5.7_HAZOP_V1.1

Embed Size (px)

Citation preview

  • 7/28/2019 5.7_HAZOP_V1.1

    1/14

    1 Hazard Evaluation, HE, Techniques

    The following HE, techniques have been used in chronological order:

    1960 - 2001 1960 - 2001 1965 - 2001 1970 - 2001 1972 - 1974 1974 - 2001

    Safety Check Lists Relative PHA What if HAZOP

    Review Ranking

    Walk Historical ICI Mond Preliminary Brainstorming Hazards

    Through Lists Index Hazard Operability

    Inspection Analysis Analysis

    Yes / No Dow FEI

    Hazardous Mtls Line by Line

    Hazardous Opns Deviation

    Analysis

    This presentation only considers the HAZOP technique.

    Press Page Down for 9 pages of further information on HAZOPS.

    (Best viewed with 24 lines per screen - adjust your Zoom% to suit)

    continue to page 2

  • 7/28/2019 5.7_HAZOP_V1.1

    2/14

    2 HAZOP Hazards and Operability Analysis

    HAZOP was developed by Lawley (1974) of ICI. Based on early account by Elliott & Owen (1968)

    Hazop studies are carried out by an experienced, multidisciplanary team, who review all physical

    aspects of a process (lines, equipment, instrumentation) to discover potential hazards and

    operability problems using a check list approach.

    The basis for a HAZOP is a critical examination of information found in a word model, a process

    flowsheet, a plant layout, equipment specification or a P&ID, (Piping and Instrument Drawing).

    The principals of examination include: See tabs D1 to D3 for examples of computer forms.

    1 Intention

    2 Deviation

    3 Causes

    4 Consequences

    (a) hazards

    (b) operating difficulties

    5 Safeguards

    6 Recommendations / Actionscontinue to page 3

  • 7/28/2019 5.7_HAZOP_V1.1

    3/14

    3 Early HAZOP studies used the following set ofGuide Words to systematically review the process:

    NO or NOT Negation of intention No Flow of A

    MORE Quantitative increase Flow of A greater than design flow

    LESS Quantitative decrease Flow of A less than design flow

    AS WELL AS Quantitative increase Transfer of some component additional to A

    PART OF Quantitative decrease Failure to transfer all components of A

    REVERSE Logical opposite of intention Flow of A in direction opposite to design direction

    OTHER THAN Complete substitution Transfer of some material other than A

    More recent computerization techniques use a Standard Set Of Generic Deviations

    For Specific Section Types. See Dev'ns tab for examples.

    continue to page 4

  • 7/28/2019 5.7_HAZOP_V1.1

    4/14

    4 Some Common HAZOP Analysis Process Parameters

    Flow Time Frequency Mixing

    Pressure Composition Viscosity Addition

    Temperature pH Voltage Separation

    Level Speed Toxicity Reaction

    continue to page 5

  • 7/28/2019 5.7_HAZOP_V1.1

    5/14

    5 Prepare for the review

    Attitude

    Preparation Meeting Leadership

    HAZOP

    Review By Documentation Follow-up

    Team

    Knowledge Info for study

    Experience Teams HAZOP P&Ids, Layout

    Experience

    Table

    Deviation Causes Consequences Safeguards Action

    continue to page 6

  • 7/28/2019 5.7_HAZOP_V1.1

    6/14

    6 HAZOP analysis method flow diagram

    Select a process

    section or

    operating step

    Explain design Repeat for all

    intention process sections

    Select a process Repeat for all

    variable or task process variables

    Apply guide word Repeat for all

    to process variable guide words

    Examine Develop action

    Consequences items

    associated withcontiue page down deviation

    6 con't

    List possible Assess acceptability

    causes of of risk based on

    deviation consequences

    Identify existing

    safeguards to

    prevent deviation

    continue to page 7

  • 7/28/2019 5.7_HAZOP_V1.1

    7/14

    7 Potential HAZOP Pitfalls

    1 Poor understanding by management of the HAZOP procedure

    An Ethylene plant has 100 P&IDs, 625 equip't items. 625 items a

    Consider 5 variables, Pressure, Temperature, Flow

    Composition and Function. 5 variables b

    Consider 6 Guidewords, None, More of, Less of

    Part of, More than and Other than. 6 guide words c

    Questions to be answered = 18750 questions d = axbxc

    Consider 5 minutes per question = 5 min./question e

    Time for ethylene plant HAZOP study = 93750 minutes f = dxe

    4 hour, 240 minutes sessions per day = 250 minutes/day g

    No. working of days = 375 days h = f / g

    Days per week = 5 days/week I

    No. of weeks to complete HAZOP for plant = 75 weeks j = h / I

    2 Inexperienced HAZOP team

    3 Inadequately trained or in-experienced leader

    continue to page 8

  • 7/28/2019 5.7_HAZOP_V1.1

    8/14

    8 Common Mistakes

    1 Failing to establish a "safe" environment for team members

    2 Consequences of events not carried to conclusion.

    3 Taking unwarranted credit for safeguards See example on page 9 - one page down

    4 Too little credit given for safeguards

    5 Making recommendations as specific as possible

    6 Poor recording of HAZOPS

    7 Failure to HAZOP start-up and shut-down procedures

    8 Poorly up-dated P&IDs

    9 A HAZOP is performed in lieu of properly executed design reviews

    10 Wrong technique for system being reviewed (See spreadsheet titled Fig 5.3)continue to page 9

  • 7/28/2019 5.7_HAZOP_V1.1

    9/14

    9 HAZOP Example See page 8 - item No. 3

    To Compressor Inlet

    Teams tend to quickly identify alarms, shut-downs

    and controls, and claim them for safeguards.

    An alarm not tested may not work when called upon

    Inlet Line to do so.

    Nuisance alarms are frequently bypassed and are

    not effective as safeguards.

    Often operators are not monitoring control panel.

    Valve in manual Automatic control routines are often set in manual

    mode.

    end See tab D1 for computer documentation example

    FV1

    LAH

    LIC1

  • 7/28/2019 5.7_HAZOP_V1.1

    10/14

    Dev'ns

    Table 1 Example Standard Set Of Generic Deviations For Process Section Types

    Source Lessons Learned From HAZOPS Reviews of FCCUs by P.E. McCluer et al, Hydrocarbon Processing, Aug 1992, p-140-C

    Tank or Heat

    ID No. Deviation Column Vessel Line Exchanger Pump Compressor

    1 High Flow X

    2 High Level X X

    3 High Interface X4 High Pressure X X X X

    5 High Temperature X X X X

    6 High Concentration X X X

    7 Low / No Flow X X

    8 Low Level X X

    9 Low Interface X

    10 Low Pressure X X X X

    11 Low Temperature X X X X

    12 Low Concentration X X X

    13 Reverse / Misdirected Flow X X

    14 Tube Leak X

    15 Tube Rupture X

    16 Leak X X X X X X

    17 Rupture X X X X X X

    Some other typical HAZOP deviations Press Page Down

    More Flow

    Less Flow

    More Pressure

    Less Pressure

    More Level

    Less Level

    Part of, wrong concentration

    As well as, contaminants

    other than, wrong material

    More Reaction

    Less Reaction

    No Reaction

    More Mixing

    Less Mixing

    More Corrosion

    More Erosion

    Sampling

    Page 10

  • 7/28/2019 5.7_HAZOP_V1.1

    11/14

    D1

    Company Nova Revision 0 Date 2-Jun-97

    Location Corunna Dwg No. Cor -123-4567 Page 1

    Leader RAH Proc Des JB Research Op Tech

    Scribe GFR Instr'ts GH Electrical HH Other

    Prod'n PM Mech FD Safety MN Other

    Node No. 1 Describe Transfer Ethane from Deethanizer to C2 KO Pot

    Intention The intent is to transfer 150,000 lb/hr of C2/C2= mix at 300 psig and at -30 F for the startup period.

    Guide Wrd High Param Flow Dev'n High Flow

    Possible Causes

    1 FV-1 Wide open

    2 Line break.

    3

    Consequences

    1 High level in KO pot with liquid carry-over to compressor with serious damage to rotor. Potential hydrocarbons release.

    2 Potential hydrocarbon release.3

    Safeguards1 High level alarm LAH-1

    2 High - High level alarm HHLA - 1 shutdown.

    3 Vessel inspection yearly.

    Recommendation / Actions Respib By Date

    1 Consider limiting flow orifice, auto SD trip on High-High level, smart check valve. 1 JB 1-Jan-99

    2 Determine extent of typical hydrocarbon release. 2 PM #######

    3 Set-up vessel inspection yearly. 3 FD #######

    Page 11

  • 7/28/2019 5.7_HAZOP_V1.1

    12/14

    D2

    Company Nova Revision 0 Date 2-Jun-97

    Location Corunna Dwg No. Cor -123-4567 Page 2

    Leader RAH Proc Des JB Research 0 Op Tech 0

    Scribe GFR Instr'ts GH Electrical HH Other 0

    Prod'n PM Mech FD Safety MN Other 0

    Node No. 1 Describe Transfer Ethane from Deethanizer to C2 KO Pot

    Intention The intent is to transfer 150,000 lb/hr of C2/C2= mix at 300 psig and at -30 F for the startup period.

    0

    0

    Guide Wrd Low Param Flow Dev'n Low Flow

    Possible Causes

    1

    2

    3

    Consequences

    1

    2

    3Safeguards

    1

    2

    3

    Rec / Actions Respib By Date

    1 1

    2 2

    3 3

    Page 12

  • 7/28/2019 5.7_HAZOP_V1.1

    13/14

    D3

    Company Revision Date

    Location Dwg No. Page

    Leader Proc Des Research Op Tech

    Scribe Instr'ts Electrical Other

    Prod'n Mech Safety Other

    Node No. Describe

    Intention

    Guide Wrd Param Dev'n

    Possible Causes

    1

    2

    3

    Consequences

    1

    2

    3Safeguards

    1

    2

    3

    Rec / Actions Respib By Date

    1 1

    2 2

    3 3

    Page 13

  • 7/28/2019 5.7_HAZOP_V1.1

    14/14

    Chk List

    Hazard & Operability Studies Check List Example

    1 Changes In Quantity a High Flow 1 Pump racing, delivery vessel pressure lost,

    suction pressurized, scale dislodged, leak in

    heat exchanger

    Loss of automatic

    control

    b Low Flow 2 Pump failure, scaling of delivery, presence

    of foreign body, poor suction condition,

    cavitation, leak in heat exchanger, drainleak, valve jammed

    Operator error

    c No Flow 3 Pump failure, delivery vessel

    overpressurized, gas blockage, presence of

    foreign body, scale, sediment, suction vessel

    empty.

    Failure of joint, pipe,

    valve, trap, bursting

    disc, relief valve.

    d Reverse Flow 4 Pump failure, pump reversed, delivery

    vessel over pressurized, poor isolation, gas

    locking, surging, back siphoning.

    2 Changes in physical

    condition

    a High or Low

    pressure

    1 Boiling, cavitation, freezing, chemical

    breakdown, flashing, condensation,

    sedimentation, scaling, foaming, gas

    release, priming, exploding, imploding.

    Changes in viscosity, density. External Fire,

    Weather conditions, Hammer.

    b High or Low

    Temperature

    2 same as 1

    c Static buildup 3 Source of Ignition, Personnel shock.

    3 Changes in chemical

    condition

    a High or Low

    Conentration

    1 Changes in proportion of mixture, in water or

    solvent content.

    b Contaminants 2 Ingress of air, water, steam, fuel, lubricant,

    corrosion products, other process materials

    from high pressure system, leakage through

    heat exchangers. gas entrainment, spray,

    mist.

    4 Startup and

    Shutdown Condition.

    a Testing 1 Vacuum, pressure testing with with harmless

    material.

    b Commissioning 2 Concentration of reactants, intermediates

    c Maintenance 3 Purging, venting, sweetening, drying,

    warming. Access, spares.

    5 Hazardous Pipelines a Pipeline

    registration

    1 Should this pipe be considered for

    registration?

    Page 14