Aste-6z3qgx r0 En

Embed Size (px)

Citation preview

  • 7/31/2019 Aste-6z3qgx r0 En

    1/60

    ElectricalInstallation

    InfraStruXure Power

    Generation System250 A ATS

    80 kW and 120 kW Generators

  • 7/31/2019 Aste-6z3qgx r0 En

    2/60

    This manual is available in English on the enclosed CD.

    Uivatelsk pruka v etin je k dispozici na piloenm CD.

    Dieses Handbuch ist in Deutsch auf der beiliegenden CD-ROM verfgbar.

    Deze handleiding staat in het Nederlands op de bijgevoegde cd.

    Este manual est disponible en espaol en el CD-ROM adjunto.

    Ce manuel est disponible en franais sur le CD-ROM ci-inclus.

    A hasznalati utasitas magyarul megtalalhato a csatolt CD-n.

    Questo manuale disponibile in italiano nel CD-ROM allegato.

    CD-ROMDenne manualen er tilgjengelig p norsk p vedlagte CD.

    Instrukcja Obsugi w jezyku polskim jest dostepna na CD.

    O manual em Portugus est disponvel no CD-ROM em anexo.

    -.

    Denna manual finns tillgnglig p svenska p medfljande CD.

    Bu kullanim kilavuzunun Trke's, lxkte gnderlen CD ersnde mevcuttur.

    CD

  • 7/31/2019 Aste-6z3qgx r0 En

    3/60

    InfraStruXure Power Generation System i

    About This Manual

    Audience

    This manual is intended forcertified electricians who will be installing the InfraStruXure Power

    Generation System. It provides detailed electrical and physical specifications, diagrams, and

    instructions on how to position and install the Generator and the Smart Distribution Panel with

    Automatic Transfer Switch (ATS).

    Companion manuals

    For additional information about the InfraStruXure Power Generation System, refer to the following

    sheets and manuals:

    ATS Unpacking Sheet(990-1842)

    ATS Operation Manual (990-2355)

    InfraStruXure Power Generation System Generator Reference Manual (990-2334)

    Network Management Interface Users Guide (available on the APC Web site or the Utility CD)

    (990-1993)

    How to find updates to this manual

    You can check for updates to this manual by clicking on the User Manuals link on the Support page

    of the APC Web site (www.apc.com). Choose Power Generation and then InfraStruXurePower

    Generation. In the list of manuals, look for the latest letter revision (A, B, etc.) of the part number

    appearing on the back cover of this manual.

  • 7/31/2019 Aste-6z3qgx r0 En

    4/60

  • 7/31/2019 Aste-6z3qgx r0 En

    5/60

    Contents

    InfraStruXure Power Generation System iii

    Safety................................................................................1

    Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

    Save these instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

    Safety symbols used in this manual . . . . . . . . . . . . . . . . . . . . . . . . . 1

    Cross-reference symbols used in this manual . . . . . . . . . . . . . 1

    Warnings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2

    Read these instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . 2The InfraStruXure Power Generation System

    is an optional standby system . . . . . . . . . . . . . . . . . . . . . . . 2

    Fuel and fumes are flammable . . . . . . . . . . . . . . . . . . . . . . . 3

    Exhaust gases are deadly . . . . . . . . . . . . . . . . . . . . . . . . . . 3

    Moving parts can cause severe personal injury or death . . . . . . 3

    Do not operate in flammable and explosive environments . . . . . 4

    Electrical shock can cause severe personal injury or death . . . . 4

    General safety precautions . . . . . . . . . . . . . . . . . . . . . . . . . 5

    Battery considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

    System Data .....................................................................7

    Electrical. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7

    Power and communication connections . . . . . . . . . . . . . . . . . 7

    Physical . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9

    Generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

    Special considerations for generator installations . . . . . . . . . 10

    Smart Distribution Panel with ATS . . . . . . . . . . . . . . . . . . . 11

    Cabling............................................................................13

    Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13

    Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14

    Pour the generator pad . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

    Install the generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

    Run cables from the generator to the ATS . . . . . . . . . . . . . . 15

    Install the ATS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

  • 7/31/2019 Aste-6z3qgx r0 En

    6/60

    iv InfraStruXure Power Generation System

    Wiring .............................................................................23

    Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

    Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24Connect power from the generator to the ATS . . . . . . . . . . . 24

    Connect mains input to the ATS . . . . . . . . . . . . . . . . . . . . . 26

    Connect the DC power input, start, and E-Stop contacts . . . . . 28

    Connect the communication cable from the ATS

    to the generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

    Run AC power from the ATS to the generator

    for the heater and battery charger . . . . . . . . . . . . . . . . . . . 33

    Connect branch distribution equipment to the ATS . . . . . . . . 34

    Connect an EPO switch to the user interface board

    and test the switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35Connect contacts to the user interface board . . . . . . . . . . . . 38

    Connect the ATS to the network

    at the surge-protected ethernet port . . . . . . . . . . . . . . . . . . 40

    Appendix A: Adding Circuit Breakers ......................... 41

    How to Add Sub-Feed OutputDistribution Circuit Breakers to the ATS . . . . . . . . . . . . . . . . . . . . . 41

    Output distribution circuit breakers available from APC . . . . . 41

    Determine the configuration of the panel . . . . . . . . . . . . . . . 42

    Preparing the breakers for installation . . . . . . . . . . . . . . . . . 43

    Parts and tools needed for installation procedures . . . . . . . . 44

    Installing circuit breakers on the ATS panel board . . . . . . . . . 45

    Appendix B: Wire Sizes ................................................ 47

    250 A ATS and 80 kW Generator . . . . . . . . . . . . . . . . . . . . . 47

    250 A ATS and 120 kW Generator . . . . . . . . . . . . . . . . . . . . 47

    Installation Checklist..................................................... 49

  • 7/31/2019 Aste-6z3qgx r0 En

    7/60

    InfraStruXure Power Generation System 1

    Safety

    Overview

    Save these instructions

    This manual contains important instructions that must be followed during installation, operation, and

    maintenance of the InfraStruXure Power Generation System.

    Safety symbols used in this manual

    Cross-reference symbols used in this manual

    ElectricalHazard

    Indicates an electrical hazard, which, if not avoided, could result in injury or

    death.

    DANGER

    Indicates a hazard, which, if not avoided, could result in severe personal injury or

    substantial damage to product or other property.

    Heavy

    Indicates a heavy load that should not be lifted without assistance.

    Note

    Indicates important information.

    Indicates that more information is available on the same subject in a different section of

    this manual.

    See also

    Indicates that more information is available on the same subject in a different manual.

  • 7/31/2019 Aste-6z3qgx r0 En

    8/60

    2 InfraStruXure Power Generation System

    Warnings

    The components in the InfraStruXure Power Generation System and UPS power distribution

    system can pose life-threatening danger when improperly installed, operated, or maintained. To

    prevent accidents, be aware of the dangers and act safely. Read and follow all of the safety

    instructions and warnings in this manual and in all of your component manuals.

    The Generator and Automatic Transfer Switch (ATS) that you purchased from American Power

    Conversion (APC) is classified as an Optional Standby Systemit provides backup or standby

    power to data centers in the event of a sustained power failure.

    The InfraStruXure Power Generation System is not to be classified as anEmergency System that

    is essential for safety to human life (e.g., fire pumps, operating room equipment, and life-

    support equipment in hospitals) as legally required by your national and local codes.

    The InfraStruXure Power Generation System is not to be classified as aLegally Required

    StandbySystem, as it is not supplying power to aid in fire fighting, rescue operations, control of

    health hazards (e.g., sewage), and similar operations as required by your national and local

    codes.

    Emergency andLegally Required Systems are not allowed to rely on municipal fuel for

    operation and municipal water for cooling.Emergency andLegally Required Systems require

    dual fuel systems, with one of them being a two-hour, on-site fuel supply.

    Your InfraStruXure Power Generation System is not to be classified as anIntegrated Electrical

    System, as an orderly shutdown is not required to prevent damage to the generator. Thegenerator is not to be paralleled with another generator.

    Your generator will operate at its rated load without being re-fueled for a minimum of six hours,

    and should be able to run with no load for a minimum of 12 hours.

    Your generator can be without electrical power to the load terminals of the ATS for a maximum

    of 60 seconds, but will typically be without power for no more than 10 seconds.

    Note

    Read these instructions

    Note

    The InfraStruXure Power Generation System is an optional standby system

  • 7/31/2019 Aste-6z3qgx r0 En

    9/60

    Safety

    InfraStruXure Power Generation System 3

    Fire, explosion, and personal injury or death can result from improper practices.

    DO NOT fill fuel tanks while the engine is running, unless the tanks are outside the engine

    compartment. Fuel contact with a hot engine or exhaust is a potential fire hazard.

    DO NOT permit any flame, cigarette, pilot light, spark, arcing equipment, or other ignition

    source near the generator or fuel tank.

    Ensure that exhaust gases are properly discharged away from enclosed or sheltered areas, as

    well as areas where individuals are likely to congregate.

    Ensure that the unit is well ventilated.

    Engine exhaust and some of its constituents are known to cause cancer, birth defects, and

    other reproductive harm. Take care not to breathe, ingest, or come in contact with exhaust

    gases.

    Keep your hands, clothing, and jewelry away from moving parts.

    Before starting work on the generator, disconnect the battery charger from its AC source, and

    then disconnect the battery. Be sure to disconnect the batterys negative () cable first. This

    should prevent accidental starting.

    Make sure that fasteners on the generator are secure. Tighten supports and clamps, and keep

    guards in position over fans, drive belts, etc.

    Do not wear loose clothing or jewelry in the vicinity of moving parts, or while working onelectrical equipment. Loose clothing and jewelry can become caught in moving parts.

    If an adjustment must be made while the unit is running, use extreme caution around hot

    manifolds, moving parts, etc.

    DANGER

    Fuel and fumes are flammable

    DANGER

    Exhaust gases are deadly

    DANGER

    Moving parts can cause severe personal injury or death

  • 7/31/2019 Aste-6z3qgx r0 En

    10/60

    Safety

    4 InfraStruXure Power Generation System

    Flammable vapor can cause an engine to overspeed and become difficult to stop, resulting inpossible fire, explosion, severe personal injury, or death. Do not operate a generator where a

    flammable vapor environment can be created by a fuel spill, leak, etc., unless the generator is

    equipped with an automatic safety device to block the air intake and stop the engine. The

    owners and operators of the generator are solely responsible for operating the generator safely.

    Disconnect or disengage electric power before removing protective shields or touchingelectrical equipment. Wear rubber boots when working on electrical equipment. Do not wear

    damp clothing (particularly wet shoes) or allow skin surface to be damp when handling

    electrical equipment. Do not wear jewelryjewelry can short out electrical contacts and

    cause shock or burns.

    Use extreme caution when working on electrical components. High voltages can cause injury

    or death. DO NOT tamper with interlocks.

    Follow all applicable national and local electrical codes. Have all electrical installations

    performed by a qualified licensed electrician. Lock out and tag open switches to avoid

    accidental closure.

    Hazardous voltages can flow from the generator into the mains line, creating a potential for

    electrocution of service personnel or property damage. DO NOT CONNECT THE

    GENERATOR DIRECTLY TO ANY BUILDING ELECTRICAL SYSTEM. CONNECT

    ONLY TO THE AUTOMATIC TRANSFER SWITCH.

    DANGER

    Do not operate in flammable and explosive environments

    ElectricalHazard

    Electrical shock can cause severe personal injury or death

  • 7/31/2019 Aste-6z3qgx r0 En

    11/60

    Safety

    InfraStruXure Power Generation System 5

    Coolants under pressure have a higher boiling point than water. DO NOT open a radiator or

    heat exchanger pressure cap while the engine is running or remains hot. Allow the generator

    to cool in order to decrease the system pressure.

    Used engine oils are known to cause cancer and reproductive toxicity. When checking or

    changing engine oil, take care not to ingest, breathe the fumes, or make bodily contact with

    used oil.

    Keep multi-class ABC fire extinguishers handy. Class A fires involve ordinary combustible

    materials such as wood and cloth; Class B fires involve combustible and flammable liquid

    fuels and gaseous fuels; and Class C fires involve live electrical equipment.

    Make sure that rags are not left on or near the engine.

    Make sure the generator is mounted in a manner that will prevent combustible materials from

    accumulating under its base.

    Remove all unnecessary grease and oil from the generator. Accumulated grease and oil can

    cause overheating and engine damage, and presents a potential fire hazard.

    Keep the generator and its surrounding area clean and free from obstructions. Remove any

    debris and keep the floor clean and dry.

    Do not work on this equipment when mentally or physically fatigued, or after consuming any

    alcohol or drug.

    Do not store any flammable liquids, such as fuel, cleaners, oil, etc., near the generator. A fire

    or explosion could result.

    Wear hearing protection when going near an operating generator.

    To prevent serious burns, avoid contact with hot metal parts such as the radiator, turbo

    charger, and exhaust system.

    Note

    General safety precautions

  • 7/31/2019 Aste-6z3qgx r0 En

    12/60

    Safety

    6 InfraStruXure Power Generation System

    Battery servicing must be performed or supervised by personnel knowledgeable of batteries

    and the required precautions. Keep unauthorized personnel away from the battery.

    When replacing the battery, use the same model number. The battery specifications are as

    follows: 12 V, 100 A, 1400 cold-cranking amps, sealed lead-acid.

    Do not dispose of a battery in a fire. It is capable of exploding.

    Do not open or mutilate a battery. Released electrolyte has been known to be harmful to the

    skin and eyes and is toxic.

    A battery presents a risk of high short-circuit current. Observe the following precautionswhen working on batteries:

    Remove watches, rings, or other metal objects.

    Use tools with insulated handles.

    Do not lay tools or metal parts on top of a battery.

    Electrolyte is a diluted sulfuric acid that is harmful to the skin and eyes. It is electrically

    conductive and corrosive. The following procedures should be observed:

    Wear full eye protection and protective clothing.

    If electrolyte contacts the skin, wash it off immediately with water.

    If electrolyte contacts the eyes, flush thoroughly and immediately with water and seek

    medical attention.

    Spilled electrolyte must be washed down with an acid neutralizing agent. Use a solution of

    500 grams (one pound) bicarbonate of soda to 4 liters (one gallon) of water. The

    bicarbonate of soda solution should be added until evidence of the reaction (foaming) has

    ceased. The resulting liquid should then be flushed with water and the area dried.

    A lead-acid battery presents a risk of fire because it generates hydrogen gas. The following

    precautions must be followed:

    DO NOT SMOKE near the battery.

    DO NOT cause flame or spark in the battery area.

    Discharge static electricity from your body before touching the battery by first touching a

    grounded metal surface.

    Note

    Battery considerations

  • 7/31/2019 Aste-6z3qgx r0 En

    13/60

    InfraStruXure Power Generation System 7

    System Data

    Electrical

    Power and communication connections

    Two sources supply power to the ATS. The typical installation has the mains connected to Source 1

    (S1) and a generator connected to Source 2 (S2). If you purchased your ATS as an InfraStruXure

    Extended Runtime Solution, your ATS was supplied with either an 80 kW or a 120 kW generator. To

    ensure a successful transition from S1 to S2, APC recommends that the mains circuit breaker rating

    match the generators circuit breaker rating as presented in the table below.

    AC Power Input to ATS from Generator

    Voltage (L-L) 3 x 400/230 V

    Output power of generator 80 kW or 120 kW

    Size of generator output circuit breaker 250 A

    Connection type 3/N/PE

    Recommended wire sizes if 30C* 50 mm2 - 240 mm2

    Recommended wire sizes if 40C* 50 mm2 - 240 mm2

    Recommended protective earthing (PE) wire size* 25 mm2 - 120 mm2

    AC Power Input to ATS from Mains

    Voltage (L-L) 3 x 400/230 V

    Size of upstream mains circuit breaker 250 A

    Connection type 3/N/PE

    Recommended wire sizes if 30C* 50 mm2 - 240 mm2

    Recommended wire sizes if 40C* 50 mm2 - 240 mm2

    Recommended protective earthing (PE) wire size* 25 mm2 - 120 mm2

    12 VDC to ATS from Generator

    Recommended wire size* Two, 1.5 mm stranded copper**

    Voltage 12 VDC

    Connection point Hard-wire to generator controller terminal block

    Communication Connection from Generator to ATS

    Recommended wire size* Belden 9830 cable or equivalent (0.2 mm; 3 twisted, shielded

    pairs; 100 ohms nominal impedance; 60 pF/ft nominal capacity)

    Connection point RS485/RS232 converter on ATS to identical converter ongenerator (requires installation)

  • 7/31/2019 Aste-6z3qgx r0 En

    14/60

    System Data

    8 InfraStruXure Power Generation System

    AC Power from ATS to Generator Heater and Battery Charger

    Recommended wire size* Two, 1.5 mm stranded copper**

    Voltage 230 VAC

    Connection style Hard-wire from T1 circuit breaker in ATS to the battery chargercontrol box in the generator

    Start Signal Connection to Generator from ATS

    Recommended wire size* Two, 1.5 mm stranded copper**

    Connection point Hard-wire to generator controller terminal block

    Emergency Stop Signal Connection to Generator from ATS

    Recommended wire size* Two, 1.5 mm stranded copper**

    Connection point Hard-wire to generator controller terminal block

    ATS Branch Distribution to Equipment***

    Circuit breaker style MCCB ABB Tmax T1 or T3 up to 225 A

    ATS Ethernet Connection

    Connection type CAT-5 network cable connected to the surge-protected ethernetport on the ATS user interface board

    ATS EPO Connection

    Recommended wire size* 2.5 mm0.2 mm**

    Connection type Voltage-free contact (NO or NC) or 24 VDC on the ATS userinterface board

    ATS User Input Contacts/Relay Outputs

    Recommended wire size* 2.5 mm0.2 mm**

    Connection type Voltage-free contact (NO or NC) on the ATS user interface board

    * Always follow your national and local codes when installing the InfraStruXure Power Generation System. The AC Power Input wire

    sizes provided in this document are recommendations only. The ATS is provided with a panel board to supply power to multiple loads.

    Since loading could increase after the products initial installation, the AC Power Input wires were selected for the maximum current

    that can be delivered by the panel board. If the ATS is purchased to supply a calculated load rated less than the panel board, and the

    load will never increase, smaller wires can be used if the requirements in your national and local codes are followed.

    **Use ferrules on the ends of stranded-copper wires to avoid creating a short circuit that could possibly damage the interface board and/or the S2 motor control circuits.

    ***Wire sizes to loads must be in accordance with the ratings of the circuit breakers selected to power the loads.

    Refer to Appendix B: Wire Sizes on page 47 for a more comprehensive listing of wire sizes

    as they relate to various installation environments.

    See also

    Refer also to EN60364-5-52, Selection and erection of electrical equipment - wiring systems.

  • 7/31/2019 Aste-6z3qgx r0 En

    15/60

    InfraStruXure Power Generation System 9

    Physical

    Generator

    80 kW 120 kW

    Height 1678 mm / 66 in 1970 mm / 77.5 in

    Length 2343 mm / 92 in 2920 mm / 115 in

    Width 1084 mm / 42.5 in 1136 mm / 44.5 in

    Length of Footprint 2343 mm / 92 in 2404 mm / 94.5 in

    Width of Footprint 918 mm / 36 in 1060 mm / 41.5 in

    Weight 1840 kg / 4057 lb 2671 kg / 5889 lb

    Operating Temperature Range 30 to 50 C / 22 to 122 F 30 to 50 C / 22 to 122 F

    Operating Relative Humidity 5 to 100% 5 to 100%

    Operating Elevation 3900 m / 12,800 ft 3900 m / 12,800 ft

    Tank Type Double-wall, steel base Double-wall, steel base

    Fuel Type Diesel Diesel

    Tank Size 300 liters / 79 gallons 435 liters / 115 gallons

    Access Clearances Working space must be in accordance with standard EN60364, and should

    not be less than 700 mm (28 in).

    1084 mm (80 kW)2343 mm (80 kW)

    1678 mm (80 kW)1970 mm (120 kW)

    2920 mm (120 kW)1136 mm (120 kW)

    The 80 kW generator isshown in this and othergraphic representationsthroughout this manual

  • 7/31/2019 Aste-6z3qgx r0 En

    16/60

    System Data

    10 InfraStruXure Power Generation System

    Special considerations for generator installations

    Installation considerations. Use the instructions in this manual as a general guide only. Follow

    the instructions of the consulting engineer regarding the placement of system components. The

    complete installation must comply with all national and local building codes, fire ordinances, andother applicable regulations. Consider these requirements prior to installation:

    Level mounting surface

    Adequate cooling air

    Adequate fresh induction air

    Discharge of generator air

    Non-combustible mounting surface

    Discharge of exhaust gases

    Electrical connections

    Accessibility for operation and servicing

    Noise levels

    Location considerations. Generator location is mainly decided by such criteria as ventilation,

    wiring, fuel, and exhaust. The generator should be located as near as possible to the main power

    service entrance. Exhaust must not be able to enter or accumulate around inhabited areas. In

    accordance with standard EN60364, provide at least 700 mm (28 in) of clearance on all sides.

  • 7/31/2019 Aste-6z3qgx r0 En

    17/60

    System Data

    InfraStruXure Power Generation System 11

    Smart Distribution Panel with ATS

    Height 1905 mm / 75.0 in

    Width 711 mm / 28.0 in

    Depth 383 mm / 15.0 in

    Weight 219 kg / 482 lb

    Operating Temperature Range 5 to 40C / 23 to 104F

    Operating Relative Humidity 5 to 95%, non-condensing

    Operating Elevation 0 to 2000 m / 0 to 6,562 ft

    Enclosure Rating IP40

    Access Clearances Working space must be in accordance with standard

    EN60364, and should not be less than 700 mm (28 in).

    1905 mm

    383 mm711 mm

  • 7/31/2019 Aste-6z3qgx r0 En

    18/60

  • 7/31/2019 Aste-6z3qgx r0 En

    19/60

    InfraStruXure Power Generation System 13

    Cabling

    Overview

    Pour the generator pad.

    Install the generator.

    Run cables from the generator to the ATS.

    Install the ATS.

    Pg0205a

  • 7/31/2019 Aste-6z3qgx r0 En

    20/60

    14 InfraStruXure Power Generation System

    Procedures

    Pour the generator pad

    Pour a concrete generator pad at the selected installation location.

    Ensure that the composition and thickness of the pad is appropriate for the conditions at the

    installation site. Check with the consulting engineer.

    Ensure that the dimensions of the pad exceed the footprint of your generator by at least 380 mm(15 in) on all sides:

    The 80 kW generator has a footprint of 2343 mm x 918 mm (92 in x 36 in). Therefore, its pad

    should be at least 3103 mm x 1678 mm (122 in x 66 in).

    The 120 kW generator has a footprint of 2404 mm x 1060 mm (94.5 in x 41.5 in). Therefore,

    its generator pad should be at least 3164 mm x 1820 mm (124.5 in x 71.5 in).

    Install the generator

    Carefully set the generator down onto the concrete generator pad using a properly rated hoist orcrane. The generator should be centrally positioned on the pad.

    Note

    These instructions are recommendations only. Follow all applicable national and local codes.

    Heavy

    At least three people are required to place the generator: one to operate the hoist or

    crane, and two or more to appropriately position the generator on its pad.

    After appropriately positioning the generator on its pad,

    verify that all four mounting pads on the bottom of the fuel

    tank make full contact with the generator pad. Level shims

    are included with the generators literature pack, and can be

    used to fill any gap between the mounting pads and the

    generator pad. Insert the maximum height stack of shims

    that will slide into the gap.

    Secure the generator to the generator pad using the

    appropriate mounting hardware. Use type J or L bolt

    anchoring (not supplied) as shown in the illustration.

    pg0004a

  • 7/31/2019 Aste-6z3qgx r0 En

    21/60

    Cabling

    InfraStruXure Power Generation System 15

    Run cables from the generator to the ATS

    1. Refer to the below left illustration for the location of the cable entry.

    2. Run cables containing the following wires through the perforations in the cable entry to the ATS

    using floor troughs or cable ladders as necessary. Refer to the below right illustration.

    Input power from the generator to the ATS

    230 VAC from the ATS to the generator for the heater and battery charger

    12 VDC from the generator to the ATS

    Start contact from the generator to the ATS

    E-Stop contact from the generator to the ATS

    Communication from the ATS to the generator

    See the table beginning onpage 7 for wiring specifications, and see Wiring on page 23

    for procedures on connecting to the ATS.

    Frfront

    Front

    Rear

    Cable

    Front

    Rear

    entry

  • 7/31/2019 Aste-6z3qgx r0 En

    22/60

    Cabling

    16 InfraStruXure Power Generation System

    Install the ATS

    Remove the ATS panel board assembly from the enclosure.

    Note

    APC recommends removing the ATS panel board assembly from the enclosure prior to

    installation. Removal of this assembly makes it easier to mount the ATS to the wall. If youare not removing the panel board assembly, continue with the procedure on page 19.

    1. Open the front door of the ATS.

    2. Remove the screw on the left that

    secures the bottom access panel.

    3. Open the dead front by first loosening

    its turn-screw on the right, and then

    pulling the top and bottom latches

    toward each other.

    4. Remove the screw on the right that

    secures the bottom access panel.

    5. Remove the bottom access panel from the enclosure.

    Remove

    Front Door Open, Dead Front Closed

    Remove

    Front Door Open, Dead Front Open

    First, pull up

    Second, pull out

  • 7/31/2019 Aste-6z3qgx r0 En

    23/60

    Cabling

    InfraStruXure Power Generation System 17

    6. Disconnect the panel board assembly wires that are connected to the following components

    inside the ATS enclosure:

    User interface circuit board

    Surge-protected ethernet port

    Door relay

    Auto switch and LEDs

    Display interface

    Neutral wire (if applicable)

    See also

    Refer to theATS Operation Manual for the exact location of these components.

    Note

    Each wire has a yellow label attached that specified its point of connection.

    7. Use a 13-mm wrench to remove the

    M8 nuts located at the top and bottom

    (4 total) of the panel board assembly.Remove

    Remove

    TOP

    BOTTOM

    Use 13-mm Wrench to Remove

  • 7/31/2019 Aste-6z3qgx r0 En

    24/60

    Cabling

    18 InfraStruXure Power Generation System

    8. Using the handle at the top of the

    panel board assembly, slowly pull the

    entire assembly toward you.

    Note

    At least two people should be involved in removing the panel board!

    9. Walk the panel board assembly out

    of the enclosure one wheel at a time,

    and then roll the assembly away from

    the enclosure.

    10. Carefully lay the panel board assembly on its back at a location apart from the enclosure.

    Note

    Do not re-install the panel board assembly until after you have mounted the ATS

    enclosure and pulled cables to it.

  • 7/31/2019 Aste-6z3qgx r0 En

    25/60

    Cabling

    InfraStruXure Power Generation System 19

    Mount the ATS to a wall.

    Prior to wall-mounting, covers must be

    removed from the horizontal slots at the

    rear of the enclosure. Use a 10-mmwrench to remove the M6 nuts securing

    the covers in place.

    Mounting to studs:

    1. Locate wall studs and draw vertical

    chalk lines to show where the studs

    are located.

    2. Place the enclosure against the

    wall.

    3. Find the chalk lines/studs through

    the horizontal slots at the rear of

    the enclosure.

    4. Drive the anchoring screws

    (supplied) into the wall studs in

    four places.

    5. Re-install covers to the horizontal

    mounting slots using the

    previously removed M6 nuts.

    Mounting to concrete:

    1. Place the enclosure against the

    wall.

    2. Drill four holes (with a 4.5-mm diameter masonry drill bit) through the horizontal slots at the

    rear of the enclosure.

    3. Drive the anchoring screws (supplied) into the drilled holes.

    4. Re-install covers to the horizontal mounting slots using the previously removed M6 nuts.

    Note

    There is no need to mount

    plywood or Unistrut metal

    framing to the wall.

    718 mm/28.25 in60 mm/2.25 in

    1748mm/68.7

    5in

    1734mm/68.2

    5in

    399mm/15.7

    5in

    385mm/15,2

    5in

    594 mm/23.50 in

    1895mm/74.5

    0in

    Mounting Hardware

    Four, 9.5-mm (3/8-in) anchoring screws76-mm/3.00 in long

    59 mm/2.25 in

  • 7/31/2019 Aste-6z3qgx r0 En

    26/60

    Cabling

    20 InfraStruXure Power Generation System

    Pull the wires into the ATS. After you mount the ATS to the wall, pull the wires that were cable-

    connected from the generator (see the list of wires on page 15) into the ATS enclosure. You can pull

    these wires in through the roof, the floor, or the sides of the ATS.

    When pulling wires through the roof or the floor of the ATS, use knockouts to the left or right side ofthe top or bottom panel rather than using knockouts in the middle. This method allows for easier

    wiring to components on the panel board.

    Note

    Properly seal any knockouts that you create on the top or bottom panel of the ATS

    according to local codes.

    Pg0007c

  • 7/31/2019 Aste-6z3qgx r0 En

    27/60

    Cabling

    InfraStruXure Power Generation System 21

    Re-install the ATS panel board assembly in the enclosure.

    Note

    If you did not remove the panel board assembly before mounting the ATS enclosure to

    the wall, proceed to Strain relief the cables inside the ATS on the following page.

    1. Roll the panel board assembly back to

    the ATS and walk it into the

    enclosure one wheel at a time.

    2. Align the mounting holes at the top

    and bottom of the assembly with the

    proper studs in the enclosure.

    3. Re-attach the four previouslyremoved M8 nuts to the studs. See

    step 7 onpage 17.

    Note: You can re-install the bottom

    access panel now, or you can reinstall

    it after connecting wires to the panel

    board. To re-install, perform the

    reverse of the panel board assembly

    removal procedures onpage 16.

    Install

    Install

    TOP

    BOTTOM

    Use 13-mm wrench to install

    http://-/?-http://-/?-
  • 7/31/2019 Aste-6z3qgx r0 En

    28/60

    Cabling

    22 InfraStruXure Power Generation System

    Strain relief the wires inside the ATS. Use cable ties to strain relief the wires you have pulled

    into the ATS before making connections.

    For top cable entry:

    Secure cables to the strain relief bracket at the top of the enclosure. The following illustration shows

    the location of the strain relief bracket.

    For bottom cable entry:

    Secure cables to the bottom rung of the panel board assembly. The following illustration shows the

    location of the bottom rung of the panel board assembly.

    4. Re-connect the panel board assembly wires that were previously disconnected from the

    following ATS components:

    User interface circuit board

    Surge-protected ethernet port

    Door relay

    Auto switch and LEDs

    Display interface

    Neutral wire (if applicable)

    Note

    Refer to the yellow label on each wire for its point of connection.

    panel board assemblyBottom rung of

  • 7/31/2019 Aste-6z3qgx r0 En

    29/60

    InfraStruXure Power Generation System 23

    Wiring

    Overview

    Connect generator input power to the ATS.

    Connect mains input to the ATS.

    Connect the 12 VDC, Start, and E-Stop contacts.

    Connect the communication cable from the ATS to the generator.

    Run AC power input from the ATS to the generator for the heater and battery charger.

    Connect the branch distribution equipment to the ATS.

    Connect an EPO switch to the user interface board and test the switch.

    Connect contacts to the user interface board.

    Connect the ATS to the network at the surge-protected ethernet port.

    Pg0134b

  • 7/31/2019 Aste-6z3qgx r0 En

    30/60

    24 InfraStruXure Power Generation System

    Procedures

    Connect power from the generator to the ATS

    Specifications and tools. The generator output breaker is equipped with saddle lugs, and the ATS

    input switches are equipped with box lugs. See Power and communication connections on page 7

    for generator input wiring specifications. Torque generator input wires to 28 nm (250 in lb) using

    an 8-mm Allen wrench.

    Routing wires. Route generator input wires into the ATS using the knockouts provided on the ATS

    enclosure. Use a knockout punch to create the size of hole that you need. You can bring these wiresinto the ATS through the roof or the floor. See the illustration on the next page for suggested wiring

    paths for both options. If possible, use the knockouts on either side of the roof or floor rather than

    knockouts in the middle of the roof or floor (seepage 20).

    Note

    If you are running wires through the roof of the ATS to connect to the Source 2 input

    switch, these wires will need to be at least 2.9 m (9.5 ft) longer than a similar group of

    wires run through the floor.

    Source2 input switch

    PE bar

    (80 kW Generator and 250 A ATS400 V input shown)

    PE wire from generator

    from generatoroutput breaker

    Generator output breaker

    N, L1, L2, L3

    PE wire

    N, L1, L2, L3

  • 7/31/2019 Aste-6z3qgx r0 En

    31/60

    Wiring

    InfraStruXure Power Generation System 25

    Making connections.

    1. Connect the neutral (N) and phase (L1, L2, L3) wires from the output breaker in the generator to

    the Source 2 input switch in the ATS. Use phase-sequence (A-B-C) clockwise rotation.

    2. Connect the protective earth (PE) wire from the generator to the PE bar in the ATS.

    pg0054c

    Source2 input switch

    Generator output breaker

    Optional wiring through the roof

    Preferred wiring through the floor

    (80 kW Generator and

    PE bar

    250 A ATS400 V input shown)

  • 7/31/2019 Aste-6z3qgx r0 En

    32/60

    Wiring

    26 InfraStruXure Power Generation System

    Connect mains input to the ATS

    Specifications and tools. The ATS input switches are equipped with box lugs. See Power and

    communication connections on page 7 for mains input wiring specifications. Torque mains input

    wires to 28 nm (250 in lb) using an 8-mm Allen wrench.

    Routing wires. Route mains input wires into the ATS using the knockouts provided on the ATS

    enclosure. Use a knockout punch to create the size of hole that you need. You can bring these wires

    into the ATS through the roof or the floor. See the illustration on the next page for suggested wiring

    paths for both options. If possible, use the knockouts on either side of the roof or floor rather than

    knockouts in the middle of the roof or floor (seepage 20).

    Note

    If you are running wires through the floor of the ATS to connect to the Source 1 input

    switch, the neutral and phase wires will need to be at least 2.0 m (6.6 ft) longer than the

    protective earth wire.

    If you are running wires through the roof of the ATS to connect to the Source 1 input

    switch, the protective earth wire will need to be at least 2.0 m (6.6 ft) longer than the

    neutral and phase wires.

    ATS panel board

    Source1 input switch

    (250 A ATS400 V input shown)

    N, L1, L2, L3,

    and PE

    PE Bar

  • 7/31/2019 Aste-6z3qgx r0 En

    33/60

    Wiring

    InfraStruXure Power Generation System 27

    Making connections.

    1. Connect the neutral (N) and phase (L1, L2, L3) wires from the mains power supply to the

    Source 1 input switch in the ATS. Use phase-sequence (A-B-C) clockwise rotation.

    2. Connect the protective earth (PE) wire from mains to PE bar in the ATS.

    pg0055c

    Source 1 input switch

    Input from mainsPreferred wiring

    Optional wiring through the floor

    (250 A ATS400 V input shown)

    through the roof

    PE bar

  • 7/31/2019 Aste-6z3qgx r0 En

    34/60

    Wiring

    28 InfraStruXure Power Generation System

    Connect the DC power input, start, and E-Stop contacts

    Specifications and tools. Use a 2.5-mm standard screwdriver to make connections to the terminal

    block. See Power and communication connections on page 7 for wiring specifications. Apply

    ferrules to the ends of each wire to avoid creating a short circuit.

    Start contact TB1, terminal 1E-Stop contact TB1, terminal 2

    DC contact, TB1,terminal 17

    Connect PE wires at

    TB1, terminal 20, 21, and 22

    Generator controller

    Connect start contact, E-Stop

    contact, and 12 VDC to

    J51, J52, and J53

    ATS interface

    Note: It does not matter

    circuit board

    whether you connectthe contact or PE wireto J51, J52, or J53.

  • 7/31/2019 Aste-6z3qgx r0 En

    35/60

    Wiring

    InfraStruXure Power Generation System 29

    Making connections. Make connections between the generator controller terminal block and the

    ATS interface board according to the table and diagram below:

    Generator Terminal Block ATS Interface Board

    DC Input Contact Terminal 17, TB1connects to

    J51 (+)

    PE Terminal 20, TB1 J51 ()

    Start Contact Terminal 1, TB1connects to J52

    PE Terminal 22, TB1

    E-Stop Contact Terminal 2, TB1connects to J53

    PE Terminal 21, TB1

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    TB2TB1

    1 2 3 4 5 6

    pg0056a

    Generator controller terminal blocksGenerator interfaceon ATS interface board

  • 7/31/2019 Aste-6z3qgx r0 En

    36/60

    Wiring

    30 InfraStruXure Power Generation System

    Connect the communication cable from the ATS to the generator

    Specifications and tools. Use a 2.5-mm standard screwdriver to make connections to the terminalblock and the converter. See Power and communication connections on page 7 for wiring

    specifications. Apply ferrules to the ends of each wire to avoid creating a short circuit.

    Install converter DB9 connection to converter

    Generator

    Power connection

    ATS panel board

    ATS monitoring unit

    for converter

    controller

  • 7/31/2019 Aste-6z3qgx r0 En

    37/60

    Wiring

    InfraStruXure Power Generation System 31

    Installing the converter in the generator.

    1. Attach the converter mounting rail

    (supplied) to the inside door of the

    generator controller using the

    screws included with the converter

    kit and a #2 Philips screwdriver.

    2. Snap the converter and the

    converter brackets onto the rail.

    3. Secure the converter onto the rail by

    tightening the converter brackets

    using a 2.5-mm standard

    screwdriver.

  • 7/31/2019 Aste-6z3qgx r0 En

    38/60

    Wiring

    32 InfraStruXure Power Generation System

    Making Connections.

    1. Connect the generator communication converter to the generator according to the table below and the

    diagram at the bottom. Apply ferrules to the ends of each wire to avoid creating a short circuit.

    2. Make connections between the generator and ATS according to the table below and the diagram at the

    bottom. Apply ferrules to the ends of each wire to avoid creating a short circuit.

    GeneratorConverter

    Connector Connection Point in GeneratorController

    [K] Tx

    DB9 cable connects to DB9 connector above terminal block [M] Rx

    [PE] PE

    [6] V+ Cable with Minifit connects to B+; Terminal 17 or 18 on TB1

    [5] V Cable with Minifit connects to PE; Terminal 20, 21, or 22 on TB1

    Cut the Minifit connector off of the cable, strip the wire ends 6.35 mm, and connect to the appropriateterminals on TB1.

    ATS Converter Generator Converter

    Pair 1 [A] Tx+ connects to [B] Rx+

    [D] Tx connects to [E] Rx

    Pair 2 [E] Rx connects to [D] Tx

    [B] Rx+ connects to [A] Tx+

    Pair 3 [C] PE connects to [C] PE

    Shield/bare [F] Shield Ground No connection

    text text

    DB 9FDB9F

    RS-485 Converter

    Tx

    Tx+

    Rx

    Rx+

    Rx

    RS-485 Converter

    Rx

    Tx

    ATS Generator

    2

    3

    5

    2

    3

    5

    Tx

    PE

    +24 VDC

    PE (TB1, pin 20, 21 or 22)

    B+ (TB1, pin 17 or 18)

    K

    M

    C

    B

    E

    A

    D

    PE

    5

    K

    M

    PE

    C

    D

    A

    E

    B

    Mini-fit (2-pin)

    ConsolePort

    ATSMonitoringUn

    it GeneratorController

    Belden 9830 Cable

    V6

    1 4 2 3

    F

    1 4 2 3

    F

    Tx

    Tx+

    Rx

    Rx+

    V+6

    V5

    Shield Shield

    V+

    Pg0074c

  • 7/31/2019 Aste-6z3qgx r0 En

    39/60

    Wiring

    InfraStruXure Power Generation System 33

    Run AC power from the ATS to the generator for the heater and battery charger

    ATS with 400 V input.

    Specifications and tools. Use a 2.5-mm standard or #1 Phillips screwdriver to make connections.

    See Power and communication connections on page 7 for wiring specifications. Apply ferrules to

    the ends of each wire to avoid creating a short circuit.

    Procedure. Run three wires (protective earth, neutral, and line) from the ATS to the terminals in the

    battery charger box in the generator:

    Run the protective earth wire from the PE bar in the ATS to the terminals in the battery chargerbox in the generator.

    Run the neutral wire from the neutral bar in the ATS to the terminals in the battery charger box

    in the generator.

    Run the line wire from the single-pole breaker in the ATS to the terminals in the battery charger

    box in the generator.

    Run the PE wirefrom the PE barto the generator

    Run the line,neutral, andPE wiresfrom the ATS tothe battery chargerbox in the generator

    Single-pole breaker

    Connect the line wire tothe single-pole breaker

    Run the neutral wirefrom the neutral bar tothe generator

  • 7/31/2019 Aste-6z3qgx r0 En

    40/60

    Wiring

    34 InfraStruXure Power Generation System

    Connect branch distribution equipment to the ATS

    Specifications and tools. Connect data center equipment to the ATS output distribution panel

    breakers according to your national and local codes. See Appendix A: Adding Circuit Breakers on

    page 41 for panel breaker specifications and installation instructions. Apply ferrules to the ends of

    each wire to avoid creating a short circuit. The following table provides the wire sizes and torquespecifications that should be used when connecting to the panel breakers.

    Installation. Install wires to the ATS using the knockouts provided on the ATS enclosure. Use a

    knockout punch to create the size of hole that you need. You can run wires to the ATS through the

    knockouts on the roof, the floor, or the sides of the enclosure. Refer to theATS OperationManual for

    instructions on installing circuit breakers on the ATS panel board,

    Breaker Rating Wire Size Torque

    T1 1.5 mm6 mm 2.26 n m (20 inlb)

    10 mm 4.52 n m (40 inlb)

    10 mm50 mm 5.08 n m (45 inlb)

    T3 50 mm2 mm 5.65 n m (50 inlb)

    152 mm21 mm 22.58 n m (200 i n lb)

    ElectricalHazard

    Hazardous voltages from the branch circuit must be isolated from the 24 VAC, the

    24 VDC, and all contact closure terminals.

    PE bar

    Neutral bar

    L1, L2, and L3 fromdata center equipment

  • 7/31/2019 Aste-6z3qgx r0 En

    41/60

    Wiring

    InfraStruXure Power Generation System 35

    Connect an EPO switch to the user interface board and test the switch

    Specifications and tools. Connect an EPO switch to the ATS according to your national and local

    codes. See Power and communication connections on page 7 for wiring specifications. Apply

    ferrules to the ends of each wire to avoid creating a short circuit. Use a 2.5-mm standard screwdriver

    to make these connections to the user interface board.

    EPO switch installation instructions begin on the next page.

    Note

    If you are not connecting an EPO switch to the ATS, ensure that the Arm/Test rocker

    switch on the ATS monitoring unit is in the Test position.

    Note

    APC offers an InfraStruXure EPO System (EPW9). Contact your sales representative,

    or go to the APC Web site for more information (www.apc.com).

    User connection plate

    User interface board

    Connect the EPO switch here

    (the user connection plate has been turned upside down for the sake of this illustration)

  • 7/31/2019 Aste-6z3qgx r0 En

    42/60

    Wiring

    36 InfraStruXure Power Generation System

    Installing the EPO switch to the user interface board.

    1. Connect the switch to the EPO connection terminals on the user interface board, which is

    located on the bottom side of the ATS user connection plate. Make the proper connections to the

    proper terminals based on your signal type:

    Contact ClosureNormally Open

    Contact ClosureNormally Closed

    24 VAC/VDCNormally Open

    2. Verify that the EPO DIP switches on the ATS monitoring unit are configured properly for the

    signal type you are using. The labels above the switches and the figure below show the correct

    settings for both the Normally Open (NO) and Normally Closed (NC) configurations.

    External set ofNormally OpenVoltage-free Contacts

    External set ofNormally ClosedVoltage-free Contacts

    24 V AC or DC Power Supply

    External set ofNormally Open Voltage-free Contacts

    Pdx0205b

    NormallyOpen

    or24VAC/DC

    Location of switcheson ATS monitoring unit

  • 7/31/2019 Aste-6z3qgx r0 En

    43/60

    Wiring

    InfraStruXure Power Generation System 37

    Test the EPO switch.

    1. Test the EPO switch to ensure that it is wired and working correctly:

    a. Place the Arm/Test rocker switch on the ATS monitoring unit in the Test position. The EPO

    state LEDs should be off and the ATS display interface should show the following alarm (inaddition to any other active alarms):

    b. Engage the EPO switch. (If your switch is momentary, engage it with one person watching

    the EPO state LEDs and another at the EPO switch.)

    c. Observe the EPO LEDs. If the switch is wired and working properly, both of the EPO state

    LEDs should turn red when the switch is engaged.

    d. If the test was successful, place the Arm/Test rocker switch back to the Arm position. The

    ATS display interface will clear the EPO test mode alarm. If the test was not successful, see

    the troubleshooting chart:

    e. Repeat this test for each EPO switch installed.

    2. After testing is completed, ensure that the Arm/Test rocker switch is in the Arm position on the

    ATS monitoring unit.

    Problem Action

    Neither state LED was lit red

    when the EPO switch was

    engaged

    Check the wiring to your EPO switch.

    Check to make sure the EPO DIP switch

    configuration is correct for your switch

    (NO or NC). See step 2 on the previous page for

    proper configuration instructions.

    Only one of the state LEDs was lit

    red when the EPO switch was

    engaged

    Check to make sure the EPO DIP switch

    configuration is correct for your switch

    (NO or NC) and re-test. See step 2 on the

    previous page for proper configuration

    instructions.

    If the switch is configured correctly and both

    LEDs have not turned red after re-testing,

    contact APC customer support (see the backcover of this manual).

    EPO Ready To TestActive Alarm xxofxx

  • 7/31/2019 Aste-6z3qgx r0 En

    44/60

    Wiring

    38 InfraStruXure Power Generation System

    Connect contacts to the user interface board

    Specifications and tools. See Power and communication connections on page 7 for wiring

    specifications. Apply ferrules to the ends of each wire to avoid creating a short circuit. Use a 2.5-mm

    standard screwdriver to make connections to the user interface board.

    Connecting contacts.

    1. Choose one or more contact numbers on the user interface board for connecting contacts. (The

    user interface board is connected to the User/EPO port on the ATS monitoring unit.)

    2. From the ATS display interface:

    a. Press the ESC orENTERkey to go to the top-level menu screen.

    b. Select Config on the top-level menu screen and press the ENTERkey.

    c. Select Contacts & Relays on the Config menu screen and press the ENTERkey.

    See also

    Refer to theATS OperationManual for more information about user contacts and the

    types of equipment that can be connected.

    User connection plate

    User interface board

    Connect user input contacts

    (the user connection plate has been turned upsidedownfor the sake of this illustration)

    and relay outputs here

    Load-Meter

    ATS/Voltage

    Generator

    Testing

    Stats

    Alarms

    Config

    Help

    System/NetworkContacts & RelaysSub-Feed Config.Electrical Config.

  • 7/31/2019 Aste-6z3qgx r0 En

    45/60

    Wiring

    InfraStruXure Power Generation System 39

    d. Select the type of contact you are connecting: Contact Inputs orRelay Outputs.

    e. Press the Up or Down arrow key to select the appropriate

    contact number and press the ENTERkey.

    f. Press the Down arrow key to enter a unique Name for the

    contact and to configure the Normal state of the contact

    (Open orClosed). The default Normal state is Open.

    Press the ENTERkey to select the item you wish to

    configure.

    g. Connect contact wires (300 V-rated cabling required) to the terminal block on the user

    interface board. Apply ferrules to the ends of each wire to avoid creating a short circuit. Use

    a 2.5-mm standard screwdriver to make connections to the user interface board

    h. Run the wires from the terminal block out the roof of the ATS to your contacts location.

    ContactInputsRelay OutputsOutputRelay Map

    Note

    You will be prompted for your password to configure these items.

    DANGER

    Ensure that the wires are properly retained and kept away from high-voltage

    wires and circuit breakers.

    Contact In 02of04Name User Contact 4

    Normal: OpenStatus: Open

  • 7/31/2019 Aste-6z3qgx r0 En

    46/60

    Wiring

    40 InfraStruXure Power Generation System

    Connect the ATS to the network at the surge-protected ethernet port

    Management options. There are two management options: You can manage the system, along

    with the rest of your InfraStruXure equipment, through the InfraStruXure Manager (APC LAN); or

    you can manage your system through APCs network management interfaces (User LAN).

    Managing through the InfraStruXure Manager. The InfraStruXure Manager is a rack-mount

    management device that coordinates the management functions of APC InfraStruXure-Certified

    devices installed in your data center. It provides a single interface to view and configure all APC

    InfraStruXure-Certified devices. See Configuring the InfraStruXure Manager in theATS Operation

    Manual for configuration instructions.

    Managing through the network management interfaces. The control console and Web

    interfaces provide menus with options that allow you to manage the system. See Configuring the

    ATS Network Management Interface in theATS OperationManual for configuration instructions.

    The SNMP interface allows you to use an SNMP browser with the PowerNet Management

    Information Base (MIB) to manage the system. See Configuring the ATS Network Management

    Interface in theATS Operation Manual for configuration instructions.

    See also

    For more information about the InfraStruXure Manager, refer to theInstallation and

    ConfigurationManual included with the InfraStruXure Manager.

    See also

    For more information about the internal user interfaces, refer to the InfraStruXurePower Generation Systems on-lineNetwork Management Users Guide.

    See also

    To use the PowerNet MIB with an SNMP browser, refer to the PowerNet SNMP

    Management Information Base (MIB) Reference Guide provided on the InfraStruXure

    Power Generation System Utility CD.

    Surge-protected ethernet port

    (the user connection platehas been turned upsidedown for the sake of this illustration)

    User connection plate

    Use a CAT-5 cable to connect.

  • 7/31/2019 Aste-6z3qgx r0 En

    47/60

    InfraStruXure Power Generation System 41

    Appendix A: Adding Circuit Breakers

    How to Add Sub-Feed Output Distribution

    Circuit Breakers to the ATS

    Output distribution circuit breakers available from APC

    Part Number Description Height on Panel

    PG1P15AT1B 15 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in

    PG1P16AT1B 16 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in

    PG1P20AT1B 20 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in

    PG1P25AT1B 25 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in

    PG1P30AT1B 30 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in

    PG1P32AT1B 32 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in

    PG3P15AT1B 15 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P20AT1B 20 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P25AT1B 25 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P30AT1B 30 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P40AT1B 40 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P50AT1B 50 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P60AT1B 60 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P63AT1B 63 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P70AT1B 70 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P80AT1B 80 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P90AT1B 90 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P100AT1B 100 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in

    PG3P125AT3B 125 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in

    PG3P150AT3B 150 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in

    PG3P160AT3B 160 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in

    PG3P175AT3B 175 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in

    PG3P200AT3B 200 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in

    PG3P225AT3B 225 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in

    PG3P300AT5B 300 A, three-pole breaker, T5 frame 139.5 mm / 5.50 in

    PG3P400AT5B 400 A, three-pole breaker, T5 frame 139.5 mm / 5.50 in

  • 7/31/2019 Aste-6z3qgx r0 En

    48/60

    Appendix A: Adding Circuit Breakers

    42 InfraStruXure Power Generation System

    Determine the configuration of the panel

    Before you begin installing circuit breakers on the ATS distribution panel, be sure that you have

    enough space on the panel for the breakers that you want to install. Use the information in the

    diagrams below to determine the final configuration of your panel.

    Amount of space requiredfor each type of circuit breaker

    T1 single-pole breaker assembly

    T1 three-pole breaker assembly

    T3 three-pole breaker assembly

    Amount of space available

    on the 250A ATSdistribution panel bus

  • 7/31/2019 Aste-6z3qgx r0 En

    49/60

    Appendix A: Adding Circuit Breakers

    InfraStruXure Power Generation System 43

    Preparing the breakers for installation

    Before installing the breakers on the ATS panel board, follow the steps provided in this section for the

    breaker(s) that you are installing. The parts that are identified in the illustrations below are included

    with your circuit breaker kit.

    Slide the bracket adapter onto the output side of the T1 single-pole breaker. The bracket adapter is

    used to attach the breaker to the breaker bracket.

    The T1 three-pole breakers are ready for installation on the panel. No additional preparation is

    needed.\

    Both the input and output sides of the T3 three-pole breaker require preparation before the breaker is

    installed on the panel.

    On the input side, follow these steps for each of the three pole positions:

    1. Place an M8 square nut into a square nut retainer, and then insert the square nut retainer into the

    pole position.

    2. Slide an M8 washer onto an M8 bolt, and then loosely attach the bolt to the M8 square nut.

    On the output side, follow these steps for each of the three pole positions:

    3. Slide a saddle lug into the pole position. You may need to loosen the bolt in the lug.

    4. Insert a saddle lug retainer into the pole position.

    Input

    Output

    T1 single-pole breaker

    Bracket Adapter

    T1 three-pole breaker

    Input

    Output

    T3 three-pole breaker

    InputOutput

    Saddle Lug

    Saddle LugRetainer

    Square

    M8 Bolt

    M8 WasherM8

    Nut RetainerSquareNut

  • 7/31/2019 Aste-6z3qgx r0 En

    50/60

    Appendix A: Adding Circuit Breakers

    44 InfraStruXure Power Generation System

    Parts and tools needed for installation procedures

    T1 single-pole breaker assembly

    T1 single-pole module

    T1 single-pole breakers

    M375 screws, washers and retainers

    breaker brackets

    M612 Torx screws

    M4 15 screws and washers

    T1 three-pole breaker assembly

    T1 three-pole module

    T1 three-pole breakers

    M470 screws and washers

    breaker brackets

    M612 Torx screws

    M470 screws and washers

    T3 three-pole breaker assembly

    T3 three-pole module

    T1 three-pole breakers

    M4 70 screws and washers

    breaker brackets

    M612 Torx screws

    M4 70 screws and washers

    Tools required

    Phillips screwdriver

    T25 Torx driver

    Allen wrench

    All parts needed for installation

    procedures are included with the

    circuit breaker kits.

  • 7/31/2019 Aste-6z3qgx r0 En

    51/60

    Appendix A: Adding Circuit Breakers

    InfraStruXure Power Generation System 45

    Installing circuit breakers on the ATS panel board

    This section shows how to install a T1 three-pole breaker assembly on a 250A ATS panel board. The

    steps are identical for installing T1 single-pole and T3 three-pole breakers.

    1. Attach the module to the ATS panel board (), and secure it by turning the module locks using

    an Allen wrench ().

    2. Place the circuit breakers onto the modules busbars () and lock in place with an M470

    screw (). Use a Phillips screwdriver to tighten.

    3. Attach the breaker brackets to the slots in the distribution bus frame () and secure with an

    M612 Torx screw (). Use a T25 Torx driver to tighten. Attach the breaker to the breaker

    bracket with an M4 70 screw (). Use a Phillips screwdriver to tighten.

  • 7/31/2019 Aste-6z3qgx r0 En

    52/60

    Appendix A: Adding Circuit Breakers

    46 InfraStruXure Power Generation System

    4. Install dividers in the circuit breakers by sliding them, one at a time, into the notches on the side

    of the breaker.

    See also

    For more information on the Divider Kits for the ATS circuit

    breakers, refer to theInstallation Instructions (990-2245) provided

    with the Divider Kit.

  • 7/31/2019 Aste-6z3qgx r0 En

    53/60

    InfraStruXure Power Generation System 47

    Appendix B: Wire Sizes

    250 A ATS and 80 kW Generator

    Copper building wire sizes.

    Aluminum building wire sizes.

    250 A ATS and 120 kW Generator

    Copper building wire sizes.

    Note

    The following wire sizes are recommendations only, and correspond to the maximumampacity for operation of the ATS and the Generator. Smaller wire sizes can be used if

    your system operates on a circuit with a lower ampacity.

    InstallationMethod

    PVC Insulation30C Ambient

    XLPE or EPR Insulation30C Ambient

    PVC Insulation40C Ambient

    XLPE or EPR Insulation30C Ambient

    B1 & N = 70 mm2PE = 35 mm2

    & N = 50 mm2PE = 25 mm2

    & N = 95 mm2PE = 50 mm2

    & N = 70 mm2PE = 35 mm2

    B2 & N = 95 mm2PE = 50 mm2

    & N = 70 mm2PE = 35 mm2

    & N = 120 mm2PE = 70 mm2

    & N = 70 mm2PE = 35 mm2

    C & N = 70 mm2PE = 35 mm2

    & N = 50 mm2PE = 25 mm2

    & N = 70 mm2PE = 35 mm2

    & N = 50 mm2PE = 25 mm2

    InstallationMethod

    PVC Insulation30C Ambient

    XLPE or EPR Insulation30C Ambient

    PVC Insulation40C Ambient

    XLPE or EPR Insulation30C Ambient

    B1 & N = 95 mm2PE = 50 mm2

    & N = 70 mm2PE = 35 mm2

    & N = 120 mm2PE = 70 mm2

    & N = 70 mm2PE = 35 mm2

    B2 & N = 120 mm2PE = 70 mm2

    & N = 95 mm2PE = 50 mm2

    & N = 185 mm2PE = 95 mm2

    & N = 95 mm2PE = 50 mm2

    C & N = 95 mm2PE = 50 mm2

    & N = 95 mm2PE = 50 mm2

    & N = 120 mm2PE = 70 mm2

    & N = 95 mm2PE = 50 mm2

    Installation

    Method

    PVC Insulation

    30C Ambient

    XLPE or EPR Insulation

    30C Ambient

    PVC Insulation

    40C Ambient

    XLPE or EPR Insulation

    30C Ambient

    B1 & N = 150 mm2PE = 95 mm2

    & N = 95 mm2PE = 50 mm2

    & N = 185 mm2PE = 95 mm2

    & N = 120 mm2PE = 70 mm2

    B2 & N = 185 mm2PE = 95 mm2

    & N = 120 mm2PE = 70 mm2

    & N = 240 mm2PE = 120 mm2

    & N = 150 mm2PE = 95 mm2

    C & N = 120 mm2PE = 70 mm2

    & N = 95 mm2PE = 50 mm2

    & N = 150 mm2PE = 95 mm2

    & N = 95 mm2PE = 50 mm2

  • 7/31/2019 Aste-6z3qgx r0 En

    54/60

    Appendix B: Wire Sizes

    48 InfraStruXure Power Generation System

    Aluminum building wire sizes.

    Notes:

    1. Explanation of installation methods:

    B1 = Insulated wires routed within a multi-jacketed cable conductor. The multi-jacketed cable conductor is mounted to a wall.

    B2 = Multi-wire cables routed within a multi-jacketed cable conductor. The multi-jacketed cable conductor is mounted to a wall.

    C = Multi-wire cables mounted to a wall.

    2. = Phase conductor; N = Neutral conductor; PE = Protective Earth conductor

    3. Number in parenthesis = Number of paralleled conductors per terminal

    4. Conductive cross-sectional areas are in accordance with IEC 60364-5-52

    InstallationMethod

    PVC Insulation30C Ambient

    XLPE or EPR Insulation30C Ambient

    PVC Insulation40C Ambient

    XLPE or EPR Insulation30C Ambient

    B1 & N = 240 mm2PE = 120 mm2

    & N = 120 mm2PE = 70 mm2

    & N = (2) 95 mm2PE = (2) 50 mm2

    & N = 185 mm2PE = 95 mm2

    B2 & N = 70 mm2PE = 35 mm2

    & N = 185 mm2PE = 95 mm2

    & N = (2) 120 mm2PE = (2) 70 mm2

    & N = 240 mm2PE = 120 mm2

    C & N = 185 mm2PE = 95 mm2

    & N = 150 mm2PE = 95 mm2

    & N = 240 mm2PE = 120 mm2

    & N = 150 mm2PE = 95 mm2

  • 7/31/2019 Aste-6z3qgx r0 En

    55/60

    InfraStruXure Power Generation System 49

    Installation Checklist

    The items below must be initialed, and the form must be signed and sent to APC, before a technician

    will be dispatched to perform start-up. Initial only the items completed. If an item is initialed ascompleted and it is not complete, there could be additional billing.

    Return completed form to:

    American Power Conversion

    Project Coordination

    Fax: 401-788-2616

    Item Initials

    Fuel tank full of diesel fuel (seepage 9)

    Generator pad poured to specifications (seepage 14)

    Generator secured to pad (seepage 14)

    ATS mounted securely to wall (seepage 16)

    Input power from the generator connected to the ATS (seepage 24)

    Mains input connected to the ATS (seepage 26)

    E-stop contact from the generator connected to the ATS (seepage 28)

    DC power input contact from the generator connected to the ATS (seepage 28)

    Start contact from the generator connected to the ATS (seepage 28)

    Communication cable from the ATS connected to the generator (seepage 30)

    230 VAC input from the ATS connected to the generator (seepage 33)

    Heater and battery charger connected to the generator (seepage 33)

    Branch distribution equipment connected to the ATS (seepage 34)

    EPO switch connected to the user interface board on the ATS (seepage 35)

    Signature of person making inspection:

    Phone number:

    Date:

    Name of company making inspection:

    Phone number:

    Date:

  • 7/31/2019 Aste-6z3qgx r0 En

    56/60

  • 7/31/2019 Aste-6z3qgx r0 En

    57/60

  • 7/31/2019 Aste-6z3qgx r0 En

    58/60

  • 7/31/2019 Aste-6z3qgx r0 En

    59/60

  • 7/31/2019 Aste-6z3qgx r0 En

    60/60

    Customer support for this or any other APC product is available at no charge in any of the following ways:

    Visit the APC Web site to access documents in the APC Knowledge Base and to submit customer

    support requests.

    www.apc.com (Corporate Headquarters)

    Connect to localized APC Web sites for specific countries, each of which provides customer support

    information.

    www.apc.com/support/

    Global support searching APC Knowledge Base and using e-support.

    Contact an APC Customer Support center by telephone or e-mail.

    Regional centers:

    Local, country-specific centers: go to www.apc.com/support/contact for contact information.

    Contact the APC representative or other distributor from whom you purchased yourAPC product for

    information on how to obtain local customer support.

    Direct InfraStruXure Customer Support Line (1)(877)537-0607 (toll free)

    APC headquarters U.S., Canada (1)(800)800-4272 (toll free)

    Latin America (1)(401)789-5735 (USA)

    Europe, Middle East, Africa (353)(91)702000 (Ireland)

    Japan (0) 35434-2021

    Australia, New Zealand, South Pacific area (61) (2) 9955 9366 (Australia)

    Entire contents copyright 2006 American Power Conversion Corporation. All rights reserved.

    APC Worldwide Customer Support

    http://www.apc.com/http://www.apcc.com/supporthttp://www.apc.com/support/contacthttp://www.apc.com/support/contacthttp://www.apcc.com/supporthttp://www.apc.com/