Upload
bhaskar-reddy
View
214
Download
0
Embed Size (px)
Citation preview
7/30/2019 Ch Hunger
1/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
CHAPTER I
EXECUTIVE SUMMARY
1.1 INTRODUCTION
The Chhunger Chal Hydroelectric Project located in Pithoragarh district of
Uttaranchal envisages utilization of the waters of the river Dhauliganga, a
tributary of Kali (Sarda), for power generation on a run of river type
development, harnessing a head of about 310 m.
The project with a proposed installation of 240 MW (2x120 MW) would affordan annual energy generation of 853.28 GWh in a 90% dependable year. The
tariff from the project at present day cost would be Rs. 0.92/KWh (levellised).
The diversion site is located at Latitude 30o 11 15 N; Longitude 80o 3430 E.
The dam site is approachable from Tankapur by road at a distance of 265
kms upto Khela and 35 kms from Khela by Kuchha road. The nearest rail
head is located at Tanakpur and nearest airport is located at Delhi.
1.2 SCOPE OF WORKS
The Chhunger Chal HE project envisages construction of:
a 78 m high Concrete Gravity diversion dam across river Dhauliganga
to provide a live storage of 1.49 M cum with FRL at 2780 m and MDDL
7/30/2019 Ch Hunger
2/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
a 81.0 m high 12 m dia surge shaft
400 m long, 4.6 m dia pressure shaft
an underground power house having an installation of 2 Vertical
Francis driven generating units of 120 MW each operating under a
rated head of 292.83 m; and
147 m long tail race tunnel to carry the power house releases back to
the river
The power of this project is intended to be evacuated by proposed 220 kV
D/C line to newly proposed 400/220 kV substation at Didi hat. The total
length of this line would be around 50 kms upto Didi hat.
1.3 HYDROLOGY
The river Dhauliganga drains a catchment area of about 840 sq. km at the
proposed dam site. The water availability for the project has been consideredon the basis of 10 daily discharge series at Pancheswar dam site for the
period 1962-92. The flow series for Chhunger Chal HE Project were derived
by carrying out runoff-runoff correlation between concurrent flows at Chirkila &
Pancheswar and subsequent reduction in proportion to the catchment area.
The computed inflow series worked out has been utilized for Power Potential
Studies. The design flood has been assessed as 4517.40 cumec.
1.4 POWER POTENTIAL STUDIES
7/30/2019 Ch Hunger
3/130
7/30/2019 Ch Hunger
4/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
formulated for Catchment Area treatment, compensatory afforestation and
other environmental issues. These issues would be addressed during the
investigation for DPR.
1.7 ESTIMATES OF THE COST
The project is estimated to cost Rs. 688.03 Crores including IDC at June,
2003 price levels. The preliminary cost estimate of the project has been
prepared as per guidelines of CEA / CWC. The break down of the cost
estimates is given below:
Civil Works : Rs. 366.20 Crores
Electro Mechanical Works : Rs. 213.22 Crores
Sub total : Rs. 579.42 Crores
Interest During construction: Rs. 108.61 Crores
Total (Generation) : Rs. 688.03 Crores
Transmission works : Rs. 37.50 Crores
Grand Total : Rs. 725.53 Crores
1.8 FINANCIAL ASPECTS
As indicated above, the Chhunger Chal HE project, with an estimated cost
(Generation only) of Rs. 688.03 Crores (including IDC of Rs. 108.61 crores)
and design energy of 845.12 GWh in a 90% dependable year is proposed to
b l t d i i d f 5 d 9 th Th t iff h b
7/30/2019 Ch Hunger
5/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
1.9 CONCLUSIONS
Chhunger Chal HE project involves simple civil works and could be completed
in 5 years and 9 months. The project would afford a design energy of
845.12 GWh in a 90% dependable year. The cost per MW installed work out
Rs. 2.41 Crores. The Preliminary Feasibility Report indicates that the scheme
merits consideration for taking up for Survey & Investigation and preparation
of DPR.
7/30/2019 Ch Hunger
6/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
CHAPTER - II
BACKGROUND INFORMATION
2.1 GENERAL
In Nov.2000, Uttaranchal State was carved out of thirteen hill districts of
Northern U.P. The state borders with Nepal and Tibet on the east, Central
Himalayas on the north, Haryana and Himachal Pradesh on the west and
northwest respectively.
Geophysically the state has four Mountain Zones namely Foot hills, Lesser
Himalayas, Greater Himalayas and Trans-Himalayas. The mountains are
covered with perpetual snow and glaciers and has gifted the north India a
perennial river system of the Ganga and its tributaries. The tributaries of
Ganga, namely Alaknanda, Bhagirathi, Yamuna and Sarda originate from
the foothills of snow capped peaks and glaciers in the Central Himalayas and
incise their respective courses through the rugged terrain, splash and surge
the steep gradients and most of the streams offer excellent potential for
Hydro power development.
The region is blessed with magnificent glaciers, majestic rivers, gigantic snow
capped peaks, Valley of flowers natural beauty and rich flora and fauna.
Many holy shrines have blessed the state spiritually and given the name of
Dev Bhoomi or Land of Gods. The seasonal influx of tourists, the seekers of
peace for visit to the holy shrines and lovers of nature contribute to the state
7/30/2019 Ch Hunger
7/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
the total population of India. The percentage of villages having population
more than 500 is about 11.4% (1991 Census). The existing majority of
smaller settlements of Uttaranchal pose a serious challenge for economic
infrastructure and lack of services to the far flung places in the hilly terrain
makes Uttaranchal as one of the extremely backward states of India.
It has 76.1% electrified villages as compared to 75.3% of villages of U.P.
The average per capita consumption of electricity is 245.57 kWh whereas
Dehradun and Nainital consume 480.81 and 447.33 kWh respectively
with a minimum consumption of 43.7 kwh in Uttarkashi.
2.2 POWER SCENARIO IN NORTHERN REGION
2.2.1 Present Status
Most of the states in the Northern Region have been experiencing energy
shortage as well as shortage of Peak Power of varying degree. Actual Power
supply position in the Northern Region during the year 2001-2002 has been
as under:
Energy (in MU), year 2001-2002
State Requirement Availability Shortage(-)/Surplus (+)
%age
Chandigarh 1110 1108 (-) 2 0.2Delhi 19350 18741 (-)609 3.1Haryana 18138 17839 (-)299 1.6Himachal Pradesh 3293 3206 (+) 87 2.6Jammu & Kashmir 6635 5899 (-) 736 11.1
7/30/2019 Ch Hunger
8/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
2.2.2 Peak Power (in MW), year 2001-2002
State Peak
Demand
Peak Met Shortage(-)/
Surplus (+)
%age
Chandigarh 180 180 0 0.0
Delhi 3118 2879 (-)239 7.7
Haryana 3000 2900 (-)100 1.6
Himachal Pradesh 562 562 0 0.0
Jammu & Kashmir 1209 999 (-) 210 17.4
Punjab 5420 4936 (-)484 8.9
Rajasthan 3700 3657 (-)43 1.2
Uttaranchal-U.P 7584 6887 (-)607 9.2
Northern Region 24773 23000 (-)1773 7.2
2.3 NECESSITY OF HYDRO POWER DEVELOPMENT IN UTTARANCHAL
2.3.1 Hydro and Thermal Power Mix
The main resources for generating electricity are by utilising the hydro
potential available along the river drops besides the use of fossil fuel.
Presently the ratio of thermal generation and Hydro-electric generation in
Uttaranchal Power grid, is quite disproportionate. With the diminishing coalresources and difficult oil position all over the world, it is necessary that
electric generation be aimed to achieve the economic balance of 40:60
between the hydro and thermal generation of power, as against the existing
25 75 ti
7/30/2019 Ch Hunger
9/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
hydro-power generation it is essential to develop the hydroelectric power
potential of state which is about 15110 MW, of which so far only 8% has been
developed.
The existing installed generating capacity in the State is about 1286
MW ( 2003 fig) and the entire capacity is from hydro generation. There is no
thermal power generation in the state . The major hydro power stations
under construction in the state are (i) Maneri Bhali, Stage-II (304 MW), (ii)
Lakhawar Vyasi, Stage-I (300 MW), (iii) Lakhwari Vyasi, Stage-II (120
MW), (iv) Srinagar H.E. Project (330 MW), (v) Vishnuprayag Scheme (400
MW), (vi) Tehri Dam Project, Stage-I (1000 MW), (vii) Tehri Dam Project,
Stage-II (1000 MW), (viii) Koteshwar Dam Project (400 MW), and (ix)Dhauliganga H.E. Project, Stage-I (280 MW).
With the rising hydro power generation and improving efficiencies in
distribution of electricity, Uttaranchal hopes to offer energy at stable prices
for eco-friendly industrial development. Though the state is more or less
sufficient in its energy generation to meet its own requirement, there is an
urgent need to develop its huge untapped hydro power potential in an early
and efficient manner, manage efficiently the hydro generation capacity of
existing power stations and to develop and promote new Hydro projects
with the purpose of harnessing hydropower resources in the state for
economic well being and growth of the people in the whole region.
In order to meet the load demand satisfactorily, it is considered essential to
maintain a minimum gross margin of about 30 per cent over the projected
k d d hil l i f i f l f iliti
7/30/2019 Ch Hunger
10/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
i Tapovan Vishnugad (360
MW)
viii Karanprayag Dam (252 MW)
ii Bowala Nandprayag (132
MW)
ix Lata Tapovan (108 MW)
iii Kishau Dam (600 MW) x Vishnugad Pipalkoti (340 MW)
iv Pala Maneri (416 MW) xi Pancheshwar Dam
v Loharinag Pala (520 MW) xii Chamgad Dam (400 MW)
vi Koth Bhel (1000 MW) xiii Dhauliganga, Stage-II
vii Utyasu Dam (1000 MW)
2.5 PRESENT STUDIES
2.5.1 With a view to prioritize the large number of identified schemes to harness
vast untapped hydro resources in the order of their attractiveness for
implementation, Ranking studies were carried out by CEA. Subsequently,
after consultation process initiated by Ministry of Power with various state
agencies, CPSUs etc., it was considered appropriate that Preliminary
Feasibility Report (PFRs) of selected hydroelectric projects be taken up so
that feasibility of the schemes considered in ranking studies could be
established.
2.5.2 In order to achieve the above objective the present preliminary feasibility
stage report presents the Chhunger Chal H.E. Project located in Pithoragarh
District, as detailed in the subsequent Chapters.
2.5.3 In view of the power scenario described above, the envisaged Chhunger Chal
7/30/2019 Ch Hunger
11/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
CHAPTER-III
PROJECT AREA
3.0 DHAULIGANGA RIVER BASIN
3.1 Dhauliganga river is the northernmost right bank tributary of river Kali and lies
entirely in the Pithoragarh district of Uttranchal state of India. The
Dhauliganga basin is bounded between latitude 290 55' - 30 0 35' N and
longitude 800 15' - 80 0 45' E. This is a glacial and snowfed river and
originates in the Lesser Himalayas from snow peaks at an elevation of 5,160
m and flows down as a small stream in a narrow valley, generally in NE SE
direction over a length of 85 km before joining the Kali river at an elevation of
approximate 1100.0 m. The average bed slope of the Dhauliganga river is
approximately 1 in 20 and can be termed as a fast flowing ferocious river.
The river valley is located in high mountain ranges on both banks over most of
its stretch. The river brings down a considerable amount of sediment load
particularly during snow-melt and flood season.
3.2 PROPOSED BASIN DEVELOPMENT
3.2.1 Currently under Execution
The available drop of about 2000 m from Bokang to the confluence of
Dhauliganga with Kali river was noticed and was under study by the UP
Irrigation Department since 1970 for utilsiation of its hydroelectric potential. A
proposal utilizing the combined flows of Dhauliganga and Goriganga was
7/30/2019 Ch Hunger
12/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
NHPC. This scheme is under execution by NHPC with a diversion dam nearChirkila village having an FRL at EL 1345.0 m. This following are the main
details of this project:
1 Reservoir level EL 1345.0 m
2 TWL EL 1034.1 m
3 Gross storage 6.2 M Cum
4 Dam height 56.0 m
5 Type of dam Rock fill
6 River bed level EL 1301.0 m
Installed capacity 4 x 65 MW
Energy Generation
(a) in 90% dependable year
(b) in 50% dependable year
1,187 Gwh
1, 354 Gwh
3.2.2 Future Development
The toposheets prepared by survey of India reveal that there is tremendous
scope of harnessing the hydro power potential available in upstream of
Dhauliganga Stage I HE project, under execution by NHPC, Central
Electricity Authority on their preliminary assessment in the Ranking studies
have identified the following projects with the FRLs & TWLs proposed by them
and as per WAPCOS investigation and studies:
7/30/2019 Ch Hunger
13/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
As per CEA As per WAPCOS
investigation
S.
No.
Name of Scheme
FRL
(m)
TWL
(m)
FRL
(m)
TWL
(m)
1 Bokang Bailing 3200 2840 3280 2780
2 Chhunger Chal 2800 2480 2780 2470
3 Sela Urthing 2480 2200 2470 2200
4 Urthing Sobala 2200 1620 N.A. N.A.
5 Sobala-Jhumrigaon 1620 1480 Dropped because of
Dhauliganga Stage II.
6 Dhauliganga Stage-
II
1597.0 1330.0
CEA has awarded the preparation of pre-feasibility Reports for schemes at Sl.
No. 1 to 5. Sobala Jhumrigaon (Sl. No. 5) has been dropped in
consultation with CEA because of the proposed Dhauliganga Stage II
downstream.
3.3 DESCRIPTION OF CHHUNGER CHAL H.E. PROJECT
Chhunger Chal H.E. Project upstream of the proposed Sela Urthing H.E.
Project will harness the hydro-power potential of the river between EL 2780 m
and EL 2470.0 m.
The project envisages the construction of a concrete gravity dam with
overflow spillway just downstream of confluence of Horba Yankti with
7/30/2019 Ch Hunger
14/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
gate of size 4.0 m x 4.0 m. The inflow into each intake is collected byindividual intake tunnel of 4.0 m dia and is led to respective desilting
chamber which is designed to flush out all silt particles of 0.20 mm size and
above. A control gate shaft is proposed at the end of the desilting chamber
for purposes of desilting the chamber, when required. The desilting chamber
is provided with silt flushing gate, so that silt laden water can be flushed out to
a silt flushing tunnel (steel lined to withstand erosion) which brings the silt
laden waters back to the river downstream of diversion structure.
The silt-free waters from the desilting chamber is led to a 3.545 Km long
5.5 m dia horse-shoe shaped Head Race tunnel. Since the length of water
conductor is more than 5 times the head, a surge shaft is proposed in thisscheme and the flow is then fed into a pressure shaft of 4.6 m dia (steel lined)
which bifurcates near the underground power house to feed 2 x 120 MW
Francis turbines.
The underground power house complex consists of 2 separate caverns, one
for the generating units and another for the transformers etc. Both the
caverns are inter-connected by bus bar tunnels and a tunnel for repair of
transformer. The power house cavern will have an installed capacity of 2 x
120 MW vertical Francis turbines. The transformer cavern will house
transformers and GIS system. A cable cum ventilation tunnel has been
proposed for connection to a small out door switchyard. The power houseand transformer cavern will be approached from a road proposed outside by
means of a common 7.0 m dia D-shaped main access tunnel.
Th d ft t b t l t th b tt f h ill i t if ld
7/30/2019 Ch Hunger
15/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
3.4 SOCIO ECONOMIC PROFILE
The entire region has undulating topography with lofty mountains jutting out
that create a rugged terrain with steep valleys. The geology, soil texture and
climate are highly variable including the habitation pattern. It has sparse and
scanty population, small sized villages, scattered on the hilly landscape. Out
migration of able bodied persons is common. Subsistence level agriculture
based economy mostly prevails with marginal holdings. The infrastructural
development becomes very costly in such terrain.
Pithoragarh District has an area of 17.3% and supports 9.55% population as
compared to the state. The density of population is about 64 persons persq.km as against 116 persons per sq.km of the state. The literacy rate both
among males and females is lowest in the district standing at 59.0% and
38.37% as against the state average of 59.6% and 42.9% respectively. The
population of schedule castes is about 20.45% against state average of
16.7%.
The main work force, about 75%, is engaged in primary and secondary
sectors and the balance in allied sectors. As regards land use pattern about
70% of land is under forest and barren lands.
About 64% of the inhabited villages are connected with road and theremaining villages suffer because of remoteness and higher altitudes. As
regard rural electrification, Uttaranchal has 76.1% electrified villages and the
per capita consumption of electricity of the state is about 245.6 kwh per
H Al d N i it l h h hi h ti
7/30/2019 Ch Hunger
16/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
CHAPTER-IV
TOPOGRAPHIC AND GEOTECHNICAL ASPECTS
4.1 INTRODUCTION
The proposed Chhunger Chal hydro-electric project on Dhauliganga river
( Lat. 300 11 15 N ; Long. 800 34 30 E) envisages construction of a 78 m
high concrete gravity dam downstream of the confluence of Horba Yankti with
Dhauliganga and about 1.3 km upstream of Chal village situated on the right
bank of the river. An underground power house with an installed
capacity of 240 MW(2 x 120 MW) is located inside the right bank hill
about 1 km upstream of Sela village. The other main components of the
project include a 3.545 Km long HRT, a Surge Shaft and a pressure shaft
etc.
4.2 PHYSIOGRAPHY
The area around the project is located in the inner part of lesser Himnalayas
and outer part of Great Central Himalayas. It represents an extremely rugged
topography with very high relief. The area is drained by a number of
streams (gads / Yanktis) which are tributaries of south-southeasterly flowing
river Dhauliganga which itself is a tributary of Kali river.
4.3 RAINFALL AND CLIMATE
7/30/2019 Ch Hunger
17/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
Munsyari is the nearest rainage station to the project area. The rainfall dataat Munsyari (El 2100.0 m) indicates that main months of rainy season
are July, August and September. The total monthly precipitation/rainfall
data of the years 19867-1988 for Munsyari raingauge station is given
below:-
Total Monthly Rainfall/Precipitation in mm
Year Jan Feb March April May June July Aug. Sept. Oct. Nov. Dec.
1986 NA NA NA NA NA 153.0 566.0 618.0 239.4 110.3 16.1 10.2
1987 52.6 35.0 5.3 70.8 173.8 87.2 751.6 858.8 278.8 65.0 0.0 55.2
1988 35.6 164.8 307.0 51.6 NA 384.2 NA 807.6 268.0 NA 32.4 148.0
The area witnesses cold temperate climate during summer and the winters
are cold with occasional snow falls in the project area.
4.4 REGIONAL GEOLOGICAL SETUP
The rocks occuring at and in the vicinity of the proposed dam site are
porphyroblastic gneisses and schists which are included in the Central
Himalayan Crystalline. The region is bounded by two major planes of
dislocations, the Main Central Thrust in the south while the Dar Martoli
Fault marks its northern limit with the rocks of the Tethyan Zone. The Main
Central Thrust is an important structural discontinuity in the area which
separates the rocks of the Garhwal group from those of central
7/30/2019 Ch Hunger
18/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
The Dar Martoli Fault demarcates the boundary between CentralHimalayan Crystallines and rocks of Tethyan Zone i.e. Budhi schists etc.
The regional trend of the fault is WNW ESE with high angle dip
towards North and is located far away from the project area.
4.5 GEO-TECHNICAL APPRAISAL
4.5.1 General
The geologic map of the area shows that the proposed project site is located
in the area which exposes the rocks belonging to Bogudiyar formation and the
lower and Middle Members of Dar Formation. These comprise garnetiferous,sillimainte and kyanite bearing schists, quartzite and various types of
gneisses. These rocks trend in WNN-ESE in general with moderate dips
towards north. The rocks are highly deformed and are folded and faulted.
The geological map of the Project Area is given at Plate I.
4.5.2 Geology at Dam Site
The site is proposed diversion structure is located across Goriganga near
Mapang village. The area exposes 3f Member of Bogudiyar Formation. The
rocks include garnetiferous mica schist, biotite schist, slate, quartzite and
phyllite. The over burden in the river is expected to be thick and needs to beascertained during detailed investigations.
4.5.3 Geology along Water Conductor System
7/30/2019 Ch Hunger
19/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
include biotite schist, gneisses, micaceous quartzite, calsilicate rock withbands of biotite schist and gneisses, quartzite with igneous intrusions,
quartzite, gneisses, biotite gneisses, (kyanite bearing) with bands of
micaceous quartzite. These rocks are traversed by ENE-WSW to E-W
trending fault likely to be intersected by the proposed HRT alignment. The
tunneling conditions are expected to be fair to good in general except for
reaches where shear/fault zones are encountered. Adequate rock cover has
to be ensured at drainage crossings. The surge shaft and pressure shaft will
also pass through the similar strata except that near the top the surge shaft
may open up in weak and disintegerated rock strata. Similarly the tailrace
tunnel near the outlet may encounter distintegerated rocks.
4.5.4 Geology at Underground Power House Site
The underground power house is located sufficiently inside the left bank
where, like water conductor system, rocks to be encountered are biotite
schist, gneisses, micaceous quartzite, calsilicate rock with bands of biotite
schist and gneisses, quartzite with igneous intrusions belonging to member 3c
of Bogudiyar formation.
4.6 SEISMICITY OF THE AREA
The area encompassed by the project falls in Zone V of the SeismicZoning Map of India (IS : 1893 1984 ). Clusters of epicentres of
medium to shallow earthquakes with magnitudes ranging between 5 and
6.5 are shown on the map of India (Appendix A of the Indian Standard
ti d b ) i d d th d j t Thi f t
7/30/2019 Ch Hunger
20/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
The Bajang (Nepal)- Dharchula earthquake (M = 6.1), which occurred on29th July 1980 had its epicentral tract in Dharchula area. A maximum
intensity of VIII was assigned to the earthquake. Therefore, a suitable
seismic factor would have to be adopted for designing the structures in
the area.
4.7 CONSTRUCTION MATERIAL
The river bed material may be sorted, crushed and utilised for construction
purposes. In addition, the excavated rocks from underground works may be
tested and used for construction. No clay or impervious materials are
available for a rock fill type dam having impervious core.
4.8 LUSIONS AND RECOMMENDATIONS
i) The rocks exposed at the proposed dam site are porphyroblastic
augen gneisses and chlorite schist belonging to Central
Himalayan Crystalline group.
ii) The overburden in the river section at site will have to be ascertained
with the help of geophysical surveys and further confirmed by drilling
during DPR stage.
iii) Large scale control plans shall have to be prepared for taking up the
detailed geological mapping of the proposed sites and forsuggesting sub-surface explorations at the detailed project report
stage.
iv) The project area falls in Zone V of the seismic zoning map of India,
h it bl i i f t ill h t b id d i th d i
7/30/2019 Ch Hunger
21/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
CHAPTER V
HYDROLOGY
5.1 WATER AVAILABILITY STUDIES
5.1.1 Catchment Area and River
The proposed Chhunger Chal dam site is located on the river Dhauliganga
which is located in Sarda Basin. The catchment area contains several
glaciers and permanent ice caps and the seasonal snow cover area in the
catchment is about 305.25 sq. km. The total catchment area of the riverMahakali upto Chhunger Chal is 840 sq. km. The catchment area map of
Chhunger Chal is shown as Plate-5.1
The elevation in the catchment ranges from 6000 m in the upper
reaches to around 2700 m near the dam site.
5.1.2 Data Availability
(a) Rainfall
There are no Raingauge / G & D stations established on the Mahakali
river The rainfall data in the Dhauliganga basin has been measured at
three raingauge stations by NHPC as given under in Table 5.1.
7/30/2019 Ch Hunger
22/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
Table 5.1Daily Rainfall data availability
Sl.
No.
Name of rainguage station Duration
1 Chirkila June 83 to Dec. 2002 with gaps
2 Nyu Jun.. 74 to Aug 80, Jan 84 toMay 89, July 89 to Dec 96,Jan 1999 to Dec 2002 withgaps.
3 Dugtu Jan 77 to Dec91 with severalgaps
The average annual basin rainfall is estimated as 2500 mm. Due to
intermittently missing rainfall data and its non-availability for later yearsit has not been possible to use the same for water availability studies in
the present studies.
(b) Gauge and Discharge Data
The discharge data observed by NHPC, CWC is available at three G
& D sites. The details are presented in Table-. 5.2 below:
Table 5.2
Gauge and Discharge data
Sl.No.
G & D Site Data availability
1 Chirkila Jan 85 to Dec 96, May.. 97 to Aug
2000, Oct 2000 to Jan 2001
7/30/2019 Ch Hunger
23/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
(c) Sediment Data
The sediment data at Chirkila G & D site is available for the period
Jan 1985 to Dec. 1996, Jan 1997 to Apr. 98 & Nov98 to Dec. 2002
5.1.3 Methodology
The Mean Monthly flows of river Mahakali at Pancheswar (CA 12100 sq. km.)
are available for the period 1962 1992 (31 years). The G&D data observed
by CWC at Tawaghat (C. A : 1372 Km) -which is 5.5 Km downstream of
Chirkila ( C.A: 1360 Km ) is available from 1977 to 1984. This series is
transposed to Chirkila site (located on Dhauliganga river, which is adjacent toMaha Kali) in proportion to catchment area.
In the absence of site specific flow data this 10-daily series at Chirkila has
been used as base data for extension of data series on catchment area
proportion basis. Hence using Pancheswar runoff data as base, the flows
series for Chirkila is extended by trying both linear and non linear runoff
runoff correlation on monthly basis. The regression equations are developed
between Pancheswar runoff series and Chirkila runoff series for concurrent 8
years flow data for the period 1977-84. Three different correlations between
the monthly flows have been established for three distinct periods of the year
as shown below keeping view of the predominant factor generating the runoff.
Finally these generated series are transposed to Chhunger Chal (C.A 840
Km2) on area proportion basis. The Pancheswar and Chirkila monthly flow
series are detailed in the Hydrology report Vol -III.
7/30/2019 Ch Hunger
24/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
(Snow melt phenomenon being causative factor of generation ofrunoff).
The correlation equations for the above mentioned periods for Chhunger Chal
are as follows:
(a) Monsoon Period (June to September)
(i) Non linear correlation equation
y = 5.3862 x 0.4713 (r = 0.824)
x = Monthly runoff in Cumecs for monsoon month atPancheswar
y = Monthly runoff in Cumecs at Chirkila
r = correlation coefficient
(b) Non monsoon period (October to February)
(i) Non linear correlation equation
y = 0.5345x0.7476
(y = 0.84)
(c) Snowmelt Period (March to May)
(i) Linear correlation equation
y = 0.195x - 1.804 (r = 0.889)
M thl ff f lt i d i C t
7/30/2019 Ch Hunger
25/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
1992. Thus a long term flow series from 1962 1992 at Chirkila hasbeen established.
The ratios between 10-daily flows & corresponding monthly flows have
been calculated . Accordingly, the monthly flow series for the extended
periods have been converted to 10-daily flow series.(calculation details
given in Hydrology report Vol III). The 10 daily flow series at Chirkila
has been transposed to Changer Chal in proportion of catchment area.
The integrated 10-daily flow series along with 50% and 90%
dependable year has been presented in Table 5.3 and have been
adopted for planning purpose. The 90% and 50% dependable year
correspond to 1967 and 1991 respectively.
5.1.4 Comparison of flow data between Tawaghat & Chirkila
Central Water Commission is maintaining G & D site on Dhauliganga river at
Tawaghat very close to Chirkila. A comparative statement of annual flows has
been prepared from 1981 to 1992 between the flows at Chirkila from NHPC
data and flows at Tawaghat with CWC data (ref. Hydrology Report Vol III).
It is observed that the annual observed flows of Tawaghat site downstream of
Chirkila based on CWC data are generally on the higher side. Therefore, the
flow series evolved based on NHPC data is on conservative side and appears
reasonable to be adopted for planning purpose.
7/30/2019 Ch Hunger
26/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
27/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
28/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
29/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
5.2 DESIGN FLOOD STUDIES
5.2.1 General
The design flood and highest flood level are very much essential for fixing the
water way and foundation depths of any hydraulic structure. For a diversion
structure, 100-year design flood or standard project flood value is considered
for hydraulic design and for storage projects, probable maximum flood or
1000 year return period flood should be considered based on following
methods.
(i) Hydro-meteorological approach (unit hydrograph method).
(ii) Flood frequency analysis.
5.2.2 Derivation of Unit Hydrograph
CWC in association with IMD and MOST has prepared Flood Estimation
Reports for small and medium catchments for efficient hydro meteorological
homogenous sub-zones. The present studies are based on CWCs Flood
Estimation Report for Western Himalayas Zone 7
The formulae for calculation of various physiographic parameters are given in
Table 5.4.
7/30/2019 Ch Hunger
30/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
Table 5.4Physiographic Parameter Calculations
Parameters Formulae Value
tp2.498
156.0
c
S
L.L
4.132 hrs.
qp 1.048 ( ) 178.0pt
0.81 cumec/sq. km.
W501.954
099.0
c
S
L.L
2.68 hrs.
W750.972
124.0
c
S
L.L
1.45 hrs.
WR50 0.189 ( ) 769.150W 1.087 hrs.
WR75 0.419 ( ) 246.175W 0.66 hrs.
TB 7.845 ( ) 453.0pt 14.92 hrs.QP qp.A 435.35cumecs
Where Tm = 63.42
113.4
2
tt rp =+=+ hrs.
The nomenclatures of the above parameters are the standard representation
of the values and detailed in Hydrology Report Vol.-III.
For the present study with a total catchment area of 840 sq. km, an area of
534.75 sq. km. is considered for the study as 305.25 sq. km. of the
catchment area is under snow and glacier cover (above 5000 m). The total
length of Mahakali river upto Chhunger Chal is 51.74 km. For the catchmentof Chhunger Chal, the value of Lc is 22.78 km. The equivalent slope of the
project area is 1 in 47.
7/30/2019 Ch Hunger
31/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
available, the same point value has been adopted for the present study
purpose. The 25 year, 50 year and 100 return period precipitation
values (12cm, 14 cm & 15 cm respectively) are adopted from the
Isohyetal Maps.
b) Design Storm Duration The base period is of 15 hours, hence one
day design storm is considered.
c) Point to Areal Rainfall Ratios For 25 year, 50 year and 100 year
return period precipitation an areal reduction factor of 0.9113
corresponding to rainfed CA of 534.75 sq. km. is adopted The PMP
value of 33.41 cm considered for the study is an point value.
d) Clock Hour Correction A clock hour correction value of 1.15 is
adopted for PMF study for converting 1 day rainfall to 24 hr rainfall.
However the increase in one day value is limited to 50 mm.
e) Time Distribution Coefficients The Time Distribution Coefficients for
24 hours is given below:
Table 5.5
Distribution Coefficients
Time in
hours
Distribution
coefficient
Time in hours Distribution
coefficient
1 0.17 13 0.792 0.27 14 0.823 0.36 15 0.844 0.43 16 0.865 0.48 17 0.88
7/30/2019 Ch Hunger
32/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
f) Design Loss RateA design loss rate of 0.5 cm/hr. has been adopted.
g) Design Base Flow and Glacial MeltA base flow rate of 0.05 cumecs
/ sq. km. has been adopted. In addition a glacier melt runoff value of 50
cumecs has also been considered tentatively, keeping view of existing
number of glaciers at the upper catchment boundary.
h) Critical Sequence of Rainfall Excess The critical sequence of rainfall
excesses are based on rainfall increments into design hyetograph
arranged in the form of two bell (12 hours each per day).
5.2.4 Computation of Unit Hydrograph
Using the basic physiographic parameters, the unit hydrograph is plotted and
volume adjusted to 1 cm. With out changing the QP, Tm and TB . The surface
flow total flood hydrograph has been computed after the rainfall excess
increment arranged in a critical sequence along with additional component of
base flow and glacier melt.
The detailed calculations showing computation of equivalent slope,
physiographic parameters, rainfall excess, convolution and the flood ordinates
for PMP, 100 year, 50 year and 25 year return period for Chhunger Chal are
given in the Hydrology Report Volume-III.
A PMF value of 4517.40 cumec has been adopted for purpose of preliminary
project planning. The hydrograph showing peak flood for PMF, 100 year, 50
d 25 fl d i i i T bl 5 6 d l t d i Pl t 5 2
7/30/2019 Ch Hunger
33/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
Table 5.6
Chhungar Chal - Flood Ordinates
Return period Design floodpeak in cumecs
Remarks
25 year 972.6650 year 1235.72
100 year 1368.471000 year 4400.00 Projected from 25 year, 50 year& 100 year flood peaks usingGumbel probability papers.
PMF 4517.39
5.3 FLOOD FREQUENCY ANALYSIS
Flood frequency analysis provides a quick estimate of the design flood and is
also useful for checking the design flood values computed by other methods.
It is carried out in two methods viz The Annual Maximum method and the
Peak over Threshold (POT) method (also known as partial duration method).
The long term annual instantaneous peak flow series at project site is not
available. As such the 32-year annual peak discharge series of Pancheswar
dam site has been used for frequency analysis. The results obtained will be
transposed to Chhunger Chal site with due correlation for the variation of
catchment size. The available data will be subjected to randomness clock
stationary test, outlier test. Extreme value distribution also known as Gumbel
distribution and Log Pearson Type III distribution are used for the present
study. Chi square test for LPT-III distribution and Gumbel distribution is used
7/30/2019 Ch Hunger
34/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
Pancheswar are transposed to Garjia dam site using Dickens formula Q =
CA 3/4. The 10,000 year flood value for Pancheswar is 15041.36. Using this
relation, the 10000 year flood at Chhunger Chal is found to be 2034.26
cumecs.
5.4 RESERVOIR SEDIMENTATION STUDIES
5.4.1 General
The suspended sediment inflow data is available at Chirkila G&D site near
project site from January '1985 to 15 December '1996 observed by M/s
NHPC. The observations have been taken by Punjab Type Bottle Sampler
with grain size classification of coarse (greater than 0.2 mm), medium (0.025
mm to 0.2 mm) and fine (less than 0.075 mm).
The bed gradient of river (Maha kali) Dhauli ganga is steep ( 1in 47 upto
project site) and the river is also fed from mountaineous catchment with a
number of glaciers which bring down considerable sediment load during snow
melt and flood season.
There is no Sediment data available for river Mahakali. Hence the Sediment
Data of adjacent Dhauliganga and Goriganga basins have been taken into
account for computing sediment inflow rate. The sediment inflow estimate for
Dhauliganga catchment (which is based on 10 years of data ) is 0.14 ha m /
100 sq. km. / year including 15% bed load which was agreed upon by CWC
while clearing Dhauliganga reservoir sedimentation studies. This estimate is
bl ith dj t G i b i di t i fl f 0 15 h /100
7/30/2019 Ch Hunger
35/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
Technology is 1.65 mm/year for Himalayan rivers. As such the silt rate of
Pancheswar appears higher and more emphasis should be given towards
project specific observation data.
Since the above average annual rates are based on comparative shorter time
horizon an additional load of 15% is added for the adopted silt rate as to
make the silt rate representing a long time average. Hence a silt rate of
0.1725 ha-m / 100 sq. km./year (0.15 x 1.15) has been adopted for
sedimentation studies of Chhunger Chal Barrage.
5.4.2 Sedimentation Aspects
It is observed from the topo sheets that both Dhauliganga and Kali the
catchments contain number of glaciers in the upper reaches at higher
elevation in beyond the proposed scheme Bokang Bailing. There are few
reserved forests, dense mixed jungles of tansen , banj, deodar etc. open
scrubs, rockfall sites and moraine deposits carried by glaciers at relatively
lower stages near its confluence with the Kali. Major catchment area contains
bare rocks with little or no soil cover. The average annual sediment rate for
Chhunger Chal has been estimated to be 1.725 mm based on observed
sediment data of Goriganga at Tham for 5 years and of Dhauliganga at
Chirkila for 10 years. The break up of suspended sediment particles for the
month of August 1988 (severe monsoon month) based on observed data at
Chirkila on the Dhauliganga is coarse 24.76%, medium 17.37% and fine
57.89%.
It i i t t t t th t Hi l t h di t
7/30/2019 Ch Hunger
36/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
river bed level is expected to be fully encroached by the rolling bed load of
pebbles, boulders etc. within one or two years and the entire rolling bed load
would pass over the crest. This warrants proper protection measures against
the damage of downstream glacis.
5.5 CONCLUSION & RECOMMENDATION
(1) The 10-daily flow series of 31 years developed and extended tentatively on
the basis of runoff-runoff correlation with Pancheswar flows may be adopted
for preliminary project planning. However, the flow series need to be reviewed
when site specific observed flow series of longer periods would become
available from the observation agencies. Continuation of all hydro-
meteorological observation in the existing stations may be assured and
identification of new station may be under taken at DPR stage. A gauge,
discharge and silt observation site at/near Chhunger Chal barrage site should
be immediately installed on scientific basis.
(2) It is suggested that short interval rainfall-runoff observation should be initiated
at the project site to enable derivation of reliable unit hydrograph from
observed data. Similarly detailed storm studies are needed to be carried out
preferably by IMD in order to obtain reliable estimate of PMS at highly
orographic catchment with snow & glacier covers.
(3) The sediment rate adopted is based on observed suspended sediment data at
Dhauliganga and neighbouring Goriganga rivers for about 10 years only. The
bed load assumed to be 15% of suspended load is quite tentative. Therefore,
th di t t d t b i d ith d t d b d d t f l
7/30/2019 Ch Hunger
37/130
PFR STUDIES OFCHHUNGER CHALHE PROJECT
5.6 OBSERVATIONS OF CWC
The draft report of this project was submitted to CEA for perusal during
October 03. The observations received from CWC on the Hydrological studies
of this project and the replies for above observations, submitted by WAPCOS
are enclosed as Appendices 1.1 and 1.2 respectively.
7/30/2019 Ch Hunger
38/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
CHAPTER-VI
CONCEPTUAL LAYOUT AND PLANNING
6.1 INTRODUCTION
The Chhunger Chal HE project is the second uppermost scheme in the
cascade development of Dhauliganga basin. This project is proposed
downstream of the proposed Bokang Bailing HE Project.
The Chhunger Chal hydro-electric project as planned envisages
construction of a 78 m high concrete gravity dam above the deepest
foundation level across the river Dhauliganga, downstream of confluence of
Horba Yankti with Dhauliganga river and about 1.3 km upstream of Chal
village. The water from the diversion dam will be led to an underground power
house located about 5 km downstream of dam site inside the right bank hills,
through a 3.545 km long head race tunnel, and a pressure shaft. The power
house is planned to have an installed capacity of 240 MW (2 x 120 MW)utilising a rated head of 292.83 m. The tail waters from the power house will
rejoin the river Dhauliganga through a tail race tunnel.
Central Electricity Authority in its planning for this project had envisaged a
diversion structure near Chhunger with FRL at 2800m, a 4 km long power
tunnel aligned on the right bank of the river with Power house located near
Chal with TWL 2480m. After detailed studies, a dam site downstream of the
confluence of Horba Yankti and about 1.3 km upstream of village Chal has
been selected where the river bed level is at about EL 2720 m The river
7/30/2019 Ch Hunger
39/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
The intake and a 3.545 km long HRT are planned on the right flank of the river
and the underground power house inside the right flank hill. The minimum
TWL at the power house is 2470 m which corresponds to FRL of the planned
sela Urthing H.E. project.
With the above changes in the location of dam, power house, TRT etc. and
the layout of the scheme including dam height, tail race and other features;
the potential of the project has been enhanced to 240 MW as against 145 MW
suggested by CEA.
The location of the dam and its height have been finalised considering
optimum power generation, topographical and geotechnical features, already
planned projects on the upstream and downstream, economy, submergence
and other relevant factors. The site is considered ideally suited for the
construction of a concrete gravity dam. Embankment type of dam was not
considered in view of non-availability of impervious materials and spillway
considerations.
The dam is 192 m long at the top and consists of overflow and non-overflow
blocks. The overflow blocks are designed as ogee control structures with a
crest level of 2759m and 21 m high radial gates. The FRL and MWL of the
dam are at EL 2780m and the top of dam is kept at EL 2783 m after allowing
for necessary freeboard. The MDDL is kept at EL 2769 m which will provide
the required peaking storage against the gates during the lean months and
also meet the requirement of power intake.
Th i t k HRT h ft d h ft l t d i it bl k
7/30/2019 Ch Hunger
40/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
The salient features of the project are included in the report. The details of the
major components of the project alongwith the design considerations are
given in subsequent paragraphs.
6.2 DIVERSION STRUCTURE
A 78 m high (above deepest foundation level) concrete gravity dam is
proposed downstream of the confluence of Horba Yankti with Dhauliganga
and 1.3 km upstream of village Chal on Dhauliganga river. The dam is
proposed at latitude 30o 1115 N and longitude 80o 3430 E. The concrete
dam will have FRL of 2780 m and MDDL of 2769 m. The MWL of the dam is
2780m and the top of the dam is kept at EL 2783 m after taking into account
the required freeboard.
The proposed dam will have a submergence area of 1,32,000 sq. m at FRL
(Refer Annexure-6.1) and all this area will be within the river gorge. The
reservoir storage for peaking purposes in the lean season between MDDL
and FRL is 1.49 M. Cum (Refer Annexure 6.2).
Overflow type of spillway blocks, two in number, with ogee control structures
have been planned to pass the design flood discharge of 4517.40 cumec.
For the spillway, ski jump bucket energy dissipators have been planned as
terminal structures with concrete apron protection beyond spillway bucket.
The dam will have seven number NOF blocks and two number overflow
blocks. The pier width for the spillways has been kept as 5 m. The choice of
ski jump energy dissipation works for this dam has been dictated by the tail
t diti A th i di t i it t tilli b i
7/30/2019 Ch Hunger
41/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
treatment measure, consolidation grouting throughout the entire base of the
dam to a depth of 10 m and one row of curtain grouting to a depth of h/2
where h is the height between FRL and deepest foundation level subject to a
minimum depth of 10 m have been provided. A grouting cum drainage
gallery has been provided at the bottom of the dam, through which the curtain
grouting as well as drainage hole works will be done.
All the hydraulic and structural designs for the dam, spillway and other
components of the dam have been done as per relevant BIS codes /
standards and the State of the art practices. The dam sections will also be
zoned with different grades of concrete in order to economise the cost without
sacrificing the stability and safety requirements.
The dam and underground power house will also be provided with measuring
devices as per BIS codes to observe and monitor the behaviour of these
structures.
The layout plan of the dam and other components of the project are shown in
drawing no. WAP/PFR/CHHUNGER CHAL/1001. The dam plan and elevation
are shown in drawing no. WAP/PFR/CHHUNGER CHAL/1003 and sectional
details of NOF and overflow blocks are shown in drawing no.
WAP/PFR/CHHUNGER CHAL/1004.
6.3 POWER INTAKE
The intake structure for diverting the design discharge of 114.0 cumec
(i l di ilt fl hi i t) i d th i ht b k f i
7/30/2019 Ch Hunger
42/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
The required flows for power generation are proposed to be diverted through
two intake structures of capacity 57.0 cumec with crest at EL. 2759 m. The
intake trashracks will have 5 spans of 5 m each separated by 4 no. piers of
1.5 m width each at center to center distance of 6.5 m. The total width of the
trashrack structure will, therefore, be 67 m. The trashracks will be in panels of
size 5 m x 0.75 m which can be easily lowered in inclined trashrack grooves.
The racks will be made out of steel flats of size 15 mm x 50 mm rounded at
inlet ends and shall be fixed vertically on each of these panels at a spacing of
100 mm c/c. Assuming 50% clogging, the velocity through the trashracks will
be restricted to 0.75 m/s.
The flow through the intake will be led to an intake tunnel with a bell mouth
entry. The vertical lift gate of size 4.0m x 4.0m will control the flow into the
intake tunnel. Stop Log has also been provided for the intake. For operation
of gates, a gate hoisting structure will be provided at EL. 2783 m. A vent
pipe of 200 mm diameter would also be provided just downstream of the
intake gate. Besides intake gate hoisting structure at EL 2783 m, a deck has
also been proposed at EL 2770 m to install / clear the trashracks when
reservoir level reaches MDDL. The details of intake structure are shown in
Drawing No. WAP/PFR/CHHUNGER CHAL/1005. The hill slope near each
intake will be stabilized with adequate slope protection measures like rock
bolts, shotcrete, benching, drainage holes etc. as necessary.
6.4 INTAKE TUNNEL
Two number intake tunnels have been proposed, one each for the two
i d d t i t k t t E h f th t l i d i d t
7/30/2019 Ch Hunger
43/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
a surge shaft. The length of each intake tunnel will vary to suit the merger
point with the headrace tunnel. To excavate these tunnels, rock support
system shall be provided to suit the geological conditions of the strata through
which these are excavated. The intake tunnels will be provided with 200 mm
thick PCC lining.
6.5 DESILTING CHAMBERS
It is proposed to provide desilting chambers to flush out all silt particles of
0.2 mm size and above.
Two no. trough type underground desilting chambers operating under
pressure flow conditions are proposed. These are fed by independent intake
tunnels. Each desilting chamber will be 12.5 m wide, 15 m deep and 266 m
long and will have smooth transitions at inlet and outlet ends to avoid eddy
formations.
The desilting chamber troughs will have 2 m x 2 m longitudinal drains at bedlevel. These drains will be covered with removable slabs having 250 mm to 25
mm dia holes at 4.0 m c/c through which the silt particles that settle will pass
to the silt collecting drains. At the end of desilting chambers, silt flushing gates
are provided in an underground hoist chamber to flush out silt laden waters in
the drains to a common silt flushing tunnel that takes the silt-laden waters
back to the river. These silt flushing gates of size 2.0 x 2.0 m can be
vertical/radial gates. An opening of about 20 cm height of these gates will
induce sufficient silt flushing velocity to flush out the accumulated silt in the
d i Th ilt fl hi di h i th h h t i ld
7/30/2019 Ch Hunger
44/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
6.6 HEAD RACE TUNNEL
A single horseshoe shaped headrace tunnel of 5.5 m finished diameter and
about 3.545 km length has been designed to carry the required flows
further upto the surge shaft. This tunnel is designed to carry a discharge of
91.2 m3/s. The head race tunnel passes under three deep nallahs along its
route. The tunnel alignment has been so fixed that it has adequate rock
cover at each nalla location. The tunnel will be provided with suitable rock
support system depending upon the geological strata / formations enroute.
Apart from the rock support system, the headrace tunnel will be provided with
a 300 mm thick plain cement concrete lining to reduce the head loss due to
friction.
The details of typical rock support system and the concrete lining of headrace
tunnel are shown in drawing no. WAP/PFR/CHHUNGER CHAL/1006.
6.7 SURGE SHAFT
To take care of pressure rise in case of sudden load rejection and to meet the
sudden demand of water in case of sudden load acceptance, a simple surge
shaft of 12 m diameter and maximum surge elevation of 2810 m has been
provided at the end of headrace tunnel. This proposed surge shaft will serve
the following functions:-
(i) To provide a free water surface close to the flow regulating
mechanism.
(ii) T li it th l th f i d t d it li bl t t
7/30/2019 Ch Hunger
45/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
(vi) To supply the additional flows required by the turbine during the load
acceptance until the headrace tunnel is accelerated to new steady
state value.
The bottom of surge shaft will be at EL 2734 m and the normal minimum
water level and maximum surge levels will be 2761 m & 2810 m respectively.
The top of surge shaft will be located at EL. 2815 m. In case during detail
design, it is found that minimum surge level comes lower than crown of HRT,
expansion chambers of suitable capacity can be considered.
The surge shaft is provided with adequate rock support system and a
reinforced concrete lining of 500 mm thickness upto maximum surge level.
Thereafter, upto the top level, only rock support system and 150 mm
shotcreting will be sufficient.
6.8 PRESSURE SHAFT
A single pressure shaft of 4.6 m diameter bifurcating to 2 numbers of 3.25diameter each near underground power house is proposed at centerline
elevation of turbine at 2463 m.
Flows to turbines will be controlled by independent butterfly valves placed in
the powerhouse cavern.
The pressure shaft shall be steel lined and shall be backfilled with 500 mm
thick M-20 grade concrete. The thickness of steel liner shall vary from 14 mm
i th b i i t 32 th h D i N
7/30/2019 Ch Hunger
46/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
6.9 UNDERGROUND POWER HOUSE COMPLEX
An underground power house is proposed for this project because river bank
at the tailrace outfall is very steep and there is no space where a surface
power house can be economically built. The geological strata at this location
comprises of upper member of Dar formations consisting of migmatites,
banded gneiss, schists with clacisilicates rocks and marble. These rocks aretraversed by migmatites veins and intruded by granite near contact with
Tethyan sequence. This geological strata is considered suitable for an
underground power house. The roof and sides of the power house and the
transformer cavities will be provided with suitable supporting system like
shotcrete, rock bolts etc. as necessary.
The underground power house complex comprises of two separate caverns
about 38 m apart. The main cavern of 21m width which will house generating
equipment is 89 m long, out of which 47 m length will house 2 units of 120
MW each and the remaining is occupied by a service bay of 22 m length and
a control block of 20 m length. The generator floor and service bay will be atEL 2474.5 m and the control block portion will be at higher elevation with a
workshop facility underneath. Besides the turbine & generators etc, this
cavern will house 2 no. main inlet valves, one for each unit. The centre line of
turbines with be at EL 2466.5 m. An EOT crane of suitable capacity will be
provided which will run from the beginning of service bay to the end of
machine hall.
The transformer cavern will be 14 m wide and would house transformers and
GIS A bl til ti t l ill b id d f thi t th
7/30/2019 Ch Hunger
47/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
The underground caverns will be approached by a common main access
tunnel of 7.0 m dia D-shaped starting from the existing road / path along the
right bank of river. This access tunnel will have a maximum gradient of 1 in
15 and will be concrete lined and properly electrified and ventilated.
The details of underground power house complex are shown in drawing no.
WAP/PFR/CHHUNGER CHAL/1007 and 1008.
6.10 ELECTROMECHANICAL WORKS
The proposed 240 MW Chhungur Chal Hydro-Electric Project would be Run
off the river type development. The installed capacity would be provided by
2 nos. Francis, Vertical axis turbine driven generating units of120 MW each
housed in an underground powerhouse. It is proposed to provide Inlet Valve
of spherical type for each turbine, which would be accommodated in the
powerhouse cavern.
The generation voltage of 11 kV would be stepped up to 220 kV through three45 MVA, 11/220/3 kV ODWF type single-phase transformers for each unit
located in Transformer cavern. The 11 kV-isolated phase phase busducts
would connect the 11 kV generator terminals with 11 kV bushings of step up
transformers. The 220 kV bushings of the transformers would be connected
with 220 kV Gas Insulated Switchgear (GIS) located on the floor above the
transformers in transformer cavern.
The arrangement of generating equipments, unit step up transformers, etc. is
i di t d i th f ll i d i
7/30/2019 Ch Hunger
48/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
The power generated would be evacuated through one 220 kV double circuit
transmission line. The single line diagram is enclosed given in Drawing NO.
WAP/PFR/ CHHUNGER CHAL/1009.
6.11 BRIEF PARTICULARS OF EQUIPMENTS
Turbine and Governor
The upstream levels, tailrace level and head available for power generation
are indicated below :
i) Upstream Levels
FRL EL 2780.0 M
MDDL EL 2769.0M
ii) Tailrace Levels
Maximum EL 2473.0M
Minimum EL 2470.0 M
iii) Heads
Maximum net head 298.0 M
Minimum net head 284.0 M
Rated head 292.83 M
The specific speed of the turbine determined as 104 RPM leads to the choice
of Francis turbine for this station. The turbine would be suitably rated to
7/30/2019 Ch Hunger
49/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
as not to increase the speed rise and pressure rise more than 45% and 30%
respectively under full load throw off condition.
6.12 MAIN INLET VALVE
It is proposed to provide spherical type Inlet Valve for each turbine as second
line of defence in stopping the water flow to the turbine when due to governormalfunctioning, the generating units may tend to go to runaway speed.
During the time when the generating unit is under stand still condition, it would
help in minimizing the water leakage through the wicket gates of the turbine.
The opening of the valve would be achieved through pressurized oil
servomotor and closing through counter weight.
6.13 GENERATOR AND EXCITATION SYSTEM
The generator shaft would be directly coupled with the turbine shaft. The
bearing arrangement would be semi-umbrella type with combined thrust and
guide bearings below the rotor and one guide bearing above the rotor. Thegenerator would be of the closed air circuit water cooled type. The main
parameters of the generator would be as indicated below:
i) Rated out put - 120 MW
ii) Power factor - 0.9 lag
iii) Speed - 300 RPM
iv) Class of Insulation of
stator and rotor winding - Class 'F'
) G ti V lt 11 kV
7/30/2019 Ch Hunger
50/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
6.14 UNIT STEP-UP TRANSFORMER
Three 45 MVA, 11/220/3 kV single-phase transformers, would be provided
for each generating unit with one spare transformer of same rating common
for all the units. The likely transport limitations have dictated the choice for
Single-phase transformers. The transformers would have Oil Directed Water
Forced (ODWF) type cooling arrangement. These transformers would be
located in the transformer cavern. The 11 kV bushing of the transformers
would be connected with 11 kV terminals of generator through 11 kV bus
ducts. The 220 kV bushing would be connected with 220 kV Gas Insulated
Switchgear located on the floor above the transformers in transformer cavern.
6.15 EOT CRANE
The heaviest equipment which the powerhouse cranes are required to handle
during erection and subsequently during maintenance is the generator rotor.
The weight of the generator rotor has been estimated to be about 365tonnes.It is proposed to provide two EOT cranes of 200/20tonnes capacity each.
6.16 AUXILIARY EQUIPMENT AND SYSTEMS FOR THE POWER HOUSE
Following equipments for the auxiliary systems of the power house would be
provided:
i) Cooling water system for turbines, generators, unit step up
t f t
S S O C G C A O C
7/30/2019 Ch Hunger
51/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
vi) 415 V LTAC supply system comprising station service transformers,
unit auxiliary transformer, station service board, unit auxiliary boards
etc.
vii) D.C. supply system comprising 220 V DC battery, chargers, DC
distribution boards etc.
viii) Ventilation system for the power house
ix) Air conditioning system for control room, conference room etc.x) Illumination system
xi) Earthing system
xii) Oil handling system
xiii) Power and control cables
xiv) Fire protection system
6.17 220 kV SWITCHYARD
Due to likely non-availability of flat space for outdoor switchyard it is proposed
to provide 220 kV Gas-Insulated Switchgear located on the floor above thetransformers in transformer cavern havingsix bays out of which two bays for
generator incoming, two bays for220 kV transmission lines, one bay for step
down transformer and one bay for bus coupler. The double bus bar
arrangement has been proposed which would provide flexibility and reliability
in the operation of the plant.
6.17 OBSERVATIONS OF CEA & CWC
Th D ft R t f thi j t b itt d t CEA f l d i
PFR STUDIES OF CHHUNGUR CHAL HE PROJECT
7/30/2019 Ch Hunger
52/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
CHAPTER-VII
POWER POTENTIAL STUDIES
7.1 GENERAL
The power potential studies have been carried out for CHHUNGUR CHAL
Hydel Scheme, which is located in Uttranchal State. The projected power
supply position for 11th Plan indicate that there would be shortage of peak
power in Uttranchal State as well as in Northern region. The execution of
this project would help in reducing the gap between supply and demand of
power.
This is a Run off the river development with diurnal storage for peaking
purpose. The powerhouse would be of Under Ground type.
The scheme is located down stream of Bokang Bailing HE Project which
has been planned as storage based scheme. Therefore, this scheme has
been planned considering regulated discharges from Bokang Bailing.
Benefits have also been determined for an alternative scheme with
unregulated inflows received.
7.2 FIXATION OF FRL/MDDL
The FRL of the pondage has been fixed at EL 2780.0 M so as to get
adequate storage capacity for peaking operation of the plant during lean
flow period (January, February and March). The FRL has also been
PFR STUDIES OF CHHUNGUR CHAL HE PROJECT
7/30/2019 Ch Hunger
53/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
estimated as 2.240 million cubic metres, thus making available live storage
of 1.490 million cubic metres. The levels v/s capacity characteristics of the
pondage are indicated in Annex 7.1.
7.3 FIXATION OF TAIL RACE WATER LEVEL (TWL)
The minimum tail water level which corresponds to discharge of onegenerating unit at 10% load has been considered as EL 2470 M. The
Maximum TWL at EL 2473 M corresponds to all the units running at full
load. The minimum TWL has also been coordinated with FRL of
downstream Sela Urthing HEP which is at EL 2470 M.
These levels, however, would need to be verified when it would be possible
to prepare tail rating curve.
7.4 WATER AVAILABILITY
The available data of water flows on 10 daily basis has been analysed inChapter No. 5 on hydrology. Water flows series for 30 years (1962-63 to
1991-92) has been utilized for power potential studies and is indicated in
Annex-7.2.
7.5 TYPE OF TURBINE
Based on rated head of 292.83 M and capacity of generating units, Francis
turbine is considered optimum choice for this station. Following efficiencies
t i i t F i t bi d i ti it h b tili d f
PFR STUDIES OF CHHUNGUR CHAL HE PROJECT
7/30/2019 Ch Hunger
54/130
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
7.6 90% AND 50% DEPENDABLE YEARS
For determining 90% and 50% dependable years, Annual energy
generation for all the 30 years (1962-63 to 1991-92) has been computed
with unlimited installed capacity. The year wise power potential and energy
generation is indicated in Annex-7.3 & 7.4 respectively. Annual energy
generation is tabulated in descending order and indicated in Annex-7.5.The 90% and 50% dependable years have been determined in the
following basis, where N is the no. of years for which inflow series is
available.
90%
year
- (N+1) x 0.9 - 31x0.9 - 28th
year
50%
year
- (N+1) x 0.5 - 31x0.5 - 16th
year
Based on above, 1976-77 and 1969-70 work out to be 90% and 50%
dependable years respectively.
Analysis of flow in lean period indicated in Annex 7.2, however, reveals
that lean period flow is maximum in 1976-77. The installation determined
on this basis would be very optimistic figure. It would thus be more
appropriate in this case to determine 90% dependable year based on lean
flow discharge. The energy generation in lean flow period has been
computed and tabulated in descending order in Annex 7.5. Based on
energy generation in lean period, 90% dependable year comes out to be
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
7/30/2019 Ch Hunger
55/130
discharges released from Bokang Beiling plus the discharge from inter-
mediate catchment. The computations of total inflows are indicated in
Annex 7.6 for 90% year and in Annex 7.9 (A) for 50% dependable year.
The energy computations for various Installed capacities (180 MW to 280
MW) are indicated in Annex 7.7 and Annex 7.9 (B) for 90% and 50%
dependable years respectively.
7.7 INSTALLED CAPACITY
7.7.1 The power supply demand scenario projected for 11 th five-year plan
indicated that there would be shortage of power during peak hours in
Uttranchal as well as in Northern Region. The peak period is about four
hours.
7.7.2 The power potential in a 90% dependable year with different installed
capacities (180 MW to 280 MW) is indicated in Annex-7.7. The studies
have been carried out with rated head of 292.83 M and friction loss in water
conductor system as 12.0 m. The study indicates that the firm power is40.21 MW continuous. Considering four hours peaking, the installed
capacity required would be about 241.0 MW.
7.7.3 For optimization of Installed Capacity, annual energy generation (KWh),
Incremental Energy generation d(KWh) and ratio of Incremental energy to
Incremental Installed Capacity d(KWh)/d(KW) have been computed for
90% dependable year for installed capacity up to 280 MW varying in steps
of 10 MW. The results are indicated in Annex-7.8. It would be seen there
f th t d(KWh)/d(KW) h t d f i i i t ll d it
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
7/30/2019 Ch Hunger
56/130
7.7.4 Keeping in view the system requirements and analysis of Incremental
energy and Incremental installed capacity, the installed capacity of 240 MW
is considered optimum. With the installation of 240 MW the load factor of
operation during lean flow period would be 16.75% corresponding to 4.02
hours of peaking.
7.7.5 Regarding number of generating units to be installed, there are threeoptions:
1 x 240 MW
2 x 120 MW
3 x 80 MW
Installation of one unit of 240 MW would be most cost effective. However,
the width of underground powerhouse cavern required for this size of unit
would not be feasible from geological considerations. Further there may be
difficulties in transportation of equipment in hilly terrain. Installations of two
units would provide increased reliability of power supply from the stationand more flexibility for peak load operation. Installation of 3 units would
have all the advantages applicable with the installation of 2 units, however,
it would result in increased capital cost of the project. Considering the
above it has been decided to install 2 units of 120 MW each. The Francis
turbine would be suitably rated to provide 120 MW at generator terminals at
rated head of 292.83 meters. The speed of the generating unit has been
determined as 300 rpm.
7 8 RESULTS OF STUDIES
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
7/30/2019 Ch Hunger
57/130
Parameters 90% dependable year 50% dependable year
Annual Energy
Generation (Gwh)
853.28 987.95
MW continuous 40.21 50.29
Average annual load
factor
40.59% 46.99%
Load factor in lean flow
months
16.75% 20.95%
The design energy computations have been carried out and indicated in
Annex-7.10. The design energy of 845.12 GWh would be considered for
financial evaluation.
The live storage capacity of the pondage at FRL of EL 2780 M and MDDL at
EL 2769 M has been computed as 1089.46 MWh (1.490 million cubic meters).
The storage capacity required for peaking operation works out to 965.04 MWh
(1.319 million cubic meters) against 1.49 million cubic metre available. Thus,
storage available is sufficient for peaking operation.
7.9 ALTERNATIVE SCHEME UTILIZING UN-REGULATED INFLOWS
Power Potential Studies have also been carried out considering un-
regulated inflows. The energy benefits determined in 90% and 50% years
are indicated in Annex. 7.11 & 7.14 respectively. The installed capacity
has been determined to be 190 MW as indicated in Annex 7 12 Design
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
7/30/2019 Ch Hunger
58/130
Parameters Scheme based on
regulated discharge
Scheme based on un-
regulated discharge
Installed capacity (MW) 240 190
Firm Power (MW) 40.21 31.08
Load Factor (Lean flow) 16.75% 16.36%
Energy Generation(GWh)
i) 90% dependable year
ii) 50% dependable year
853.28
987.95
773.63
884.24
Design Energy (GWh) 845.12 752.66
It would be seen from above, that use of regulated inflows result in
increase in firm power generation which consequently leads to higher
installed capacity and increase in annual energy generation, design energy
etc. Therefore, the alternative utilizing regulated inflows has been
selected.
7.10 CONCLUSIONS
The power potential studies carried out indicate that installed capacity of 240
MW comprising of 2 generating units of 120 MW each would be required for
this HEP to derive optimum power benefits. The project would afford energy
generation of 853.28 Gwh in a 90% dependable year.
PFR STUDIES OFCHHUNGUR CHALHE PROJECT
7/30/2019 Ch Hunger
59/130
level corresponding to discharge. In the present study, tail race water level
was considered constant.
7.11.2 The storage at FRL and MDDL should be computed with more accuracy
based on the data of topographic survey.
7.11.3 As the benefits from the project gets increased by utlising regulated inflows, itis recommended that construction of this project should be planned after
implementation of Bokang Bailing.
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
60/130
CHAPTER - VIII
POWER EVACUATION
8.1 APPRAISAL OF EXISTING POWER EVACUATION FACILITIES
The Project is located between latitude 29-30-00 (D-M-S) East to latitude
31-30-00 (D-M-S) East and longitude 78.5o N to 81o N. The installed capacity
of Uttaranchal State is 1286.15 MW as on March 2003. Its peak demand has
been estimated as 771 MW whereas the met peak is 705 MW in the present
scenario. This amounts to deficit of 66 MW (8.56%). Accordingly, energy
requirement is 3774 MU against the available energy of about 3670 MU. This
depicts deficit of 104 MU (2.8%). For the purpose of evacuation of power
pooling has been proposed for various Hydro Electric Power Projects. As per
the geographical locations the following proposed Hydel Projects lie between
the longitude 78.5o
N to 79.5o
N namely Harsil, Bhaironghati, Gangotri,
Jadhganga, Karmoli Hydro Power Projects. The next group of Hydro Electric
Projects which lie between longitude 79.3o
N to 80o
N are Badrinath, Gohana
Tal, Rishiganga II, Rishiganga I, Jelum Tamak, Deodi, Devasari Dam and
Malari Jelam. Whereas in the next series the Hydro Electric Projects which lie
between longitude 80o N to 81o N are Mapang Bogudiyar, Sirkari Bhyol
Bogudiyar, Sirkari Bhytol Rus Bagar, Khasiya Bada, Khartoli Lumti Talli,
Kalika Dantu, Garba Tawaghat, Sobala Jhimrigaon, Sela Urthing, Chhanger
Chal, Bokang Beiling. The power map of Uttranchal as on 1/1/2002 is shown
at Annex-8.1.
8 2 PROPOSED EVACUATION SYSTEM TO NEAREST FACILITY
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
61/130
8.3 ARRANGEMENT FOR EVACUATION OF POWER FROM CHHUNGUR
CHAL HEP
The 240 MW power generated at 11 kV at Chhungur Chal HEP will be
stepped upto 220 kV by unit step-up-transformers. The power will be taken to
newly proposed 400/220 kV Substation at Didi hat. Proposed line from
Chhungur Chal to Didi hat for evacuation of power is shown at Annexure-8.3.
8.4 ROUTE LENGTH AND COSTING OF 220 KV D/C TRANSMISSION LINE
FOR EVACUATION OF POWER FROM CHHUNGUR CHAL HEP
The power of this project is intended to be evacuated by proposed 220 kV
D/C line to newly proposed 400/220 kV substation at Didi hat. The totallength of this line would be around 50 kms upto Didi hat. The cost of this
portion of line is estimated as Rs.37.50 crores.
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
62/130
CHAPTER IX
INITIAL ENVIRONMENTAL EXAMINATION STUDIES
9.1. INTRODUCTION
The Initial Environmental Examination of Chhunger Chal hydroelectric project
has following objectives through various phases of development which are
proposed to be covered.
provide information on baseline environmental setting;
preliminary assessment of impacts likely to accrue during construction
and operation phases;
identify key issues which need to be studied in detail during
subsequent environmental studies
It is essential to ascertain the baseline status of relevant environmental
parameters that could undergo significant changes as a result of construction
and operation of the project. In an Initial Environmental Examination (IEE)
study, baseline status is ascertained through review of secondary data,
reconnaissance survey and interaction with the locals.
The Preliminary Impact Assessment conducted as a part of IEE Study, is
essentially a process to forecast the future environmental scenario of the
project area that might be expected to occur as a result of construction and
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
63/130
9.2 ENVIRONMENTAL BASELINE SETTING
The study area covered includes the area within 7 km radius of various project
appurtenances. The data was collected through review of existing documents
and various engineering reports and reconnaissance surveys.
The various parameters for which baseline setting has been described have
been classified into physio-chemical, ecological and socio-economic aspects.
9.2.1 Physio-Chemical Aspects
a) Water Quality
The proposed project is located in an area with low population density.
Such areas are characterised by absence of pollution sources, which is
also reflected in excellent water quality.
The present population in the catchment area intercepted at the
diversion structure site is of the order of 400. The major source of
water in the project area are rivers or nallahs which flow adjacent to the
habitations, which are conveyed to the consumers. The sewage so
generated, too outfalls into various streams or nallahs flowing adjacent
to the settlements. The total BOD loading from domestic sources in the
catchment area is of the order of 18 kg/day. The effluent ultimately
reaches river Goriganga through various streams/channels outfalling
into the river. The quantity of BOD loading is insignificant to cause any
d i t t lit f th i i fl i th i
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
64/130
b) Landuse
The landuse pattern of the project area was studied using satellite
data. The submergence area was superimposed on the satellite data,
and the landuse pattern was ascertained, which is given in Table-9.1.
The satellite imagery (IRS 1C, LISS-III + PAN Data) of the study area is
given as Figure-9.1.
Table-9.1Landuse pattern of the submergence area
S. No. Landuse / Land cover Area (ha)
1. Dense forest 8.10
2. Grass land 1.35
3. Water bodies 4.05
Total 13.5
The submergence area is 13.5 ha. The major portion of the
submergence is the forest land (8.1 ha), which accounts for 60 % of the
total submergence area. The other major landuse category is water
bodies (3.60 ha). The area under grasslands is 1.35 ha.
As a part of next phase of Environmental study, it is recommended that
detailed studies be conducted to ascertain the ownership status ofthese lands, i.e. whether the land belongs Forest Department or is it a
non-forest government land. The pasture land could still be
categorized as forest land as far as ownership status is concerned In
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
65/130
submergence area lies in Askot Wildlife sanctuary, the entire area
irrespective of its land cover is to considered as forest land.
9.2.2 Ecological Aspects
a) Vegetation
The proposed project site is located in Askot wild life Sanctuary, about
2 km upstream of the confluence of Dhauliganga with Nagling gad. The
power house is proposed to be constructed at about 1.5 km
downstream of Chal village on the right bank of Dhauliganga. The
forests in the area can be categorized as temperate forest with
Kharsu-Oak forest being the dominant forest sub-type. The dominant
floral species observed in the project area are Kharsu (Quercus
semicarpifolia) with associates such as Kathboj (Baular aloides),
Buransh (Rhododendron arboreum) and Bhojpatra (Betula utilies). The
proposed site is located in deep gorge, where fairly dense oak forest
was observed on south facing hill slops, while on the right bank
vegetation can be categorised as open forests. The hill top are
generally barren with scattered trees mainly consisting of Bhojpatra,
Tuner and Kathbhoj. Vegetation in the vally near project site include
Ringal, Thumer, Timla, Akhrot and Kail. Due to the high elevation and
cold climate several herbs of medicinal importance have also been
reported in this area. Dominant species of herbs are Ghingaru
(Pysectautha crenulata), Hinsalu (Rubus ellipticus), Kutki (Pierotchiza
kurroa), etc.
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
66/130
Table 9.2
Major floral species observed in the study area
Local Names Scientific Names
A. TreesBhojpatra Betula utiliesTansen Tsuga demosaThuner Taxus bacataAkhrot Juglans regia
Timla Ficus auriculataBurans Rhododendron arboriumKail Pinus racuburghilKathbhoj Baula aloides
B. Shurbs
Hinsalu Rubus ellipticusKutki Picrotchiza
Ghingaru Rysectsantha CrenulataKilmora Berberis asiaticaBankakri Podophyllum emodiKapoor Kachari Hedychinum spieatumChirayata Swartia onirataHans Ray Curculigo orchioidesJatamashi Nardostachys grandifolia
b) Fauna
As mentioned earlier, the proposed project is located in Askot wildlife
Sanctuary. The same was formed in July 1986 for protection of Musk
deer. The project area has fairly good forests on hill slopes but major
portion of the catchment is snow bound. The forests in the project area
does not represent good habitat for wildlife. Some mammals who
prefer cooler area have been reported in the project area.
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
67/130
Reptiles are not very common in the area> The only reptilian species
noticed during field study was common lizard (Himidectyles brooki).
Amongst avi fauna, monal (Zophophorus impejanus), snow partridge
(Lerwa lerwa) and Crow (Corvus macrorhnchus) are the dominant
species.
The major faunal species reported in this area are given in Table-9.3.
Table 9.3Major faunal species reported in the study area
Local Name Scientific Name Scientific as per wildlife act
Mammals
Kasturi Mrig Moschus Moschifirus Schedule ISnow Leopard Panthera uncia - do Barking deer Muntiacus Muntjark - do Goral Nemarhaeus goral - do Black Bear Selevactos thibetanus - do
Reptiles
Common lizard Himidectyles brookiAvi fauna
Monal Zophophorus impyanusBlue rock pigion Colimba liviaHill lpatridge Arbasophila torquotaCrow Corvus macrorhchus
Snow patridge Lerwa lirwaSnow cock Tetraogallus himalayensisSnow pigeon Columba leuconota
PFR STUDIES OFCHHUNGER CHALHE PROJECT
7/30/2019 Ch Hunger
68/130
the primary and secondary productivity is very low. The temperature
and natural biota are main factors which govern the growth of fish in
the waters body. Two type of fish i.e. snow Trout and Mahaseer are
reported in river Dhauliganga. However these groups are reported only
near the confluence of river Dhauli with river Kali. It is recommended
that a detailed fisheries survey be conducted in the river as a part of
EIA study to ascertain the spatio-temporal occurrence of fishes. Tank
or pond fisheries is not in vogue in the project area.
9.2.2 Socio-economic aspects
There are a total 9 villages observed in the study area. The average family
size in the study area is 3.7 with a total population on 1008. The number of
females per 1000 male is about 938. The SC and ST population in the area is
13% and 84% of the total production respectively. The male and female
literacy rates are 48.5% and 19.5% respectively. The overall literacy rate in
the study area villages is 34.4%. The demographic profile of the study area
villages is given in Table 9.4.
Table 9.4Demographic profile of study area villages
Population LiteratesS.No
Village No. ofhouseholds Male Female Total
SC ST
Male Female
1. Bauling 29 58 71 129 25 103 25 82. Nagling 40 101 78 179 53 105 50 173. Sela 26 54 50 104 18 86 21 74. Chal 28 63 42 105 13 91 30 25. Baling 34 70 64 134 6 127 46 126 Dugtu 49 85 100 185 0 185 33 31
PFR STUDIES OFCHHUNGER CHALHE PROJECT
C O O C S
7/30/2019 Ch Hunger
69/130
9.3 PREDICTION OF IMPACTS
Based on the project details and the baseline environmental status, potential
impacts as a result of the construction and operation of the proposed project
have been identified. As a part of IEE study, impacts on various aspects listed
as below have been assessed:
- Land environment- Water resources- Water quality- Terrestrial flora- Terrestrial fauna- Aquatic ecology- Noise environment
- Ambient air quality- Socio-economic environment
9.3.1 Impacts on land environment
(a) Construction Phase
Quarrying operations
A hydroelectric project requires significant amount of construction
material, which needs to be extracted from various quarry sites in and
around the project