408-2012-Lec04 DCF3

Embed Size (px)

Citation preview

  • 8/21/2019 408-2012-Lec04 DCF3

    1/904

    • Discounted Cash Flow continued

    MIN E 408: Mining Enterprise Economics

    Project Evaluation Methods

    1. Discounted Cash Flow (DCF):

    Cash flow discounted at an investor arbitrarily selected discount rate

     –  Net Present Value (NPV).

     –  Internal Rate Of Return (IRR).

     –  Profitability index or benefit cost ratio.

     –  Payback and discounted payback period.

    2. Capital Asset Pricing Method (CAPM):

    Discount rate quantitatively modeled using the beta of a security or project with

    comparable risk as project.

    3. Option Pricing Method:

    Uses Portfolio replication to duplicate the project as consisting of certain basicassets that are risk free. The resulting portfolio of assets must have a returnequal to the risk f ree rate.

    Project Evaluation Methods

  • 8/21/2019 408-2012-Lec04 DCF3

    2/904

    • IRR is the discount rate that sets the NPV to zero

    • Independent of the interest rates in the capital market and sointrinsic to project cash flow

    • Solution by tr ial and error

    • Solver or goal seek in Excel does it!

    •  Accept Pro ject i f IRR > discount rate (MARR)

    Investment Decision Criteria:Internal Rate of Return (IRR)

    0

    1

    01

    CF  NPV I 

     RRR

    NPV=-$9,325

    -$30,000

    $0

    $30,000

    $60,000

    $90,000

    0 0.04 0.08 0.12 0.16

    Rate of Return

          N      P      V

    IRR = 8.445%

    Investment Decision Criteria:

    Internal Rate of Return (IRR)

  • 8/21/2019 408-2012-Lec04 DCF3

    3/904

    1. No IRR

    This project has no IRR:

    1 2

    + 1,000 – 3,000 2,500

    0

    • NPV at 10%:

    84.3381.1

    500,2

    1.1

    000,3000,1 2  

    IRR (Some Problems)

    2. Implied reinvestment

    Project I0 C1 C2 C3 C4 IRR

     A $-100m $10m $50m $60m $70m 24.73%

    • Misconception that 24.73% is return on 100million; thus

    7074.8477.7919.40

    01yr 2yrs3yrs

    70m60m50m10m

     Amount (m$)

    Reinvestment

    242.03

    Total

    IRR (Some Problems)

    4100 (1 0.2473) $242.03m

  • 8/21/2019 408-2012-Lec04 DCF3

    4/904

    3. Scale problems: similar to PI’s problem

    4. Timing Problems

     –  Projects with back-loaded cash flows may look worse with IRRwhen both IRRs > discount rate

    Project I0 C1 C2 C3 C4 IRR MARR NPV

     A $-100 $10 $50 $60 $70 24.7% 12% $35.98

    B $-100 $70 $50 $30 $10 30.5% 12% $30.07

    IRR (mutually exclusive projects)

    35.98

    24.73%

    30.07

    30.46%0

    20

    40

    60

    80

    100

    0% 4% 8% 12% 16% 20% 24% 28% 32% 36%

    r- discount rate %

       N   P   V

       (  m   i   l   l   i  o  n   $   )

    Project A 

    Project B

    IRR (Mutually Exclusive Projects)

  • 8/21/2019 408-2012-Lec04 DCF3

    5/904

    Find the difference between the alternatives. The resulting cash flowshould depict net investment

    Project I0 C1 C2 C3 C4 IRR NPV

     A-B 0 -60 $0 $30 $60 16.54% $5.91

    If the difference between alternatives depict

    a net borrowing, reverse decision criteria.

    Choose A

    IRR – Incremental Approach

    • Payback Period:- The number of years required to recover initialinvestment on a project.

    • The decision rule: Accept all projects with payback periods

  • 8/21/2019 408-2012-Lec04 DCF3

    6/904

    Year A B C

    0 -$100m -$100m -$100m

    1 $20m $50m $50m

    2 $30m $30m $30m

    3 $50m $20m $20m

    4 $60m $60m $99m

    PBP 3 3 3

    • With DPBP cash flows are discounted by the appropriate discount rateand the payback rule applied.

    Payback Period and DiscountedPayback Period

    • The payback period (PBP) and the discounted paybackperiod (DPBP) are used to reduce the time exposure ofinvested capital to risk.

    • For every project,

    DPBP estimate > PBP estimate

    • If DPBP is > project li fe

     –  NPV

  • 8/21/2019 408-2012-Lec04 DCF3

    7/904

    • Contemplating which of two dozers to buy.

    • Very similar in terms of output.

    • Will not directly effect cash flow except through costs.

    • r =10%.

    Initial Cost Operating costs per year Life

    $100,000 $28,500 5

    $145,000 $24,000 7

    Projects with Different Life Spans

    Machine 1

    Machine 2

    Projects with Different Life Spans

  • 8/21/2019 408-2012-Lec04 DCF3

    8/904

    • Replacement Chain

     –  Find common life for the tw o and calculate NPV over that life.

    • Uniform Annual Series (UAS) or Equivalent Annual Cost (EAC)

    Projects with Different Life Spans

    5

    1 1208,037.42 1

    0.10 1.10

    $54,879.75

     A

     A

    7

    1 1261,842.05 1

    0.10 1.10

    $53,783.8

     A

     A

    Machine 1

    Machine 2

    Equivalent Annual Cost

  • 8/21/2019 408-2012-Lec04 DCF3

    9/904

    Review Of Main Points

    • Discounted Cash Flow (DCF) Methods:

     – Net Present Value

     – Internal Rate of Return

    • DCFROR and DCFROI

    • Commonly used in practice

     – Pay Back Period (PBP) and Discounted Pay BackPeriod (DPBP)

    • Simple and common