Upload
scrbdgharavi
View
212
Download
0
Embed Size (px)
Citation preview
7/28/2019 5.7_HAZOP_V1.1
1/14
1 Hazard Evaluation, HE, Techniques
The following HE, techniques have been used in chronological order:
1960 - 2001 1960 - 2001 1965 - 2001 1970 - 2001 1972 - 1974 1974 - 2001
Safety Check Lists Relative PHA What if HAZOP
Review Ranking
Walk Historical ICI Mond Preliminary Brainstorming Hazards
Through Lists Index Hazard Operability
Inspection Analysis Analysis
Yes / No Dow FEI
Hazardous Mtls Line by Line
Hazardous Opns Deviation
Analysis
This presentation only considers the HAZOP technique.
Press Page Down for 9 pages of further information on HAZOPS.
(Best viewed with 24 lines per screen - adjust your Zoom% to suit)
continue to page 2
7/28/2019 5.7_HAZOP_V1.1
2/14
2 HAZOP Hazards and Operability Analysis
HAZOP was developed by Lawley (1974) of ICI. Based on early account by Elliott & Owen (1968)
Hazop studies are carried out by an experienced, multidisciplanary team, who review all physical
aspects of a process (lines, equipment, instrumentation) to discover potential hazards and
operability problems using a check list approach.
The basis for a HAZOP is a critical examination of information found in a word model, a process
flowsheet, a plant layout, equipment specification or a P&ID, (Piping and Instrument Drawing).
The principals of examination include: See tabs D1 to D3 for examples of computer forms.
1 Intention
2 Deviation
3 Causes
4 Consequences
(a) hazards
(b) operating difficulties
5 Safeguards
6 Recommendations / Actionscontinue to page 3
7/28/2019 5.7_HAZOP_V1.1
3/14
3 Early HAZOP studies used the following set ofGuide Words to systematically review the process:
NO or NOT Negation of intention No Flow of A
MORE Quantitative increase Flow of A greater than design flow
LESS Quantitative decrease Flow of A less than design flow
AS WELL AS Quantitative increase Transfer of some component additional to A
PART OF Quantitative decrease Failure to transfer all components of A
REVERSE Logical opposite of intention Flow of A in direction opposite to design direction
OTHER THAN Complete substitution Transfer of some material other than A
More recent computerization techniques use a Standard Set Of Generic Deviations
For Specific Section Types. See Dev'ns tab for examples.
continue to page 4
7/28/2019 5.7_HAZOP_V1.1
4/14
4 Some Common HAZOP Analysis Process Parameters
Flow Time Frequency Mixing
Pressure Composition Viscosity Addition
Temperature pH Voltage Separation
Level Speed Toxicity Reaction
continue to page 5
7/28/2019 5.7_HAZOP_V1.1
5/14
5 Prepare for the review
Attitude
Preparation Meeting Leadership
HAZOP
Review By Documentation Follow-up
Team
Knowledge Info for study
Experience Teams HAZOP P&Ids, Layout
Experience
Table
Deviation Causes Consequences Safeguards Action
continue to page 6
7/28/2019 5.7_HAZOP_V1.1
6/14
6 HAZOP analysis method flow diagram
Select a process
section or
operating step
Explain design Repeat for all
intention process sections
Select a process Repeat for all
variable or task process variables
Apply guide word Repeat for all
to process variable guide words
Examine Develop action
Consequences items
associated withcontiue page down deviation
6 con't
List possible Assess acceptability
causes of of risk based on
deviation consequences
Identify existing
safeguards to
prevent deviation
continue to page 7
7/28/2019 5.7_HAZOP_V1.1
7/14
7 Potential HAZOP Pitfalls
1 Poor understanding by management of the HAZOP procedure
An Ethylene plant has 100 P&IDs, 625 equip't items. 625 items a
Consider 5 variables, Pressure, Temperature, Flow
Composition and Function. 5 variables b
Consider 6 Guidewords, None, More of, Less of
Part of, More than and Other than. 6 guide words c
Questions to be answered = 18750 questions d = axbxc
Consider 5 minutes per question = 5 min./question e
Time for ethylene plant HAZOP study = 93750 minutes f = dxe
4 hour, 240 minutes sessions per day = 250 minutes/day g
No. working of days = 375 days h = f / g
Days per week = 5 days/week I
No. of weeks to complete HAZOP for plant = 75 weeks j = h / I
2 Inexperienced HAZOP team
3 Inadequately trained or in-experienced leader
continue to page 8
7/28/2019 5.7_HAZOP_V1.1
8/14
8 Common Mistakes
1 Failing to establish a "safe" environment for team members
2 Consequences of events not carried to conclusion.
3 Taking unwarranted credit for safeguards See example on page 9 - one page down
4 Too little credit given for safeguards
5 Making recommendations as specific as possible
6 Poor recording of HAZOPS
7 Failure to HAZOP start-up and shut-down procedures
8 Poorly up-dated P&IDs
9 A HAZOP is performed in lieu of properly executed design reviews
10 Wrong technique for system being reviewed (See spreadsheet titled Fig 5.3)continue to page 9
7/28/2019 5.7_HAZOP_V1.1
9/14
9 HAZOP Example See page 8 - item No. 3
To Compressor Inlet
Teams tend to quickly identify alarms, shut-downs
and controls, and claim them for safeguards.
An alarm not tested may not work when called upon
Inlet Line to do so.
Nuisance alarms are frequently bypassed and are
not effective as safeguards.
Often operators are not monitoring control panel.
Valve in manual Automatic control routines are often set in manual
mode.
end See tab D1 for computer documentation example
FV1
LAH
LIC1
7/28/2019 5.7_HAZOP_V1.1
10/14
Dev'ns
Table 1 Example Standard Set Of Generic Deviations For Process Section Types
Source Lessons Learned From HAZOPS Reviews of FCCUs by P.E. McCluer et al, Hydrocarbon Processing, Aug 1992, p-140-C
Tank or Heat
ID No. Deviation Column Vessel Line Exchanger Pump Compressor
1 High Flow X
2 High Level X X
3 High Interface X4 High Pressure X X X X
5 High Temperature X X X X
6 High Concentration X X X
7 Low / No Flow X X
8 Low Level X X
9 Low Interface X
10 Low Pressure X X X X
11 Low Temperature X X X X
12 Low Concentration X X X
13 Reverse / Misdirected Flow X X
14 Tube Leak X
15 Tube Rupture X
16 Leak X X X X X X
17 Rupture X X X X X X
Some other typical HAZOP deviations Press Page Down
More Flow
Less Flow
More Pressure
Less Pressure
More Level
Less Level
Part of, wrong concentration
As well as, contaminants
other than, wrong material
More Reaction
Less Reaction
No Reaction
More Mixing
Less Mixing
More Corrosion
More Erosion
Sampling
Page 10
7/28/2019 5.7_HAZOP_V1.1
11/14
D1
Company Nova Revision 0 Date 2-Jun-97
Location Corunna Dwg No. Cor -123-4567 Page 1
Leader RAH Proc Des JB Research Op Tech
Scribe GFR Instr'ts GH Electrical HH Other
Prod'n PM Mech FD Safety MN Other
Node No. 1 Describe Transfer Ethane from Deethanizer to C2 KO Pot
Intention The intent is to transfer 150,000 lb/hr of C2/C2= mix at 300 psig and at -30 F for the startup period.
Guide Wrd High Param Flow Dev'n High Flow
Possible Causes
1 FV-1 Wide open
2 Line break.
3
Consequences
1 High level in KO pot with liquid carry-over to compressor with serious damage to rotor. Potential hydrocarbons release.
2 Potential hydrocarbon release.3
Safeguards1 High level alarm LAH-1
2 High - High level alarm HHLA - 1 shutdown.
3 Vessel inspection yearly.
Recommendation / Actions Respib By Date
1 Consider limiting flow orifice, auto SD trip on High-High level, smart check valve. 1 JB 1-Jan-99
2 Determine extent of typical hydrocarbon release. 2 PM #######
3 Set-up vessel inspection yearly. 3 FD #######
Page 11
7/28/2019 5.7_HAZOP_V1.1
12/14
D2
Company Nova Revision 0 Date 2-Jun-97
Location Corunna Dwg No. Cor -123-4567 Page 2
Leader RAH Proc Des JB Research 0 Op Tech 0
Scribe GFR Instr'ts GH Electrical HH Other 0
Prod'n PM Mech FD Safety MN Other 0
Node No. 1 Describe Transfer Ethane from Deethanizer to C2 KO Pot
Intention The intent is to transfer 150,000 lb/hr of C2/C2= mix at 300 psig and at -30 F for the startup period.
0
0
Guide Wrd Low Param Flow Dev'n Low Flow
Possible Causes
1
2
3
Consequences
1
2
3Safeguards
1
2
3
Rec / Actions Respib By Date
1 1
2 2
3 3
Page 12
7/28/2019 5.7_HAZOP_V1.1
13/14
D3
Company Revision Date
Location Dwg No. Page
Leader Proc Des Research Op Tech
Scribe Instr'ts Electrical Other
Prod'n Mech Safety Other
Node No. Describe
Intention
Guide Wrd Param Dev'n
Possible Causes
1
2
3
Consequences
1
2
3Safeguards
1
2
3
Rec / Actions Respib By Date
1 1
2 2
3 3
Page 13
7/28/2019 5.7_HAZOP_V1.1
14/14
Chk List
Hazard & Operability Studies Check List Example
1 Changes In Quantity a High Flow 1 Pump racing, delivery vessel pressure lost,
suction pressurized, scale dislodged, leak in
heat exchanger
Loss of automatic
control
b Low Flow 2 Pump failure, scaling of delivery, presence
of foreign body, poor suction condition,
cavitation, leak in heat exchanger, drainleak, valve jammed
Operator error
c No Flow 3 Pump failure, delivery vessel
overpressurized, gas blockage, presence of
foreign body, scale, sediment, suction vessel
empty.
Failure of joint, pipe,
valve, trap, bursting
disc, relief valve.
d Reverse Flow 4 Pump failure, pump reversed, delivery
vessel over pressurized, poor isolation, gas
locking, surging, back siphoning.
2 Changes in physical
condition
a High or Low
pressure
1 Boiling, cavitation, freezing, chemical
breakdown, flashing, condensation,
sedimentation, scaling, foaming, gas
release, priming, exploding, imploding.
Changes in viscosity, density. External Fire,
Weather conditions, Hammer.
b High or Low
Temperature
2 same as 1
c Static buildup 3 Source of Ignition, Personnel shock.
3 Changes in chemical
condition
a High or Low
Conentration
1 Changes in proportion of mixture, in water or
solvent content.
b Contaminants 2 Ingress of air, water, steam, fuel, lubricant,
corrosion products, other process materials
from high pressure system, leakage through
heat exchangers. gas entrainment, spray,
mist.
4 Startup and
Shutdown Condition.
a Testing 1 Vacuum, pressure testing with with harmless
material.
b Commissioning 2 Concentration of reactants, intermediates
c Maintenance 3 Purging, venting, sweetening, drying,
warming. Access, spares.
5 Hazardous Pipelines a Pipeline
registration
1 Should this pipe be considered for
registration?
Page 14