8.APRIL MPR- 2012

Embed Size (px)

Citation preview

  • 7/31/2019 8.APRIL MPR- 2012

    1/91

    National Cyclone Ri

    (NCRevenue (DGovernment of

    National Cyclone Ri

    (NCRevenue (DGovernment of

    k Mitigation Project

    MP)) DepartmentAndhra Pradesh

    k

    Mitigation Project

    MP)) DepartmentAndhra Pradesh

  • 7/31/2019 8.APRIL MPR- 2012

    2/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    INDEX

    1.0 Project Background 2

    2.0 Third Party Quality Audit Consultant 3

    3.0 Major Activities and Review Meetings of the Month 3

    4.0 Status of TPQA Visits 4

    5.0 Progress of NCRMP works 5

    TPQA Status Report for NCRMP Works To the end of(30-04-2012) 6

    6.0 District wise status of tests conducted by TPQA 29

    7.0 Details of Audit Reports Submitted during this Month 30

  • 7/31/2019 8.APRIL MPR- 2012

    3/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1.0 Project Background

    Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state, the

    nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December,

    cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are

    increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging

    from 1892 to 1989, there were as many as 67 cyclones within the State.

    It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due

    to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on

    experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

    existing facilities available in the project area in Andhra Pradesh.

    The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

    Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

    proceeds to payments for goods, works, related services and consulting services under this Project.National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at

    Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

    Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,

    Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

    Shelters, and Roads to habitations and Roads & Bridges under NCRMP is funded by International Development

    Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

    implemented by various line departments working under PIU. The number of works under progress / for whichagreements are concluded in each district is shown in the table below.

  • 7/31/2019 8.APRIL MPR- 2012

    4/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    2.0 Third Party Quality Audit Consultant.

    To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

    Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

    Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV

    with Egis India Consulting Engineers (I) Pvt. Ltd. On 31 st May2011, the Contract for Consultancy Service was signed

    between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

    the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

    3.0 Major Activities and Review Meetings of the Month

  • 7/31/2019 8.APRIL MPR- 2012

    5/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4.0 Status of TPQA Visits:

    The following table shows the details of TPQA visits to sites in respective districts.

    District Total Number of Visits

    Up to Mar.'2012 In Apr.'2012 Up to Apr.'2012

    Srikakulam 188 24 212

    Vizianagaram 66 5 71

    Vishakhapatnam 179 29 208

    East Godavari 300 64 364

    West Godavari 247 39 286

    Krishna 166 21 187

    Guntur 167 22 189

    Prakasam 223 21 244

    Nellore 176 17 193

    No. of Visits by TPQA

  • 7/31/2019 8.APRIL MPR- 2012

    6/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    5.0 Progress of NCRMP works:The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

    Krishna District has just started. At many places the first milestone is completed but works are not started. The line

    departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the

    agreement conditions should be imposed.

    Third Party Quality Audit by Egis India consulting services

    Summary of Activities

    S.No. District

    Agreements for PackagesCommunicated Status of works

    PR R&B Progress Not Started

    1 Srikakulam 6 5 17 4

    2 Vizianagaram - 3 3 0

    3 Visakhapatnam 13 0 21 0

    4 East Godavari 7 0 12 1

    5 West Godavari 3 0 10 0

    6 Krishna 4 0 8 0

  • 7/31/2019 8.APRIL MPR- 2012

    7/91

    MONTHLY REPORT

    6 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    TPQA Status Report for NCRMP Works To the end of(30-04-2012)

    S.No. District

    Packages /Works

    entrustedStatus of Works

    No.of

    Visitsof

    TPQA

    TotalNo.

    of QCtestsdone

    NCRsQC

    ReportsIssued

    Environmentaland Social

    ReportsIssued

    Issued closed PendingPR R&B Started NotStarted

    1 Srikakulam 06_16 5_5 17 4 212 732 10 9 1 13 17

    2 Vizianagaram - 3_3 3 0 71 366 2 - 2 9 5

    3 Visakhapatnam 13_21 - 21 0 208 1161 9 9 - 23 16

    4 East Godavari 07_13 - 12 1 364 666 4 4 - 21 11

    5 West Godavari 03_10 - 10 0 286 229 - - - 17 19

    6 Krishna 04_08 - 8 0 187 42 3 3 - 8 13

    7 Guntur 06_15 2_2 12 5 189 350 10 10 - 14 5

    8 Prakasham 12_23 1_1 23 1 244 1874 14 13 1 18 15

    9 Nellore 16_24 - 24 0 193 835 8 8 - 16 9

    Total 67_130 11_11 130 11 1954 6351 60 56 4 139 110

  • 7/31/2019 8.APRIL MPR- 2012

    8/91

    MONTHLY REPORT

    7 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Srikakulam District up to 30.04.2012

    Category Packages allotted under Phase - 1 Names of works under each package Agreement No. / Date DHS DFCProgress up to30.04.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

    Road from DPN R&Broad to Uddandapalem

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12 complete Entire work

    Road from K. UmiladaJunction to Koduru (LinkRoad)

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12 complete Entire work

    Road from Borubadra,Malagam to Kollipadu viaSeepuram, Gantapeta

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12 complete Entire work

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

    Road from R&B roadMobagam to

    Duubakavanipeta viaGajapathinagaram

    /2010-11, Dt.

    30.04.201130.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Road fromTalasamudram to DolaRegulator

    /2010-11, Dt.30.04.2011 30.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

    Road from R&B roadEdulavalasa - Killam toJonnam viaTalasamudram

    /2011-12, Dt.30.04.2011 30.04.11 31.01.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Bridges

    NCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001

    Construction of bridge atKm 11/6-8 of NH-5 toPatnavanipetaConnectingSundarapalem

    46/2011, Dt.17.12.2010 17.12.10 17.06.12

    Second Milestone i.eCompletion up to

    below the deck slab.

    NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003

    Construction of Minor Bridge at Km 12/2-4 of NH-5 to SurampetaRoad via Naruva,Mentada

    45/2010-2011,Dt17.12.2010 17.12.10 17.03.12

    Second Milestone i.eCompletion up to

    below the deck slab.

  • 7/31/2019 8.APRIL MPR- 2012

    9/91

    MONTHLY REPORT

    8 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004

    Construction of Highlevel bridge acrossBendigadda at KM 4/10of Pundi-Parlakimidi roadin Srikakulam Dt, A.P.

    1/2010,Dt.11.11.2010 11.11.10 11.05.12First Milestone i.e

    Foundation up to wellcaping

    Roads NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)Improvements Naupada-Venkatapuram road from0/0to15/0km

    43/2010-11,17.12.2010 17.12.10 17.03.12Completion of entire

    work

    RCS

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturui/002

    Road from NP road toURK Puram

    G.O.Rt.No.451, Dt.06.04.2011 06.04.11 29.09.12

    E/W,pipeculverts,GSB,R/W

    Road from Deppuru,Bahadapalli road toOnkuluru to CycloneShelter

    G.O.Rt.No.451, Dt.06.04.2011 06.04.11 29.09.12

    E/W,pipeculverts,GSB,R/W

    Road from R & B Road

    to Devunthalada

    G.O.Rt.No.451, Dt.

    06.04.201106.04.11 29.09.12 E/W,pipe

    culverts,GSB,R/WRoad from Pollada toKomarthalada toCyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011 06.04.11 29.09.12

    E/W,pipeculverts,GSB,R/W

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

    Road from Koyyam R &B Road toMoosavanipeta

    G.O.Rt.No.451, Dt.06.04.2011 30.04.11 07.05.12

    Completion of workup to WBM gr-II, gr-III

    Road from Mentada toDovupeta

    G.O.Rt.No.451, Dt.06.04.2011 30.04.11 07.05.12

    Completion of workup to WBM gr-II, gr-III

    Road from Kotcherelaroad to Kollibhemavaram& Cyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011 30.04.11 07.05.12

    Completion of workup to WBM gr-II, gr-III

    Road from Kotcherlaroad toPathesundrapalem

    G.O.Rt.No.451, Dt.06.04.2011 30.04.11 07.05.12

    Completion of workup to WBM gr-II, gr-III

  • 7/31/2019 8.APRIL MPR- 2012

    10/91

    MONTHLY REPORT

    9 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    MPCSNCRMP/B_W/AP/MPCS/PRED/01/Sa

    nthabommali/005

    Construction of Cyclone shelter at Kollipadu

    G.o rt No451 dt

    06.04.2010

    07.01.2013

    Completion of Ground floor Plinth level

    Completion of Ground floor Plinth level

    Construction of Cyclone Shelter at Runku

    G.o rt No451 dt

    06.04.2010

    07.01.2013

    Completion of Ground floor Plinth level

    Completion of Ground floor Plinth level

    Status of works in Vizianagaram District up to 30.04.2012

    Category Packages allottedunder Phase - 1Names of works under each

    package Agreement No./ Date DHS DFCProgress up to

    30.04.2012

    Bridges

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Puligadda/ 007

    Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P.

    Road)

    31/2010-201 Dt.1.12.2010 01.12.10 31.05.12

    97.66% of workcompleted

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Chakaligadda / 008

    Construction of Minor Bridge atKm 15/2 near Chakaligedda of

    Konada Ramatheertham R&B roadto Konatalapalem (via) Yerukonda,

    Pasupam, Kollayavalasa (ZPRoad)

    34/2010-2011 Dt.8.12.2010 08.12.10 07.06.12

    78.99% of workcompleted

    Road (R&B)NCRMP/B-

    W/AP/RD/R&B/ 02/Konada/009

    Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)

    Pasupam, Yerukonda,Kollayavalasa from Km 12/0 to

    16/5 (Km 0/0 to 4/0 i.e. up to NH-5crossing)

    33/2010-201 Dt.8.12.2010 08.12.10 07.03.12

    100% of workcompleted

  • 7/31/2019 8.APRIL MPR- 2012

    11/91

    MONTHLY REPORT

    10 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 30.04.2012

    Category Packages allotted under Phase- 1Names of works

    under eachpackage

    Agreement

    No. / DateDHS DFC Progress up to 30.04.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

    Road from Vempadu toPatimeeda

    /2010-11, Dt.11.01.2011 11.01.11 11.01.12 Milestone is completed

    Road from R&B road toMulaparra up to Beach

    end

    /2010-11, Dt.11.01.2011 11.01.11 27.10.11 Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003

    Road from R&B B.PKallalu to

    Matchvanipalem

    /2010-11, Dt.10.03.2011 10.03.11 09.12.11

    Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

    Road from R & B roadto Pothu Rajannapalem

    /2010-11, Dt.28.03.2011 28.03.11 27.12.11 Milestone is completed

    Road from R & B roadto Jalaripeta

    /2010-11, Dt.28.03.2011 28.03.22 28.12.11 Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 Road from R & B roadto Venkayyapalem/2010-11, Dt.11.01.2011 11.01.11 11.10.11 Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/007

    Road from R&B road to Ava- Somavaram

    /2011-12, Dt.27.04.2011 27.04.11 26.01.12 Milestone is completed

    Road from R&B Roadto Avarajam

    /2011-12, Dt.27.04.2011 27.04.11 26.01.12 Milestone is completed

  • 7/31/2019 8.APRIL MPR- 2012

    12/91

    MONTHLY REPORT

    11 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 30.04.2012

    Category Packages allotted under

    Phase - 1

    Names of works under each

    package

    Agreement No. /

    DateDHS DFC

    Progress upto

    30.04.2012

    RCS

    NCRMP/B-W/AP/RCS/PRED/03/ Anandapuram/001

    Road from NH-5 toRamarayadupalem /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    RoadFurniture &Shoulder work is inprogress

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

    Road from R&B road toKrishnampalem /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD works areProgress &B.T work isCompleted

    Road from R & B road toKattubolu to Marripalem /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD works arein progress &WBM Grade-3 work is inprogress

    Road from R & B road toRajakoduru /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD Work iscompleted &B.T work iscompleted

    NCRMP/B-W/AP/RCS/PRED/03/

    Nakkapalli/003

    Road from R & B road toPedateenarla to Chinateenarla /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    B.T & C.Croad worksareCompleted.

    Road from Upamaka RajayyapetaR & B road to Janakayyapeta /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    CD works areCompleted &B.T work iscompleted

  • 7/31/2019 8.APRIL MPR- 2012

    13/91

    MONTHLY REPORT

    12 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 30.04.2012

    Category Packages allotted under Phase - 1 Names of works under each packageAgreement No.

    / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    30.04.2012First Second Third

    MPCS

    NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cycloneshelter at Gajapathi

    Nagaram

    /2011-12, Dt.03.10.2011 02.02.12 02.06.12 02.10.12

    Earth work is inprogress.

    Construction of cycloneshelter at Ratnayampeta

    /2011-12, Dt.03.10.2011 02.02.12 02.06.12 02.10.12

    Stilt Slab and 1stFloor Columns

    work are completed& 1st Floor Slabform work is in

    progress.

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cycloneshelter at Patimeeda

    /2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

    Foundation footing

    work is completedand Columns areprogress up tobottom level of

    Plinth beam andFoundation

    Refilling work is incompleted.

    Construction of cycloneshelter at Moolaparra

    /2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

    Columns laid up tobottom of plinth

    beam or Basementwork is in

    completed & Plinthbeam PCC iscompleted.

    Construction of cycloneshelter at Bangarampeta

    /2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

    Stair case & Rampworks are in

    progress, Columnslaid up to Roof

    level and Stilt Slabis Completed.

  • 7/31/2019 8.APRIL MPR- 2012

    14/91

    MONTHLY REPORT

    13 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/MPCS/PRED/03/Rambillii/004Construction of cyclone

    shelter atVenkayyapalem

    /2011-12, Dt.03.10.2011 02.01.12 02.04.12 02.07.12

    Earth work inprogress, Workstopped due tofinalization of

    foundation designs.

    NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001Construction of cyclone

    shelter atTikkavanipalem

    /2011-12, Dt.07.10.2011 06.01.12 06.04.12 06.07.12

    E/W foundationexcavation is

    completed & Dueto site problem

    work is stopped.

    Status of works in East Godavari District up to 30.04.2012

    Category Packages allotted under Phase - INames of works

    under eachpackage

    Agreement

    No. / Date

    Mile stonesRemarks

    First Second Third

    RHB (2 )RCS (8)

    MPCS (3)

    NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR roadsto Dasarivanipeta and

    to Cyclone Shelter

    /2011-12Dt:27.04.2011 30-11-2011 30-11-2011 20-01-2012

    Completed.

    NCRMP/B-W /RCS/PRED/04/Karapa/001 Approach Road tocyclone Shelter at

    Adavipudi

    2011-12Dt:20.05.2011 30-11-2011 31-10-2011 31-01-2012

    Completed.

    NCRMP/B-W/AP/RHB/PRED/04/Karapa/001/

    Road fromGurajanapalli to

    Bandulavaripalem

    2011-12Dt:27.04.2011 30-09-2011 31-10-2011 31-01-2012

    Completed.

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto P.Chodipallipeta CS

    2011-12Dt:07.09.2011 3 months 3 months 3 months

    65% completedShoulders Work is in

    Progress

  • 7/31/2019 8.APRIL MPR- 2012

    15/91

    MONTHLY REPORT

    14 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto K.Chodipallipeta CS

    /2011-12Dt:07.09.2011 3 months 3 months 3 months

    65% completedShoulders Work is in

    Progress

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Hukumpeta CS

    /2011-12Dt:07.09.2011 3 months 3 months 3 months

    65% completedShoulders Work is in

    Progress

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Gaddipeta CS

    /2011-12Dt:07.09.2011 3 months 3 months 3 months

    65% completedShoulders Work is in

    Progress

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Danavaipeta CS

    /2011-12Dt:07.09.2011 3 months 3 months 3 months

    65% completedShoulders Work is in

    Progress

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004/

    Road from R&B Roadto G.MusalayyapetaCS

    2011-12Dt:07.09.2011 3 months 3 months 3 months

    Not yet Started

    NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

    Road from R&B Roadto Chinaraghavulapeta

    Cyclone Shelter

    /2011-12 Dt:23.09.2011

    3 months/22.11.2011

    3 months22.06.2011 -----------

    Jungle Clarence inProgress

    NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction of Cyclone Shelter at

    Pedaraghavulapeta of Uppalaguptam Mandal

    E.G.Dt.

    /2011-12Dt:17.10.2011

    3 months16.01.2012

    3 months16.04.2012 3 months16.07.2012

    Sand filling work is inprogress below plinthbeam

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction of Cyclone Shelter atLaxamanudupadu

    inThondangi

    /2011-12Dt:07.09.2011

    PCC work is inprogress below plinthbeam & RR masonryOuter row

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction of Cyclone Shelter at

    Avulamanda

    /2011-12Dt:07.09.2011

    Sand filling work is inprogress below plinthbeam

  • 7/31/2019 8.APRIL MPR- 2012

    16/91

    MONTHLY REPORT

    15 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in West Godavari District up to 30.04.2012

    Category Packages allotted under Phase- 1Names of works under

    each packageAgreementNo. / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    30.04.2012

    RemarksFirst Second Third

    RHB

    Mogalthuru Mandal NCRMPW.G.Dist

    Road from NH 214 A atRanga Statue center to

    Harijanawada of Kalipatnam(E) (Mogalthuru Mandal

    W.G.Dist.)

    16 /2011-12Dt.27.04.2011

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012

    65.91%

    Gr-III & CC PavementCompleted.

    Shoulders work is inProgress.

    R&B road at PanchayatOffice to Pulaparthivarithota

    via Badava(Mogalthuru Mandal

    W.G.Dist.)

    68.65%

    Gr-III & CC PavementCompleted.

    Shoulders work is inProgress.

    Mogalthuru Vempa R&BRoad at Uchintha Kalava

    Bridge to GogulammaHarijanapeta (Mogalthuru

    Mandal W.G.Dist.)

    75.34%

    Gr-III & CC PavementCompleted.

    Shoulders work is inProgress.

    From Narsapur Mogalthur R&B road to Dayadaldaspeta

    via Venkateswara Swamytemple (Mogalthuru Mandal

    W.G.Dist.)

    85.79%

    CC Pavement Completed.Shoulders work is in

    Progress.

    Road from NH 214 A road toHarijanapeta of Kothota

    (Mogalthuru MandalW.G.Dist.)

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/201299.20% CC Road Completed.

    Narsapur Mandal W.G.Dist.

    R&B road to Indira Nagar (via) Pochamma temple

    (Narsapur Mandal W.G.Dist.)21 /2011-12Dt.09.05.2011

    09/05/2011to

    04/09/2011

    05/09/2011to

    06/01/2012

    07/01/2011to

    08/5/2012

    55.44% Gr-III Completed.

    Road from R&B road toPedalanka (Narsapur Mandal

    W.G.Dist.)52.70%

    Gr-III Completed. CCPavement is in Progress.

  • 7/31/2019 8.APRIL MPR- 2012

    17/91

    MONTHLY REPORT

    16 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna District up to 30.04.2012

    Category Packages allotted under Phase - 1 Names of works under eachpackageAgreement No. /

    Date DHS DFCProgress up to

    30.04.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001

    Road connecting R&B roadthrough Gantalammapalem /2011-12Dt.27.4.2011 27.04.11 26.01.2012

    CD works,GSB,Gr-II,Gr-III,BT completed

    NCRMP/B-

    W/AP/RHB/PRED/06/Machipatnam/002

    Road from R & B Road to B.VThota

    /2011-12

    Dt.27.4.201127.04.11 26.01.2012

    CD works,GSB,Gr-II,Gr-III,BT completed

    Road from Potlapalem Z.P roadto Chikativanipalem

    CD works,GSB,Gr-II,Gr-III,BT completed

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru R&B Road toRangaraopet

    /2011-12Dt.27.4.2011 27.04.11 26.01.2012

    CD works,GSB,Gr-II,Gr-III,BT completed

    Road from R&B road to CycloneShelter at Chandala CD works,GSB,Gr-II,Gr-III,BT completed

    Road from LB Cheria CCroad to Chillapalemm of LBCheria (Narsapur Mandal

    W.G.Dist.

    75.64%

    Gr-III& CC PavementCompleted.

    Shoulders work is inProgress.

    Kalla Mandal W.G.Dist.

    From A-U R&B Road toSatyanarayanapuram (Kalla

    Mandal W.G.Dist.)25 /2011-12

    Dt.26.05.2011

    26/5/2011To

    20/8/2011

    20/8/2011to

    21/11/2011

    22/11/2011To

    23/2/2012

    100% Completed.

    From A-U R&B Road toMekaladibba (Kalla Mandal

    W.G.Dist.)100% Completed.

  • 7/31/2019 8.APRIL MPR- 2012

    18/91

    MONTHLY REPORT

    17 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna Districts up to 30.04.2012

    Category Packages allotted under Phase - 1Names of works

    under eachpackage

    AgreementNo. / Date

    Milestone Completion Dates Progressw.r.t.

    milestoneup to

    30.04.2012

    RemarksFirst Second Third

    RCS NCRMP/B-W/AP/RCS/PRED/06/Machipatnam/001

    Road fromBhogireddipalli R&B

    Road toRamakhandam

    /2011-12/Dt.02.09.2011 01.12.2011 01.03.12 01.06.12 13.20% GSB workcompleted

    Road from R&BRoad Chinnapuram

    to Gundupalem

    /2011-12/27.04.2011 01.12.2011 01.03.12 01.06.12

    31.68%GSB, GRIIcompleted.

    Road fromPotlapalem Z.P

    road to Pothepalli.

    /2011-12/Dt.02.09.2011 01.12.2011 01.03.12 01.06.12 41.38%

    GSB, Gr-II,GR III

    completed

  • 7/31/2019 8.APRIL MPR- 2012

    19/91

    MONTHLY REPORT

    18 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 30.04.2012

    Category Packages allotted under

    Phase - 1Names of works under each package Agreement No./

    DateDHS DFC Progress up to

    30.04.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/07/KARLAPAL

    EM/001

    R/f Ganapavaram R&BRoad t o Kesavapuri ST colony 7/2011-2012

    27.04.2011 27.04.11 26.01.2012 Completed.

    NCRMP/B-W/AP/PRED/07/Nagaram/002

    R/f R&B Road to Mohammad Alipalem

    8/2011-201227.04.2011 27.04.11 26.4.2012

    CC RoadCompleted

    R/f R&B Road to Katuivaripalem. CC RoadCompleted

    Bridges

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

    Reconstruction of High level Bridge @Km5/2 of Bapatla-Suryalanka Road across Perali drain in

    Guntur 79/2010-2011

    1.12.2010 01.12.10 31.5.2012 Approaches is in

    progress

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

    Reconstruction of High level Bridge @Km2/4 of Bapatla-Pandurangapuram Road across Perali

    drain in Guntur 78/2010-20111.12.2010 01.12.10 31.5.2012 Approaches is in

    progress

  • 7/31/2019 8.APRIL MPR- 2012

    20/91

    MONTHLY REPORT

    19 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 30.04.2012

    Category Packages allotted under Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC Progress up to 30.04.2012

    RCS

    NCRMP/B-W/AP/RCS/PRED/07/PPalem/001

    Road from R&B Road toMandevaripalem

    /2010-11Dt.01.11.2011

    01.11.11 31.07.2012BT completed, Shoulder Work

    is in Progress.

    Road from R&B Road Alluru toYadavapalem

    /2010-11Dt.01.11.2011

    01.11.11 31.07.2012Work yet to be started

    NCRMP/B-W/AP/RCS/PRED/07/KarlaPalem/002

    Road from Ganapavaram R & Broad to Pedamarpuvaripalem

    /2010-11Dt.01.11.2011

    01.11.11 31.10.2012Work yet to be started

    Road from R & B Road to

    Chinapuluguvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2011

    Work yet to be started

    Road from R & B road toYaramvaripalem

    /2010-11Dt.01.11.2011

    01.11.11 31.10.2011 CC Road work is Completed,Shoulders, and GSB is in

    progress.

    Road from R & B road toPedagollapalem Cyclone Shelter

    /2010-11Dt.01.11.2011

    01.11.11 31.10.201 CC Road work is Completed,Shoulder work is in progress.

    Pedagollapalem PR Road toBonthagorlapalem

    /2010-11Dt.01.11.2011

    01.11.11 31.10.201Work yet to be started

    NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003

    Road from R&B Road toGurunadhanagar

    /2010-11 Dt.17.10.2011

    17.10.11 16.07.12 Work yet to be started

    Road from R&B Road to AdavalaH/O Bavajipalem

    /2010-11 Dt.17.10.2011

    17.10.11 16.07.12 CC Road work is Completed,Shoulder work yetobe start.

  • 7/31/2019 8.APRIL MPR- 2012

    21/91

    MONTHLY REPORT

    20 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&B Road to Atlavaripalem

    /2010-11 Dt.17.10.2011

    17.10.11 16.07.12CC Road work is Completed.

    NCRMP/B-W/AP/RCS/PRED/07/Bapatla/004

    Road from R&B Road to

    Hanumanthanagar 2010-11Dt13.10.2011

    13.10.11 12.07.2012CC Road work is Completed,Shoulder work is in progress.

    Road from R & B road to Adarsanagar CC Road work is Completed,Shoulder work is in progress.

    Status of works in Prakasam District up to 30.04.2012

    Category Packages allottedunder Phase - 1

    Names of worksunder eachpackage

    Agreement No. /Date

    Milestone completion dates

    Progress up to30.04.2012 RemarksFirst Second Third

    BRIDGESNCRMP/B-

    W/AP/Br/R&B/08/Kanaparthy/012

    Construction of High level Bridge at

    Km 16/10 of Naguluppalapadu Kanaparthy road inPrakasam District

    76/2010-11 Dated1/12/2010

    5/31/2011Completion

    up to silllevel

    12/31/2011Completion upto below deck

    slab

    5/31/2012Completion of

    entire workincluding

    approaches

    Revitment work,Wearing coat,

    Approach road, &Gsb completed.WMM & Aprons

    work is in progress

    Reached Milestone-III

    RHBNCRMP/B-

    W/AP/RHB/PRED/08/S.Konda/001

    Road from PakalaZP Road to

    Aulavaripalem

    Cyclone shelter

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001

    Dated 25.04.2011 8/24/2011Earth work,

    CD work,GSB

    12/24/2011WBM, Grade II

    & III

    4/24/2012 BT,Shoulders &road furniture

    CC RoadCompleted.

    Shoulders work in

    progress

    Reached Milestone-III

    Road from R&BRoad to

    Somarajupalli

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001Dated 25.04.2011

    BT, CC road &culverts are

    completed from KM0/0 to 2/146.

    Reached Milestone-III

  • 7/31/2019 8.APRIL MPR- 2012

    22/91

    MONTHLY REPORT

    21 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&Broad to

    Narravaripalem

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001Dated 25.04.2011

    BT & culverts areCompleted fromKM 0/0 to 0/900.

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002

    Road from NH5 toMulaguntapadu

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011 6/9/2011

    Earth work,CD work,

    GSB

    10/9/2011WBM, Grade II

    & III

    2/9/2012 BT,Shoulders &road furniture

    WBM-Grade-IIwork iscompleted.WBMgr-III work to bestarted

    Not Reached asper Mile stone-III (Awaiting for EOT Proposal)

    Road from R&Broad to

    Chalivendradibba

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated -10/02/2011

    CC work iscompleted from KM0/0 to KM 0/270

    Not Reached asper Mile stone-III (Awaiting for EOT Proposal)

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002

    Road from PakalaR&B road to

    Mosanaladinne

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    dated 10/02/2011

    6/9/2011Earth work,

    CD work,GSB

    10/9/2011WBM, Grade II

    & III

    2/9/2012 BT,Shoulders &road furniture

    WBM-Grade-IImaterial collectionis in progress

    Not Reached asper Mile stone-III (Awaiting for EOT Proposal)

    Road from R&Broad to Binginapalli

    HarijanawadaCyclone Shelter

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011

    GSB completed

    Not Reached asper Mile stone-III (Awaiting for EOT Proposal)

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

    Road from R&BRoad Allur to M T

    Raju colony

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003Dated 27/04/2011

    8/26/2011Earth work,

    CD work,GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    BT, CC road &culverts arecompleted from km0/0 to km 3/8.

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    Road from KEMR&B Road to

    NCRMP/B-W/AP/RHB/PRED/0

    9/26/2011Earth work,

    2/26/2012WBM, Grade II

    7/26/2012 BT,Shoulders &

    BT completed.CDwork completed.CC

    Reached Milestone-III

  • 7/31/2019 8.APRIL MPR- 2012

    23/91

    MONTHLY REPORT

    22 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    8/Kothapatnam/004 Sankuvar igunta 8/Kothapatnam/004Dated 27/04/2011

    CD work,GSB

    & III road furniture road workcompleted from km

    0/0 to km 1/430

    Road from KEM R& B Road to

    Pullareddypalem

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011

    BT completed.CDwork completed.CCroad workcompleted from km0/0 to km 3/900

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/07

    Road from MCRoad to

    SubbarayaduSatram

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/07dated 27/04/2011

    8/26/2011Earth work,

    CD work,GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad workcompleted from km0/0 to km 4/4

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/08

    Road from R&Broad Tettu to

    Ramayapatnam

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/08dated 27/04/2011

    8/26/2011Earth work,

    CD work,GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &

    road furniture

    BT completed.CDwork completed.CCroad work

    completed from km0/0 to km 5/086

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/09

    Road from R&Broad Pellur toVasepallipadu

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/09dated 16/03/2011

    7/15/2011Earth work,

    CD work,GSB

    11/15/2011WBM, Grade II

    & III

    3/15/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad workcompleted from km0/0 to km 4/5

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/10

    Road from R&Broad to Kesupalem

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/10dated 19/04/2011

    7/18/2011Earth work,

    CD work,GSB

    10/18/2011WBM, Grade II

    & II

    1/18/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad workcompleted from km0/0 to km 2/103

    Reached Milestone-III

    RCSNCRMP/B-

    W/AP/RCS/PRED/08/Vetapalem/001

    Road from R&Broad to

    Vijayanagaramcolony cyclone

    shelter

    NCRMP/B-W/AP/RCS/PRED/0

    8/Vetapalem/001dated 2011/12

    dated 30.09.2011

    1/29/2012Earth work,

    GSB

    5/29/2012shoulders, Gr-

    III

    9/29/2012 BT,CC pavement

    and roadfurniture

    cc road completed,BT road

    completed&shoulders

    progress. Roadfrom km 0/0 to km

    0/525

    Reached Milestone-III

  • 7/31/2019 8.APRIL MPR- 2012

    24/91

    MONTHLY REPORT

    23 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from NH roadto

    Challareddypalem

    cc road completed,BT roadcompleted&shouldersprogress. Roadfrom km 0/0 to km1/735

    Reached Milestone-III

    Road from R&Broad to jeevaraksh

    nagar colonycyclone shelter

    C.C.completed.Shoulders Progress.

    Reached Milestone-III

    Road from R&Broad to Ramnagar

    colony cycloneshelter

    C.C.completedRoad from km 0/0to km0/475.ShouldersProgress.

    Reached Milestone-III

    Road from R&Broad to cyclone

    shelter atMankenavaripalem

    Not Grounded

    NCRMP/B-W/AP/RCS/PRED/0

    8/Chirala/002

    Road from R&BRoad to

    Keertivaripalemcyclone shelter NCRMP/B-

    W/AP/RCS/PRED/08/Chirala/002

    dated 27.08.2011

    C.C.completedRoad from km 0/0to km 0/265.ShouldersProgress.

    Reached Milestone-III

    Road from R&BRoad to Devinutulacyclone shelter of

    Chirala mandal inPrakasham district.

    C.C.completedRoad from km 0/0to km

    0/800.ShouldersProgress.

    Reached Milestone-III

    MPCSNCRMP/B-

    W/APMPCS/PRED/08/Ulavapadu/001

    Chakicharla cycloneshelter in

    Ulavapadu mandalPrakasam district

    NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001

    24.11.2011 All items upto stilt floor

    slabincluding

    ramp, stair case

    foundations,

    24.02.2012 Allitems up to

    second floor slab includingfirst floor, and

    in 2nd floor including stair case, columns

    24.05.2012Head room,plastering,

    flooring, water supply

    arrangements,sanitary fitting,

    electrical

    St ilt floor, G.F, &Terrace floor- roof slab completed.Brick workcompleted,Plastering work isin progress, Cattleplatform completed

    Reached Milestone-III

  • 7/31/2019 8.APRIL MPR- 2012

    25/91

    MONTHLY REPORT

    24 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    columns,beams,pcc

    flooring etc.,

    etc., items,compound

    wall, ccpavement.

    Earthenmounds(raised

    portion), water harvesting,septic tank,slump and

    soak pit.etc.

    revetment work isin progress,flooring work is inprogress,compound wall 120meters lengthcompleted,Electrical work is inprogress.

    NCRMP/B-W/APMPCS/PRED/

    08/NG Padu/003

    Kanaparthy cycloneshelter in

    Naguluppapadumandal Prakasam

    district

    NCRMP/B-W/AP/MPCS/PRED

    /08/NG Padu/003

    23.11.2011 All items upto stilt floor

    slabincluding

    ramp, stair case

    foundations,columns,bea

    ms,pccflooring etc.,

    23.02.2012 Allitems up to

    first floor slaband head

    room slab in 2nd floor

    including stair case, columns

    etc.,

    23.05.2012plastering,

    flooring, water supply

    arrangements,sanitary fitting,

    electricalitems,

    compoundwall, cc

    pavement.Earthenmounds(raised

    portion), water harvesting,septic tank,slump and

    soak pit.etc.

    Stilt floor, Groundfloor roof slabcompleted. Curingis in progress.

    As per Milestone-II, NotCompleted

  • 7/31/2019 8.APRIL MPR- 2012

    26/91

    MONTHLY REPORT

    25 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Nellore District up to 30.04.2012

    (RCS)

    Package Number Name of Work Milestone1 Milestone2 Milestone3 Remarks

    Progress up

    to30.04.2012

    NCRMP/B-W/AP/09MUTHUKUR/RC

    S/002

    Road from R&B Roadkappaladoruvu to bandla

    palem H.wada

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII,GrII,CC

    Pavement andShoulders

    9 Months: BTCC road and

    Road Furniturework completed 94% of workcompleted

    NCRMP/B-W/AP/09/D.V.SATRAM/R

    CS/008

    Road from R&B road toSullurpeta Mallam to

    berjengalapalli cyclone shelter 3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII, GrII Shouldersand CC Pavement

    9 Months: BT,CC Pavement

    and RoadFurniture

    BT IS Completed,shoulders is in

    progress

    94 % of workcompleted

    NCRMP/B-

    W/AP/09T.P.GUDUR/RCS/005

    Road from7/2 M.C Road tovenkannapalem pattapupalem work completed

    96 % of workcompleted

    NCRMP/B-W/AP/09chillakur/RCS/00

    4

    Road from KatuivaripalemR&B road to vellapalm

    3Months: EarthWork,CD

    Works,GSB

    6 Months: WBMGrII, GrII and

    Shoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    BT is completed 76 % of workcompleted

    NCRMP/B-W/AP/09kota/RCS /001

    road from R&B road to A.SPURAM 3Months: Earth

    Work, PipeCulverts, GSB

    6 Months: WBMGrII, GrII and

    Shoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    work completed 97 % of workcompleted

    Road from GD Road toVavillapalem

    BT IS Completed,shoulders is in

    progress

    96 % of workcompleted

    NCRMP/B-W/AP/RCS/PRED/09/KA

    VALI/007

    Road from Kotha Satram R&Bto Indiranagar (via)

    Thumalapenta palam,Patharavadu palam, Ramudu

    palam, Karaduvari palam&Sreeramapuram in SPSR

    Nellore District.

    4Months: EarthWork, Pipe

    Culverts, GSB

    4 Months: WBMGrII, GrII ,

    Shoulders and CCPavement

    4 Months: BT,CC Pavement

    and RoadFurniture

    BT IS Completed,shoulders is in

    progress

    78 % of workcompleted

  • 7/31/2019 8.APRIL MPR- 2012

    27/91

    MONTHLY REPORT

    26 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/09/KA

    VALI/006

    Road Connecting R&B Roadthrough Voter Village in SPSR

    Nellore District.

    4 Months: EarthWork, Pipe

    Culverts,GSB

    4 Months: WBMGrII, GrII ,

    Shoulders and CCPavement

    4 Months: BT,CC Pavement

    and RoadFurniture

    GSB 2/0 to 2/8 is inprogress, 6nos pipe

    culverts is inprogress

    16% of workcompleted

    Status of works in Nellore District up to 30.04.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/09RHB/K

    AVALI/004

    Road from5/8 of Chennayapalem Road to

    Gummadi bandla

    5Months:Earthwork, CD

    Works,ccpavement and GSB

    10 Months: WBMGrII,GrII and

    Shoulders

    15 Months: BTand RoadFurniture

    BT IS completed87 % of work is

    completed

    Road from PedattapupalemR&B road to Chennayapalem

    H.wada

    WBM Gr -III isCompleted

    73 % of work is

    completed

    Road from K.T R&B Road to Alliguntapalem

    BT IS Completed,

    shoulders is inprogress

    85 % of

    work iscompleted

    NCRMP/B-W/AP/RHB/PRED/09BOGOL

    U/RHB/002

    Road from 1/6 of ZuvvaladinneR&B Road to Tellagunta KM to

    2/720

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII, GrII and

    Shoulders

    9 Months: BTand RoadFurniture

    BT IS Completed,shoulders is in

    progress

    95 % of work is

    completed

    NCRMP/B-W/AP/RHB/PRED/09BOGOL

    O/RHB/001

    1. Road from NH5 toSambasivapuram

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months: WBMGrII, GrII and

    Shoulders

    15 Months: BTand RoadFurniture

    BT IS Completed,shoulders is in

    progress

    94 % of work is

    completed

    Road from 9/6 of JuvvaladinneR&B Road to 11/0 of

    Juvvaladinne R&B Road ViaVekateshpalem

    BT IS Completed,shoulders is in

    progress

    94 % of work is

    completed!

  • 7/31/2019 8.APRIL MPR- 2012

    28/91

    MONTHLY REPORT

    27 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/09/VIDAV

    ALURU/005

    1)Road from kt R&B ROAD TO ALLAGANIPADU to Vavilla

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months: WBMGrII, GrII and

    Shoulders

    15 Months: BTand RoadFurniture

    construction of structures is

    completed,ccPavement is

    Completed.GSB ISCOMPLETED

    42 % of work is

    completed!

    Road from R&B roadKancharapalem HW to

    Alaganipadu.

    earth work inembankment is in

    progress

    18 % of work is

    completed

    NCRMP/B-W/AP/RHB/PRED/09V.CHAL

    EM/RHB/007

    ROAD FROM SUVEPALLI-PUDIPARTHI ROAD TO

    SRIKANTH COLONY 4Months: EarthWork, Pipe

    Culverts, GSB

    8 Months: WBMGrII, GrII and

    Shoulders

    12 Months: BTand RoadFurniture

    WorkCOMPLETED,

    98 % of work is

    completed!

    providing BT Surface to the

    road from R&B road to EdagaliKandriga

    Work COMPLETED

    97 % of

    work iscompleted

    NCRMP/B-W/AP/RHB/PRED/09CHITTA

    MURU/003

    Road from R&B Road toMuttembake Via Pittuvanipalli 5Months: Earth

    Work, PipeCulverts, GSB

    10 Months: WBMGrII, GrII and

    Shoulders

    15 Months: BTand RoadFurniture

    WBM Gr -III, IS INPROGRESS

    49 % of work is

    completed

    Road from R&B Chittamur toSoma Samudram

    WBM Gr -III, IS INPROGRESS

    14 % of work is

    completed

    NCRMP/B-W/AP/09/MUTHUKUR/RHB/

    006

    Road from R&B roadtopatuvarikandriga

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII,GrII,CC

    Pavement andShoulders

    9 Months: BTand RoadFurniture

    Work Completed99 % of work is

    completed

  • 7/31/2019 8.APRIL MPR- 2012

    29/91

    MONTHLY REPORT

    28 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/09Allur/RHB/009

    Road from R&Broad alluru toGalidibbalu (via)Chukavani

    dibba

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months: WBMGrII, GrII and

    Shoulders

    15 Months: BTand RoadFurniture

    2 VENT SLABCULVERT IS INPROGRESS, BTKm 3.02 to 0/0 is

    completed,remaining is in

    progress

    62 % of work is

    completed

    NCRMP/B-W/AP/RHB/PRED/009/T.P.G

    UDUR/012

    Ring Road to TP Gudur-Salipeta R & B Road via CS

    Puram and Mandapam Village3Months: Earth

    Work, PipeCulverts, GSB

    6 Months: WBMGrII,GrII,CC

    Pavement andShoulders

    9 Months: BTand RoadFurniture

    GSB ,WBM Gr - II &Gr-III is completed

    71 % of work is

    completed

    Road from R & B Road C SPuram to Sivaramapuram

    GSB is completedWBM Gr -III is in

    progressCCPAVEMENT IS

    COMPLETED

    73 % of work is

    completed

  • 7/31/2019 8.APRIL MPR- 2012

    30/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    6.0 District wise status of tests conducted by TPQA:

    Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various

    stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are

    carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of

    tests conducted in the field till end of September 2011 are presented.

    Summary of QC Tests - Up to 30.4.2012

    S.No. District

    No. TestsConductedduring the

    Month

    Total no. of TestsCumulativeTests Done

    Total no. of Tests

    Passed Failed Passed Failed

    1 Srikakulam 220 220 0 732 732 0

    2 Vizianagaram 48 48 0 366 366 0

    3 Visakhapatnam 117 117 0 1161 1161 0

    4 East Godavari 79 79 0 666 666 0

    5 West Godavari 52 49 3 229 226 3

  • 7/31/2019 8.APRIL MPR- 2012

    31/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    7.0 Details of Quality Control Audit Reports Submitted During this Month:

    Package Number Name of Work Site Visit Dates District

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

    PROVIDING BT SURFACETO THE ROAD FROM R&B ROAD TO

    RAJAKODURU INRAMBILLI MANDAL

    17.12.11, 28.12.11, 10.01.12,09.02.12, 15.02.12, 22.02.12,24.02.12, 29.02.12, 02.03.12,

    09.03.12, 12.03.12 &27.03.12

    Vishakhapatnam

    NCRMP/B Road from Upmaka 16 02 12 24 02 12 29 02 12 Vishakhapatnam

  • 7/31/2019 8.APRIL MPR- 2012

    32/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR road toDasarivanipeta and to

    Cyclone Shelter

    09.03.12,13.03.12,14.03.12 & 17.03.12

    East Godavari

    NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

    Road from R&B road toB.V.Thota

    05.08.11, 12.08.11,19.08.11, 22.09.11,23.09.11, 10.10.11,03.11.11, 19.11.11,01.01.12, 24.02.12,10.03.12 & 15.03.12

    Krishna

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from R&B road toCyclone shelter at

    Chandala

    17.09.11, 23.09.11,14.10.11, 03.11.11,

    30.12.11, 13.01.12,24.01.12, 02.02.12,11.02.12, 15.02.12,21.02.12, 24.02.12,29.02.12, 06.03.12&15.03.12

    Krishna

    NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

    Road from PotalapalemZ.P road toChikativanipalem

    05.08.11, 19.08.11,29.08.11, 2.09.11, 10.09.11,22.09.11, 23.09.11,10.10.11, 12.10.11,15.10.11, 17.10.11, 3.11.11,9.11.11,19.11.11, 15.12.11,16.12.11, 22.12.11,27.12.11, 1.01.12,24.01.12,4.02.12, 8.02.12, 12.02.12,14.02.12, 18.02.12,22.02.12, 24.02.12,

    25.02.12 14.03.12 &15.03.12

    Krishna

    NCRMP/B- Road connecting R&B 05 08 11 12 08 11 Krishna

  • 7/31/2019 8.APRIL MPR- 2012

    33/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    01.01.12 24.02.12 &14.03.12

    NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001 Road from PotalapalemZP road to Potepalli 05.11.2011, 12.11.2011,19.11.2011, 25.11.2011,26.11.2011, 07.12.2011,12.12.2011, 13.12.2011,14.12.2011, 15.12.2011,19.12.2011, 26.12.2011,27.12.2011, 01.01.2012,02.01.2012, 03.01.2012,04.01.2012, 22.02.2012,

    24.02.2012 &14.03.2012

    Krishna

    NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

    Road from BhogireddipalliR&B road toRamakhandam

    05.11.2011, 12.11.2011,19.11.2011, 01.01.2012,07.01.2012, 09.01.2012,17.01.2012, 24.01.12,24.02.2012 &14.03.2012

    Krishna

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru ZProad to Rangaraopet

    17.09.2011, 23.09.2011,14.10.2011, 3.11.2011,20.12.2012, 22.12.2012,30.12.2011, 13.01.2012,2.02.2012, 11.02.2012,21.02.2012, 24.02.2012,29.02.2012, 5.03.2012 ,9.03.2012 &15.03.2012

    Krishna

    NCRMP/ B-W/ AP/ Br/ R&B/ 02/Puligadda/ 007

    Construction of Minor Bridge at Km. 7/2 near Puligadda of Konada

    04.12.11, 13.12.11,10.01.12, 12.01.12,08 02 12 14 02 12

    Vizianagaram

  • 7/31/2019 8.APRIL MPR- 2012

    34/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    24.02.2012,29.02.2012, 03.03.2012,

    05.03.2012,12.03.2012, 15.03.2012,18.03.2012,27.03.2012, 30.03.2012,03.04.2012 &18.04.2012

    NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction of CycloneShelter atPedaraghavulapeta inUppalaguptam Mandal,E.G.Dt.

    05.10.2011, 01.11.2011,02.12.2011,15.12.2012, 22.12.2011,13.01.2012, 31.01.2012,13.02.2012, 19.02.2012,24.02.2012, 29.02.2012,03.03.2012, 05.03.2012,12.03.2012, 15.03.2012,17.03.2012, 27.03.2012,30.03.2012, 02.04.2012 &19.04.2012

    East Godavari

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

    Construction of CycloneShelter at Avulamanda inThondangi Mandal,E.G.Dt.

    05.10.2011, 01.11.2011,02.12.2011,15.12.2011,22.12.2011,13.01.2012, 31.01.2012,13.02.2012, 19.02.2012,24.02.2012, 29.02.2012,03.03.2012, 05.03.2012,12.03.2012, 15.03.2012,

    18.03.2012, 27.03.2012,30.03.2012, 03.04.2012,08.04.2012, 12.04.2012,

    East Godavari

  • 7/31/2019 8.APRIL MPR- 2012

    35/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    8.0 Details of Environmental and Social Reports Submitted During this Month:

    Package Number Name of Work DistrictNCRMP/B-W/AP/MPCS/PRED/04/Thondangi/003

    Construction of cyclone shelter at Avulamanda in East Godavari District

    East Godavari

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/003

    Construction of cyclone shelter atLakshmanudipeta in East Godavari

    District

    East Godavari

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Road to Danavaipeta CS East Godavari

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Road to G.Musalayyapeta CS

    East Godavari

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Road to Gaddipeta CS East Godavari

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Road to Hukumpeta CS East Godavari

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Road to K.Chodipallipeta CS

    East Godavari

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Road to P.Chodipallipeta CS

    East Godavari

    9.0 Observations in the submitted reports:

    Name of

    Work:

    PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO RAJAKODURU IN

    RAMBILLI MANDAL1. Three works are there in this package:1) Road from R & B road to Rajakoduru and2) R d f R & B d K b l M i l d

  • 7/31/2019 8.APRIL MPR- 2012

    36/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    table 500.1310 Aggregate for Seal Coat: The gradation of seal coat chips was verified and the observed values are fairly

    satisfying the requirements of MORD Para 510.2.211 During execution, The rate of spraying of prime coat is verified and found within the specified limits as per

    Clause 502 and Table 500.1 of MORD. The spraying temperatures are also observed during executionand found varying from 300C to 340 C, which is within the specified limits as per MORD specification.

    12 During execution, the rate of spreading of tack coat is verified and found within the specified limits as per Clause 503 and Table 500.2 of MORD. The spraying temperatures are also observed during executionand found varying from 31C to 36C, which are within the specified limits as per MORD specifications.

    13 During execution, Temperature at mixing, laying and at compaction are verified and found to be within thespecified temperature range as per MORD Para 508.1.3.4

    14 The obtained values of Bitumen Extraction Test Results for OGPC and Seal Coat in % from KM 0/00 andKm 3/531 are verified and found tallying with the requirement as per IRC:SP:20 and IRC:SP:11. Thedetails are given in Annexure - 4.

    15 The measurements like width and thickness of the OGPC & Seal coat from Km 0/0 to Km 2/274, Km2/319 to Km 2/795 and Km 2/860 to Km 3/531 are verified and found fairly tallying with the requiredmeasurements. The details are given in Annexure-5.

    16 The measurements like width and thickness of the WBM Layers from Km 0/0 to Km 2/274, Km 2/319 toKm 2/795 and Km 2/860 to Km 3/531 are verified and found fairly tallying with the requiredmeasurements. The details are given in Annexure-2.

    17 Volumetric analysis tests conducted for WBM layers from Km 0/0 to Km 3/531. It is fairly tallying to thespecfication of MORD.

    18 Sand: a) Sieve Analysis tests are conducted. Sand is confirming to Zone II of MORD Para 1501.2.4.2.

    The results are found satisfactory.19 Graded Aggregates: Sieve analysis for 20mm graded metal is conducted and observed values are withinthe specified range as per MORD Para 802.3.1.

    20 At the time of laying C.C Road We have checked the physical properties, Gradation and proportioning of various ingredients.

    21 The C.C road contraction joints are provided, but the joints are not properly sealed. The field officers arerequested to take necessary action to seal the same as per MORD Sub clause 1501.22.

    22 The measurements like width and length of parapets and pipes of all the culverts are verified and foundtallying with the estimate.

    23 The approved letters of quarries like earth and aggregates have not been produced by field officers for

    verification.24 Pre-levels of earth work are not submitted for verification. Requested to furnish the pre-levels to the TPQAfor verification.

  • 7/31/2019 8.APRIL MPR- 2012

    37/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    same shall be furnished to the TPQA staff for verification.

    5 The field officers have furnished the test results for Soil, GSB and WBM obtained from Department of CivilEngineering, Gitam University and Sheladia Associates, VisakhapatnamMaterials.

    6 Sand: a) Sieve Analysis tests conducted for Sand. The Fine aggregate s found to confirm to Zone II of MORD Clause 1202. Fineness modulus is varying from 2.50 -2.53 as against the allowable limit 2.0 to3.50. The results are tabulated in Annexure

    7 Graded Aggregates : Sieve analysis for 20mm graded metal are conducted and observed values arewithin the specified range as per MORD Clause 1202

    8 Cement: Cement is tested for all the required tests on cement such as fineness, initial setting time, finalsetting time, consistency etc and the values observed within the specified range as per MORD Clause1202

    9 C.C Cubes : M20 grade C.C Cubes are tested for body wall concrete and the results are satisfying therequirements and M30 Cube Compressive strength results are found satisfactory.

    10 Construction of 2no.s of slab culverts are completed, During execution checked the placement of reinforcement as per SP -20, unit weight of steel, Workability test & pH value..etc.

    11 The formation width and shoulder widths are verified from KM 0/00 to KM 2/550 & KM 0/0 to KM 0/248mand at some locations the width of formation is less. The field officers are requested to furnish thereasons. (Avg. road widths from Km: 0/00 to KM 0/130 and 0/198 to KM 0/248 is 6.5 to 7.0m)

    12 Aggregate for OGPC and Seal Coat: The gradation and other physical tests are conducted for Coarseaggregate and the observed values are satisfied the requirements of MORD Para 508.1.2.1 and MORDtable 500.13

    13 Aggregate for Seal Coat: The gradation of seal coat chips was conducted and the observed values are

    fairly satisfying the requirements of MORD Para 510.2.214 During execution, The rate of spraying of prime coat is verified and found within the specified limits as per

    Clause 502 and Table 500.1 of MORD. The spraying temperatures are also observed during executionand found varying from 270C to 320 C, which is within the specified limits as per MORD specification.

    15 During execution, the rate of spreading of tack coat is verified and found within the specified limits as per Clause 503 and Table 500.2 of MORD. The spraying temperatures are also observed during executionand found varying from 30C to 36C, which are within the specified limits as per MORD specifications.

    16 During execution, Temperature at mixing, laying and at compaction are verified and found fairly satisfyingthe specified temperature range as per MORD Para 508.1.3.4

    17 The obtained values of Bitumen Extraction Test Results for OGPC and Seal Coat in % from KM 0/00 and

    Km 2/550 & KM 0/0 to KM 0/248 (Bit-II) are verified and found tallying with the requirement as per IRC:SP:20 and IRC:SP:11. The details are given in Annexure - 3.18 The measurements like width and thickness of the OGPC & Seal coat from KM 0/00 and Km 2/550 & KM

  • 7/31/2019 8.APRIL MPR- 2012

    38/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1) Road from R & B road to Rajakoduru and2) Road from R & B road to Kattubolu to Marripalem and3) Road from R & B road to Krishnampalem in Rambilli MandalThe individual progress of this work is 91.05% value of work is completed.The combined progress of this package is 68.19%.

    2 91.05 % value of the work is completed. Shoulder work is in progress.3 Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 14.01.12- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 14.05.12- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 14.09.12- BT and Road furniture.

    4 The material registers are maintained at site and same shall be shown to the TPQA for verification.

    5 The field officers have not furnished the bills and MTC's for cement and bitumen used for the road work.The same shall be furnished to the TPQA staff during the inspection for verification.6 The field officers are requested to test the samples of cement from every consignment and water before

    proceeding with the concrete work.7 The field officers have furnished the test results for Soil, GSB, WBM and Mix Designs obtained from

    Department of Civil Engineering, Gitam University, and Visakhapatnam.8 It is observed that obstruction of trees, electrical poles, Houses and building compound wall are inside the

    road width from Km 0/790 to Km 0/870.9 The formation width and earthen shoulder widths are verified from Km 0/0 to Km 0/870 and at some

    locations shoulders are slipped and requires rectified.10 The shoulder material of sand and gravel is not mixed properly. It shall be scarified, suitably remixed,

    watered to OMC and compacted to achieve the required relative compaction of min.98% of lab MDD as

    per the agreement clause.11 Aggregate for OGPC and Seal Coat: The gradation and other physical tests are conducted for Coarse

    aggregate and the observed values are satisfying the requirements of MORD Para 508.1.2.1 and MORDtable 500.13

    12 Aggregate for Seal Coat: The gradation seal coat chips conducted and the observed values are fairlysatisfying the requirements of MORD Para 510.2.2

    13 During execution, The rate of spraying of prime coat is verified and found within the specified limits as per Clause 502 and Table 500.1 of MORD. The spraying temperatures are also observed during executionand found varying from 270C to 300 C fairly satisfying specified limits as per MORD specification.

    14 During execution, the rate of spreading of tack coat is verified and found within the specified limits as per

    Clause 503 and Table 500.2 of MORD. The spraying temperatures are also observed during executionand found varying from 30C to 37C, which are within the specified limits as per MORD specifications.15 During execution, Temperature at mixing, laying and at compaction are verified and found to be within the

  • 7/31/2019 8.APRIL MPR- 2012

    39/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    route for easy passage of water.26 White washing is observed to parapet walls of the newly constructed culvert for the clear visibility of

    vehicular traffic.27 The test reports for water utilized in the construction of C.C Road are not shown to the TPQA staff for

    verification.28 The approved letters of quarries like earth and aggregates have not been produced by field officers for

    verification.29 Village name boards, cautionary and mandatory signboards at necessary points all along the outer edge

    of sharp curves and at school locations shall be erected.30 The Project informatory boards with all details is provided in site as per the guide lines by PIU, NCRMP.31 Para wise compliance report shall be furnished duly attending to the above remarks.

    Name of Work:

    PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO KATTUBOLU TOMARRIPALEM IN RAMBILLI MANDAL

    1. Three works are there in this package:1) Road from R & B road to Rajakoduru and2) Road from R & B road to Kattubolu to Marripalem and3) Road from R & B road to Krishnampalem in Rambilli MandalThe individual progress of this work is 17.71% value of work is completed.The combined progress of this package is 68.19%.

    2 18.00 % value of the work is completed. WBM Grade-II is completed. WBM Grade-III is to be

    taken up.3 Works to be done as per Milestone:Mile stone 1 to the end of Dt: 14.01.12- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 14.05.12- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 14.09.12- BT and Road furniture.

    4 The material registers should be provided at site and same shall be furnished to the TPQA for verification.

    5 The field officers are requested to test the samples of cement from every consignment and water beforeproceeding with the concrete work.6 The field officers have furnished the test results for Soil, GSB, WBM and Mix Designs obtained from

    Department of Civil Engineering, Gitam University, and Visakhapatnam.7 The formed width is varying from 6.0 to 7.0m from Km 0/0 to Km 0/390 and Km 0/597 to Km 0/707.The

    reasons has to be furnished for the same.8 The formation slopes are slipped at some locations between Km 0/0 to Km 0/390 and Km 0/597 to Km

    0/707 same shall be rectified

  • 7/31/2019 8.APRIL MPR- 2012

    40/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    19 The Project informatory boards with all details shall be provided in site as per the guide lines by PIU,NCRMP.

    20 The Project informatory boards with all details shall be provided in site as per the guide lines by PIU,NCRMP.

    Name of Work: Providing B.T to the Road from NH-5 to Ramarayadupalem.

    1. 95.59 % value of the work is completed.2 Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 14.12.11- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 14.03.12- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 14.06.12- BT and Road furniture.

    3 The field officers have not furnished the bills and MTC's for cement and bitumen used for the road work.The same shall be furnished to the TPQA staff for verification.

    4 The field officers have furnished the test results for Soil, GSB, WBM and Mix Design obtained fromDepartment of Civil Engineering, Gitam University, and Visakhapatnam.

    5The formation width is less than the approved drawing width of 7.5m. The formed width is varying from6.0 to 7.0m. It is observed that hand pump and electrical poles are inside the road width on both sidesfrom Km 0/30 to Km 0/200m.

    6 The formation width and earthen shoulder widths are verified from Km 0/0 to Km 0/391 and at somelocations shoulders have slipped and the same shall be rectified.

    7 The shoulder material of sand and gravel shall be mixed properly. It shall be scarified, suitably remixed,watered to OMC and compacted to achieve the required relative compaction of min.98% of lab MDD asper the agreement clause.

    8 Aggregate for OGPC and Seal Coat: The gradation and other physical tests are conducted for Coarseaggregate and the observed values are satisfying the requirements of MORD Para 508.1.2.1 and MORDtable 500.13

    9 Aggregate for Seal Coat: The gradation seal coat chips conducted and the observed values are fairlysatisfying the requirements of MORD Para 510.2.2

    10 During execution, The rate of spraying of prime coat is verified and found within the specified limits as per Clause 502 and Table 500.1 of MORD. The spraying temperatures are also observed during executionand found varying from 270C to 300 C, fairly satisfying the specified limits as per MORD specification.

    11 During execution, the rate of spreading of tack coat is verified and found within the specified limits as per

  • 7/31/2019 8.APRIL MPR- 2012

    41/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    specification.20 During execution of C.C Road TPQA conducted sieve analysis and physical properties of Aggregates,

    Workability test, pH value.etc.21 Contraction joints are provided but the joints are not sealed. The field officers are requested to take

    necessary action to improve the same as per MORD Sub clause 1501.22.22 The test reports are not shown for water utilized in the construction of C.C Road to the TPQA staff for

    verification.23 The approved letters of quarries like earth and aggregates have not been produced by field officers for

    verification.24 Village name boards, cautionary and mandatory signboards at necessary points all along the outer edge

    of sharp curves and at school locations shall be erected.25 The Project informatory boards with all details is provided in site as per aggrement.The same may be

    provided immediately at site as per the guide lines by PIU, NCRMP.

    Name of Work: Road from PR road to Dasarivanipeta and to Cyclone Shelter

    1. 100% value of the work is completed

    2. As per the Agreement the Mile stones fixed are as follows.Milestone 1 to the end of Dt.26.07.2011, Earth work, CD Works, GSBMilestone 2 to the end of Dt.26.10.2011, WBM Gr II , Gr III and Shoulders

    Milestone 3 to the end of Dt.26.01.2012, BT and Road Furniture3. The measurements like width and thickness of the OGPC + Seal Coat Layer from Km 0.000 to Km 2.280is verified and found to be fairly tallying with the required measurements, Primer Coat,Bitminius extractiontests conducted for OGPC + Seal Coat layer and Tack Coat in the same reach and they are tallying withthe agreement requirements. The details are given in Annexure-1 and in QC test summary from km 0.000to km.2.280

    4. Widening of earthwork formation is to be done prior to taking up BT layers5. Widening of the formation is not done as per requirement and it is less than 7.5M at almost all the

    locations. The formation width is varying from 5.00m to 6.50m at Km 0.470 of temple L/S, Km 0.650 of built-up area L/S, Km 0.790, in between Km 1.435 to Km 1.475 and from Km 2.114 to Km 2.165 of and

    built-up area R/S. Lateral support to the road crest is very important.6. Guard stones shall be fixed at Curved areas and canal side berg portion from Km 0.500 to Km 2.040 andL/S from Km 2.075 to Km 2.280. Painting as Black & White Strips is to be done to stones for clear visibility

  • 7/31/2019 8.APRIL MPR- 2012

    42/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    summary. They are fairly tallying with the specfication requirements of clause 405.13 of MORD.6. The 600mm dia single row pipe culvert 1 No. is completed in Km 0/47. While laying WBM simultaneously shoulders shall be also compacted.8 The project informatory boards with all details, Cautionary sign boards at necessary points and Village

    name boards are not provided as per aggregement.The same shall be provided as per the guidelinesgiven by PIU,NCRMP.

    9 Parawise compliance report shall be furnished duly attending to the above remarks.

    Name of Work: Road from R&B road to Cyclone shelter at Chandala

    1. 60.48 % value of the work is completed. Total stretch of road is 625 mts. GSB for length of 625mts; WBMGr-II & Gr-III for length of 575mts is completed.2. Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 26.07.2011 - Earthwork, Pipe Culverts, GSB - 3 MonthsMile stone 2 to the end of Dt: 26.10.2011 - WBM Gr-II, Gr-III and Shoulders - 3 MonthsMile stone 3 to the end of Dt: 26.01.2012 - BT and Road furniture - 3 Months

    3. 3rd Milestone Completed but BT and Road Furniture Works are not yet Completed. Progress needs to beimproved

    4. The measurements like width and thickness of the GSB, WBM Gr-II & Gr-III Layers from Km 0.000 to Km0.575 are verified and found to be fairly tallying with the required measurements. The details are given in

    Annexure - 1.5. Volumetric analysis tests were conducted for WBM Gr-II & Gr-III layers from Km 0/0 to Km 0/575. QC tests

    were conducted for WBM Gr-II & Gr-III (field & Lab) i.e., Gradation, The Details are givenin QC testsummary. They are fairly tallying with the specfication requirements of clause 405.13 of MORD.

    6. The 600mm dia single row pipe culvert (1 No's) completed in 0/4.7. While laying WBM simultaneously shoulders shall be also compacted.8. The project informatory boards with all details, Cautionary sign boards at necessary points and Village

    name boards are not provided as per aggregement.The same shall be provided as per the guidelinesgiven by PIU,NCRMP.

    9. Parawise compliance report shall be furnished duly attending to the above remarks.

    Name of

  • 7/31/2019 8.APRIL MPR- 2012

    43/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Name of Work: Road connecting R&B road through Gantalammapalem

    1. 53.47 % value of the work is completed. Total stretch of road is 2.0450 mts. GSB, WBM Gr-II & Gr-IIIfor length of 2045 mts is completed.

    2 Works to be done as per Milestone:Mile stone 1 to the end of Dt: 26.07.2011 - Earthwork, Pipe Culverts, GSB - 3 MonthsMile stone 2 to the end of Dt: 26.10.2011 - WBM Gr-II, Gr-III and Shoulders - 3 MonthsMile stone 3 to the end of Dt: 26.01.2012 - BT and Road furniture - 3 Months

    3 3rd Milestone Completed but BT and Road Furniture Works are not yet Completed. Progress needs to beimproved

    4 The measurements like width and thickness of the GSB, WBM Gr-II % Gr-III Layers from Km 0.000 toKm2.350 are verified and found to be fairly tallying with the required measurements. The details are givenin Annexure - 1.

    5 Volumetric analysis tests were conducted for WBM Gr-II & Gr-III layers from Km 0/0 to Km 2.350. QC testswere conducted for WBM Gr-II & Gr-III (field & Lab) i.e., Gradation. The Details are givenin QC testsummary. They are fairly tallying with the specfication requirements of clause 405.13 of MORD.

    6 The 600mm dia single row pipe culverts (3 Nos.) completed in 1/2, 3/0 & 3/4.7 While laying WBM simultaneously shoulders shall be also compacted.8 The project informatory boards with all details, Cautionary sign boards at necessary points and Village

    name boards are not provided as per aggregement.The same shall be provided as per the guidelines

    given by PIU,NCRMP.9 Parawise compliance report shall be furnished duly attending to the above remarks.

    Name of Work: Road from Chinnapuram R&B road to Gundupalem

    1. 12.14 % value of the work is completed. Total stretch of road is 0.485 mts. GSB is completed for length of 0.435mts against length of 0.485 mts

    2 Works to be done as per Milestone:Mile stone 1 to the end of Dt: 01.12.2011 - Earthwork, Pipe Culverts, GSB - 3 MonthsMile stone 2 to the end of Dt: 01.03.2012 - WBM Gr-II, Gr-III and Shoulders - 3 MonthsMile stone 3 to the end of Dt: 01.06.2012 - BT and Road furniture - 3 Months

  • 7/31/2019 8.APRIL MPR- 2012

    44/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    are verified and found to be fairly tallying with the required measurements. The details are given in Annexure - 1.

    5 Volumetric analysis tests were conducted for WBM Gr-II layer from Km 0/0 to Km 0/595. QC tests wereconducted for WBM Gr-II (field & Lab) i.e., Gradation. The Details are givenin QC test summary. They arefairly tallying with the specfication requirements of clause 405.13 of MORD.

    6 The project informatory boards with all details, Cautionary sign boards at necessary points and Villagename boards are not provided as per aggregement.The same shall be provided as per the guidelinesgiven by SPIU, NCRMP.

    7 Parawise compliance report shall be furnished duly attending to the above remarks.

    Name of Work: Road from Bhogireddipalli R&B road to Ramakhandam

    1. 13.20 % value of the work is completed. Total stretch of road is 1.470 mts. GSB is completed for length of 1420mts...

    2 Works to be done as per Milestone:Mile stone 1 to the end of Dt: 01.12.2011 - Earthwork, Pipe Culverts, GSB - 3 MonthsMile stone 2 to the end of Dt: 01.03.2012 - WBM Gr-II, Gr-III and Shoulders - 3 MonthsMile stone 3 to the end of Dt: 01.06.2012 - BT and Road furniture - 3 Months

    3 2nd Milestone Completed but WBM Gr-II & Gr-III Works are not yet Completed. 1st Milestone works likeEarthwork and Pipe Culverts are also still in balance. Progress needs to be improved.

    4 The measurements like width and thickness of the GSB Layers from Km 0.000 to Km 1.420 are verified andfound to be fairly tallying with the required measurements. The details are given in Annexure - 1.

    5 The 600mm dia single row pipe culverts (3 No's) are not completed in 0/2, 0/4 & 1/4.6 While laying WBM simultaneously shoulders shall be also compacted.7 The project informatory boards with all details, Cautionary sign boards at necessary points and Village

    name boards are not provided as per aggregement.The same shall be provided as per the guidelines givenby SPIU, NCRMP.

    8 Parawise compliance report shall be furnished duly attending to the above remarks.

    Name of Work: Road from Intheru ZP road to Rangaraopeta

    1. 59.34 % value of the work is completed. Total stretch of road is 635 mts. GSB, WBM Gr-II & Gr-III iscompleted for length of 635mts.

    2 Works to be done as per Milestone:

  • 7/31/2019 8.APRIL MPR- 2012

    45/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1. Bridge Work and approach work is completed except for Quadrants, shoulders and fixing strip real joints.2 Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 30.06.2011- Earthwork for foundation, PCC for Foundation, Footings.Mile stone 2 to the end of Dt: 31.01.2012- Substructure for abutments and wing walls,Supply and fixing of elastomeric neoprene bearings, Super structure and 300mm thick Grouted roughstone revetment, Earth work for approaches etc.,.Mile stone 3 to the end of Dt: 30.05.2012- Super structure and construction of precast RCC railing, Stripseal expansion joints, Completion of SDBC etc.

    3 The field officers have furnished the test results for Soil, GSB, WMM and SDBC obtained from Departmentof Civil Engineering, Andhra University & Gitam College, and Visakhapatnam.

    4 Quality control lab is available at site and material registers are shown to TPQA for verification.Materials

    5 Sand: a) Sieve Analysis tests are conducted. Sand is confirming to Zone II as per MORT & H Table 1000-2.

    Fineness modulus is varying from 2.57 -3.07 as against the allowable limits of. 2.0 to 3.50. The results arefound satisfactory.

    6 Graded Aggregates : Sieve analysis for 20mm graded metal are conducted and observed values are withinthe specified range as per MORT&H table 1000-1

    7 Water: Sample is collected and sent to Gitam University for testing of Physical properties and the obtainedresults are within the specified range as per IS: 456-2000 & IS: 3025-1986.

    8 Cement: cement Samples are collected and tested for Fineness, Standard consistancy,Initial and finalsetting times and the obtained results are within the specified range as per MORT & H Clause 1006

    9 Steel: Steel samples are collected and tested for mechanical properties and the obtained results are withinthe specified range as per IS 1786. The steel samples are randomly collected and tested for verification of

    Mass per Meter Run, the results are given in annexure-I10 Cement slurry coating for Steel: The protection of reinforcement against corrosion prior to the concretingwas done by applying a Cement slurry coating on the steel.

    11 The diameter of piers is verified and the values are fairly tallying as per drawings. The dimensions of pedestal over pier P1 and P2 are verified and found 2.00m x 2.01m x 0.5m and 2.01 x 2.015m x 0.5mrespectively as against of 2.0m x 2.0m x 0.5m.The Measurement Books are not produced for verification.

    12 The dimensions of the hammer head bed block over pier P1,P2 are verified and the same are fairly tallyingas per drawing

    13 The dimensions of Elastomeric bearings are verified and found fairly satisfying the requirements Table2000-2 of MORT & H the result are given in Annexure 2

    14 The finished levels of slabs are verified and fairly tallying with the drawing. Plumb is verified for the sides of the girders and the same is observed to be fair and within tolerance limits as per cl. 2208 of MORT&Hspecifications. The levels are tabulated in Annexure-8

  • 7/31/2019 8.APRIL MPR- 2012

    46/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    23 During execution of Bridge Approaches, Gradation, Physical properties like AIV, FI & EI etc and Relativecompaction tests are conducted for embankment, GSB and WMM layers and the test results are foundwithin the specified limits as per Agreement condition.

    24 The measurements like width and thickness of the GSB and WMM layers from Km 6/841 to Km 6/945 andKm 6/996 to Km 7/083m are verified and found to be tallying with the required measurements. The detailsare given in Annexure - 2 & 3.

    25 During execution,Temparature at mixing, laying and at compaction are verified and found to be within thespecified temperature range as per MORT & H Para's 508.4.6, 508.4.7 & 508.4.8.

    26 The measurement like width and thickness of the SDBC layer from Km 6/841 to Km 6/945 and Km 6/996 toKm 7/083m is verified and found to be tallying with the required approved drawing.

    27 The obtained values of Bitumen Extraction Test Results for SDBC from Km: 6/841 to Km 6/945 and Km:6/996 to Km 7/083m are verified and found tallying with the requirement as per MORT &H Cl: 508. Thedetails are given in Annexure - 5.

    28 The embankment formation requires trimming of side slopes as specified in MORT & H sections 301 & 305.29 The stone samples using for protection of slope are collected for testing the size and weight. The result of

    Some samples are not satisfying the requirements as per MORT & H Para 2504.1. NCR is issued for thesame.

    30 SBC required as per designs is 26T/m2 for Piers and 21 T/m2 for Abutments. As per the soil test resultsobtained from the Andhra University , Visakhapatnam for piers P1, P2, the values of SBC are 38 T/m2and 40.80T/m2 respectively and for Abutment A1 is 30.9 T/m2 ,A2 is 34.1T/m2.The confirmatory SBC testconducted by TPQA and the value is 28T/m2 for pier foundation.

    31 TPQA staff regularly inspecting the site and gives the OK card by conducting the tests on input material.32 The approved letters of quarries like earth and aggregates have not been produced by field officers for

    verification33 The Project informatory board is erected with all details at site.34 Para wise compliance report shall be furnished for this and previous QCR's duly attending to the remarks.

    Name of Work:

    Construction of Minor Bridge at Km. 15/2 near Chakaligadda of Konada RamatheerthamR&B Road to Konathalapalem (via) Yerukonda, Pasupam, Kollayavalsa (Z.P. Road) inVizianagaram District.

    1. Progress: About 78.76% of work is completed as against of 82.07%.The progress of work is slightly slow.

    Awaiting for approval of Working estimate for retaining wall2 works to be done as per milestone:

    Milestone:1 to the end of date 07-07-2011-Foundation Up to sill level

  • 7/31/2019 8.APRIL MPR- 2012

    47/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Drg. No.SD/114. Necessary cover blocks, chairs, spacers are provided to fix the reinforcement firmly in itscorrect position

    12 During execution, tests are conducted for Water pH value, temperature and workability of concrete andfound within the specified limits as per MORT& H.

    13 C.C Cubes : M30 grade C.C Cubes Compressive strength results are satisfactory as per MORT&Hsection 1700. The result are given in the Annexure-2

    14 During execution of Bridge Approaches, Relative compaction tests are conducted for embankment layersand the test results are found within the specified limits as per Agreement conditions.

    15 The tie rods and steel rods used for supporting the centering are to be cut and removed immediately andsurface finished neatly as per MORT&H Cl: 1714.

    16 Non destructive test conducted with rebound hammer on Abutment, bed block over abutment,Hammerhead bed block, and deck slab and the results are tabulated in the Annexure-3

    17 The weep holes in abutment are blocked at some places. The field officers are instructed to get them

    cleared immediately. Dead mortar is observed on Abutment and the surface finishing appears to be rough.The field officers are requested to clear the dead mortar immediately.

    18 Rough stone collected for protection works are examined. Some stones are weighing less than 40 Kgs andmeasuring less than 300mm which are specified as per MORT&H cl: 2504. NCR was issued in this regard.

    19 TPQA staff regularly visits the site and gives the OK card by conducting the tests on input material.20 The approved letters of quarries like earth and aggregates have not been produced by field officers for

    verification21 The Project informatory board is erected with all details at site.22 The Contractor shall take necessary precautions for safety of the workers and preserving their health while

    working in such jobs, which require special protection and precaution.

    23 Para wise compliance report shall be furnished for this and previous QCR's duly attending to the remarks.

    Name of Work: Construction of cyclone shelter at Lakshmanudipeta in Thondangi Mandal, E.G.Dt.

    1. Two works are there in this package:1) Construction of cyclone shelter at Lakshmanudipeta in Thondangi Mandal Type -A and2) Construction of cyclone shelter at Avulamanda in Thondangi Mandal Type -BThe individual progress of this work is 17.36% value of work is completed.

    2 17.36 % value of the work is completed. Sand Filling work is in progress.

    3 Works to be done as per Combined Milestone:Mile stone 1 to the end of Dt: 16.02.2012- Ground Floor and Plinth Level.Mile stone 2 to the end of Dt: 16.06.2012- First Floor Roof Slab Cast.

  • 7/31/2019 8.APRIL MPR- 2012

    48/91

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    15 Alkali Aggregate Reactivity Tests: Samples are collected and sent to Civil Aid for testing of Alkali Aggregatereactivity test for Fine