Upload
thyago-oliveira
View
212
Download
0
Embed Size (px)
Citation preview
8/21/2019 408-2012-Lec04 DCF3
1/904
• Discounted Cash Flow continued
MIN E 408: Mining Enterprise Economics
Project Evaluation Methods
1. Discounted Cash Flow (DCF):
Cash flow discounted at an investor arbitrarily selected discount rate
– Net Present Value (NPV).
– Internal Rate Of Return (IRR).
– Profitability index or benefit cost ratio.
– Payback and discounted payback period.
2. Capital Asset Pricing Method (CAPM):
Discount rate quantitatively modeled using the beta of a security or project with
comparable risk as project.
3. Option Pricing Method:
Uses Portfolio replication to duplicate the project as consisting of certain basicassets that are risk free. The resulting portfolio of assets must have a returnequal to the risk f ree rate.
Project Evaluation Methods
8/21/2019 408-2012-Lec04 DCF3
2/904
• IRR is the discount rate that sets the NPV to zero
• Independent of the interest rates in the capital market and sointrinsic to project cash flow
• Solution by tr ial and error
• Solver or goal seek in Excel does it!
• Accept Pro ject i f IRR > discount rate (MARR)
Investment Decision Criteria:Internal Rate of Return (IRR)
0
1
01
T
t
t
t
CF NPV I
RRR
NPV=-$9,325
-$30,000
$0
$30,000
$60,000
$90,000
0 0.04 0.08 0.12 0.16
Rate of Return
N P V
IRR = 8.445%
Investment Decision Criteria:
Internal Rate of Return (IRR)
8/21/2019 408-2012-Lec04 DCF3
3/904
1. No IRR
This project has no IRR:
1 2
+ 1,000 – 3,000 2,500
0
• NPV at 10%:
84.3381.1
500,2
1.1
000,3000,1 2
IRR (Some Problems)
2. Implied reinvestment
Project I0 C1 C2 C3 C4 IRR
A $-100m $10m $50m $60m $70m 24.73%
• Misconception that 24.73% is return on 100million; thus
7074.8477.7919.40
01yr 2yrs3yrs
70m60m50m10m
Amount (m$)
Reinvestment
242.03
Total
IRR (Some Problems)
4100 (1 0.2473) $242.03m
8/21/2019 408-2012-Lec04 DCF3
4/904
3. Scale problems: similar to PI’s problem
4. Timing Problems
– Projects with back-loaded cash flows may look worse with IRRwhen both IRRs > discount rate
Project I0 C1 C2 C3 C4 IRR MARR NPV
A $-100 $10 $50 $60 $70 24.7% 12% $35.98
B $-100 $70 $50 $30 $10 30.5% 12% $30.07
IRR (mutually exclusive projects)
35.98
24.73%
30.07
30.46%0
20
40
60
80
100
0% 4% 8% 12% 16% 20% 24% 28% 32% 36%
r- discount rate %
N P V
( m i l l i o n $ )
Project A
Project B
IRR (Mutually Exclusive Projects)
8/21/2019 408-2012-Lec04 DCF3
5/904
Find the difference between the alternatives. The resulting cash flowshould depict net investment
Project I0 C1 C2 C3 C4 IRR NPV
A-B 0 -60 $0 $30 $60 16.54% $5.91
If the difference between alternatives depict
a net borrowing, reverse decision criteria.
Choose A
IRR – Incremental Approach
• Payback Period:- The number of years required to recover initialinvestment on a project.
• The decision rule: Accept all projects with payback periods
8/21/2019 408-2012-Lec04 DCF3
6/904
Year A B C
0 -$100m -$100m -$100m
1 $20m $50m $50m
2 $30m $30m $30m
3 $50m $20m $20m
4 $60m $60m $99m
PBP 3 3 3
• With DPBP cash flows are discounted by the appropriate discount rateand the payback rule applied.
Payback Period and DiscountedPayback Period
• The payback period (PBP) and the discounted paybackperiod (DPBP) are used to reduce the time exposure ofinvested capital to risk.
• For every project,
DPBP estimate > PBP estimate
• If DPBP is > project li fe
– NPV
8/21/2019 408-2012-Lec04 DCF3
7/904
• Contemplating which of two dozers to buy.
• Very similar in terms of output.
• Will not directly effect cash flow except through costs.
• r =10%.
Initial Cost Operating costs per year Life
$100,000 $28,500 5
$145,000 $24,000 7
Projects with Different Life Spans
Machine 1
Machine 2
Projects with Different Life Spans
8/21/2019 408-2012-Lec04 DCF3
8/904
• Replacement Chain
– Find common life for the tw o and calculate NPV over that life.
• Uniform Annual Series (UAS) or Equivalent Annual Cost (EAC)
Projects with Different Life Spans
5
1 1208,037.42 1
0.10 1.10
$54,879.75
A
A
7
1 1261,842.05 1
0.10 1.10
$53,783.8
A
A
Machine 1
Machine 2
Equivalent Annual Cost
8/21/2019 408-2012-Lec04 DCF3
9/904
Review Of Main Points
• Discounted Cash Flow (DCF) Methods:
– Net Present Value
– Internal Rate of Return
• DCFROR and DCFROI
• Commonly used in practice
– Pay Back Period (PBP) and Discounted Pay BackPeriod (DPBP)
• Simple and common