD | DPP 1.912,53 429,24 603,37 140,57 452,55 40,97 (68,45)PLTG | GTPP 502,50 - - - - 3,03 (100,00)PLTMG | GTMPP - 6,52 - - 7,42 - - INDONESIA POWER 39.876,15 42.965,92 39.730,12 92,47 43.322,50 (0,20) (0,37)
PRODUKSI PER JENIS PEMBANGKITPRODUCTION PER POWER PLANT TYPE
Realisasi | Realization 2014 Realisasi | Realization 2015 Rencana | Plan 2016
INDONESIA POWER
PLTMGGTMPP
PLTGGTPP
PLTDDPP
PLTDGGTDPP
PLTA HPP
PLTPGPP
PLTDDPP
PLTGUCPP
PLTGGTPP
PLTU SPP
23.5
28,4
5
22.
596,
76
22.9
48,7
5
39.7
30,1
2
39.8
76,1
5
43.
322,
50
1.0
85,7
9
615,
73
405,
35 6.
887,
14
8.2
71,9
8
11.
862,
48
2.8
42,5
6
2.8
92,8
7 2.
686,
63
4.04
0,38
3
.395
,00
3.6
58,2
3
422,
69
1.30
1,10
1.9
12,5
3
603
,37
452
,55
8,4
8 0,
02
0 0 502
,50
0 0 0 0 7,42
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY JAWA BALI GRID & EMBEDDED
Tabel Table
18Realisasi Produksi Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016Production Realization Per Power Plant Type in 2014-2015 and Plan of 2016
Grafik Graph
16Realisasi Produksi Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Production Realization Per Power Plant Type in 2014-2015 and Plan of 2016 (GWh)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 39LAPORAN STATISTIK
STATISTIC REPORT 2015
Pertumbuhan Produksi 2015 | Production Growth 2015Pertumbuhan Produksi 2014 | Production Growth 2014
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY JAWA BALI GRID & EMBEDDED
INDONESIAPOWER
PLTG GTPP
PLTG GTPP
PLTD DPP
PLTD DPP
PLTDGGTDPP
PLTAHPP
PLTP|GPP
PLTDDPP
PLTGU CPP
PLTGGTPP
PLTUSPP PLTMG
GTMPP
-100
-80
-60
-40
-20
0
20
40
60
Jenis PembangkitanPower Plant Type
Triwulan | Quarterly
2015TW I TW II TW III TW IV
Produksi (GWh) | Production (GWh)
A. JAWA BALI GRID & EMBEDDED 9.035,99 9.943,04 9.608,69 10.539,02 39.126,74 PLTU | SPP 5.057,38 5.967,31 6.247,05 6.256,71 23.528,45
PLTU (batu bara) | Coal-fired SPP 5.057,38 5.967,31 6.247,05 6.256,71 23.528,45 PLTG | GTPP 254,78 186,55 61,10 113,30 615,73
PLTG (Gas) | Gas GTPP 8,99 30,95 49,62 82,48 172,05 PLTG (HSD) | HSD GTPP 245,79 155,59 11,48 30,81 443,68
PLTGU | CPP 1.695,47 1.833,87 1.995,61 2.747,04 8.271,98 PLTGU (Gas) | Gas CPP 1.694,44 1.831,46 1.989,43 2.726,71 8.242,04 PLTGU (HSD) | HSD CPP 1,03 2,41 6,18 20,33 29,94
PLTD | DPP 0,004 0,01 - 0,01 0,02 PLTP | GPP 737,12 713,95 759,55 682,25 2.892,87 PLTA | HPP 1.288,49 1.010,54 430,84 665,13 3.395,00 PLTDG | GTDPP 2,74 230,82 114,54 74,59 422,69
PLTDG (MFO) | MFO GTDPP 2,74 58,39 5,95 53,05 120,13 PLTDG (HSD) | HSD GTDPP - 172,43 108,59 21,53 302,55
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY 308,34 202,79 62,47 29,78 603,37 PLTD | DPP 308,34 202,79 62,47 29,78 603,37 INDONESIA POWER 9.344,33 10.145,83 9.671,16 10.568,80 39.730,12
Tabel Table
19Produksi Per Jenis Pembangkit Tahun 2015 Production Per Power Plant Type in 2015
Grafik Graph
17Pertumbuhan Produksi Per Jenis Pembangkit Tahun 2014 dan Tahun 2015 (%)Production Growth Per Power Plant Type in 2014 and 2015 (%)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION40 LAPORAN STATISTIK
STATISTIC REPORT2015
254,
78
186,
55
61,
10
113,
30
230
,82
2,7
4
114,
54
74,
59
202
,79
308
,34
62,
47
29,7
8
0,00
40,
010 0,
01
TW IIITW IITW I TW IV
INDONESIA POWERPLTD DPP
PLTDGGTDPP
PLTAHPP
PLTPGPP
PLTDDPP
PLTGU CPP
PLTGGTPP
PLTUSPP
5.05
7,38
5.
967,
31
6.2
47,0
5
6.2
56,7
1
1.6
95,4
7
1.8
33,8
7 1.
995,
61
2.7
47,0
4
737,
12
682
,25
713,
95
759
,55
1.28
8,49
1
.010
,54
430,
84
665,
13
9.34
4,33
10.5
68,8
0
10.1
45,8
3
9.67
1,16
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY JAWA BALI GRID & EMBEDDED
1,59%PLTG GTPP
7,47%PLTPGPP
21,37%PLTGU
CPP
8,77%PLTAHPP
0%PLTD DPP
60,79%PLTUSPP
Grafik Graph
18Produksi Per Jenis Pembangkit Tahun 2015 (GWh)Production Per Power Plant Type in 2015 (GWh)
Produksi Per Jenis Pembangkit Tahun 2015 Production Per Power Plant Type in 2015
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 41LAPORAN STATISTIK
STATISTIC REPORT 2015
Jenis PembangkitanPower Plant Type
Realisasi Realization
(GWh)
Rencana Plan
(GWh)
Realisasi Realization
(GWh)
Pencapaian Achievement
(%)
Rencana Plan
(GWh)
Pertumbuhan Growth
(%)
2014 2015 2016 2014 2015
A. JAWA BALI GRID & EMBEDDED 35.892,42 40.668,55 37.408,37 91,98 40.944,38 (1,61) 4,22 PLTU | SPP 21.368,90 22.483,02 22.201,18 98,75 21.646,03 0,73 3,89
PLTU (batu bara) | Coal-fired SPP 21.374,64 21.916,78 22.206,08 101,32 21.076,25 1,20 3,89 PLTU (Gas) | Gas SPP - 190,87 - - 569,79 - - PLTU (MFO) | MFO SPP (5,74) 375,37 (4,90) - - (106,20) 0,00
PLTG | GTPP 1.070,86 705,87 606,35 85,90 400,95 (6,36) (43,38)PLTG (Gas) | Gas GTPP 221,67 369,84 171,00 46,23 379,21 70,38 (22,86)PLTG (HSD) | HSD GTPP 849,18 336,02 435,36 129,56 21,75 (16,21) (48,73)
PLTGU | CPP 6.716,87 9.939,70 8.054,36 81,03 11.468,78 (14,10) 19,91 PLTGU (Gas) | Gas CPP 6.452,45 8.994,07 8.028,26 89,26 11.423,71 2,90 24,42 PLTGU (HSD) | HSD CPP 264,42 945,64 26,10 2,76 45,06 (82,93) (90,13)
PLTD | DPP 7,31 - 0,01 - - (93,45) (99,89)PLTP | GPP 2.709,00 2.451,54 2.759,19 112,55 2.556,18 (2,84) 1,85 PLTA | HPP 4.019,37 4.318,29 3.373,79 78,13 3.630,97 18,14 (16,06)PLTDG | GTDPP - 770,13 413,40 53,68 1.241,46 (100,00) -
PLTDG (Gas) | Gas GTDPP - - - - 1.200,66 - - PLTDG (MFO) | MFO GTDPP - 770,13 117,27 15,23 - (100,00) - PLTDG (HSD) | HSD GTDPP - - 296,13 - 40,79 - -
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY 2.407,60 435,76 602,74 138,32 459,97 31,10 (74,97)PLTD | DPP 1.912,53 429,24 602.74 140,42 452,55 40,97 (68,48)PLTG | GTPP 495,08 - - - - 3,20 (100,00)PLTMG | GTMPP - 6,52 - - 7,42 - - INDONESIA POWER 38.300,02 41.104,31 38.011,11 92,47 41.404,35 (0,04) (0,75)
PENJUALAN PER JENIS PEMBANGKITSALES PER POWER PLANT TYPE
Realisasi | Realization 2015Realisasi | Realization 2014 Rencana | Plan 2016
INDONESIA POWER
PLTMG GTMPP
PLTGGTPP
PLTD DPP
PLTDGGTDPP
PLTAHPP
PLTPGPP
PLTDDPP
PLTGU CPP
PLTGGTPP
PLTUSPP
22.2
01,1
8
21.3
68,9
0
21.6
46,0
3
7,31
0
,01
0
2.7
09,0
0
2.7
59,1
9
2.5
56,1
8
4.01
9,37
3.3
73,7
9 3
.630
,97
1,2
41,4
6
1.9
12,5
360
2,74
452,
55
495,
08
0 0 0 0 7,42
38.
300,
02
38.0
11,1
1
41.
404,
35
413,
40
0
1.0
70,8
6
606,
35
400,
95 6.7
16,8
7
8.0
54,3
611
.468
,78
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY
JAWA BALI GRID & EMBEDDED
Tabel Table
20Realisasi Penjualan Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 Sales Realization Per Power Plant Type in 2014-2015 and Plan of 2016
Grafik Graph
19Realisasi Penjualan Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 (GWh)Sales Realization Per Power Plant Type in 2014-2015 and Plan of 2016 (GWh)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION42 LAPORAN STATISTIK
STATISTIC REPORT2015
Pertumbuhan Produksi 2015 | Production Growth 2015Pertumbuhan Produksi 2014 | Production Growth 2014
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY JAWA BALI GRID & EMBEDDED
PLTG GTPP
PLTG GTPP
PLTD DPP
PLTDDPP
PLTUSPP
PLTMGGTMPP
PLTGGTPP PLTGU
CPP
PLTGU CPP
PLTAHPP
PLTDGGTDPP-100
-80
-60
-40
-20
0
20
40
60PLTD DPP
PLTPGPP
INDONESIAPOWER
Jenis PembangkitanPower Plant Type
Triwulan | Quarterly
2015TW I TW II TW III TW IV
Produksi (GWh) | Production (GWh)
A. JAWA BALI GRID & EMBEDDED 8.637,90 9.507,65 9.172,43 10.090,39 37.408,37 PLTU | SPP 4.746,29 5.623,43 5.906,98 5.924,47 22.201,18
PLTU (batu bara) | Coal-fired SPP 4.747,35 5.624,54 5.908,27 5.925,92 22.206,08 PLTU (Gas) | Gas SPP - - - - - PLTU (MFO) | MFO SPP (1,05) (1,11) (1,29) (1,44) (4,90)
PLTG | GTPP 252,35 183,99 58,91 111,11 606,35 PLTG (Gas) | Gas GTPP 8,72 30,67 49,35 82,26 171,00 PLTG (HSD) | HSD GTPP 243,63 153,32 9,56 28,85 435,36
PLTGU | CPP 1.652,97 1.787,85 1.942,68 2.670,86 8.054,36 PLTGU (Gas) | Gas CPP 1.653,94 1.785,98 1.937,11 2.651,24 8.028,26 PLTGU (HSD) | HSD CPP (0,96) 1,87 5,57 19,62 26,10
PLTD | DPP 0,001 0,002 - 0,00 0,008 PLTP | GPP 702,90 681,13 724,84 650,32 2,759,19 PLTA | HPP 1.280,89 1.003,95 427,86 661,09 3.373,79 PLTDG | GTDPP 2,48 227,26 111,15 72,52 413,40
PLTDG (MFO) | MFO GTDPP 2,48 57,61 5,46 51,73 117,27 PLTDG (HSD) | HSD GTDPP - 169,65 105,69 20,79 296,13
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY 308,33 202,78 62,24 29,39 602,74 PLTD | DPP 308,33 202,78 62,24 29,39 602,74 INDONESIA POWER 8.946,23 9.710,43 9.234,68 10.119,77 38.011,11
Tabel Table
21Penjualan Per Jenis Pembangkit Tahun 2015 Sales Per Power Plant Type in 2015
Grafik Graph
20Pertumbuhan Penjualan Per jenis Pembangkit Tahun 2014-2015 (%)Sales Growth Per Power Plant Type in 2014 and 2015 (%)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 43LAPORAN STATISTIK
STATISTIC REPORT 2015
PEMBELIAN LISTRIKPURCHASE OF ELECTRICITY
JAWA BALI GRID & EMBEDDED
1.65
2,97
1.7
87,8
5 1.
942,
68
TW IIITW IITW I TW IV
INDONESIA POWER
PLTD DPP
PLTDGGTDPP
PLTAHPP
PLTPGPP
PLTDDPP
PLTGU CPP
PLTGGTPP
PLTUSPP
4.7
46,2
9
5.62
3,43
5.
906,
98
5.92
4,47
0,00
1 0,
002
0 0,00
2
2,4
8 2
27,2
611
1,15
72
,52
308
,33
202
,78
62,2
429
,39
702
,90
681,
13
724,
84
650
,32
1.28
0,89
1.
003,
95 4
27,8
6 6
61,0
9
252
,35
183,
99
58,9
1 11
1,11
8.94
6,23
9.
710,
43
9.2
34,6
8 1
0.11
9,77
2.6
70,8
6
1,64%PLTG GTPP
7,46%PLTPGPP
21,77%PLTGU
CPP
9,12%PLTAHPP
0%PLTD DPP
60,01%PLTUSPP
Grafik Graph
21Penjualan Per Jenis Pembangkit Tahun 2015 (GWh)Sales Per Power Plant Type in 2015 (GWh)
Penjualan Per Jenis Pembangkit Tahun 2015 Sales Per Power Plant Type in 2015
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION44 LAPORAN STATISTIK
STATISTIC REPORT2015
PEMAKAIAN SENDIRI PER JENIS PEMBANGKITSELF CONSUMPTION PER POWER PLANT TYPE
Jenis PembangkitanPower Plant Type
RealisasiRealization
Rencana Plan
Realisasi Realization Pencapaian
Achievement (%)
Rencana | Plan
(GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%)
2014 2015 2016
A. JAWA BALI GRID & EMBEDDED 1.568,70 4,19 1.861,61 4,38 1.718,37 4,39 92,31 1.918,15 4,53 PLTU | SPP 1.227,86 5,43 1.333,84 5,60 1.327,27 5,64 99,51 1.302,71 5,68
PLTU (batu bara) | Coal-fired SPP 1.222,12 5,41 1.291,22 5,56 1.322,37 5,62 102,41 1.259,83 5,64 PLTU (Gas) | Gas SPP - - 14,37 7,00 - - - 42,89 7,00 PLTU (MFO) | MFO SPP 5,74 - 28,25 - 4,90 - - - -
PLTG | GTPP 14,94 1,38 11,65 1,62 9,38 1,52 80,51 4,39 1,08 PLTG (Gas) | Gas GTPP 1,06 0,48 3,74 1,00 1,05 0,61 28,20 3,83 1,00 PLTG (HSD) | HSD GTPP 13,88 1,61 7,91 2,30 8,32 1,88 105,22 0,56 2,53
PLTGU | CPP 170,27 2,47 312,10 3,04 217,63 2,63 69,73 393,70 3,32 PLTGU (Gas) | Gas CPP 153,55 2,32 275,98 2,98 213,78 2,59 77,46 391,40 3,31 PLTGU (HSD) | HSD CPP 16,73 5,95 36,12 3,68 3,85 12,84 10,65 2,31 4,87
PLTD | DPP 1,17 13,84 - - 0,01 62,71 - - - PLTP | GPP 133,57 4,70 124,49 4,83 133,68 4,62 107,39 130,44 4,86 PLTA | HPP 21,00 0,52 28,72 0,66 21,21 0,62 73,85 27,26 0,75 PLTDG | GTDPP - - 50,82 6,19 9,28 2,20 18,27 59,64 4,58
PLTDG (Gas) | Gas GTDPP - - - - - - - 57,68 4,58 PLTDG (MFO) | MFO GTDPP - - 50,82 6,19 2,86 2,38 5,63 - - PLTDG (HSD) | HSD GTDPP - - - - 6,42 2,12 - 1,96 4,58
INDONESIA POWER 1.568,70 4,19 1.861,61 4,38 1.718,37 4,39 92,31 1.918,15 4,53
Tabel Table
22Realisasi Pemakaian Sendiri Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 Self Consumption Realization Per Power Plant Type in 2014-2015 and Plan of 2016
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 45LAPORAN STATISTIK
STATISTIC REPORT 2015
PEMAKAIAN SENDIRI PER JENIS PEMBANGKITSELF CONSUMPTION PER POWER PLANT TYPE
Realisasi | Realization 2015 Rencana | Plan 2016Realisasi | Realization 2014
INDONESIA POWER
PLTDG GTDPP
PLTA HPP
PLTP GPP
PLTD DPP
PLTGU CPP
PLTG GTPP
PLTU SPP
5,43
5,64
5,6
8
1,3
8
1,5
2
1,08
2,4
7
2,6
3
3,32
13,
84
62,
71
o
4,7
0
4,6
2
4,8
6
0,5
2
0,6
2
0,7
5
2,20
o
4,5
8
4,1
9
4,39
4,53
Grafik Graph
22Realisasi Pemakaian Sendiri Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 (%)Self Consumption Realization Per Power Plant Type in 2014-2015 and Plan of 2016 (%)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION46 LAPORAN STATISTIK
STATISTIC REPORT2015
Jenis PembangkitanGenerating Unit
Triwulan | Quarterly 2015
TW I TW II TW III TW IV (GWh) (%)
(GWh) (%) (GWh) (%) (GWh) (%) (GWh) (%)
A. JAWA BALI GRID & EMBEDDED 398,09 4,41 435,39 4,38 436,26 4,54 448,63 4,26 1.718,37 4,39 PLTU | SPP 311,08 6,15 343,88 5,76 340,07 5,44 332,24 5,31 1.327,27 5,64
PLTU (batu bara) | Coal-fired SPP 310,03 6,13 342,77 5,74 338,78 5,42 330,79 5,29 1.322,37 5,62 PLTU (Gas) | Gas SPP - - - - - - - - - - PLTU (MFO) | MFO SPP 1,05 - 1,11 - 1,29 - 1,44 - 4,90 -
PLTG | GTPP 2,44 0,96 2,55 1,37 2,20 3,60 2,19 1,93 9,38 1,52 PLTG (Gas) | Gas GTPP 0,27 3,06 0,28 0,90 0,28 0,55 0,23 0,27 1,05 0,61 PLTG (HSD) | HSD GTPP 2,16 0,88 2,27 1,46 1,92 16,75 1,97 6,38 8,32 1,88
PLTGU | CPP 42,50 2,51 46,02 2,51 52,93 2,65 76,18 2,77 217,63 2,63 PLTGU (Gas) | Gas CPP 40,50 2,39 45,49 2,48 52,32 2,63 75,47 2,77 213,78 2,59 PLTGU (HSD) | HSD CPP 1,99 193,39 0,53 22,21 0,61 9,83 0,71 3,49 3,85 12,84
PLTD | DPP 0,00 72,79 0,00 - - 54,83 - 66,27 0,01 62,71 PLTP | GPP 34,22 4,64 32,81 4,60 34,71 4,57 31,93 4,68 133,68 4,62 PLTA | HPP 7,60 0,59 6,59 0,65 2,98 0,69 4,04 0,61 21,21 0,62 PLTDG | GTDPP 0,27 9,69 3,56 1,54 3,39 2,96 2,07 2,77 9,28 2,20
PLTDG (MFO) | MFO GTDPP 0,27 9,69 0,78 1,33 0,49 8,29 1,33 2,50 2,86 2,38 PLTDG (HSD) | HSD GTDPP - - 2,78 1,61 2,90 2,67 0,74 3,43 6,42 2,12
INDONESIA POWER 398,09 4,41 435,39 4,38 436,26 4,54 448,63 4,26 1.718,37 4,39
TW IIITW IITW I TW IV
INDONESIA POWER
PLTDG GTDPP
PLTA HPP
PLTP GPP
PLTD DPP
PLTGU CPP
PLTG GTPP
PLTU SPP
6,15
5,76
5,44
5,3
1
0,96
1,37
3,60
1,93
2,51
2,5
1
2,65
2,77
4,6
4
54,8
3
66,2
7
0
72,7
9
4,60
4,57
4,68
0,5
9
0,6
5
0,6
9
0,61
1,5
4
9,6
9
2,9
6
2,7
7
4,41
4,38
4,5
4
4,2
6
Tabel Table
23Pemakaian Sendiri Per Jenis Pembangkit Tahun 2015Self Consumption Per Power Plant Type in 2015
Grafik Graph
23Pemakaian Sendiri Per Jenis Pembangkit Tahun 2015 (%)Self Consumption Per Power Plant Type in 2015 (%)
PRODUKSI, PENJUALAN DAN PEMAKAIAN SENDIRI PRODUCTION, SALES AND SELF CONSUMPTION 47LAPORAN STATISTIK
STATISTIC REPORT 2015
Pemakaian Bahan Bakar
Fuel Consumption
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION48 LAPORAN STATISTIK
STATISTIC REPORT2015
Tabel Table
24Pemakaian Bahan Bakar Tahun 2011-2015Fuel Consumption in 2011-2015
2011 2012 2013 2014 2015
Batu bara | Coal (ton) 11.766.489,00 11.073.637,92 12.147.717,11 11.562.703,83 12.168.481,74
Pertumbuhan Pemakaian Batubara | Coal Consumption Growth (0,58) (5,89) 9,70 (4,82) 5,24
HSD (kiloliter) 2.261.263,36 1.039.142,73 915.700,03 778.070,12 326.944,37
Pertumbuhan Pemakaian HSD | HSD Consumption Growth (%) 3,99 (54,05) (11,88) (15,03) (57,98)
MFO (kiloliter) 545.631,87 198.953,28 132.096,78 121.422,19 100.803,69
Pertumbuhan Pemakaian MFO | MFO Consumption Growth (%) (14,58) (63,54) (33,60) (8,08) (16,98)
Gas (mmbtu) 34.883.625,00 57.648.169,95 65.226.077,55 62.838.572,47 76.851.476,82
Pertumbuhan Pemakaian Gas | Gas Consumption Growth (%) 45,23 65,26 13,15 (3,66) 22,30
Grafik Graph
24Pemakaian Bahan Bakar HSD dan MFO Tahun 2011-2015 (kiloliter)HSD and MFO Fuel Consumption in 2011-2015 (kiloliter)
545
.631
,87
2.2
61.2
63,3
6
1.0
39.1
42,7
3
198.
953,
28
132
.096
,78
121
.422
,19
100
.803
,69
HSD (kiloliter) MFO (kiloliter)
2011 2012 2013 2014 2015
915
.700
,03
778
.070
,12
326
.944
,37
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION 49LAPORAN STATISTIK
STATISTIC REPORT 2015
Grafik Graph
25Pertumbuhan Pemakaian Bahan Bakar HSD dan MFO Tahun 2011-2015 (%)HSD and MFO Consumption Growth in 2011-2015 (%)
-80
-70
-60
-50
-40
-30
-20
-10
0
10
2011 2012 2013 2014 2015
Pertumbuhan Pemakaian MFO | MFO Consumption Growth (%) Pertumbuhan Pemakaian HSD | HSD Consumption Growth (%)
Grafik Graph
26Pemakaian Bahan Bakar Gas (mmbtu) dan Batubara (ton) Tahun 2011-2015Gas (mmbtu) and Coal (ton) Consumption in 2011-2015
2011 2013 2014 20152012
34.88
3.625
,00
57.64
8.169
,95
65.22
6.077
,55
11.07
3.637
,92
11.76
6.489
12.14
7.717
,11
62.83
8.572
,47
11.56
2.703
,83 76
.851.4
76,82
12.16
8.481
,74
Batu bara | Coal (ton) Gas (mmbtu)
Grafik Graph
27Pertumbuhan Pemakaian Bahan Bakar Gas dan Batubara Tahun 2011-2015 (%)Gas Consumption and Coal Consumption Growth in 2011-2015 (%)
Pertumbuhan Pemakaian Batubara | Coal Consumption Growth (%)Pertumbuhan Pemakaian Gas | Gas Consumption Growth (%)
-10
0
10
20
30
40
50
60
70
80
2014201320122011 2015
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION50 LAPORAN STATISTIK
STATISTIC REPORT2015
Unit Jenis Bahan BakarFuel Type
Realisasi Realization
RencanaPlan
Realisasi Realization
Pencapaian Achievement
(%)
Rencana Plan
Pertumbuhan Growth
(%) 2014 2015 2016 2014 2015
A. JAWA BALI GRID & EMBEDDED
Suralaya Batubara | Coal (ton) 11.562.703,83 12.184.200,00 12.168.481,74 99,87 11.726.437,54 4,42 5,24 HSD (kiloliter) 6.288,40 - 6.856,20 - - (56,83) 9,03
Priok HSD (kiloliter) 44.768,69 172.904,03 7.245,11 4,19 8.145,00 (86,93) (83,82)Gas (mmbtu) 31.763.849,44 32.040,000,00 29.333.742,50 91,55 30.260,000 13,25 (7,65)
Semarang HSD (kiloliter) 32.498,54 110.893,98 656,36 0,59 7.200,00 (49,22) (97,98)MFO (kiloliter) 2.097,51 84.344,38 - - - (93,10) (100,00)Gas (mmbtu) 2.946.034,78 24.591.416,67 23.690.310,75 96,34 51.027,000 662,29 704,14
Perak Grati HSD (kiloliter) 3.485,96 - 2.423,46 - - (66,95) (30,48)MFO (kiloliter) - 24.632,70 - - - (100,00) - Gas (mmbtu) 28.128.688,25 33.061.806,73 23.827.423,57 72,07 36.276,400 (3,72) (15,29)
Bali HSD (kiloliter) 327.295,37 136.497,99 242.109,79 177,37 19.927,81 (19,17) (26,03)MFO (kiloliter) - 213.446,45 25.817,20 12,10 - - - Gas (mmbtu) - - - - 11.209,728 - -
Total Batubara | Coal (ton) 11.562.703,83 12.184.200,00 12.168.481,74 99,87 11.726.437,54 4,42 5,24 HSD (kiloliter) 414.336,96 430.296,00 259.290,91 60,26 45.272,81 (50,47) (37,42)MFO (kiloliter) 2.097,51 322.423,53 25.817,20 8,01 - (96,96) 1.130,85 Gas (mmbtu) 62.838.572,47 89.693.223,39 76.851.476,82 85,68 128.773,128 9,00 22,30
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY
Pesanggaran MFO (kiloliter) 119.324,68 100.179,00 74.986,49 74,85 101.867,00 (8,22) 62,84 HSD (kiloliter) 268.071,86 - 67.653,46 - - 21,611,25 25,24
Pemaron HSD (kiloliter) 95.661,30 - - - - (52,48) - Nusa Penida - - - - - - - Karimunjawa Gas (mmbtu) - 91.250,000,00 - - 89,000,00 - - INDONESIA POWER Batubara | Coal (ton) 11.562.703,83 12.184.200,00 12.168.481,74 99,87 11.726.437,54 4,42 5,24
HSD (kiloliter) 778.070,12 430.296,00 326.944,37 75,98 45.272,81 (25,12) (57,98)MFO (kiloliter) 121.422,19 422.602,53 100.803,69 23,85 101.867,00 (38,97) (16,98)Gas (mmbtu) 62.838.572,47 180.943.223,39 76.851.476,82 42,47 128.862.128,00 9,00 22,30
PEMAKAIAN BAHAN BAKAR PER UNITFUEL CONSUMPTION PER UNIT
MFO (kiloliter) HSD (kiloliter)
Realisasi | Realization 2014 Rencana | Plan 2016
121
.422
,19
778.
070,
12
326
.944
,37
100
.803
,69
45.
272,
8110
1.86
7,00
Realisasi | Realization 2015
Tabel Table
25Realisasi Pemakaian Bahan Bakar Per Unit Tahun 2014-2015 dan Rencana Tahun 2016 Fuel Consumption Realization Per Unit in 2014-2015 and Plan of 2016
Grafik Graph
28Realisasi Pemakaian Bahan Bakar HSD dan MFO Per Unit Tahun 2014-2015 dan Rencana Tahun 2016 (kiloliter)HSD and MFO Consumption Realization Per Unit in 2014-2015 and Plan of 2016 (kiloliter)
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION 51LAPORAN STATISTIK
STATISTIC REPORT 2015
Unit Jenis Bahan BakarFuel Type
Triwulan | Quarterly2015
TW I TW II TW III TW IV A. JAWA BALI GRID & EMBEDDED
Suralaya Batubara | Coal (ton) 2.650.916,97 3.217.413,50 3.145.119,68 3.155.031,59 12.168.481,74 HSD (kiloliter) 2.622,70 1.418,10 1.426,50 1.388,90 6.856,20
Priok HSD (kiloliter) 75.52 563,71 1.462,88 5.142,99 7.245,11 Gas (mmbtu) 7.474.458,76 7.903.472,38 6.148.424,58 7.807.386,79 29.333.742,50
Semarang HSD (kiloliter) 349,11 30,07 40,04 237,13 656,36 MFO (kiloliter) - - - - - Gas (mmbtu) 2.930.673,89 2.749.541,89 6.163.671,92 11.846.423,04 23.690.310,75
Perak Grati HSD (kiloliter) 33,68 - - 2.389,78 2.423,46 Gas (mmbtu) 4.762.157,47 5.926.425,22 6.228.890,37 6.909.950,51 23.827.423,57
Bali HSD (kiloliter) 95.461,05 101.166,63 30.465,70 15.016,41 242.109,79 MFO (kiloliter) - 13.159,50 1.232,00 11.425,70 25.817,20 Gas (mmbtu) - - - - -
Total Batubara | Coal (ton) 2.650.916,97 3.217.413,50 3.145.119,68 3.155.031,59 12.168.481,74 HSD (kiloliter) 98.542,06 103.178,51 33.395,13 24.175,22 259.290,91 MFO (kiloliter) - 13.159,50 1.232,00 11.425,70 25.817,20 Gas (mmbtu) 15.167.290,11 16.579.439,49 18.540.986.87 26.563.760,34 76.851.476,82
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY Pesanggaran HSD (kiloliter) 40.542,72 24.195,31 2.419,49 495,93 67.653,46
MFO (kiloliter) 34.712,16 24.487,72 10.776,63 5.009,99 74.986,49 Nusa Penida - - - - - INDONESIA POWER Batubara | Coal (ton) 2.650.916,97 3.217.413,50 3.145.119,68 3.155.031,59 12.168.481,74
HSD (kiloliter) 139.084,78 127.373,82 35.814,62 24.671,15 326.944,37 MFO (kiloliter) 34.712,16 37.647,21 12.008,63 16.435,69 100.803,69 Gas (mmbtu) 15.167.290,11 16.579.439,49 18.540.986,87 26.563.760,34 76.851.476,82
Batu bara | CoalGas (mmbtu)
Realisasi | Realization 2014 Rencana | Plan 2016 Realisasi | Realization 2015
62.8
38.5
72.4
7
76.8
51.4
76.8
2 128.
862.
128.
00
11.7
26.4
37.5
4
12.
168.
481.
74
11.5
62.7
03.8
3
Tabel Table
26Pemakaian Bahan Bakar Per Unit Tahun 2015 Fuel Consumption Per Unit in 2015
Grafik Graph
29Realisasi Pemakaian Bahan Bakar Gas (mmbtu) dan Batubara (ton) 2014-2015 dan Rencana Tahun 2016Gas (mmbtu) and Coal (ton) Consumption Realization in 2014-2015 and Plan of 2016
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION52 LAPORAN STATISTIK
STATISTIC REPORT2015
139.
084,
78
34.7
12,1
6
127.
373,
82
37.6
47,2
1
35.8
14,6
212
.008
,63
24.6
71,1
5
16.4
35,6
9 TW I TW II TW III TW IV
MFO (kiloliter) HSD (kiloliter)
Batu bara | Coal (ton)Gas (mmbtu)
TW I TW II TW III TW IV
15.1
67.2
90,1
1
16.5
79.4
39,4
9
18.5
40.9
86,8
7
26.5
63.7
60,3
4
3.21
7.41
3,50
2.65
0.91
6,97
3.15
5.03
1,59
3.14
5.11
9,68
Grafik Graph
30Pemakaian Bahan Bakar HSD dan MFO Tahun 2015 (kiloliter)HSD and MFO Fuel Consumption in 2015 (kiloliter)
Grafik Graph
31Pemakaian Bahan Bakar Gas (mmbtu) dan Batubara (ton) Tahun 2015Gas (mmbtu) and Coal (ton) Consumption in 2015
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION 53LAPORAN STATISTIK
STATISTIC REPORT 2015
PEMAKAIAN BAHAN BAKAR PER JENIS PEMBANGKITFUEL CONSUMPTION PER POWER PLANT TYPE
Jenis Pembangkitan
Power Plant Type
Jenis Bahan Bakar
Fuel Type
Realisasi Realization
Rencana Plan
RealisasiRealization
Pencapaian Achievement
(%)
Rencana Plan
PertumbuhanGrowth
(%)
2014 2015 2016 2014 2015
A. JAWA BALI GRID & EMBEDDED
PLTU | SPP Batubara Coal (ton)
11.562.703,83 12.184.200,00 12.168.481,74 99,87 11.726.437,54 4,42 5,24
HSD (kiloliter) 6.289,24 - 6.856.20 - - (57,85) 9,01
MFO (kiloliter) - 108.977,08 - - - (100,00) -
Gas (mmbtu) - 2.355.139,33 - - 6.739.406,90 - -
PLTG | GTPP HSD (kiloliter) 328.299,02 142.483,50 171.748,49 120,54 8.160,14 (13,46) (47,69)
Gas (mmbtu) 3.753.427,20 6.052.000,00 2.655.552,66 43,88 6.052.000,00 98,37 (29,25)
PLTGU | CPP HSD (kiloliter) 77.383,08 277.812,50 7.740,60 2,79 14.345,00 (81,09) (90,00)
MFO (kiloliter) 2.097,51 - - - - 358,09 (100,00)
Gas (mmbtu) 59.085.145,27 81.286.084,06 74.195.924,16 91,28 104.771.993,10 5,97 25,57
PLTD | DPP HSD (kiloliter) 2.365,63 - - - - (92,85) (100,00)
PLTDG | GTDPP HSD (kiloliter) - - 72.945,63 12.767,68 - -
MFO (kiloliter) - 213.446,45 25.817,20 12,10 - - -
Gas (mmbtu) - - - - 11.209.728,00
Total Batubara Coal (ton)
11.562.703,83 12.184.200,00 12.168.481,74 99,87 11.726.437,54 4,42 5,24
HSD (kiloliter) 414.336,96 430.296,00 259.290,91 60,26 45.272,81 (51,06) (37,42)
MFO (kiloliter) 2.097,51 322.423,53 25.817,20 8,01 - (96,96) 1,130,85
Gas (mmbtu) 62.838.572,47 89.693.223,39 76.851.476,82 85,68 128.773.128,00 9,00 22,30
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY
PLTD | DPP HSD (kiloliter) 363.733,16 - 67.653,46 - - 79,57 (81,40)
MFO (kiloliter) 119.324,68 100.179,00 74.986,49 74,85 101.867,00 (8,22) (37,16)
PLTMG | GTMPP Gas (mmbtu) - 91.250.000,00 - - 89.000,00 - -
INDONESIA POWER
Batubara Coal (ton)
11.562.703,83 12.184.200,00 12.168.481,74 99,87 11.726.437,54 4,42 5,24
HSD (kiloliter) 778.070,12 430.296,00 326.944,37 75,98 45.272,81 (25,84) (57,98)
MFO (kiloliter) 121.422,19 422.602,53 100.803,69 23,85 101.867,00 (38,97) (16,98)
Gas (mmbtu) 62.838.572,47 180.943.223,39 76.851.476,82 42,47 128.862.128,00 9,00 22,30
Tabel Table
27Realisasi Pemakaian Bahan Bakar Per Jenis Pembangkit Tahun 2014-2015 dan Rencana Tahun 2016 Fuel Consumption Realization Per Power Plant Type in 2014-2015 and Plan of 2016
PEMAKAIAN BAHAN BAKARFUEL CONSUMPTION54 LAPORAN STATISTIK
STATISTIC REPORT2015
Jenis PembangkitanPower Plant Type
Jenis Bahan BakarFuel Type
Triwulan | Quarterly2015
TW I TW II TW III TW IV
A. JAWA BALI GRID & EMBEDDED
PLTU | SPP Batubara | Coal (ton) 2.650.916,97 3.217.413,50 3.145.119,68 3.155.031,59 12.168.481,74
HSD (kiloliter) 2.622,70 1.418,10 1.426,50 1.388,90 6.856,20
MFO (kiloliter) - - - - -
PLTG | GTPP HSD (kiloliter) 95.477,95 60.029,09 4.578,71 11.662,74 171.748,49
Gas (mmbtu) 159.770,37 489.250,46 771.098,76 1.235.433,07 2.655.552,66
PLTGU | CPP HSD (kiloliter) 439,96 592,16 1.501,09 5.207,39 7.740,60
MFO (kiloliter) - - - - -
Gas (mmbtu) 15.007.519,74 16.090.189,04 17.769.888,11 25.328.327,27 74.195.924,16
PLTDG | GTDPP HSD (kiloliter) 1,46 41.139,15 25.888,83 5.916,18 72.945,63
MFO (kiloliter) - 13.159,50 1.232,00 11.425,70 25.817,20
Total Batubara | Coal (ton) 2.650.916,97 3.217.413,50 3.145.119,68 3.155.031,59 12.168.481,74
HSD (kiloliter) 98.542,06 103.178,51 33.395,13 24.175,22 259.290,91
MFO (kiloliter) - 13.159,50 1.232,00 11.425,70 25.817,20
Gas (mmbtu) 15.167.290,11 16.579.439,49 18.540.986,87 26.563.760.34 76.851.476,82
B. PEMBELIAN LISTRIK | PURCHASE OF ELECTRICITY
PLTD | DPP HSD (kiloliter) 40.542,72 24.195,31 2.419,49 495,93 67.653,46
MFO (kiloliter) 34.712,16 24.487,72 10.776,63 5.009,99 74.986,49
INDONESIA POWER Batubara | Coal (ton) 2.650.916,97 3.217.413,50 3.145.119,68 3.155.031,59 12.168.481,74
HSD (kiloliter) 139.084,78 127.373,82 35.814,62 24.671,15 326.944,37
MFO (kiloliter) 34.712,16 37.647,21 12.008,63 16.435,69 100.803,69
Gas (mmbtu) 15.167.290,11 16.579.439,49 18.540.986,87 26.563.760,34 76.851.476,82
Tabel Table
28Pemakaian Bahan Bakar Per Jenis Pembangkit Tahun 2015 Fuel Consumption Per Power Plant Type in 2015
Kinerja OperasionalOperational
Performance
KINERJA OPERASIONALOPERATIONAL PERFORMANCE56 LAPORAN STATISTIK
STATISTIC REPORT2015
Tabel Table
29Kinerja Unit Indonesia Power Tahun 2011-2015 Indonesia Power Unit Performance in 2011-2015
Unsur KinerjaPerformance Factor
Tahun | Year
2011 2012 2013 2014 2015
Faktor Efisiensi | Efficiency Factor
CF (%) 60,39 51,88 55,30 50,17 51,89
Faktor Keandalan | Reliability Factor
EAF (%) 91,09 92,33 93,04 89,88 90,85
Grafik Graph
32Kinerja Unit Indonesia Power Tahun 2011-2015 (%)Indonesia Power Unit Performance in 2011-2015 (%)
KINERJAPERFORMANCE
EAF (%)CF (%)
2011 2012 2013 2014 2015
100
80
60
40
KINERJA OPERASIONALOPERATIONAL PERFORMANCE 57LAPORAN STATISTIK
STATISTIC REPORT 2015
Tabel Table
30Realisasi EAF Tahun 2014-2015 dan Rencana Tahun 2016EAF Realization in 2014-2015 and Plan of 2016
Tabel Table
31Realisasi CF Tahun 2014-2015 dan Rencana Tahun 2016CF Realization in 2014-2015 and Plan of 2016
Unit Realisasi
Realization Rencana
PlanRealisasi
RealizationPencapaian
Achievement (%) Rencana
Plan
2014 2015 2016
Suralaya 84,05 90,44 91,41 101,07 90,00
Priok 87,48 92,27 90,81 98,42 89,40
Saguling 97,30 93,30 92,26 98,89 91,21
Kamojang 91,97 96,33 96,61 100,29 92,91
Semarang 96,77 90,59 84,09 92,83 88,48
Mrica 97,90 97,39 98,09 100,71 96,55
Perak Grati 95,78 93,01 93,44 100,47 92,51
Bali 91,78 91,06 87,19 95,75 88,10
INDONESIA POWER 89,88 91,70 90,85 99,07 90,32
Unit Realisasi
Realization Rencana
PlanRealisasi
RealizationPencapaian
Achievement (%) Rencana
Plan
2014 2015 2016
Suralaya 75,98 77,90 78,93 101,32 74,91 Priok 35,66 43,84 34,79 79,35 35,66 Saguling 45,31 46,97 35,82 76,27 37,93 Kamojang 87,36 85,69 96,44 112,55 89,35 Semarang 3,25 32,04 24,89 77,71 53,29 Mrica 32,24 39,06 32,77 83,90 36,88 Perak Grati 39,59 47,73 32,83 68,79 50,55 Bali 28,75 23,83 18,47 77,50 27,57 INDONESIA POWER 50,17 56,41 51,89 91,98 56,79
KINERJA OPERASIONALOPERATIONAL PERFORMANCE58 LAPORAN STATISTIK
STATISTIC REPORT2015
Unsur KinerjaPerformance Factor
Triwulan I Quarter
s/d MaretUntil March
s/d JuniUntil June
s/d SeptemberUntil September
s/d DesemberUntil December
Faktor Efisiensi | Efficiency Factor
CF (%) 36,29 37,17 34,16 34,79
Faktor Keandalan | Reliability Factor
EAF (%) 94,41 91,77 92,30 90,81
EAF (%)CF (%)
s/d Maret/Until March s/d Juni/Until June s/d September/Until September s/d Desember/Until December
100
80
60
KINERJA PER UNITPERFORMANCE PER UNIT
Unsur KinerjaPerformance Factor
Triwulan I Quarters/d Maret
Until Marchs/d Juni
Until Junes/d September
Until Septembers/d Desember
Until DecemberFaktor Efisiensi | Efficiency FactorCF (%) 68,43 74,34 77,37 78,93 Faktor Keandalan | Reliability FactorEAF (%) 87,72 89,54 91,33 91,41
Tabel Table
32Kinerja Unit Pembangkitan Suralaya Tahun 2015Suralaya Generating Unit Performance in 2015
Tabel Table
33Kinerja Unit Pembangkitan dan Jasa Pembangkitan Priok Tahun 2015Priok Generating and Generating Services Unit Performance in 2015
Grafik Graph
33Kinerja Unit Pembangkitan Suralaya Tahun 2015 (%)Suralaya Generating Unit Performance in 2015 (%)
KINERJA OPERASIONALOPERATIONAL PERFORMANCE 59LAPORAN STATISTIK
STATISTIC REPORT 2015
Unsur KinerjaPerformance Factor
Triwulan I Quarter
s/d MaretUntil March
s/d JuniUntil June
s/d SeptemberUntil September
s/d DesemberUntil December
Faktor Efisiensi | Efficiency Factor
CF (%) 54,52 47,47 38,12 35,82
Faktor Keandalan | Reliability Factor
EAF (%) 99,29 98,61 93,71 92,26
EAF (%)CF (%)
s/d Maret/Until March s/d Juni/Until June s/d September/Until September s/d Desember/Until December20
40
60
80
100
EAF (%)CF (%)
s/d Maret/Until March
100
80
60
40
20 s/d Juni/Until June s/d September/Until September s/d Desember/Until December
Tabel Table
34Kinerja Unit Pembangkitan Saguling Tahun 2015Saguling Generating Unit Performance in 2015
Grafik Graph
34Kinerja Unit Pembangkitan dan Jasa Pembangkitan Priok Tahun 2015 (%)Priok Generating and Generating Services Unit Performance in 2015 (%)
Grafik Graph
35Kinerja Unit Pembangkitan Saguling Tahun 2015 (%)Saguling Generating Unit Performance in 2015 (%)
KINERJA OPERASIONALOPERATIONAL PERFORMANCE60 LAPORAN STATISTIK
STATISTIC REPORT2015
Unsur KinerjaPerformance Factor
Triwulan I Quarter
s/d MaretUntil March
s/d JuniUntil June
s/d SeptemberUntil September
s/d DesemberUntil December
Faktor Efisiensi | Efficiency Factor
CF (%) 99,64 97,55 98,55 96,44
Faktor Keandalan | Reliability Factor
EAF (%) 99,12 96,88 97,71 96,61
80
60
40
20
100
EAF (%)CF (%)
s/d Maret/Until March s/d Juni/Until June s/d September/Until September s/d Desember/Until December
Tabel Table
35Kinerja Unit Pembangkitan dan Jasa Pembangkitan Kamojang Tahun 2015Kamojang Generating and Generating Services Unit Performance in 2015
Grafik Graph
36Kinerja Unit Pembangkitan dan Jasa Pembangkitan Kamojang Tahun 2015 (%)Kamojang Generating and Generating Services Unit Performance in 2015 (%)
KINERJA OPERASIONALOPERATIONAL PERFORMANCE 61LAPORAN STATISTIK
STATISTIC REPORT 2015
Unsur KinerjaPerformance Factor
Tahun | Year
s/d MaretUntil March
s/d JuniUntil June
s/d SeptemberUntil September
s/d DesemberUntil December
Faktor Efisiensi | Efficiency Factor
CF (%) 52,09 48,51 36,23 32,77
Faktor Keandalan | Reliability Factor
EAF (%) 99,68 99,67 97,68 98,09
20
40
60
80
100
EAF (%)CF (%)
s/d Maret/Until March s/d Juni/Until June s/d September/Until September s/d Desember/Until December
Tabel Table
36Kinerja Unit Pembangkitan Mrica Tahun 2015Mrica Generating Unit Performance in 2015
Grafik Graph
37Kinerja Unit Pembangkitan Mrica Tahun 2015 (%)Mrica Generating Unit Performance in 2015 (%)
KINERJA OPERASIONALOPERATIONAL PERFORMANCE62 LAPORAN STATISTIK
STATISTIC REPORT2015
Unsur KinerjaPerformance Factor
Triwulan I Quarter
s/d MaretUntil March
s/d JuniUntil June
s/d SeptemberUntil September
s/d DesemberUntil December
Faktor Efisiensi | Efficiency Factor
CF (%) 11,89 11,41 16,41 24,89
Faktor Keandalan | Reliability Factor
EAF (%) 95,90 88,68 85,70 84,09
20
40
60
80
100
0
EAF (%)CF (%)
s/d Maret/Until March s/d Juni/Until June s/d September/Until September s/d Desember/Until December
Tabel Table
37Kinerja Unit Pembangkitan Semarang Tahun 2015Semarang Generating Unit Performance in 2015
Grafik Graph
38Kinerja Unit Pembangkitan Semarang Tahun 2015 (%)Semarang Generating Unit Performance in 2015 (%)
KINERJA OPERASIONALOPERATIONAL PERFORMANCE 63LAPORAN STATISTIK
STATISTIC REPORT 2015
Unsur KinerjaPerformance Factor
Triwulan I Quarter
s/d MaretUntil March
s/d JuniUntil June
s/d SeptemberUntil September
s/d DesemberUntil December
Faktor Efisiensi | Efficiency Factor
CF (%) 28,11 31,44 32,71 32,83
Faktor Keandalan | Reliability Factor
EAF (%) 99,58 97,49 97,96 93,44
EAF (%)CF (%)
s/d Mar | Until Mar s/d Jun | Until June s/d Sept | Until Sept s/d Des | Until Dec20
40
60
80
100
Tabel Table
38Kinerja Unit Pembangkitan Perak Grati Tahun 2015Perak Grati Generating Unit Performance in 2015
Grafik Graph
39Kinerja Unit Pembangkitan Perak Grati Tahun 2015 (%)Perak Grati Generating Unit Performance in 2015 (%)
KINERJA OPERASIONALOPERATIONAL PERFORMANCE64 LAPORAN STATISTIK
STATISTIC REPORT2015
Unsur KinerjaPerformance Factor
Triwulan I Quarter
s/d MaretUntil March
s/d JuniUntil June
s/d SeptemberUntil September
s/d DesemberUntil December
Faktor Efisiensi | Efficiency Factor
CF (%) 21,85 27,67 21,88 18,47
Faktor Keandalan | Reliability Factor
EAF (%) 96,91 84,74 88,59 87,19
100
0
20
40
60
80
100
EAF (%)CF (%)
s/d Maret/Until March s/d Juni/Until June s/d September/Until September s/d Desember/Until December
Tabel Table
39Kinerja Unit Pembangkitan dan Jasa Pembangkitan Bali Tahun 2015Bali Generating and Generating Services Unit Performance in 2015
Grafik Graph
40Kinerja Unit Pembangkitan dan Jasa Pembangkitan Bali Tahun 2015 (%)Bali Generating and Generating Services Unit Performance in 2015 (%)
KINERJA OPERASIONALOPERATIONAL PERFORMANCE 65LAPORAN STATISTIK
STATISTIC REPORT 2015
KeuanganFinancial
KEUANGANFINANCIAL66 LAPORAN STATISTIK
STATISTIC REPORT2015
Grafik Graph
41Jumlah Aktiva, Laba Tahun Berjalan dan Pendapatan Usaha Tahun 2011-2015 (dalam Rp miliar)Total Asset, Income for the Year and Revenue in 2011-2015 (in billion Rp)
Tabel Table
40Pertumbuhan Jumlah Aktiva, Laba Tahun Berjalan, Pendapatan Usaha dan Pendapatan Penjualan Energi Listrik Tahun 2011-2015Growth of Total Asset, Income of the Year, Revenue and Electricity Sales Revenue in 2011-2015
Uraian Description
Tahun | Year
2011 2012 2013 2014**) 2015*)
Jumlah Aktiva (dalam Rp miliar) Total Asset (in billion Rp)
53.485,11 53,557,38 53.480,49 53.248,06 226.486,56
Pertumbuhan | Growth (%) 2,19 0,14 (0,14) (0,43) 325,34
Jumlah Laba Tahun Berjalan (dalam Rp miliar)Total Income for The Year (in billion Rp)
1.157,63 1.266,74 1.242,47 1.647,23 4.679,53
Pertumbuhan | Growth (%) 10,10 9,43 (1,92) 32,58 184,08
Pendapatan Usaha (dalam Rp miliar)Electricity Sales Revenue (in billion Rp)
43.416,12 32.472,48 33.531,49 35.723,62 32.020,19
Pertumbuhan | Growth (%) 25,80 (25,21) 3,26 6,54 (10,37)
Pendapatan Penjualan Energi Listrik (dalam Rp miliar)Electricity Sales Revenue (in billion Rp)
42.917,04 31.852,55 32.933,05 34.828,75 30.680,91
Pertumbuhan | Growth (%) 25,70 (25,78) 3,39 5,76 (11,91)
*) Data setelah revaluasi aset**) Data keuangan tahun 2014 restated
*) Data after asset revaluation**) 2014 Financial data - restated
2011 2013 2014 20152012
1.15
7,63
1.2
66,7
4
1.6
47,2
3
4.67
9,53
1.24
2,47
Jumlah Aktiva (dalam Rp miliar) Total Assets (in billion Rp)
Jumlah Laba Tahun Berjalan (dalam Rp miliar)Total Income for the Year (in billion Rp)
Pendapatan Usaha (dalam Rp miliar)Electricity Sales Revenue (in billion Rp)
53.4
85,1
1
43.4
16,1
2
53.
557,
38
32.4
72,4
8
53.
480,
49
53.2
48,0
6
35.
723,
62
33.5
31,4
9
226
.486
,56
32.0
20,1
9
KEUANGANFINANCIAL
KEUANGANFINANCIAL 67LAPORAN STATISTIK
STATISTIC REPORT 2015
Grafik Graph
42Pertumbuhan Jumlah Aktiva, Laba Tahun Berjalan dan Pendapatan Usaha Tahun 2011-2015 (%) Total Asset, Income for the Year and Revenue Growth in 2011-2015 (%)
Tabel Table
41Pendapatan Penjualan Energi Listrik Per Unit Tahun 2015 (dalam juta)Electricity Sales Revenue Per Unit in 2015 (in million)
Unit Triwulan | Quarter
Jumlah | Total TW I TW II TW III TW IV
Suralaya 2.955.624,93 3.366.080,57 3.514.798,56 3.478.951,31 13.315.455,38
Priok 1.277.939,21 1.331.925,30 1.204.289,50 1.261.173,83 5.075.327,85
Saguling 194.367,63 187.634,99 153.989,94 167.420,19 703.412,75
Kamojang 631.154,40 608.429,54 691.509,85 656.571,06 2.587.664,85
Semarang 507.968,59 470.192,99 833.074,43 1.343.838,43 3.155.074,45
Mrica 74.823,78 72.858,75 56.338,94 57.184,78 261.206,26
Perak Grati 526.736,03 546.449,57 711.051,24 769.848,49 2.554.085,33
Bali 1.194.158,71 1.183.856,38 401.901,01 248.766,09 3.028.682,18
INDONESIA POWER 7.362.773,29 7.767.428,10 7.566.953,48 7.983.754,19 30.680.909,05
Pertumbuhan Laba Tahun BerjalanGrowth of Income for The Year (%)
Pertumbuhan Pendapatan Usaha Growth of Revenue (%)
Pertumbuhan Aktiva Growth of Assets (%)
2011 2012 2013 2014 2015
-50
0
50
100
150
200
250
300
350
KEUANGANFINANCIAL68 LAPORAN STATISTIK
STATISTIC REPORT2015
Jenis PembangkitPower Plant Type
Triwulan | Quarter Jumlah | Total
TW I TW II TW III TW IV
PLTG | GTPP 741.950,43 532.992,06 201.940,70 303.519,41 1.780.402,59
PLTU | SPP 2.991.522,88 3.402.574,24 3.547.939,90 3.515.811,15 13.457.848,18
PLTU-B | SPP-C 2.955.624,93 3.366.080,57 3.514.798,56 3.478.951,31 13.315.455,38
PLTU-M | SPP-F 35.897,95 36.493,67 33.141,34 36.859,85 142.392,80
PLTGU | CPP 2.210.488,47 2.227.554,51 2.580.612,14 3.135.117,87 10.153.773,00
PLTA | HPP 269.191,41 260.493,74 210.328,88 224.604,98 964.619,01
PLTP | GPP 631.154,40 608.429,54 691.509,85 656.571,06 2.587.664,85
PLTD | DPP 518.465,70 353.574,45 86.807,99 16.295,93 975.144,07
PLTDG | GTDPP - 381.809,55 247.814,01 131.833,79 761.457,36
INDONESIA POWER 7.362.773,29 7.767.428,10 7.566.953,48 7.983.754,19 30.680.909,05
Uraian | Description 2015 2014
Pendapatan Usaha | Revenue 32.020.186 35.723.617
Penjualan Tenaga Listrik | Electricity Sales 30.680.909 34.828.754
Pendapatan Jasa | Service Revenue 1.339.277 894.863
Beban Usaha | Operational Cost 29.929.498 33.527.047
Bahan Bakar dan Minyak Pelumas | Fuel and Lubricant 22.431.963 26.543.914
Pemeliharaan | Maintenance 2.405.605 2.080.842
Kepegawaian | Human Resource 1.760.602 1.337.719
Penyusutan aset tetap | Depreciation of Fixed Asset 2.728.472 2.674.160
Pembelian Tenaga Listrik dan Sewa | Electricity Purchase and Lease 244.555 612.366
Lain-lain | Others 358.301 278.046
Laba Usaha | Operating Income 2.090.688 2.196.570
Pendapatan (Beban) Lain-lain | Other Income (Cost) 8.198 73.881
Penghasilan bunga | Interest Income 31.383 28.718
Kerugian kurs mata uang asing-bersih | Foreign Exchange Loss - nett (5.358) (35.077)
Beban bunga | Interest Expense (238) (342)
Penghasilan lain-lain bersih | Other Income - nett (17.589) 80.582
Laba Sebelum Pajak Penghasilan | Income before tax 2.098.886 2.270.451
Manfaat (Beban) Pajak | Tax Benefit (Expense) 2.580.643 (623.219)
Pajak Kini | Current Tax (689.947) (687.753)
Manfaat Pajak Tangguhan | Deferred Tax Benefit 3.270.590 64.534
Laba tahun berjalan | Income of the Year 4.679.529 1.647.232
Tabel Table
42Pendapatan Penjualan Energi Listrik Per Jenis Pembangkit Tahun 2015 (dalam juta)Electricity Sales Revenue Per Power Plant Type in 2015 (in million)
Tabel Table
43Laba Rugi Tahun 2014-2015 (dalam juta)Profit/Loss Statement in 2014-2015 (in million)
KEUANGANFINANCIAL 69LAPORAN STATISTIK
STATISTIC REPORT 2015
KepegawaianHuman
Resources
KEPEGAWAIANHUMAN RESOURCES70 LAPORAN STATISTIK
STATISTIC REPORT2015
KEPEGAWAIAN HUMAN RESOURCES
Grafik Graph
43Jumlah Pegawai Aktif Tahun 2011-2015Total of Active Employees in 2011-2015
Jumlah Pegawai Aktif | Total of Active Employees
2011 2012 2013 2014 2015
3.659
3.498 3.462
3.553
3.639
Tabel Table
44Jumlah Pegawai Aktif Tahun 2011-2015Total of Active Employees in 2011-2015
UnitTahun | Year
2011 2012 2013 2014 2015Kantor Pusat | Head Office 336 346 374 374 356UP Suralaya | Suralaya GU 759 723 696 703 722UPJP Priok | Priok GGSU 314 301 304 315 308UP Saguling | Saguling GU 351 302 271 232 209UPJP Kamojang | Kamojang GGSU 307 289 271 254 247UP Semarang | Semarang GU 356 335 319 298 298UP Mrica | Mrica GU 300 274 223 196 180UP Perak Grati | Perak Grati GU 226 231 217 203 210UPJP Bali | Bali GGSU 245 238 231 292 351UJH | MSU 137 129 160 207 210UJP Banten 1 Suralaya | Banten 1 Suralaya GSU 65 66 74 71 77UJP Banten 2 Labuan | Banten 2 Labuan GSU 93 88 79 75 69UJP Banten 3 Lontar | UJP Banten 3 Lontar GSU 113 114 117 119 124UJP Jabar 2 Pel. Ratu | Jabar 2 Pel. Ratu GSU 57 62 93 97 115UJP Jateng 2 Adipala | Jateng 2 Adipala GSU - - 33 46 81UJP Pangkalan Susu | Pangkalan Susu GSU - - - 71 82Jumlah Pegawai Aktif | Total of Active Employees 3.659 3.498 3.462 3.553 3.639
KEPEGAWAIANHUMAN RESOURCES 71LAPORAN STATISTIK
STATISTIC REPORT 2015
Grafik Graph
44Jumlah Pegawai Berdasarkan Usia Tahun 2015Total Employees Based on Age in 2015
Tabel Table
45Jumlah Pegawai Berdasarkan Usia Tahun 2015Total Employees Based on Age in 2015
Unit
Umur (Tahun) | Age (Year) Jumlah Pegawai Total of
Employees
Usia Rata-Rata Average
Age < 26 26 - 30 31 - 35 36 - 40 41 - 45 46 - 50
51-55
51 - 54 ≥ 55
Kantor Pusat | Head Office 8 82 31 78 48 50 58 1 356 40
UP Suralaya | Suralaya GU 202 88 61 13 91 113 153 1 722 38
UPJP Priok | Priok GGSU 83 48 31 11 68 34 33 0 308 37
UP Saguling | Saguling GU 36 20 13 7 18 30 83 2 209 43
UPJP Kamojang | Kamojang GGSU 36 27 8 6 96 21 53 0 247 41
UP Semarang | Semarang GU 63 56 33 17 43 21 61 4 298 38
UP Mrica | Mrica GU 17 22 9 5 29 29 69 0 180 44
UP Perak Grati | Perak Grati GU 41 54 37 11 35 10 20 2 210 35
UPJP Bali | Bali GGSU 109 69 48 16 55 27 26 1 351 34
UJH | MSU 76 35 15 15 37 11 21 0 210 34
UJP Banten 1 Suralaya | Banten 1 Suralaya GSU 15 30 9 5 2 5 11 0 77 35
UJP Banten 2 Labuan | Banten 2 Labuan GSU 8 17 17 2 12 8 5 0 69 37
UJP Banten 3 Lontar | UJP Banten 3 Lontar GSU 35 50 8 2 7 9 13 0 124 33
UJP Jabar 2 Pel. Ratu | Jabar 2 Pel. Ratu GSU 33 50 2 2 10 6 12 0 115 33
UJP Jateng 2 Adipala | Jateng 2 Adipala GSU 24 25 11 6 5 8 2 0 81 33
UJP Pangkalan Susu | Pangkalan Susu GSU 33 25 7 6 10 1 0 0 82 30
Jumlah Pegawai Aktif | Total of Active Employees 819 698 340 202 566 383 620 11 3.639 38
Prosentase | Percentage (%) 22,51 19,18 9,34 5,55 15,55 10,52 17,04 0,30 100
22,51%< 26
Tahun | Year
19,18% 26 - 30
Tahun | Year
17,04% 51- 55
Tahun | Year
9,34% 31 - 35
Tahun | Year
10,52% 46 - 50
Tahun | Year
5,55% 36 - 40
Tahun | Year
15,55% 41 - 45
Tahun | Year
0,30% ≥ 55
Tahun | Year
KEPEGAWAIANHUMAN RESOURCES72 LAPORAN STATISTIK
STATISTIC REPORT2015
0,16%Eksekutif UtamaFirst Executive
Unit
Jenjang Jabatan | Position Level
Jumlah Pegawai Total Employees
Eksekutif Utama
First Executive
Eksekutif Senior | Senior
Executive
Eksekutif Executive
Penyelia Atas | Senior Supervisor
Penyelia Dasar | Junior
Supervisor
Pelaksana Officer
Kantor Pusat | Head Office 4 53 121 68 98 12 356
UP Suralaya | Suralaya GU 1 3 16 86 179 437 722
UPJP Priok | Priok GGSU - 1 6 36 69 196 308
UP Saguling | Saguling GU - 1 6 39 62 101 209
UPJP Kamojang | Kamojang GGSU - 1 5 43 63 135 247
UP Semarang | Semarang GU - 1 6 43 64 184 298
UP Mrica | Mrica GU - 1 4 38 52 85 180
UP Perak Grati | Perak Grati GU - 1 6 39 51 113 210
UPJP Bali | Bali GGSU - 1 13 49 105 183 351
UJH | MSU 1 4 32 47 37 89 210
UJP Banten 1 Suralaya | Banten 1 Suralaya GSU - 1 5 22 35 14 77
UJP Banten 2 Labuan | Banten 2 Labuan GSU - 1 5 24 33 6 69
UJP Banten 3 Lontar | UJP Banten 3 Lontar GSU - 1 5 33 49 36 124
UJP Jabar 2 Pel. Ratu | Jabar 2 Pel. Ratu GSU - 1 5 23 32 54 115
UJP Jateng 2 Adipala | Jateng 2 Adipala GSU - 1 5 22 27 26 81
UJP Pangkalan Susu | Pangkalan Susu GSU - 1 5 17 30 29 82
Jumlah Pegawai Aktif | Total of Active Employees 6 73 245 629 986 1700 3.639
Prosentase | Percentage (%) 0,16 2,01 6,73 17,28 27,10 46,72 100
27,10%Penyelia Dasar
Junior Supervisor
6,73%Eksekutif Executive
17,28%Penyelia Atas
Senior Supervisor
2,01%Eksekutif Senior
Senior Executive
46,72%Pelaksana
Officier
Grafik Graph
45Jumlah Pegawai Berdasarkan Jenjang Jabatan Tahun 2015Total Employees Based on Position Level in 2015
Tabel Table
46Jumlah Pegawai Berdasarkan Jenjang Jabatan Tahun 2015Total Employees Based on Position Level in 2015
KEPEGAWAIANHUMAN RESOURCES 73LAPORAN STATISTIK
STATISTIC REPORT 2015
10,17%WanitaFemale
89,83%Pria
Male
UnitDesember | December 2015
Jumlah | Total Pria | Male Wanita | Female
Kantor Pusat | Head Office 244 112 356
UP Suralaya | Suralaya GU 678 44 722
UPJP Priok | Priok GGSU 279 29 308
UP Saguling | Saguling GU 191 18 209
UPJP Kamojang | Kamojang GGSU 229 18 247
UP Semarang | Semarang GU 268 30 298
UP Mrica | Mrica GU 160 20 180
UP Perak Grati | Perak Grati GU 187 23 210
UPJP Bali | Bali GGSU 325 26 351
UJH | MSU 185 25 210
UJP Banten 1 Suralaya | Banten 1 Suralaya GSU 69 8 77
UJP Banten 2 Labuan | Banten 2 Labuan GSU 66 3 69
UJP Banten 3 Lontar | UJP Banten 3 Lontar GSU 118 6 124
UJP Jabar 2 Pel. Ratu | Jabar 2 Pel. Ratu GSU 114 1 115
UJP Jateng 2 Adipala | Jateng 2 Adipala GSU 78 3 81
UJP Pangkalan Susu | Pangkalan Susu GSU 78 4 82
Jumlah Pegawai Aktif | Total of Active Employees 3.269 370 3.639
Grafik Graph
46Jumlah Pegawai Berdasarkan Jenis Kelamin Tahun 2015Total Employees Based on Gender in 2015
Tabel Table
47Jumlah Pegawai Berdasarkan Jenis Kelamin Tahun 2015Total Employees Based on Gender in 2015
KEPEGAWAIANHUMAN RESOURCES74 LAPORAN STATISTIK
STATISTIC REPORT2015
1,48%SMP
Junior HighSchool
27,21%S1
Bachelor Degree
0,25%SD
PrimarySchool
5,41%SMU
Senior HighSchool
19,79%D3
Diploma Degree
2,42%S2
Master Degree
Unit
Pendidikan | Education Jumlah Pegawai
Total Employees
SD Primary School
SMP Junior High
School
SMU Senior High
School
SMK Vocational High School
D3 Diploma Degree
S1 Bachelor Degree
S2 Master Degree
Kantor Pusat | Head Office - 2 20 25 42 213 54 356 UP Suralaya | Suralaya GU - 10 45 418 134 110 5 722 UPJP Priok | Priok GGSU - 5 12 169 69 48 5 308 UP Saguling | Saguling GU 1 15 27 118 23 24 1 209 UPJP Kamojang | Kamojang GGSU 1 5 22 147 44 28 - 247 UP Semarang | Semarang GU 3 6 18 147 58 62 4 298 UP Mrica | Mrica GU 4 9 17 85 30 33 2 180 UP Perak Grati | Perak Grati GU - - 9 96 39 65 1 210 UPJP Bali | Bali GGSU - 1 8 156 93 91 2 351 UJH | MSU - 1 11 82 43 67 6 210 UJP Banten 1 Suralaya | Banten 1 Suralaya GSU - - 1 14 9 52 1 77 UJP Banten 2 Labuan | Banten 2 Labuan GSU - - 2 19 17 29 2 69 UJP Banten 3 Lontar | UJP Banten 3 Lontar GSU - - 2 41 33 47 1 124 UJP Jabar 2 Pel. Ratu | Jabar 2 Pel. Ratu GSU - - 2 25 25 62 1 115 UJP Jateng 2 Adipala | Jateng 2 Adipala GSU - - - 19 32 28 2 81 UJP Pangkalan Susu | Pangkalan Susu GSU - - 1 20 29 31 1 82 Jumlah Pegawai Aktif | Total of Active Employees 9 54 197 1.581 720 990 88 3.639
43,45%SMK
Vocational HighSchool
Grafik Graph
47Jumlah Pegawai Berdasarkan Pendidikan Tahun 2015Total Employees Based on Education in 2015
Tabel Table
48Jumlah Pegawai Berdasarkan Pendidikan Tahun 2015Total Employees Based on Education in 2015
75LAPORAN STATISTIKSTATISTIC REPORT 2015
Istilah, definisi dan rumus-rumus yang digunakan adalah sebagai berikut:
1. FAKTOR KAPASITAS
yaitu kWh produksi bruto, adalah energi yang dibangkitkan oleh generator sebelum dikurangi energi pemakaian sendiri (untuk peralatan bantu, penerangan sentral, dan lain-lain), atau produksi energi listrik yang diukur pada terminal generator.
2. KAPASITAS TERPASANG
adalah kapasitas suatu unit pembangkit sebagaimana tertera pada papan nama (name plate) dari generator atau mesin penggerak utama, dipilih mana yang lebih kecil. Khusus untuk PLTG, kapasitas terpasangnya adalah sebagaimana tertera pada papan nama berdasarkan base-load, bukan berdasarkan peak load.
3. EQUIVALENT AVAILABILITY FACTOR (EAF)
Equivalent Availability Factor (EAF) yaitu faktor ketersediaan mesin pembangkit untuk beroperasi pada Daya Mampu Nettonya; dengan perhitungan = (jumlah jam unit pembangkit siap dioperasikan - (derating permanen + derating tidak permanen)) dibagi dengan jumlah jam dalam periode tertentu. Untuk PLTA yang dihitungkan adalah unit mesinnya, bukan ketersediaan debit air. Jam tersedia: jumlah jam dimana unit dalam keadaan operasi dan atau siap operasi.
4. PEMAKAIAN SENDIRI (PS)
Perhitungan pemakaian sendiri (PS), merupakan selisih antara produksi bruto dengan penjualan (MWh) yang disalurkan ke sistem transmisi.
Term, definitions and formulas used in this report as follow:
1. CAPACITY FACTOR kWh gross production is the amount of power generated
before being subtracted by self consumption energy (for assisting machinery, central lighting,etc.), or production of energy as measured by terminal generator.
2. INSTALLED CAPACITY is the capacity of a generating unit, as it shown on generator’s
name plate of prime mover, whichever is smaller. Especially GTPP, the installed capacity is whatever shown on the name plate based on base load, not based on peak load.
3. EQUIVALENT AVAILABILITY FACTOR (EAF) Equivalent Availability Factor (EAF) is the availability factor of
power plant engine to operate the Net Maximum Capacity the calculation is (number of hours the generating unit is ready to operate - (permanent derating + non-permanent derating)) divided by the number of hours in a given period. For HPP the derivative is the number of machine (unit), not the water volume. Availability hours: total hours of operation and/ or running hours.
4. SELF CONSUMPTION Measurement for self consumption is the difference between
gross production value and sales (MWh) delivered to the transmission system.
PENJELASANGLOSSARY OF TERMS
76 LAPORAN STATISTIKSTATISTIC REPORT2015
CF : Capacity FactorEAF : Equivalent Available FactorGWh : Giga Watt-hourHSD : High Speed DieselIPP : Independent Power ProducerKW : Kilo WattKWh : Kilo Watt-hourMFO : Marine Fuel OilMW : Mega WattMWh : Mega Watt-hourPJB : Pembangkitan Jawa-BaliPLTA : Pusat Listrik Tenaga AirPLTD : Pusat Listrik Tenaga DieselPLTDG : Pusat Listrik Tenaga Diesel GasPLTG : Pusat Listrik Tenaga GasPLTGU : Pusat Listrik Tenaga Gas dan UapPLTMG : Pusat Listrik Tenaga Mesin GasPLTP : Pusat Listrik Tenaga Panas BumiPLTU : Pusat Listrik Tenaga UapP3B : Penyaluran dan Pusat Pengatur Beban Jawa-BaliUP : Unit Pembangkitan UJH : Unit Jasa PemeliharaanUJP : Unit Jasa PembangkitanUPJP : Unit Pembangkitan dan Jasa PembangkitanMMBTU : 106 British Thermal Unit (MM=106)
British Thermal Unit (BTU) adalah jumlah kalori yang diperlukan untuk menaikan 1 pound air 1 derajat Fahrenheit pada temperatur 60 derajat Fahrenheit, pada tekanan absolute 14,7 pound per square inch.
Standard Cubic Foot (SCF) adalah sejumlah gas yang diperlukan untuk mengisi ruangan 1 Cubic Foot, dengan tekanan sebesar 14,7 pounds per square inch absolute dan pada temperatur 60 derajat Fahrenheit, dalam kondisi kering.
1.000 BTU Gas adalah gas yang mempunyai Gross Heating Value sebesar 1.000 BTU tiap SCF.
British Thermal Unit (BTU) is the total calories needed to raise 1 pound of water 1 Fahrenheit degree from temperature 60 Fahrenheit degrees with pressure 14.7 pound per square inc absolute.
Standard Cubic Foot (SCF) is the total gas which needed to fit 1 Cubic Foot room, with pressure 14.7 pounds per square inch absolute and in temperature of 60 Fahrenheit degrees in dry condition.
1,000 BTU Gas is gas which has Gross Heating Value 1,000 BTU per SCF.
DAFTAR SINGKATANLIST OF ABBREVIATION
LAPORAN STATISTIKSTATISTIC REPORT
2015
PT INDONESIA POWERJl. Jend Gatot Subroto Kav. 18Jakarta 12950Tel. (62-21) 526 7666 (hunting)Fax. (62-21) 525 1923, 525 2623www.indonesiapower.co.id