Upload
suvankar-bhattacharyya
View
218
Download
0
Embed Size (px)
Citation preview
7/31/2019 Aste-6z3qgx r0 En
1/60
ElectricalInstallation
InfraStruXure Power
Generation System250 A ATS
80 kW and 120 kW Generators
7/31/2019 Aste-6z3qgx r0 En
2/60
This manual is available in English on the enclosed CD.
Uivatelsk pruka v etin je k dispozici na piloenm CD.
Dieses Handbuch ist in Deutsch auf der beiliegenden CD-ROM verfgbar.
Deze handleiding staat in het Nederlands op de bijgevoegde cd.
Este manual est disponible en espaol en el CD-ROM adjunto.
Ce manuel est disponible en franais sur le CD-ROM ci-inclus.
A hasznalati utasitas magyarul megtalalhato a csatolt CD-n.
Questo manuale disponibile in italiano nel CD-ROM allegato.
CD-ROMDenne manualen er tilgjengelig p norsk p vedlagte CD.
Instrukcja Obsugi w jezyku polskim jest dostepna na CD.
O manual em Portugus est disponvel no CD-ROM em anexo.
-.
Denna manual finns tillgnglig p svenska p medfljande CD.
Bu kullanim kilavuzunun Trke's, lxkte gnderlen CD ersnde mevcuttur.
CD
7/31/2019 Aste-6z3qgx r0 En
3/60
InfraStruXure Power Generation System i
About This Manual
Audience
This manual is intended forcertified electricians who will be installing the InfraStruXure Power
Generation System. It provides detailed electrical and physical specifications, diagrams, and
instructions on how to position and install the Generator and the Smart Distribution Panel with
Automatic Transfer Switch (ATS).
Companion manuals
For additional information about the InfraStruXure Power Generation System, refer to the following
sheets and manuals:
ATS Unpacking Sheet(990-1842)
ATS Operation Manual (990-2355)
InfraStruXure Power Generation System Generator Reference Manual (990-2334)
Network Management Interface Users Guide (available on the APC Web site or the Utility CD)
(990-1993)
How to find updates to this manual
You can check for updates to this manual by clicking on the User Manuals link on the Support page
of the APC Web site (www.apc.com). Choose Power Generation and then InfraStruXurePower
Generation. In the list of manuals, look for the latest letter revision (A, B, etc.) of the part number
appearing on the back cover of this manual.
7/31/2019 Aste-6z3qgx r0 En
4/60
7/31/2019 Aste-6z3qgx r0 En
5/60
Contents
InfraStruXure Power Generation System iii
Safety................................................................................1
Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
Save these instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Safety symbols used in this manual . . . . . . . . . . . . . . . . . . . . . . . . . 1
Cross-reference symbols used in this manual . . . . . . . . . . . . . 1
Warnings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2
Read these instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . 2The InfraStruXure Power Generation System
is an optional standby system . . . . . . . . . . . . . . . . . . . . . . . 2
Fuel and fumes are flammable . . . . . . . . . . . . . . . . . . . . . . . 3
Exhaust gases are deadly . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Moving parts can cause severe personal injury or death . . . . . . 3
Do not operate in flammable and explosive environments . . . . . 4
Electrical shock can cause severe personal injury or death . . . . 4
General safety precautions . . . . . . . . . . . . . . . . . . . . . . . . . 5
Battery considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
System Data .....................................................................7
Electrical. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
Power and communication connections . . . . . . . . . . . . . . . . . 7
Physical . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9
Generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Special considerations for generator installations . . . . . . . . . 10
Smart Distribution Panel with ATS . . . . . . . . . . . . . . . . . . . 11
Cabling............................................................................13
Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13
Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
Pour the generator pad . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Install the generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Run cables from the generator to the ATS . . . . . . . . . . . . . . 15
Install the ATS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
7/31/2019 Aste-6z3qgx r0 En
6/60
iv InfraStruXure Power Generation System
Wiring .............................................................................23
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24Connect power from the generator to the ATS . . . . . . . . . . . 24
Connect mains input to the ATS . . . . . . . . . . . . . . . . . . . . . 26
Connect the DC power input, start, and E-Stop contacts . . . . . 28
Connect the communication cable from the ATS
to the generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Run AC power from the ATS to the generator
for the heater and battery charger . . . . . . . . . . . . . . . . . . . 33
Connect branch distribution equipment to the ATS . . . . . . . . 34
Connect an EPO switch to the user interface board
and test the switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35Connect contacts to the user interface board . . . . . . . . . . . . 38
Connect the ATS to the network
at the surge-protected ethernet port . . . . . . . . . . . . . . . . . . 40
Appendix A: Adding Circuit Breakers ......................... 41
How to Add Sub-Feed OutputDistribution Circuit Breakers to the ATS . . . . . . . . . . . . . . . . . . . . . 41
Output distribution circuit breakers available from APC . . . . . 41
Determine the configuration of the panel . . . . . . . . . . . . . . . 42
Preparing the breakers for installation . . . . . . . . . . . . . . . . . 43
Parts and tools needed for installation procedures . . . . . . . . 44
Installing circuit breakers on the ATS panel board . . . . . . . . . 45
Appendix B: Wire Sizes ................................................ 47
250 A ATS and 80 kW Generator . . . . . . . . . . . . . . . . . . . . . 47
250 A ATS and 120 kW Generator . . . . . . . . . . . . . . . . . . . . 47
Installation Checklist..................................................... 49
7/31/2019 Aste-6z3qgx r0 En
7/60
InfraStruXure Power Generation System 1
Safety
Overview
Save these instructions
This manual contains important instructions that must be followed during installation, operation, and
maintenance of the InfraStruXure Power Generation System.
Safety symbols used in this manual
Cross-reference symbols used in this manual
ElectricalHazard
Indicates an electrical hazard, which, if not avoided, could result in injury or
death.
DANGER
Indicates a hazard, which, if not avoided, could result in severe personal injury or
substantial damage to product or other property.
Heavy
Indicates a heavy load that should not be lifted without assistance.
Note
Indicates important information.
Indicates that more information is available on the same subject in a different section of
this manual.
See also
Indicates that more information is available on the same subject in a different manual.
7/31/2019 Aste-6z3qgx r0 En
8/60
2 InfraStruXure Power Generation System
Warnings
The components in the InfraStruXure Power Generation System and UPS power distribution
system can pose life-threatening danger when improperly installed, operated, or maintained. To
prevent accidents, be aware of the dangers and act safely. Read and follow all of the safety
instructions and warnings in this manual and in all of your component manuals.
The Generator and Automatic Transfer Switch (ATS) that you purchased from American Power
Conversion (APC) is classified as an Optional Standby Systemit provides backup or standby
power to data centers in the event of a sustained power failure.
The InfraStruXure Power Generation System is not to be classified as anEmergency System that
is essential for safety to human life (e.g., fire pumps, operating room equipment, and life-
support equipment in hospitals) as legally required by your national and local codes.
The InfraStruXure Power Generation System is not to be classified as aLegally Required
StandbySystem, as it is not supplying power to aid in fire fighting, rescue operations, control of
health hazards (e.g., sewage), and similar operations as required by your national and local
codes.
Emergency andLegally Required Systems are not allowed to rely on municipal fuel for
operation and municipal water for cooling.Emergency andLegally Required Systems require
dual fuel systems, with one of them being a two-hour, on-site fuel supply.
Your InfraStruXure Power Generation System is not to be classified as anIntegrated Electrical
System, as an orderly shutdown is not required to prevent damage to the generator. Thegenerator is not to be paralleled with another generator.
Your generator will operate at its rated load without being re-fueled for a minimum of six hours,
and should be able to run with no load for a minimum of 12 hours.
Your generator can be without electrical power to the load terminals of the ATS for a maximum
of 60 seconds, but will typically be without power for no more than 10 seconds.
Note
Read these instructions
Note
The InfraStruXure Power Generation System is an optional standby system
7/31/2019 Aste-6z3qgx r0 En
9/60
Safety
InfraStruXure Power Generation System 3
Fire, explosion, and personal injury or death can result from improper practices.
DO NOT fill fuel tanks while the engine is running, unless the tanks are outside the engine
compartment. Fuel contact with a hot engine or exhaust is a potential fire hazard.
DO NOT permit any flame, cigarette, pilot light, spark, arcing equipment, or other ignition
source near the generator or fuel tank.
Ensure that exhaust gases are properly discharged away from enclosed or sheltered areas, as
well as areas where individuals are likely to congregate.
Ensure that the unit is well ventilated.
Engine exhaust and some of its constituents are known to cause cancer, birth defects, and
other reproductive harm. Take care not to breathe, ingest, or come in contact with exhaust
gases.
Keep your hands, clothing, and jewelry away from moving parts.
Before starting work on the generator, disconnect the battery charger from its AC source, and
then disconnect the battery. Be sure to disconnect the batterys negative () cable first. This
should prevent accidental starting.
Make sure that fasteners on the generator are secure. Tighten supports and clamps, and keep
guards in position over fans, drive belts, etc.
Do not wear loose clothing or jewelry in the vicinity of moving parts, or while working onelectrical equipment. Loose clothing and jewelry can become caught in moving parts.
If an adjustment must be made while the unit is running, use extreme caution around hot
manifolds, moving parts, etc.
DANGER
Fuel and fumes are flammable
DANGER
Exhaust gases are deadly
DANGER
Moving parts can cause severe personal injury or death
7/31/2019 Aste-6z3qgx r0 En
10/60
Safety
4 InfraStruXure Power Generation System
Flammable vapor can cause an engine to overspeed and become difficult to stop, resulting inpossible fire, explosion, severe personal injury, or death. Do not operate a generator where a
flammable vapor environment can be created by a fuel spill, leak, etc., unless the generator is
equipped with an automatic safety device to block the air intake and stop the engine. The
owners and operators of the generator are solely responsible for operating the generator safely.
Disconnect or disengage electric power before removing protective shields or touchingelectrical equipment. Wear rubber boots when working on electrical equipment. Do not wear
damp clothing (particularly wet shoes) or allow skin surface to be damp when handling
electrical equipment. Do not wear jewelryjewelry can short out electrical contacts and
cause shock or burns.
Use extreme caution when working on electrical components. High voltages can cause injury
or death. DO NOT tamper with interlocks.
Follow all applicable national and local electrical codes. Have all electrical installations
performed by a qualified licensed electrician. Lock out and tag open switches to avoid
accidental closure.
Hazardous voltages can flow from the generator into the mains line, creating a potential for
electrocution of service personnel or property damage. DO NOT CONNECT THE
GENERATOR DIRECTLY TO ANY BUILDING ELECTRICAL SYSTEM. CONNECT
ONLY TO THE AUTOMATIC TRANSFER SWITCH.
DANGER
Do not operate in flammable and explosive environments
ElectricalHazard
Electrical shock can cause severe personal injury or death
7/31/2019 Aste-6z3qgx r0 En
11/60
Safety
InfraStruXure Power Generation System 5
Coolants under pressure have a higher boiling point than water. DO NOT open a radiator or
heat exchanger pressure cap while the engine is running or remains hot. Allow the generator
to cool in order to decrease the system pressure.
Used engine oils are known to cause cancer and reproductive toxicity. When checking or
changing engine oil, take care not to ingest, breathe the fumes, or make bodily contact with
used oil.
Keep multi-class ABC fire extinguishers handy. Class A fires involve ordinary combustible
materials such as wood and cloth; Class B fires involve combustible and flammable liquid
fuels and gaseous fuels; and Class C fires involve live electrical equipment.
Make sure that rags are not left on or near the engine.
Make sure the generator is mounted in a manner that will prevent combustible materials from
accumulating under its base.
Remove all unnecessary grease and oil from the generator. Accumulated grease and oil can
cause overheating and engine damage, and presents a potential fire hazard.
Keep the generator and its surrounding area clean and free from obstructions. Remove any
debris and keep the floor clean and dry.
Do not work on this equipment when mentally or physically fatigued, or after consuming any
alcohol or drug.
Do not store any flammable liquids, such as fuel, cleaners, oil, etc., near the generator. A fire
or explosion could result.
Wear hearing protection when going near an operating generator.
To prevent serious burns, avoid contact with hot metal parts such as the radiator, turbo
charger, and exhaust system.
Note
General safety precautions
7/31/2019 Aste-6z3qgx r0 En
12/60
Safety
6 InfraStruXure Power Generation System
Battery servicing must be performed or supervised by personnel knowledgeable of batteries
and the required precautions. Keep unauthorized personnel away from the battery.
When replacing the battery, use the same model number. The battery specifications are as
follows: 12 V, 100 A, 1400 cold-cranking amps, sealed lead-acid.
Do not dispose of a battery in a fire. It is capable of exploding.
Do not open or mutilate a battery. Released electrolyte has been known to be harmful to the
skin and eyes and is toxic.
A battery presents a risk of high short-circuit current. Observe the following precautionswhen working on batteries:
Remove watches, rings, or other metal objects.
Use tools with insulated handles.
Do not lay tools or metal parts on top of a battery.
Electrolyte is a diluted sulfuric acid that is harmful to the skin and eyes. It is electrically
conductive and corrosive. The following procedures should be observed:
Wear full eye protection and protective clothing.
If electrolyte contacts the skin, wash it off immediately with water.
If electrolyte contacts the eyes, flush thoroughly and immediately with water and seek
medical attention.
Spilled electrolyte must be washed down with an acid neutralizing agent. Use a solution of
500 grams (one pound) bicarbonate of soda to 4 liters (one gallon) of water. The
bicarbonate of soda solution should be added until evidence of the reaction (foaming) has
ceased. The resulting liquid should then be flushed with water and the area dried.
A lead-acid battery presents a risk of fire because it generates hydrogen gas. The following
precautions must be followed:
DO NOT SMOKE near the battery.
DO NOT cause flame or spark in the battery area.
Discharge static electricity from your body before touching the battery by first touching a
grounded metal surface.
Note
Battery considerations
7/31/2019 Aste-6z3qgx r0 En
13/60
InfraStruXure Power Generation System 7
System Data
Electrical
Power and communication connections
Two sources supply power to the ATS. The typical installation has the mains connected to Source 1
(S1) and a generator connected to Source 2 (S2). If you purchased your ATS as an InfraStruXure
Extended Runtime Solution, your ATS was supplied with either an 80 kW or a 120 kW generator. To
ensure a successful transition from S1 to S2, APC recommends that the mains circuit breaker rating
match the generators circuit breaker rating as presented in the table below.
AC Power Input to ATS from Generator
Voltage (L-L) 3 x 400/230 V
Output power of generator 80 kW or 120 kW
Size of generator output circuit breaker 250 A
Connection type 3/N/PE
Recommended wire sizes if 30C* 50 mm2 - 240 mm2
Recommended wire sizes if 40C* 50 mm2 - 240 mm2
Recommended protective earthing (PE) wire size* 25 mm2 - 120 mm2
AC Power Input to ATS from Mains
Voltage (L-L) 3 x 400/230 V
Size of upstream mains circuit breaker 250 A
Connection type 3/N/PE
Recommended wire sizes if 30C* 50 mm2 - 240 mm2
Recommended wire sizes if 40C* 50 mm2 - 240 mm2
Recommended protective earthing (PE) wire size* 25 mm2 - 120 mm2
12 VDC to ATS from Generator
Recommended wire size* Two, 1.5 mm stranded copper**
Voltage 12 VDC
Connection point Hard-wire to generator controller terminal block
Communication Connection from Generator to ATS
Recommended wire size* Belden 9830 cable or equivalent (0.2 mm; 3 twisted, shielded
pairs; 100 ohms nominal impedance; 60 pF/ft nominal capacity)
Connection point RS485/RS232 converter on ATS to identical converter ongenerator (requires installation)
7/31/2019 Aste-6z3qgx r0 En
14/60
System Data
8 InfraStruXure Power Generation System
AC Power from ATS to Generator Heater and Battery Charger
Recommended wire size* Two, 1.5 mm stranded copper**
Voltage 230 VAC
Connection style Hard-wire from T1 circuit breaker in ATS to the battery chargercontrol box in the generator
Start Signal Connection to Generator from ATS
Recommended wire size* Two, 1.5 mm stranded copper**
Connection point Hard-wire to generator controller terminal block
Emergency Stop Signal Connection to Generator from ATS
Recommended wire size* Two, 1.5 mm stranded copper**
Connection point Hard-wire to generator controller terminal block
ATS Branch Distribution to Equipment***
Circuit breaker style MCCB ABB Tmax T1 or T3 up to 225 A
ATS Ethernet Connection
Connection type CAT-5 network cable connected to the surge-protected ethernetport on the ATS user interface board
ATS EPO Connection
Recommended wire size* 2.5 mm0.2 mm**
Connection type Voltage-free contact (NO or NC) or 24 VDC on the ATS userinterface board
ATS User Input Contacts/Relay Outputs
Recommended wire size* 2.5 mm0.2 mm**
Connection type Voltage-free contact (NO or NC) on the ATS user interface board
* Always follow your national and local codes when installing the InfraStruXure Power Generation System. The AC Power Input wire
sizes provided in this document are recommendations only. The ATS is provided with a panel board to supply power to multiple loads.
Since loading could increase after the products initial installation, the AC Power Input wires were selected for the maximum current
that can be delivered by the panel board. If the ATS is purchased to supply a calculated load rated less than the panel board, and the
load will never increase, smaller wires can be used if the requirements in your national and local codes are followed.
**Use ferrules on the ends of stranded-copper wires to avoid creating a short circuit that could possibly damage the interface board and/or the S2 motor control circuits.
***Wire sizes to loads must be in accordance with the ratings of the circuit breakers selected to power the loads.
Refer to Appendix B: Wire Sizes on page 47 for a more comprehensive listing of wire sizes
as they relate to various installation environments.
See also
Refer also to EN60364-5-52, Selection and erection of electrical equipment - wiring systems.
7/31/2019 Aste-6z3qgx r0 En
15/60
InfraStruXure Power Generation System 9
Physical
Generator
80 kW 120 kW
Height 1678 mm / 66 in 1970 mm / 77.5 in
Length 2343 mm / 92 in 2920 mm / 115 in
Width 1084 mm / 42.5 in 1136 mm / 44.5 in
Length of Footprint 2343 mm / 92 in 2404 mm / 94.5 in
Width of Footprint 918 mm / 36 in 1060 mm / 41.5 in
Weight 1840 kg / 4057 lb 2671 kg / 5889 lb
Operating Temperature Range 30 to 50 C / 22 to 122 F 30 to 50 C / 22 to 122 F
Operating Relative Humidity 5 to 100% 5 to 100%
Operating Elevation 3900 m / 12,800 ft 3900 m / 12,800 ft
Tank Type Double-wall, steel base Double-wall, steel base
Fuel Type Diesel Diesel
Tank Size 300 liters / 79 gallons 435 liters / 115 gallons
Access Clearances Working space must be in accordance with standard EN60364, and should
not be less than 700 mm (28 in).
1084 mm (80 kW)2343 mm (80 kW)
1678 mm (80 kW)1970 mm (120 kW)
2920 mm (120 kW)1136 mm (120 kW)
The 80 kW generator isshown in this and othergraphic representationsthroughout this manual
7/31/2019 Aste-6z3qgx r0 En
16/60
System Data
10 InfraStruXure Power Generation System
Special considerations for generator installations
Installation considerations. Use the instructions in this manual as a general guide only. Follow
the instructions of the consulting engineer regarding the placement of system components. The
complete installation must comply with all national and local building codes, fire ordinances, andother applicable regulations. Consider these requirements prior to installation:
Level mounting surface
Adequate cooling air
Adequate fresh induction air
Discharge of generator air
Non-combustible mounting surface
Discharge of exhaust gases
Electrical connections
Accessibility for operation and servicing
Noise levels
Location considerations. Generator location is mainly decided by such criteria as ventilation,
wiring, fuel, and exhaust. The generator should be located as near as possible to the main power
service entrance. Exhaust must not be able to enter or accumulate around inhabited areas. In
accordance with standard EN60364, provide at least 700 mm (28 in) of clearance on all sides.
7/31/2019 Aste-6z3qgx r0 En
17/60
System Data
InfraStruXure Power Generation System 11
Smart Distribution Panel with ATS
Height 1905 mm / 75.0 in
Width 711 mm / 28.0 in
Depth 383 mm / 15.0 in
Weight 219 kg / 482 lb
Operating Temperature Range 5 to 40C / 23 to 104F
Operating Relative Humidity 5 to 95%, non-condensing
Operating Elevation 0 to 2000 m / 0 to 6,562 ft
Enclosure Rating IP40
Access Clearances Working space must be in accordance with standard
EN60364, and should not be less than 700 mm (28 in).
1905 mm
383 mm711 mm
7/31/2019 Aste-6z3qgx r0 En
18/60
7/31/2019 Aste-6z3qgx r0 En
19/60
InfraStruXure Power Generation System 13
Cabling
Overview
Pour the generator pad.
Install the generator.
Run cables from the generator to the ATS.
Install the ATS.
Pg0205a
7/31/2019 Aste-6z3qgx r0 En
20/60
14 InfraStruXure Power Generation System
Procedures
Pour the generator pad
Pour a concrete generator pad at the selected installation location.
Ensure that the composition and thickness of the pad is appropriate for the conditions at the
installation site. Check with the consulting engineer.
Ensure that the dimensions of the pad exceed the footprint of your generator by at least 380 mm(15 in) on all sides:
The 80 kW generator has a footprint of 2343 mm x 918 mm (92 in x 36 in). Therefore, its pad
should be at least 3103 mm x 1678 mm (122 in x 66 in).
The 120 kW generator has a footprint of 2404 mm x 1060 mm (94.5 in x 41.5 in). Therefore,
its generator pad should be at least 3164 mm x 1820 mm (124.5 in x 71.5 in).
Install the generator
Carefully set the generator down onto the concrete generator pad using a properly rated hoist orcrane. The generator should be centrally positioned on the pad.
Note
These instructions are recommendations only. Follow all applicable national and local codes.
Heavy
At least three people are required to place the generator: one to operate the hoist or
crane, and two or more to appropriately position the generator on its pad.
After appropriately positioning the generator on its pad,
verify that all four mounting pads on the bottom of the fuel
tank make full contact with the generator pad. Level shims
are included with the generators literature pack, and can be
used to fill any gap between the mounting pads and the
generator pad. Insert the maximum height stack of shims
that will slide into the gap.
Secure the generator to the generator pad using the
appropriate mounting hardware. Use type J or L bolt
anchoring (not supplied) as shown in the illustration.
pg0004a
7/31/2019 Aste-6z3qgx r0 En
21/60
Cabling
InfraStruXure Power Generation System 15
Run cables from the generator to the ATS
1. Refer to the below left illustration for the location of the cable entry.
2. Run cables containing the following wires through the perforations in the cable entry to the ATS
using floor troughs or cable ladders as necessary. Refer to the below right illustration.
Input power from the generator to the ATS
230 VAC from the ATS to the generator for the heater and battery charger
12 VDC from the generator to the ATS
Start contact from the generator to the ATS
E-Stop contact from the generator to the ATS
Communication from the ATS to the generator
See the table beginning onpage 7 for wiring specifications, and see Wiring on page 23
for procedures on connecting to the ATS.
Frfront
Front
Rear
Cable
Front
Rear
entry
7/31/2019 Aste-6z3qgx r0 En
22/60
Cabling
16 InfraStruXure Power Generation System
Install the ATS
Remove the ATS panel board assembly from the enclosure.
Note
APC recommends removing the ATS panel board assembly from the enclosure prior to
installation. Removal of this assembly makes it easier to mount the ATS to the wall. If youare not removing the panel board assembly, continue with the procedure on page 19.
1. Open the front door of the ATS.
2. Remove the screw on the left that
secures the bottom access panel.
3. Open the dead front by first loosening
its turn-screw on the right, and then
pulling the top and bottom latches
toward each other.
4. Remove the screw on the right that
secures the bottom access panel.
5. Remove the bottom access panel from the enclosure.
Remove
Front Door Open, Dead Front Closed
Remove
Front Door Open, Dead Front Open
First, pull up
Second, pull out
7/31/2019 Aste-6z3qgx r0 En
23/60
Cabling
InfraStruXure Power Generation System 17
6. Disconnect the panel board assembly wires that are connected to the following components
inside the ATS enclosure:
User interface circuit board
Surge-protected ethernet port
Door relay
Auto switch and LEDs
Display interface
Neutral wire (if applicable)
See also
Refer to theATS Operation Manual for the exact location of these components.
Note
Each wire has a yellow label attached that specified its point of connection.
7. Use a 13-mm wrench to remove the
M8 nuts located at the top and bottom
(4 total) of the panel board assembly.Remove
Remove
TOP
BOTTOM
Use 13-mm Wrench to Remove
7/31/2019 Aste-6z3qgx r0 En
24/60
Cabling
18 InfraStruXure Power Generation System
8. Using the handle at the top of the
panel board assembly, slowly pull the
entire assembly toward you.
Note
At least two people should be involved in removing the panel board!
9. Walk the panel board assembly out
of the enclosure one wheel at a time,
and then roll the assembly away from
the enclosure.
10. Carefully lay the panel board assembly on its back at a location apart from the enclosure.
Note
Do not re-install the panel board assembly until after you have mounted the ATS
enclosure and pulled cables to it.
7/31/2019 Aste-6z3qgx r0 En
25/60
Cabling
InfraStruXure Power Generation System 19
Mount the ATS to a wall.
Prior to wall-mounting, covers must be
removed from the horizontal slots at the
rear of the enclosure. Use a 10-mmwrench to remove the M6 nuts securing
the covers in place.
Mounting to studs:
1. Locate wall studs and draw vertical
chalk lines to show where the studs
are located.
2. Place the enclosure against the
wall.
3. Find the chalk lines/studs through
the horizontal slots at the rear of
the enclosure.
4. Drive the anchoring screws
(supplied) into the wall studs in
four places.
5. Re-install covers to the horizontal
mounting slots using the
previously removed M6 nuts.
Mounting to concrete:
1. Place the enclosure against the
wall.
2. Drill four holes (with a 4.5-mm diameter masonry drill bit) through the horizontal slots at the
rear of the enclosure.
3. Drive the anchoring screws (supplied) into the drilled holes.
4. Re-install covers to the horizontal mounting slots using the previously removed M6 nuts.
Note
There is no need to mount
plywood or Unistrut metal
framing to the wall.
718 mm/28.25 in60 mm/2.25 in
1748mm/68.7
5in
1734mm/68.2
5in
399mm/15.7
5in
385mm/15,2
5in
594 mm/23.50 in
1895mm/74.5
0in
Mounting Hardware
Four, 9.5-mm (3/8-in) anchoring screws76-mm/3.00 in long
59 mm/2.25 in
7/31/2019 Aste-6z3qgx r0 En
26/60
Cabling
20 InfraStruXure Power Generation System
Pull the wires into the ATS. After you mount the ATS to the wall, pull the wires that were cable-
connected from the generator (see the list of wires on page 15) into the ATS enclosure. You can pull
these wires in through the roof, the floor, or the sides of the ATS.
When pulling wires through the roof or the floor of the ATS, use knockouts to the left or right side ofthe top or bottom panel rather than using knockouts in the middle. This method allows for easier
wiring to components on the panel board.
Note
Properly seal any knockouts that you create on the top or bottom panel of the ATS
according to local codes.
Pg0007c
7/31/2019 Aste-6z3qgx r0 En
27/60
Cabling
InfraStruXure Power Generation System 21
Re-install the ATS panel board assembly in the enclosure.
Note
If you did not remove the panel board assembly before mounting the ATS enclosure to
the wall, proceed to Strain relief the cables inside the ATS on the following page.
1. Roll the panel board assembly back to
the ATS and walk it into the
enclosure one wheel at a time.
2. Align the mounting holes at the top
and bottom of the assembly with the
proper studs in the enclosure.
3. Re-attach the four previouslyremoved M8 nuts to the studs. See
step 7 onpage 17.
Note: You can re-install the bottom
access panel now, or you can reinstall
it after connecting wires to the panel
board. To re-install, perform the
reverse of the panel board assembly
removal procedures onpage 16.
Install
Install
TOP
BOTTOM
Use 13-mm wrench to install
http://-/?-http://-/?-7/31/2019 Aste-6z3qgx r0 En
28/60
Cabling
22 InfraStruXure Power Generation System
Strain relief the wires inside the ATS. Use cable ties to strain relief the wires you have pulled
into the ATS before making connections.
For top cable entry:
Secure cables to the strain relief bracket at the top of the enclosure. The following illustration shows
the location of the strain relief bracket.
For bottom cable entry:
Secure cables to the bottom rung of the panel board assembly. The following illustration shows the
location of the bottom rung of the panel board assembly.
4. Re-connect the panel board assembly wires that were previously disconnected from the
following ATS components:
User interface circuit board
Surge-protected ethernet port
Door relay
Auto switch and LEDs
Display interface
Neutral wire (if applicable)
Note
Refer to the yellow label on each wire for its point of connection.
panel board assemblyBottom rung of
7/31/2019 Aste-6z3qgx r0 En
29/60
InfraStruXure Power Generation System 23
Wiring
Overview
Connect generator input power to the ATS.
Connect mains input to the ATS.
Connect the 12 VDC, Start, and E-Stop contacts.
Connect the communication cable from the ATS to the generator.
Run AC power input from the ATS to the generator for the heater and battery charger.
Connect the branch distribution equipment to the ATS.
Connect an EPO switch to the user interface board and test the switch.
Connect contacts to the user interface board.
Connect the ATS to the network at the surge-protected ethernet port.
Pg0134b
7/31/2019 Aste-6z3qgx r0 En
30/60
24 InfraStruXure Power Generation System
Procedures
Connect power from the generator to the ATS
Specifications and tools. The generator output breaker is equipped with saddle lugs, and the ATS
input switches are equipped with box lugs. See Power and communication connections on page 7
for generator input wiring specifications. Torque generator input wires to 28 nm (250 in lb) using
an 8-mm Allen wrench.
Routing wires. Route generator input wires into the ATS using the knockouts provided on the ATS
enclosure. Use a knockout punch to create the size of hole that you need. You can bring these wiresinto the ATS through the roof or the floor. See the illustration on the next page for suggested wiring
paths for both options. If possible, use the knockouts on either side of the roof or floor rather than
knockouts in the middle of the roof or floor (seepage 20).
Note
If you are running wires through the roof of the ATS to connect to the Source 2 input
switch, these wires will need to be at least 2.9 m (9.5 ft) longer than a similar group of
wires run through the floor.
Source2 input switch
PE bar
(80 kW Generator and 250 A ATS400 V input shown)
PE wire from generator
from generatoroutput breaker
Generator output breaker
N, L1, L2, L3
PE wire
N, L1, L2, L3
7/31/2019 Aste-6z3qgx r0 En
31/60
Wiring
InfraStruXure Power Generation System 25
Making connections.
1. Connect the neutral (N) and phase (L1, L2, L3) wires from the output breaker in the generator to
the Source 2 input switch in the ATS. Use phase-sequence (A-B-C) clockwise rotation.
2. Connect the protective earth (PE) wire from the generator to the PE bar in the ATS.
pg0054c
Source2 input switch
Generator output breaker
Optional wiring through the roof
Preferred wiring through the floor
(80 kW Generator and
PE bar
250 A ATS400 V input shown)
7/31/2019 Aste-6z3qgx r0 En
32/60
Wiring
26 InfraStruXure Power Generation System
Connect mains input to the ATS
Specifications and tools. The ATS input switches are equipped with box lugs. See Power and
communication connections on page 7 for mains input wiring specifications. Torque mains input
wires to 28 nm (250 in lb) using an 8-mm Allen wrench.
Routing wires. Route mains input wires into the ATS using the knockouts provided on the ATS
enclosure. Use a knockout punch to create the size of hole that you need. You can bring these wires
into the ATS through the roof or the floor. See the illustration on the next page for suggested wiring
paths for both options. If possible, use the knockouts on either side of the roof or floor rather than
knockouts in the middle of the roof or floor (seepage 20).
Note
If you are running wires through the floor of the ATS to connect to the Source 1 input
switch, the neutral and phase wires will need to be at least 2.0 m (6.6 ft) longer than the
protective earth wire.
If you are running wires through the roof of the ATS to connect to the Source 1 input
switch, the protective earth wire will need to be at least 2.0 m (6.6 ft) longer than the
neutral and phase wires.
ATS panel board
Source1 input switch
(250 A ATS400 V input shown)
N, L1, L2, L3,
and PE
PE Bar
7/31/2019 Aste-6z3qgx r0 En
33/60
Wiring
InfraStruXure Power Generation System 27
Making connections.
1. Connect the neutral (N) and phase (L1, L2, L3) wires from the mains power supply to the
Source 1 input switch in the ATS. Use phase-sequence (A-B-C) clockwise rotation.
2. Connect the protective earth (PE) wire from mains to PE bar in the ATS.
pg0055c
Source 1 input switch
Input from mainsPreferred wiring
Optional wiring through the floor
(250 A ATS400 V input shown)
through the roof
PE bar
7/31/2019 Aste-6z3qgx r0 En
34/60
Wiring
28 InfraStruXure Power Generation System
Connect the DC power input, start, and E-Stop contacts
Specifications and tools. Use a 2.5-mm standard screwdriver to make connections to the terminal
block. See Power and communication connections on page 7 for wiring specifications. Apply
ferrules to the ends of each wire to avoid creating a short circuit.
Start contact TB1, terminal 1E-Stop contact TB1, terminal 2
DC contact, TB1,terminal 17
Connect PE wires at
TB1, terminal 20, 21, and 22
Generator controller
Connect start contact, E-Stop
contact, and 12 VDC to
J51, J52, and J53
ATS interface
Note: It does not matter
circuit board
whether you connectthe contact or PE wireto J51, J52, or J53.
7/31/2019 Aste-6z3qgx r0 En
35/60
Wiring
InfraStruXure Power Generation System 29
Making connections. Make connections between the generator controller terminal block and the
ATS interface board according to the table and diagram below:
Generator Terminal Block ATS Interface Board
DC Input Contact Terminal 17, TB1connects to
J51 (+)
PE Terminal 20, TB1 J51 ()
Start Contact Terminal 1, TB1connects to J52
PE Terminal 22, TB1
E-Stop Contact Terminal 2, TB1connects to J53
PE Terminal 21, TB1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
TB2TB1
1 2 3 4 5 6
pg0056a
Generator controller terminal blocksGenerator interfaceon ATS interface board
7/31/2019 Aste-6z3qgx r0 En
36/60
Wiring
30 InfraStruXure Power Generation System
Connect the communication cable from the ATS to the generator
Specifications and tools. Use a 2.5-mm standard screwdriver to make connections to the terminalblock and the converter. See Power and communication connections on page 7 for wiring
specifications. Apply ferrules to the ends of each wire to avoid creating a short circuit.
Install converter DB9 connection to converter
Generator
Power connection
ATS panel board
ATS monitoring unit
for converter
controller
7/31/2019 Aste-6z3qgx r0 En
37/60
Wiring
InfraStruXure Power Generation System 31
Installing the converter in the generator.
1. Attach the converter mounting rail
(supplied) to the inside door of the
generator controller using the
screws included with the converter
kit and a #2 Philips screwdriver.
2. Snap the converter and the
converter brackets onto the rail.
3. Secure the converter onto the rail by
tightening the converter brackets
using a 2.5-mm standard
screwdriver.
7/31/2019 Aste-6z3qgx r0 En
38/60
Wiring
32 InfraStruXure Power Generation System
Making Connections.
1. Connect the generator communication converter to the generator according to the table below and the
diagram at the bottom. Apply ferrules to the ends of each wire to avoid creating a short circuit.
2. Make connections between the generator and ATS according to the table below and the diagram at the
bottom. Apply ferrules to the ends of each wire to avoid creating a short circuit.
GeneratorConverter
Connector Connection Point in GeneratorController
[K] Tx
DB9 cable connects to DB9 connector above terminal block [M] Rx
[PE] PE
[6] V+ Cable with Minifit connects to B+; Terminal 17 or 18 on TB1
[5] V Cable with Minifit connects to PE; Terminal 20, 21, or 22 on TB1
Cut the Minifit connector off of the cable, strip the wire ends 6.35 mm, and connect to the appropriateterminals on TB1.
ATS Converter Generator Converter
Pair 1 [A] Tx+ connects to [B] Rx+
[D] Tx connects to [E] Rx
Pair 2 [E] Rx connects to [D] Tx
[B] Rx+ connects to [A] Tx+
Pair 3 [C] PE connects to [C] PE
Shield/bare [F] Shield Ground No connection
text text
DB 9FDB9F
RS-485 Converter
Tx
Tx+
Rx
Rx+
Rx
RS-485 Converter
Rx
Tx
ATS Generator
2
3
5
2
3
5
Tx
PE
+24 VDC
PE (TB1, pin 20, 21 or 22)
B+ (TB1, pin 17 or 18)
K
M
C
B
E
A
D
PE
5
K
M
PE
C
D
A
E
B
Mini-fit (2-pin)
ConsolePort
ATSMonitoringUn
it GeneratorController
Belden 9830 Cable
V6
1 4 2 3
F
1 4 2 3
F
Tx
Tx+
Rx
Rx+
V+6
V5
Shield Shield
V+
Pg0074c
7/31/2019 Aste-6z3qgx r0 En
39/60
Wiring
InfraStruXure Power Generation System 33
Run AC power from the ATS to the generator for the heater and battery charger
ATS with 400 V input.
Specifications and tools. Use a 2.5-mm standard or #1 Phillips screwdriver to make connections.
See Power and communication connections on page 7 for wiring specifications. Apply ferrules to
the ends of each wire to avoid creating a short circuit.
Procedure. Run three wires (protective earth, neutral, and line) from the ATS to the terminals in the
battery charger box in the generator:
Run the protective earth wire from the PE bar in the ATS to the terminals in the battery chargerbox in the generator.
Run the neutral wire from the neutral bar in the ATS to the terminals in the battery charger box
in the generator.
Run the line wire from the single-pole breaker in the ATS to the terminals in the battery charger
box in the generator.
Run the PE wirefrom the PE barto the generator
Run the line,neutral, andPE wiresfrom the ATS tothe battery chargerbox in the generator
Single-pole breaker
Connect the line wire tothe single-pole breaker
Run the neutral wirefrom the neutral bar tothe generator
7/31/2019 Aste-6z3qgx r0 En
40/60
Wiring
34 InfraStruXure Power Generation System
Connect branch distribution equipment to the ATS
Specifications and tools. Connect data center equipment to the ATS output distribution panel
breakers according to your national and local codes. See Appendix A: Adding Circuit Breakers on
page 41 for panel breaker specifications and installation instructions. Apply ferrules to the ends of
each wire to avoid creating a short circuit. The following table provides the wire sizes and torquespecifications that should be used when connecting to the panel breakers.
Installation. Install wires to the ATS using the knockouts provided on the ATS enclosure. Use a
knockout punch to create the size of hole that you need. You can run wires to the ATS through the
knockouts on the roof, the floor, or the sides of the enclosure. Refer to theATS OperationManual for
instructions on installing circuit breakers on the ATS panel board,
Breaker Rating Wire Size Torque
T1 1.5 mm6 mm 2.26 n m (20 inlb)
10 mm 4.52 n m (40 inlb)
10 mm50 mm 5.08 n m (45 inlb)
T3 50 mm2 mm 5.65 n m (50 inlb)
152 mm21 mm 22.58 n m (200 i n lb)
ElectricalHazard
Hazardous voltages from the branch circuit must be isolated from the 24 VAC, the
24 VDC, and all contact closure terminals.
PE bar
Neutral bar
L1, L2, and L3 fromdata center equipment
7/31/2019 Aste-6z3qgx r0 En
41/60
Wiring
InfraStruXure Power Generation System 35
Connect an EPO switch to the user interface board and test the switch
Specifications and tools. Connect an EPO switch to the ATS according to your national and local
codes. See Power and communication connections on page 7 for wiring specifications. Apply
ferrules to the ends of each wire to avoid creating a short circuit. Use a 2.5-mm standard screwdriver
to make these connections to the user interface board.
EPO switch installation instructions begin on the next page.
Note
If you are not connecting an EPO switch to the ATS, ensure that the Arm/Test rocker
switch on the ATS monitoring unit is in the Test position.
Note
APC offers an InfraStruXure EPO System (EPW9). Contact your sales representative,
or go to the APC Web site for more information (www.apc.com).
User connection plate
User interface board
Connect the EPO switch here
(the user connection plate has been turned upside down for the sake of this illustration)
7/31/2019 Aste-6z3qgx r0 En
42/60
Wiring
36 InfraStruXure Power Generation System
Installing the EPO switch to the user interface board.
1. Connect the switch to the EPO connection terminals on the user interface board, which is
located on the bottom side of the ATS user connection plate. Make the proper connections to the
proper terminals based on your signal type:
Contact ClosureNormally Open
Contact ClosureNormally Closed
24 VAC/VDCNormally Open
2. Verify that the EPO DIP switches on the ATS monitoring unit are configured properly for the
signal type you are using. The labels above the switches and the figure below show the correct
settings for both the Normally Open (NO) and Normally Closed (NC) configurations.
External set ofNormally OpenVoltage-free Contacts
External set ofNormally ClosedVoltage-free Contacts
24 V AC or DC Power Supply
External set ofNormally Open Voltage-free Contacts
Pdx0205b
NormallyOpen
or24VAC/DC
Location of switcheson ATS monitoring unit
7/31/2019 Aste-6z3qgx r0 En
43/60
Wiring
InfraStruXure Power Generation System 37
Test the EPO switch.
1. Test the EPO switch to ensure that it is wired and working correctly:
a. Place the Arm/Test rocker switch on the ATS monitoring unit in the Test position. The EPO
state LEDs should be off and the ATS display interface should show the following alarm (inaddition to any other active alarms):
b. Engage the EPO switch. (If your switch is momentary, engage it with one person watching
the EPO state LEDs and another at the EPO switch.)
c. Observe the EPO LEDs. If the switch is wired and working properly, both of the EPO state
LEDs should turn red when the switch is engaged.
d. If the test was successful, place the Arm/Test rocker switch back to the Arm position. The
ATS display interface will clear the EPO test mode alarm. If the test was not successful, see
the troubleshooting chart:
e. Repeat this test for each EPO switch installed.
2. After testing is completed, ensure that the Arm/Test rocker switch is in the Arm position on the
ATS monitoring unit.
Problem Action
Neither state LED was lit red
when the EPO switch was
engaged
Check the wiring to your EPO switch.
Check to make sure the EPO DIP switch
configuration is correct for your switch
(NO or NC). See step 2 on the previous page for
proper configuration instructions.
Only one of the state LEDs was lit
red when the EPO switch was
engaged
Check to make sure the EPO DIP switch
configuration is correct for your switch
(NO or NC) and re-test. See step 2 on the
previous page for proper configuration
instructions.
If the switch is configured correctly and both
LEDs have not turned red after re-testing,
contact APC customer support (see the backcover of this manual).
EPO Ready To TestActive Alarm xxofxx
7/31/2019 Aste-6z3qgx r0 En
44/60
Wiring
38 InfraStruXure Power Generation System
Connect contacts to the user interface board
Specifications and tools. See Power and communication connections on page 7 for wiring
specifications. Apply ferrules to the ends of each wire to avoid creating a short circuit. Use a 2.5-mm
standard screwdriver to make connections to the user interface board.
Connecting contacts.
1. Choose one or more contact numbers on the user interface board for connecting contacts. (The
user interface board is connected to the User/EPO port on the ATS monitoring unit.)
2. From the ATS display interface:
a. Press the ESC orENTERkey to go to the top-level menu screen.
b. Select Config on the top-level menu screen and press the ENTERkey.
c. Select Contacts & Relays on the Config menu screen and press the ENTERkey.
See also
Refer to theATS OperationManual for more information about user contacts and the
types of equipment that can be connected.
User connection plate
User interface board
Connect user input contacts
(the user connection plate has been turned upsidedownfor the sake of this illustration)
and relay outputs here
Load-Meter
ATS/Voltage
Generator
Testing
Stats
Alarms
Config
Help
System/NetworkContacts & RelaysSub-Feed Config.Electrical Config.
7/31/2019 Aste-6z3qgx r0 En
45/60
Wiring
InfraStruXure Power Generation System 39
d. Select the type of contact you are connecting: Contact Inputs orRelay Outputs.
e. Press the Up or Down arrow key to select the appropriate
contact number and press the ENTERkey.
f. Press the Down arrow key to enter a unique Name for the
contact and to configure the Normal state of the contact
(Open orClosed). The default Normal state is Open.
Press the ENTERkey to select the item you wish to
configure.
g. Connect contact wires (300 V-rated cabling required) to the terminal block on the user
interface board. Apply ferrules to the ends of each wire to avoid creating a short circuit. Use
a 2.5-mm standard screwdriver to make connections to the user interface board
h. Run the wires from the terminal block out the roof of the ATS to your contacts location.
ContactInputsRelay OutputsOutputRelay Map
Note
You will be prompted for your password to configure these items.
DANGER
Ensure that the wires are properly retained and kept away from high-voltage
wires and circuit breakers.
Contact In 02of04Name User Contact 4
Normal: OpenStatus: Open
7/31/2019 Aste-6z3qgx r0 En
46/60
Wiring
40 InfraStruXure Power Generation System
Connect the ATS to the network at the surge-protected ethernet port
Management options. There are two management options: You can manage the system, along
with the rest of your InfraStruXure equipment, through the InfraStruXure Manager (APC LAN); or
you can manage your system through APCs network management interfaces (User LAN).
Managing through the InfraStruXure Manager. The InfraStruXure Manager is a rack-mount
management device that coordinates the management functions of APC InfraStruXure-Certified
devices installed in your data center. It provides a single interface to view and configure all APC
InfraStruXure-Certified devices. See Configuring the InfraStruXure Manager in theATS Operation
Manual for configuration instructions.
Managing through the network management interfaces. The control console and Web
interfaces provide menus with options that allow you to manage the system. See Configuring the
ATS Network Management Interface in theATS OperationManual for configuration instructions.
The SNMP interface allows you to use an SNMP browser with the PowerNet Management
Information Base (MIB) to manage the system. See Configuring the ATS Network Management
Interface in theATS Operation Manual for configuration instructions.
See also
For more information about the InfraStruXure Manager, refer to theInstallation and
ConfigurationManual included with the InfraStruXure Manager.
See also
For more information about the internal user interfaces, refer to the InfraStruXurePower Generation Systems on-lineNetwork Management Users Guide.
See also
To use the PowerNet MIB with an SNMP browser, refer to the PowerNet SNMP
Management Information Base (MIB) Reference Guide provided on the InfraStruXure
Power Generation System Utility CD.
Surge-protected ethernet port
(the user connection platehas been turned upsidedown for the sake of this illustration)
User connection plate
Use a CAT-5 cable to connect.
7/31/2019 Aste-6z3qgx r0 En
47/60
InfraStruXure Power Generation System 41
Appendix A: Adding Circuit Breakers
How to Add Sub-Feed Output Distribution
Circuit Breakers to the ATS
Output distribution circuit breakers available from APC
Part Number Description Height on Panel
PG1P15AT1B 15 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in
PG1P16AT1B 16 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in
PG1P20AT1B 20 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in
PG1P25AT1B 25 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in
PG1P30AT1B 30 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in
PG1P32AT1B 32 A, single-pole breaker, T1 frame 25.4 mm / 1.00 in
PG3P15AT1B 15 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P20AT1B 20 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P25AT1B 25 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P30AT1B 30 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P40AT1B 40 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P50AT1B 50 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P60AT1B 60 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P63AT1B 63 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P70AT1B 70 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P80AT1B 80 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P90AT1B 90 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P100AT1B 100 A, three-pole breaker, T1 frame 76.2 mm / 3.00 in
PG3P125AT3B 125 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in
PG3P150AT3B 150 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in
PG3P160AT3B 160 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in
PG3P175AT3B 175 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in
PG3P200AT3B 200 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in
PG3P225AT3B 225 A, three-pole breaker, T3 frame 104.9 mm / 4.13 in
PG3P300AT5B 300 A, three-pole breaker, T5 frame 139.5 mm / 5.50 in
PG3P400AT5B 400 A, three-pole breaker, T5 frame 139.5 mm / 5.50 in
7/31/2019 Aste-6z3qgx r0 En
48/60
Appendix A: Adding Circuit Breakers
42 InfraStruXure Power Generation System
Determine the configuration of the panel
Before you begin installing circuit breakers on the ATS distribution panel, be sure that you have
enough space on the panel for the breakers that you want to install. Use the information in the
diagrams below to determine the final configuration of your panel.
Amount of space requiredfor each type of circuit breaker
T1 single-pole breaker assembly
T1 three-pole breaker assembly
T3 three-pole breaker assembly
Amount of space available
on the 250A ATSdistribution panel bus
7/31/2019 Aste-6z3qgx r0 En
49/60
Appendix A: Adding Circuit Breakers
InfraStruXure Power Generation System 43
Preparing the breakers for installation
Before installing the breakers on the ATS panel board, follow the steps provided in this section for the
breaker(s) that you are installing. The parts that are identified in the illustrations below are included
with your circuit breaker kit.
Slide the bracket adapter onto the output side of the T1 single-pole breaker. The bracket adapter is
used to attach the breaker to the breaker bracket.
The T1 three-pole breakers are ready for installation on the panel. No additional preparation is
needed.\
Both the input and output sides of the T3 three-pole breaker require preparation before the breaker is
installed on the panel.
On the input side, follow these steps for each of the three pole positions:
1. Place an M8 square nut into a square nut retainer, and then insert the square nut retainer into the
pole position.
2. Slide an M8 washer onto an M8 bolt, and then loosely attach the bolt to the M8 square nut.
On the output side, follow these steps for each of the three pole positions:
3. Slide a saddle lug into the pole position. You may need to loosen the bolt in the lug.
4. Insert a saddle lug retainer into the pole position.
Input
Output
T1 single-pole breaker
Bracket Adapter
T1 three-pole breaker
Input
Output
T3 three-pole breaker
InputOutput
Saddle Lug
Saddle LugRetainer
Square
M8 Bolt
M8 WasherM8
Nut RetainerSquareNut
7/31/2019 Aste-6z3qgx r0 En
50/60
Appendix A: Adding Circuit Breakers
44 InfraStruXure Power Generation System
Parts and tools needed for installation procedures
T1 single-pole breaker assembly
T1 single-pole module
T1 single-pole breakers
M375 screws, washers and retainers
breaker brackets
M612 Torx screws
M4 15 screws and washers
T1 three-pole breaker assembly
T1 three-pole module
T1 three-pole breakers
M470 screws and washers
breaker brackets
M612 Torx screws
M470 screws and washers
T3 three-pole breaker assembly
T3 three-pole module
T1 three-pole breakers
M4 70 screws and washers
breaker brackets
M612 Torx screws
M4 70 screws and washers
Tools required
Phillips screwdriver
T25 Torx driver
Allen wrench
All parts needed for installation
procedures are included with the
circuit breaker kits.
7/31/2019 Aste-6z3qgx r0 En
51/60
Appendix A: Adding Circuit Breakers
InfraStruXure Power Generation System 45
Installing circuit breakers on the ATS panel board
This section shows how to install a T1 three-pole breaker assembly on a 250A ATS panel board. The
steps are identical for installing T1 single-pole and T3 three-pole breakers.
1. Attach the module to the ATS panel board (), and secure it by turning the module locks using
an Allen wrench ().
2. Place the circuit breakers onto the modules busbars () and lock in place with an M470
screw (). Use a Phillips screwdriver to tighten.
3. Attach the breaker brackets to the slots in the distribution bus frame () and secure with an
M612 Torx screw (). Use a T25 Torx driver to tighten. Attach the breaker to the breaker
bracket with an M4 70 screw (). Use a Phillips screwdriver to tighten.
7/31/2019 Aste-6z3qgx r0 En
52/60
Appendix A: Adding Circuit Breakers
46 InfraStruXure Power Generation System
4. Install dividers in the circuit breakers by sliding them, one at a time, into the notches on the side
of the breaker.
See also
For more information on the Divider Kits for the ATS circuit
breakers, refer to theInstallation Instructions (990-2245) provided
with the Divider Kit.
7/31/2019 Aste-6z3qgx r0 En
53/60
InfraStruXure Power Generation System 47
Appendix B: Wire Sizes
250 A ATS and 80 kW Generator
Copper building wire sizes.
Aluminum building wire sizes.
250 A ATS and 120 kW Generator
Copper building wire sizes.
Note
The following wire sizes are recommendations only, and correspond to the maximumampacity for operation of the ATS and the Generator. Smaller wire sizes can be used if
your system operates on a circuit with a lower ampacity.
InstallationMethod
PVC Insulation30C Ambient
XLPE or EPR Insulation30C Ambient
PVC Insulation40C Ambient
XLPE or EPR Insulation30C Ambient
B1 & N = 70 mm2PE = 35 mm2
& N = 50 mm2PE = 25 mm2
& N = 95 mm2PE = 50 mm2
& N = 70 mm2PE = 35 mm2
B2 & N = 95 mm2PE = 50 mm2
& N = 70 mm2PE = 35 mm2
& N = 120 mm2PE = 70 mm2
& N = 70 mm2PE = 35 mm2
C & N = 70 mm2PE = 35 mm2
& N = 50 mm2PE = 25 mm2
& N = 70 mm2PE = 35 mm2
& N = 50 mm2PE = 25 mm2
InstallationMethod
PVC Insulation30C Ambient
XLPE or EPR Insulation30C Ambient
PVC Insulation40C Ambient
XLPE or EPR Insulation30C Ambient
B1 & N = 95 mm2PE = 50 mm2
& N = 70 mm2PE = 35 mm2
& N = 120 mm2PE = 70 mm2
& N = 70 mm2PE = 35 mm2
B2 & N = 120 mm2PE = 70 mm2
& N = 95 mm2PE = 50 mm2
& N = 185 mm2PE = 95 mm2
& N = 95 mm2PE = 50 mm2
C & N = 95 mm2PE = 50 mm2
& N = 95 mm2PE = 50 mm2
& N = 120 mm2PE = 70 mm2
& N = 95 mm2PE = 50 mm2
Installation
Method
PVC Insulation
30C Ambient
XLPE or EPR Insulation
30C Ambient
PVC Insulation
40C Ambient
XLPE or EPR Insulation
30C Ambient
B1 & N = 150 mm2PE = 95 mm2
& N = 95 mm2PE = 50 mm2
& N = 185 mm2PE = 95 mm2
& N = 120 mm2PE = 70 mm2
B2 & N = 185 mm2PE = 95 mm2
& N = 120 mm2PE = 70 mm2
& N = 240 mm2PE = 120 mm2
& N = 150 mm2PE = 95 mm2
C & N = 120 mm2PE = 70 mm2
& N = 95 mm2PE = 50 mm2
& N = 150 mm2PE = 95 mm2
& N = 95 mm2PE = 50 mm2
7/31/2019 Aste-6z3qgx r0 En
54/60
Appendix B: Wire Sizes
48 InfraStruXure Power Generation System
Aluminum building wire sizes.
Notes:
1. Explanation of installation methods:
B1 = Insulated wires routed within a multi-jacketed cable conductor. The multi-jacketed cable conductor is mounted to a wall.
B2 = Multi-wire cables routed within a multi-jacketed cable conductor. The multi-jacketed cable conductor is mounted to a wall.
C = Multi-wire cables mounted to a wall.
2. = Phase conductor; N = Neutral conductor; PE = Protective Earth conductor
3. Number in parenthesis = Number of paralleled conductors per terminal
4. Conductive cross-sectional areas are in accordance with IEC 60364-5-52
InstallationMethod
PVC Insulation30C Ambient
XLPE or EPR Insulation30C Ambient
PVC Insulation40C Ambient
XLPE or EPR Insulation30C Ambient
B1 & N = 240 mm2PE = 120 mm2
& N = 120 mm2PE = 70 mm2
& N = (2) 95 mm2PE = (2) 50 mm2
& N = 185 mm2PE = 95 mm2
B2 & N = 70 mm2PE = 35 mm2
& N = 185 mm2PE = 95 mm2
& N = (2) 120 mm2PE = (2) 70 mm2
& N = 240 mm2PE = 120 mm2
C & N = 185 mm2PE = 95 mm2
& N = 150 mm2PE = 95 mm2
& N = 240 mm2PE = 120 mm2
& N = 150 mm2PE = 95 mm2
7/31/2019 Aste-6z3qgx r0 En
55/60
InfraStruXure Power Generation System 49
Installation Checklist
The items below must be initialed, and the form must be signed and sent to APC, before a technician
will be dispatched to perform start-up. Initial only the items completed. If an item is initialed ascompleted and it is not complete, there could be additional billing.
Return completed form to:
American Power Conversion
Project Coordination
Fax: 401-788-2616
Item Initials
Fuel tank full of diesel fuel (seepage 9)
Generator pad poured to specifications (seepage 14)
Generator secured to pad (seepage 14)
ATS mounted securely to wall (seepage 16)
Input power from the generator connected to the ATS (seepage 24)
Mains input connected to the ATS (seepage 26)
E-stop contact from the generator connected to the ATS (seepage 28)
DC power input contact from the generator connected to the ATS (seepage 28)
Start contact from the generator connected to the ATS (seepage 28)
Communication cable from the ATS connected to the generator (seepage 30)
230 VAC input from the ATS connected to the generator (seepage 33)
Heater and battery charger connected to the generator (seepage 33)
Branch distribution equipment connected to the ATS (seepage 34)
EPO switch connected to the user interface board on the ATS (seepage 35)
Signature of person making inspection:
Phone number:
Date:
Name of company making inspection:
Phone number:
Date:
7/31/2019 Aste-6z3qgx r0 En
56/60
7/31/2019 Aste-6z3qgx r0 En
57/60
7/31/2019 Aste-6z3qgx r0 En
58/60
7/31/2019 Aste-6z3qgx r0 En
59/60
7/31/2019 Aste-6z3qgx r0 En
60/60
Customer support for this or any other APC product is available at no charge in any of the following ways:
Visit the APC Web site to access documents in the APC Knowledge Base and to submit customer
support requests.
www.apc.com (Corporate Headquarters)
Connect to localized APC Web sites for specific countries, each of which provides customer support
information.
www.apc.com/support/
Global support searching APC Knowledge Base and using e-support.
Contact an APC Customer Support center by telephone or e-mail.
Regional centers:
Local, country-specific centers: go to www.apc.com/support/contact for contact information.
Contact the APC representative or other distributor from whom you purchased yourAPC product for
information on how to obtain local customer support.
Direct InfraStruXure Customer Support Line (1)(877)537-0607 (toll free)
APC headquarters U.S., Canada (1)(800)800-4272 (toll free)
Latin America (1)(401)789-5735 (USA)
Europe, Middle East, Africa (353)(91)702000 (Ireland)
Japan (0) 35434-2021
Australia, New Zealand, South Pacific area (61) (2) 9955 9366 (Australia)
Entire contents copyright 2006 American Power Conversion Corporation. All rights reserved.
APC Worldwide Customer Support
http://www.apc.com/http://www.apcc.com/supporthttp://www.apc.com/support/contacthttp://www.apc.com/support/contacthttp://www.apcc.com/supporthttp://www.apc.com/